Method of Statement Scaffolding
Method of Statement Scaffolding
1. INTRODUCTION 1
2. PURPOSE 2
3. SCOPE 2
4. DEFINITIONS 3
This Safe Work Method Statement provides information on how to manage risks
associated with scaffolds and scaffolding work at a workplace. It is supported by
guidance for scaffold installation, scaffold dismantling, scaffold inspection and
maintenance, and advice for contractor and workers on managing the risks associated
with scaffolds and related scaffolding work.
Every metal tube scaffold exceeding 40 meter in height and every other scaffold
exceeding 15 meters in height shall be constructed in accordance with the design and
drawings of a Professional Engineer.
2. PURPOSE
The following method statement is written to provide a safe and efficient system of
work for the installation of general working scaffold to all areas of construction sites
both internal and external. It will also cover all scaffold adaption’s to general scaffold
and any safety and maintenance checks to be held under current safety legislation
within the construction industry. It will cover such areas as; first installation scaffold,
basic lifts (internal and external), adaption’s as work progresses during the duration of
project to basic scaffolding and general working guidelines. Any deviation which is
necessary for Safe Work Method Statement must first be notified to Project Manager
and P.E who will agree the best approach to Safe Work Method Statement with
principle contractor’s approval.
3. SCOPE
This guide covers the erecting, altering and dismantling of prefabricated frame
modular scaffolding founded on the ground or another solid surface.
Fully decked scaffolds over 15 m in height may exceed the design strength of the system
and the design should be verified by an engineer competent in scaffold design.
3|P a g e
4. DEFINITIONS
BASE LIFT the first level of transoms and ledgers above the jacks.
4|P a g e
SHOULD indicates a recommendation to do something that is not
a mandatory requirement under the occupational health
and
safety legislation.
WORKING FACE the face of a building or structure at which the scaffold has been
erected to enable work to be carried out at some stage
of the project.
• placing signs at the access points to each platform, advising if closed or indicating the duty rating of
a working platform
• assigning an on-site scaffold coordinator to the relevant contractors, to control the use of various
5|P a g e
platforms, or sections of platform.
Principal contractors must clearly identify in their site-specific occupational health and safety (OHS)
management plan those responsible for implementing the control measures.
• include in the site induction the control measures and the names of those persons responsible for
implementing the controls
• have means to identify working platforms that are closed – this can be discussed at regular toolbox
meetings
• have means to monitor and review the control measures regularly – if the control measures are not
effective, they should be modified, and records of the monitoring and modifications should be kept.
• The scaffolder must work from a safe position when installing edge protection for the platform above,
eg by:
• The scaffolder should be supported on a fully planked platform when installing the platform
immediately above.
• The fully planked platforms should be nominally 2 m apart, vertically, and remain in place until the
scaffold is dismantled.
• The first platform can be up to 3 m above the ground or supporting surface, except for the access
bay.
• Safe access must be provided up to the first platform and between platforms on the scaffold.
guardrails (suitable for Erection platform area: minimum 500 mm x 600 mm.
scaffolding platform
On scaffolding edge sides, incorporate a built-in mid-rail.
spacing of up to 2 m)
Scaffold planks supported Platform area: minimum 2 x 225 mm wide scaffold planks.
on temporary transoms
(suitable for scaffolding
platform spacing of up to 2
m)
7|P a g e
6.2 DESIGN CRITERIA FOR TEMPORARY EDGE PROTECTION
Temporary edge protection must meet the strength requirements for guardrails and mid-rails specified in
BOWEC General requirements and should be designed to allow the installation and removal of the
permanent guardrails whilst it is in position.
Where work methods differ from the generic work sequence below alternative methods must provide an
equivalent level of safety to those specified in this guide.
Complete first lift • Install access stairway or ladder to platform for the first lift.
• If access is by stairway, ensure the stair access bay is erected with the
run of the scaffold.
• Install edge protection comprising guardrail, mid-rail and toeboard
8|P a g e
Erect next lift Working from a fully planked platform on the first lift, install standards (where
from a platform the standard joint is 1 to 1.5 m above the platform level), transoms, ledgers
and hop-ups for the next lift above.
9|P a g e
Task Activity
Erect next lifts • Unless a specific engineering design is provided, fix the first row of ties
no more than 4 m above the ground. Do not allow a scaffold to free
stand more than 4 m above the ground or a row of ties.
10 | P a g e
Dismantle scaffold General precautions
• Remove chain wire mesh and shade cloth while working from a fully
planked platform.
Task Activity
Break the job down
into steps
11 | P a g e
Dismantling sequence
Note: Follow the below dismantling sequence if you are using erection platforms. If you
are using a temporary edge protection system, modify the dismantling sequence to suit.
12 | P a g e