Charles F Bowman - Seth N Bowman - Engineering of Power Plant and Industrial Cooling Water Systems-CRC Press (2021)
Charles F Bowman - Seth N Bowman - Engineering of Power Plant and Industrial Cooling Water Systems-CRC Press (2021)
Charles F. Bowman
Seth N. Bowman
First edition published 2022
by CRC Press
6000 Broken Sound Parkway NW, Suite 300, Boca Raton, FL 33487-2742
Reasonable efforts have been made to publish reliable data and information, but the authors and
publisher cannot assume responsibility for the validity of all materials or the consequences of their use.
The authors and publishers have attempted to trace the copyright holders of all material reproduced in
this publication and apologize to copyright holders if permission to publish in this form has not been
obtained. If any copyright material has not been acknowledged, please write and let us know so we may
rectify in any future reprint.
Except as permitted under U.S. Copyright Law, no part of this book may be reprinted, reproduced,
transmitted, or utilized in any form by any electronic, mechanical, or other means, now known or
hereafter invented, including photocopying, microfilming, and recording, or in any information storage
or retrieval system, without written permission from the publishers.
For permission to photocopy or use material electronically from this work, access www.copyright.com
or contact the Copyright Clearance Center, Inc. (CCC), 222 Rosewood Drive, Danvers, MA 01923, 978-
750-8400. For works that are not available on CCC, please contact [email protected].
Trademark notice: Product or corporate names may be trademarks or registered trademarks and are used
only for identification and explanation without intent to infringe.
Typeset in Times
by Straive, India
To Nancy
Without whose help this book could not have been possible
Contents
Preface xi
Authors xiii
List of Abbreviations and Acronyms xv
Chapter 1 Introduction.......................................................................................... 1
1.1 Background������������������������������������������������������������������������������ 1
1.2 Types of Cooling Water Systems��������������������������������������������� 1
1.3 Types of Cooling Water System Pumps����������������������������������� 1
1.4 Intake Pumping Stations���������������������������������������������������������� 2
1.5 Cooling Water System Piping and Valves�������������������������������� 3
1.6 Cooling Water System Flow Deficiencies������������������������������� 3
1.7 Heat Exchanger Fouling���������������������������������������������������������� 5
1.8 Engineering Design Errors������������������������������������������������������ 5
1.9 NRC Oversight������������������������������������������������������������������������ 6
1.10 Authors’ Perspective���������������������������������������������������������������� 7
References������������������������������������������������������������������������������������������� 7
Chapter 4 Pumps................................................................................................ 27
4.1 Types of Pumps......................................................................... 27
4.2 Types of Pump Impellers.......................................................... 27
vii
viiiContents
4.3 Specific Speed......................................................................... 29
4.4 Cavitation and Pump Suction Specific Speed......................... 30
4.5 System Head Curve................................................................ 31
4.6 Pump Head Capacity Curve.................................................... 31
4.7 Pump Size, Efficiency, and Speed.......................................... 33
4.8 Net Positive Suction Head...................................................... 34
4.9 Pump Minimum Flow Rate..................................................... 35
4.10 Air Venting.............................................................................. 35
4.11 Pump Line Shaft Seals............................................................ 36
4.12 Pump Motors.......................................................................... 36
4.13 Pump Margin and In-Service Testing..................................... 37
4.14 Potential Improvements in the Engineering of Cooling
Water Pumps�������������������������������������������������������������������������� 37
References.......................................................................................... 39
Nomenclature��������������������������������������������������������������������������������������������������������� 149
Index���������������������������������������������������������������������������������������������������������������������� 153
Preface
Although this book draws heavily on lessons learned from the authors’ experience in
the nuclear power industry, they are equally applicable to many other types of power
plants as well as to industrial plants. From 1945 to 1975, when most of the existing
electric power plants were designed and constructed, engineering of the plant cooling
water system was considered a low priority item. These systems made little or no
contribution to the actual production of electricity and their failures rarely resulted in
a plant outage. Established engineering handbooks such as the Cameron Hydraulic
Data Book and the Hydraulic Institute Standards were employed in a cook book
fashion to arrive at more-or-less standard designs. All of that started to change as the
current fleet of nuclear power plants began operating in the 1960s and 70s.
The Tennessee Valley Authority (TVA) entered the nuclear power industry in
1966 by beginning construction of Unit 1 of the Browns Ferry Nuclear Plant, an
essentially turnkey 1,100 MWe boiling water reactor plant designed by General
Electric. The TVA fleet was expanded with the start of construction of Unit 1 at
Sequoyah (1970), followed by Watts Bar Unit 1 (1973). In September 1973, the TVA
Division of Engineering Design was reorganized with design projects dedicated to
each nuclear project and engineering branches to support the projects. As part of that
reorganization, Charles F. (Chuck) Bowman, a graduate of the University of
Tennessee (BSME in 1964 and MSME in 1966), was selected to supervise a section
in the Mechanical Engineering Branch that was responsible for engineering the cool-
ing water systems for all of the TVA nuclear plants. Chuck is indebted to the out-
standing engineers who worked for him during that period and developed much of
the technology described herein. In 1986, he was promoted to be the corporate spe-
cialist for thermal performance and cooling water systems, supporting all seven of
the TVA operating nuclear units.
In 1976, when Chuck reviewed the results of preoperational flow tests conducted
on Browns Ferry Unit 1, he realized that these systems had major problems. The tests
showed that critical heat exchangers were not receiving the required cooling water
flow. What followed was years of learning lessons of how to deal with issues such as
microbiologically induced corrosion and Asiatic clams. Based on his experience and
that of others, a better way of engineering these systems for both nuclear and fossil
power plants as well as industrial plants is possible in the future.
In 1994, Chuck retired from the TVA to form Chuck Bowman Associates, Inc.,
serving the electric power industry and specializing in cooling water systems and the
analysis and testing of pumping systems, heat exchangers, cooling towers, spray
ponds, etc., as well as the thermal aspects of turbine cycle systems. The purpose of
this book is to impart to the next generation knowledge and experience received dur-
ing more than 50 years of working in the field of cooling water systems.
The term cooling water systems (sometimes referred to as service water systems)
refers principally to the systems required to cool the many heat exchangers used in
all power and industrial plants. Although many of the lessons learned also apply to
the large condenser circulating water system that condenses the steam coming from
the main condenser, that system is not the primary emphasis of this book.
xi
Authors
Charles F. (Chuck) Bowman, P.E., is the president of Chuck Bowman Associates,
Inc. (CBA), an engineering consulting firm serving the electric power industry since
1994. Chuck received his BS and MS degrees in Mechanical Engineering from the
University of Tennessee, and he is a registered professional engineer in Tennessee.
CBA specializes in engineering analysis of electric power generating cycles and
related fields including the design and analysis of heat exchangers, cooling towers,
spray ponds, cooling water systems, etc. Before forming CBA, Chuck was with the
Tennessee Valley Authority (TVA) for 28 years where he supervised the engineering
of the cooling water systems for all of the TVA nuclear plants. Prior to his retirement
from TVA, he was the senior engineering specialist for thermal performance and
cooling water systems in TVA’s Corporate Engineering Office. Chuck has served as
a consultant to the Electric Power Research Institute (EPRI). He is the author of
EPRI Report No. 1007248, Alternative to Thermal Performance Testing and/or Tube-
Side Inspections of Air-to-Water Heat Exchangers; EPRI Software Manual No.
3002005344, Turbine Cycle Equipment Evaluation Workbook, and was a paid
reviewer of EPRI Report No. 1021065, Heat Exchanger Performance Analysis.
Chuck serves on the American Nuclear Society (ANS) Working Group ANS 2.21,
Criteria for Assessing Atmospheric Effects on the Ultimate Heat Sink, and has served
on American Society of Mechanical Engineers (ASME) committees that authored
ASME PTC 23.1 – 1983, Code on Spray Cooling Systems and ASME PTC 12.5 -
2000, Single Phase Heat Exchangers and is a contributing editor to Marks’ Handbook,
12th Edition. His most recent publication is Thermal Engineering of Nuclear Power
Stations: Balance-of Plant Systems, published by CRC Press.
Seth N. Bowman received his BS and MS degrees in Chemical Engineering from the
University of Tennessee. He currently serves as the senior manager of the corrective
action program at the Y-12 National Security Complex, managed and operated by
Consolidated Nuclear Security, LLC. In prior roles, Seth has been responsible for the
assessment function for the Engineering Division at Y-12 and also served as a shift
technical adviser and shift manager for Building 9212. He is co-author of Thermal
Engineering of Nuclear Power Stations: Balance-of Plant Systems, published by
CRC Press.
xiii
List of Abbreviations and
Acronyms
ACRS Advisory Committee on Reactor Safeguards
ASME American Society of Mechanical Engineers
AWHX air-to-water heat exchanger
AWWA American Water Works Association
BCDMH bromochlordimethylhydantoin
BFNP Browns Ferry Nuclear Plant
BTA best technology available
C Colbert
CCW condenser circulating water
CFU colony-forming units
CGS Columbia Generating Station
CML cement-mortar lining
CP&L Carolina Power & Light
CPP concrete pressure pipe
CS carbon steel
CU Cumberland
CWA Clean Water Act
EECW emergency equipment cooling water
EPA Environmental Protection Agency
ERCW essential raw cooling water
FBSP flat bed spray pond
FRP fiberglass-reinforced plastic
G Gallatin
HDPE high density polyethylene
HX heat exchanger
HXs heat exchangers
IAM Institute for Applied Microbiology
IN Information Notice
INPO Institute of Nuclear Power Operations
IPS intake pumping station
JS John Sevier
K Kingston
MC main condenser
MIC microbiologically induced corrosion
MPY mils per year
NDCT natural draft cooling tower
NDE nondestructive examination
NPDES National Pollution Discharge Elimination System
NRC Nuclear Regulatory Commission
OSCS oriented spray cooling system
xv
xvi List of Abbreviations and Acronyms
1.1 BACKGROUND
The overall operating and safety record of the existing nuclear industry is outstand-
ing, but as one will see in this introductory chapter, the record of the engineering of
the cooling water systems has been less than sterling, as indicated by the public
records maintained by the Nuclear Regulatory Commission (NRC). The purpose of
this chapter is not to point fingers or rehash old problems but to learn from them so
that the engineering of future industrial and electric power plants, both fossil and
nuclear, will not repeat the same mistakes.
licensees of a problem of high vibration levels on one of the cooling water pumps at
the Grand Gulf Nuclear Station. Disassembly of the pump showed extensive corrosion
of the carbon steel (CS) bolts and lock washers used in the pump shaft coupling
assembly. A survey of cooling water pump failures conducted by Operating
Experience Digest between 1998 and 2005 reported more than one failure per year,
with several nuclear plants experiencing more than one failure. The most frequent
cause was reported to be corrosion of shaft and/or bolting material. Pump performance
degradation occurs due to normal wear, requiring clearance adjustments or overhaul
of the pump impeller/bowl assembly.
• Fitzpatrick Nuclear Plant, debris caused shear pins on both screens to fail and
causing the screen to bow inward and allowing some of the debris to pass
around the screens
• Millstone Nuclear Plant Unit 1, debris caused three of the five screens to collapse
• Arkansas Nuclear One, debris caused the screens to fail causing the screen to
bow inward and allowing the debris to pass around the screens, clogged strain-
ers on the discharge of the cooling water pumps on both operating loops.
More recently, nuclear plants have reported a large ingress of marsh grass at Hope
Creek and Oyster Creek Generating Stations, a massive algae problem at Pickering
Nuclear Plant, and frazil ice blocking the intakes of other plants. (Frazil ice is a
collection of loose, randomly oriented ice crystals formed in supercooled turbulent
water.) Clearly, the current design of intake structures makes them vulnerable to site-
specific intake blockage scenarios.
Introduction 3
cooling units at Unit 1 of the Arkansas Nuclear One, due to plugging of the heat
exchanger (HX) by Asiatic clams (Corbicula). Also in 1981, the NRC issued
IN 81-2114 to report on a growth of some form of sea mollusk that was discovered on
the cooling water piping serving the component cooling HX in Unit 1 at the San
Onofre Nuclear Generating Station. The mollusks impaired movement of the but-
terfly valves used to isolate the HX, reduced the cross-sectional diameter of the cool-
ing water piping, and blocked the HX tubes. As a result, the cooling water flow rate
to the HX was reduced. In that same year, the NRC issued IN 81-2114 to report that
the baffle plate in the U-tube type residual heat removal HX at Unit 1 of the Brunswick
Nuclear Plant was damaged, allowing the cooling water to bypass the tube bundle. A
flow test indicated that the HX was unable to remove the decay heat because oyster
shells had blocked the inlet side of the HX tubes. Similar events occurred with the
reactor building closed cooling water HX at the Pilgrim Nuclear Power Station. In
1986, the NRC issued IN 86-9615 to report that the HXs cooling the gearbox on the
charging pumps that are part of the emergency reactor core cooling system at Unit 1
of the Farley Nuclear Plant failed to adequately cool the gearboxes, causing them to
overheat due to silt in the cooling water system. A similar event occurred at Unit 2 of
the Salem Nuclear Power Plant.
In 1988, the NRC issued IN 88-3716 to report that when Unit 2 of the Catawba
Nuclear Plant was at 20% power after the first refueling outage, the feedwater
regulating valve failed open, causing a main turbine to trip off line due to a high-high
level in one of the steam generators. When both auxiliary feedwater pumps started
automatically, low suction pressure resulted in an automatic swap over to the cooling
water system, resulting in raw cooling water (RCW) from Lake Wylie being pumped
into the steam generators. When the water level in the steam generators dropped to
their low-low level set point, the reactor tripped automatically. After normal feedwater
flow was established, the auxiliary feedwater control valves were found to be clogged
with Asiatic clams. A similar event occurred at the Davis-Besse Nuclear Power
Station in 1985. Catawba has also experienced serious corrosion and debris buildup
in their cooling water system, challenging the ability of the system to provide the
required flow during an accident.
In 1989 the NRC issued IN 89-7617 concerning a presentation at an EPRI confer-
ence by representatives of the Ontario Ministry of the Environment, Detroit Edison
Company, and the U.S. Fish and Wildlife Service on zebra mussels. Bio-fouling due
to zebra mussels was observed at several power plants, water treatment plants, and
industrial facilities along Lake Erie where they threatened operation of the condens-
ers and cooling water and fire protection systems.
Also in 1989, the NRC issued IN 90-3918 to report on inadequate cooling water
flow to safety-related HXs at several nuclear stations. At the Farley Nuclear Plant,
flow was inadequate to certain safety-related HXs and required operator action. At
the Peach Bottom Power Plant, Unit 2, flow was found to be inadequate due to the
accumulation of silt and corrosion products in the cooling water piping. At Fitzpatrick
Power Plant, silt was found in check valves in the cooling water system lines to the
seal water coolers for residual heat removal pumps that could have prevented the
system from performing its safety function.
Introduction 5
flow would result in hydrodynamic loads due to water hammer that would exceed the
piping and piping support structural limits.
1.9 NRC OVERSIGHT
In 1981, the NRC issued Bulletin 81-0313 to require nuclear plant licensees to deter-
mine whether or not Asiatic clams or other mussels were present in their cooling
water systems and if present to confirm that the individual components were receiv-
ing adequate cooling water flow. The response to that bulletin indicated that bivalves
were present in approximately 45% of the nuclear plant sites in the United States.
Serious fouling was reported at several sites as indicated above. Up until that time,
some nuclear stations had not ever verified that the HXs were receiving adequate
cooling water flow.
In 1988, the NRC published NUREG 1275. Vol. 3,23 a comprehensive review and
evaluation of cooling water system failures and degradations reported in nuclear
plants from 1980 to 1987. The report identified 29 events involving significant degra-
dation or failures of the cooling water system, an average of 3.6 events a year.22
In 1989, the NRC issued Generic Letter 89-132 requiring nuclear plant licensees
to do the following:
It should be noted that Generic Letter 89-13 did not require the nuclear plants to
conduct flow balance tests of their cooling water systems. For example, in 1990,
when Clinton Power Station measured the actual flows to their room coolers, they
found that the flows were from 10% to 80% less than the design flows.21 Flows to
other HXs ranged from 2% to 42% less than the design flows, while other components
served by the cooling water system were receiving excess flow up to 213% of the
design value.21
Introduction 7
In 1992, the NRC issued Temporary Instruction 2515/11824 and initiated a pro-
gram of conducting operational performance inspections of the cooling water sys-
tems for nuclear plants the United States. The inspections included a review of the
mechanical systems engineering design and configuration control and nuclear plant
operations, maintenance, and testing and quality assurance (QA)/corrective actions.
Although the findings of these inspections are too numerous to enumerate here, they
did instill in the nuclear industry an awareness of the importance of cooling water
systems to nuclear safety. Additional inspections are ongoing.
In 2007, the NRC issued IN 2007-06 25 to report on potential common cause vul-
nerabilities in essential cooling water systems. Two of the nuclear stations were out-
side the United States. In the first such case, a manhole pipe broke; in the second a
cooling water pipe ruptured, flooding the piping gallery with sea water. In the United
States, a 3 gallons per hour through-wall leak in a 30-inch (76.2 cm) pipe was found
at Unit 2 of the South Texas Project due to cavitation damage downstream of a heav-
ily throttled butterfly valve, and a through-wall leak was found in the endbell of one
of the emergency diesel generator HXs due to MIC.
1.10 AUTHORS’ PERSPECTIVE
Over the years, workable solutions to many of the deficiencies in the engineering of
cooling water systems have been developed by the authors and others, but in many
cases, these solutions have not been widely disseminated. It is the hope of the authors
that this book will aid in imparting to the next generation the knowledge and experi-
ence gained during more than 50 years of working in the field of cooling water
systems.
REFERENCES
1. IN 94-45. Potential Common-Mode Failure Mechanism for Large Vertical Pumps,
Nuclear Regulatory Commission, Washington, D.C., 1994.
2. Generic Letter 89-13. Service Water System Problems Affecting Safety-Related
Equipment, Nuclear Regulatory Commission, Washington, DC, 1989.
3. IN 92-49. Recent Loss or Severe Degradation of Service Water Systems, Nuclear
Regulatory Commission, Washington, DC, 1992.
4. Bulletin 80-24. Prevention of Damage Due to Water Leakage Inside Containment
(October 17, 1980 Indian Point 2 Event), Nuclear Regulatory Commission, Washington,
DC, 1989.
5. IN 85-30. Microbiologically Induced Corrosion of Containment Service Water System,
Nuclear Regulatory Commission, Washington, DC, 1985.
6. IN 94-79. Microbiologically Influenced Corrosion of Emergency Diesel Generator
Service Water Piping, Nuclear Regulatory Commission, Washington, DC, 1994.
7. Generic Letter 90-05. Guidance for Performing Temporary Non-Code Repair of ASME
Code Class 1, 2, and 3 Piping, Nuclear Regulatory Commission, Washington, DC,
1990.
8. IE IN 83-46. Common-Mode Valve Failures Degrade Surry’s Recirculation Spray
Subsystem, Nuclear Regulatory Commission, Washington, DC, 1983.
8 Engineering of Power Plant and Industrial Cooling Water Systems
2.1 TEMPERATURE
There are four temperature scales in common use, two in English units and two in
standard international (SI) units, The English units are degree Fahrenheit (°F) and
degree Rankine (°R). The SI units are degree Celsius (°C) and degree Kelvin (°K).
Figure 2.1 shows the temperatures in English units.
Figure 2.2 shows the temperatures in SI units. Virtually all engineering of cooling
water systems is performed in either Fahrenheit or Celsius units. The formula for
converting from SI units to English units is shown in Equation 2.1
F 1.8 C 32 (2.1)
2.2 PRESSURE
As seen in Figure 2.3, pressure may be measured in three different ways: (1) gauge
pressure (i.e. pressure above atmospheric pressure), (2) vacuum pressure (i.e. pres-
sure below atmospheric pressure), and (3) absolute pressure (i.e. pressure above zero
pressure or a perfect vacuum).
Perhaps one of the most common mistakes made in any power plant is confusing
gauge pressure with absolute pressure. Most gauges inside a power plant measure
absolute pressure. Since the turbine cycle is isolated from the atmosphere, gauge
pressure is largely irrelevant. Also, the properties of steam and condensate in a
turbine cycle are related to absolute pressure. However, there may be the odd gauge
212 ºF
32 ºF
0 ºF
–459.67 ºF
0 ºR (absolute zero)
9
10 Engineering of Power Plant and Industrial Cooling Water Systems
100 ºC
-273.15 ºC
0 ºC (absolute zero)
Pressure
Gauge pressure
Vacuum pressure
Zero pressure
that reads in gauge pressure. There also may be an occasional instrument that mea-
sures vacuum. Be warned! In dealing with cooling systems, almost all instruments
read gauge pressure. The units lbf/in2 (English) and kPa (SI) refer to gauge pressure
herein. As will be seen later, much of the hydraulic analysis of cooling water systems
is performed in units of “head” in feet of water. For most cooling water systems,
1.0 lbf/in2 is equal to 2.31 ft of head.
2.3 DENSITY
The properties of water, whether in the form of ice, liquid, or steam, depend on the
state of the water and are independent of the path that was taken to achieve the state.
For example, the properties (e.g. temperature, pressure, etc.) of a volume of liquid
water are independent of whether it was condensed in a cloud or melted from ice.
Properties may be either extensive or intensive. For example, a bucket of water
Properties of Water 11
having a mass (the amount of matter contained in a substance), volume, pressure, and
temperature might be divided equally into two buckets. The water in each bucket
might still have the same pressure and temperature, but the mass and volume in each
bucket would be one half of that contained in the original bucket. The mass and vol-
ume are said to be extensive properties, while the pressure and temperature are said
to be intensive properties, because they are the same for each small element of water
in the bucket. However, as shown in Equation 2.2, if one divides the mass by the
volume, one gets density (an intensive property).
m
(2.2)
V
where
ρ = density
m = mass
V = volume.
2.4 VISCOSITY
The viscosity of water flowing in a pipe is a measure of its resistance to flow. There
are two measures of viscosity: dynamic (or absolute) and kinematic. Water is said to
be a “Newtonian” fluid, meaning that its dynamic viscosity is a function of tempera-
ture alone. Dynamic viscosity is used to calculate the Reynolds number and Prandtl
number of water. Kinematic viscosity is simply the dynamic viscosity divided by the
density of the water. Dynamic viscosity is an indication of the pressure drop required
to pass the water through a pipe, and kinematic viscosity is an indication of how fast
the water is moving when that pressure is applied.
2.5 REYOLDS NUMBER
The Reynolds number of flow in a pipe is a non-dimensional property characterizing
the flow as laminar or turbulent. The Reynolds number depends on the liquid veloc-
ity, the viscosity, and the pipe diameter and is calculated as follows:
Vp di
Re (2.3)
where
Vp = water velocity in a pipe or tube
di = inside diameter of a pipe or tube
μ = dynamic viscosity of the water.
Figure 2.4 shows the Moody diagram relating the Reynolds number to the friction
factor.1 If the Reynolds number is less that 2000, the flow is said to be laminar. If the
number is greater than 4000, it is said to be turbulent in the pipe or tube. Between
12 Engineering of Power Plant and Industrial Cooling Water Systems
these values, transitional flow exists. If one knew the relative roughness of the pipe,
one could calculate the pressure drop. Unfortunately, for CS cooling water piping,
determining the relative roughness is a function of the tuberculation that frequently
occurs in the pipe due to MIC, etc. In that case, the only major benefit derived from
the Moody diagram is to verify that the flow is turbulent. Although in piping systems
the flow is almost always turbulent, in some HX applications the flow may be lami-
nar, affecting both the pressure drop through the HX and the rate of heat transfer.
2.6 PRANDTL NUMBER
The Prandtl number is a key parameter in determining heat transfer in a HX. The
Prandtl number is defined as the ratio of the momentum diffusivity to the thermal
diffusivity and depends on the dynamic viscosity, specific heat, and thermal conduc-
tivity of the water and is calculated as follows:
cp
Pr (2.4)
k
where
Pr = Prandtl number
cp = specific heat
k = thermal conductivity of water.
Properties of Water 13
2.7 SPECIFIC GRAVITY
The specific gravity of water is the ratio of the density of water at a given temperature
to that of water at a reference temperature. In English units, the reference tempera-
ture is 60°F (15.6°C), and the density of water is 62.36 lb/ft3 (1,000 kg/m3).
REFERENCE
1. Moody, L. F., Friction Factors for Pipe Flow. ASME Transactions, Vol. 66, pp. 671–684,
1944.
3 Intake Structures
VS
FD = (3.1)
gD
where
FD = Froude number
VS = velocity at suction inlet
D = pump bell diameter
g = gravitational constant
Smin D 1 2.3 FD
where the units must be consistent to yield a dimensionless Froude number and S is
in the same units as D.
Although among pump types and manufacturers there may be some variation in
the bell velocity (i.e. flow rate divided by the pump bell area), this is of secondary
importance, since basing the dimensions on the pump bell diameter would ensure
geometric similarity of flow patterns.1
The intake should supply an evenly distributed flow of water to the suction bell, as
an uneven distribution of flow may result in vortices that may introduce air into the
pump, resulting in reduced pump capacity.1 The amount of submergence for success-
ful operation depends upon the design of the approach to the pump intake and the
size of the pump.1 Dimension “H” is based on “minimum normal water level”, taking
into consideration normal operating friction losses through intake channel, trash
rack, and the traveling screen.1
If the bottom elevation of the sump must be below the source of the cooling water
to meet submergence requirements, the slope of the floor of the intake structure
should not be greater than 10 degrees.1
15
16 Engineering of Power Plant and Industrial Cooling Water Systems
W/2
W
A
Trash
Sluice
A
Plan View
A
Y
H S
B
D
C
Elevation View
TABLE 3.1
Sump Dimensions as a Function of Pump Bell Diameter
Dimension Number of Diameters
A 5D
B 0.75D
C 0.3D to 0.5D
H S+C
S See Equation (3.1)
Y 4D
TABLE 3.2
Sump Dimensions vs. Pump Flow
Dimension Pump Flow Sump Dimension Pump Flow Sump
(gal/min) (in) (gal/min) Dimension (in)
A 3,000 87 10,000 165
B 3,000 14 10,000 26
C 3,000 13 10,000 19
H 3,000 41 10,000 58
W* 3,000 34 10,000 61
Y 3,000 60 10,000 108
Assuming a pump bell velocity of 5.0 ft/sec ( 1.524 m/s), the sump dimensions in
Table 3.2 are in good agreement with those calculated from Table 3.1 with the excep-
tion of the value for C, which is considerably higher than that calculated from
Table 3.1 for 3,000 and 10,000 gal.min pumps (208% and 166%, respectively).
Of course many if not most IPS are considerably more complex than that shown
in Figure 3.1. In many cases, a single IPS houses both the CCW pumps and the cool-
ing water pump and may also house high pressure fire protection pumps and service
water pumps. Figure 3.2 illustrates such an IPS.
Preferably water should not flow past one pump to reach the next pump.3 If such
an arrangement is required, dividing walls should be located around each pump to
provide conditions similar to those in Figure 3.1, and/or turning vanes may be
required under the pump to deflect the water upward.3
18 Engineering of Power Plant and Industrial Cooling Water Systems
FIGURE 3.2 Intake pumping station with CCW pumps and cooling water pumps.
The screening material in many existing traveling water screens are of CS that has
been in service for decades. The ability of these screens to withstand the forces
resulting from a significant challenge is questionable.
commonly proposed, is to modify or replace the existing traveling water screens with
screens designed to minimize fish impingement onto the screens. However, the Rule
specified that if the NPDES permit director determines that the modified screens are
insufficient, additional measures may be required. This option may pose greater
challenges for the reliability of the cooling water system. In a report dated November
2001, the EPA reviewed the efficacy of alternatives to conventional traveling screens
for cooling water intake structures including the following:
The EPA reported that conventional traveling screens used by approximately 60% of
power plants have 3/8-inch (0.9525 cm) mesh wire to prevent clogging of HX tubes
with screen wash at a typical pressure between 80 and 120 lbf/in (552 and 827 kPa).6
These screens are normally rotated and washed only intermittently, so fish that are
impinged on the screens by high intake velocity for extended periods of time die
there or are killed by the high-pressure wash when the screens are operating.5
Ristroph screens are conventional traveling screens that have been modified with
baskets or buckets on the front of the screens as shown in Figure 3.3 to hold fish in
the water until the screen rotates to a point where the fish are spilled onto a trough
where they are sluiced along with any trash back into the source water.6 Of course,
the screens should be continuously operating when large numbers of fish are present.
free CCW that was available from rivers, lakes, and oceans. The economic optimum
design was a high-flow, low head, system with a single-pressure MC designed with
minimal surface areas. Therefore, the potential may exist to reduce the required CCW
flow to existing power plants by redesigning and modifying the existing CCW system
to minimize intake flow based on current technology. The result could be a new
and improved MC and other turbine cycle equipment and perhaps new CCW pumps
and/or turbine rotors, resulting in the same or better plant performance. The following
is taken from Reference 9 where “NDCT” stands for “Natural Draft Cooling Tower”.9
“Alternative C – Refurbish the existing two NDCT and convert the existing MC
into a multi-pressure condenser.
Alternative C would also require the refurbishment of the existing two NDCTs.
However, in lieu of an expensive third NDCT, the existing MC would be recon-
figured such that the CCW flow through the three shells of the MC would be in
series rather than in parallel. The existing 10 foot square pressure equalizing
ducts between the three shells would be blocked, making it a multi-pressure
condenser. The CCW flow through the MC would be reduced by one-third and
the velocity through the 0.75-inch (1.91 cm) titanium tubes would be increased
from 5.5 to 10.9 ft/sec. To accommodate the higher pressure drop through the
MC tubes, the CCW Pumps would be replaced with higher head pumps and
motors. A new transformer would be provided to serve the larger motors. To
accommodate the higher head pumps, 10 foot diameter cement mortar-lined CS
piping would be installed inside of the existing 13.5’ × 13.5’ concrete conduits
between the IPS and the MC. By reducing the CCW flow rate by one-third, the
water loading on the existing NDCT would be reduced. Even though the tem-
perature rise through the MC would be increased and the hot water temperature
would be greater, the cold water temperature coming from the NDCT would
be less. For a NDCT, the hot water temperature has only a small effect on the
cold water temperature, as a higher hot water temperature increases the air flow
through the tower. The overall reduction in electrical output of this alternative is
41 MWe per unit per year or 3.5%.
Skimmer walls across the intake channel that restrict intake flow to the bottom of the
channel can achieve similar results at some locations. Continuous operation of a
traveling water screen as required with fish baskets or buckets protects the cooling
water system from unexpected events that can quickly overcome the intake.
Figure 3.5 illustrates several modifications to the wet-pit intake structure shown in
Figure 3.1. The following enhancements are proposed:
W/2
W
A
A
Y
H S
B
D
C
Elevation View
• In areas where frazil ice is a hazard, design the IPS to accept recirculated warm
water from the condenser discharge;
• Provide redundant screen wash pumps so that the cooling water system is not
vulnerable to challenges when one pump or motor is out of service and so that
the second screen wash pump may be started to increase screen wash flow if
required during an intrusion;
• Provide automatic backwashing cooling water strainers at the discharge of the
cooling water pumps to strain out all but larvae, veligers (larval with ciliated
flaps for swimming) and fish eggs, etc.;
• Increase cooling water pump submergence such that the pumps would con-
tinue to operate satisfactorily even when the structural design maximum dif-
ferential pressure across the traveling screens is reached;
Intake Structures 25
REFERENCES
1. American National Standard for Pump Intake Design, ANSI/HI 9.8-1998, Hydraulic
Institute, Parsippany, NJ, 1998.
2. Greutink, Herman. Recommendations for Vertical Pump Intakes, Pumps and Systems
Magazine, Birmingham, AL, November, 1994.
3. Hydr aulic Institute Standards for Centrifugal, Rotary, and Reciprocating Pumps, 14th
ed., Hydraulic Institute, Parsippany, NJ, 1983.
4. Russell, Ray. EPA’s 316(b) Rule: Are You Ready? Power Engineering, September 2013.
5. 40 CFR Part 122 and 125, National Pollution Discharge Elimination – Final Regulations
to Establish Requirements for Cooling Water Intake Structures at Existing Facilities and
Amend Requirements at Phase I Facilities, Environmental Protection Agency,
Washington, DC, May 9, 2014.
6. Technical Development Document for the Final Regulations Addressing Cooling Water
Intake Structures for New Facilities, EPA-821-R-01-036, Chapter 5, Environmental
Protection Agency, Washington, DC, November, 2001.
7. Clubb, Richard. When Budgeting for §316(b) Compliance, Consider All Options. Power
Engineering Magazine, Tulsa, OK, March 2013.
8. Bowman, C. F. The Third Option for Meeting 316(b) Requirements, Power 2014-32113,
Proceedings of the ASME 2014 Power Conference, Baltimore, MD, July 2014.
9. Sequoyah Nuclear Plant §316(b) – §122.21(r)(10) – (13) Information, Appendix A to
Transmittal from TVA to Tennessee Department of Environment and Conservation, June
29, 2018.
4 Pumps
4.1 TYPES OF PUMPS
Cooling water and CCW system pumps may be classified as either vertical wet pit
pumps as described in Chapter 3 or dry-pit pumps as discussed in Section 1.2. In
power plants with open once-through CCW systems, the CCW pumps are typically
of the vertical wet pit type as shown in Figure 3.2. In some power plants with cooling
towers, the CCW pumps may be arranged as dry-pit pumps with the shaft and motor
mounted either horizontally or vertically as shown in Figure 13 in Reference 1.
Cooling water system pumps that are supplied from a lake, river, or ocean, etc., as
shown in Figures 3.1 and 3.5 are of the vertical wet pit type. However, in some power
plants, the cooling water pumps take suction from the CCW pumps and are horizon-
tal pumps located inside the turbine building.
adjustment. Initially, the impeller rests on this seat, and the clearance is adjusted to
allow for the line shaft to stretch while maintaining a close clearance during opera-
tion. The impeller clearance is adjusted by means of an adjusting nut at the top of the
motor. However, if the line shaft and the pump column are of different materials, this
clearance can easily come out of adjustment due to cooling water temperature
changes. By contrast, the wear ring encloses a closed impeller in the vertical direc-
tion which is free to move up and down slightly due to changes in the cooling water
temperature as the line shaft expands or contracts relative to the pump casing.
However, whereas the clearance between a semi-open impeller may be adjusted to
compensate for wear, the same is not true with a closed impeller.
Figure 4.3 shows a cooling water pump with a semi-open impeller on the left and
a CCW pump with a propeller on the right.
Pumps 29
FIGURE 4.3 Vertical wet pit cooling water and CCW pumps. (Courtesy of Johnston
Pump Co.)
4.3 SPECIFIC SPEED
The specific speed of an impeller, n, is defined as the revolutions per minute at which
a geometrically similar impeller would run if it were of such a size as to discharge
one gallon per minute against one foot of head. Specific speed is a parameter used to
select the type of pump that is best suited to a particular application and to check
suction limitations of the pump.2,3 The shape of the pump impeller producing maxi-
mum efficiency is a function of the specific speed as defined by Equation (4.1).1
1
NQ 2
n = 3
(4.1)
H 4
where
N = rototional speed, rev/min
Q = flow rate, gal/min
Η = total head, ft.
30 Engineering of Power Plant and Industrial Cooling Water Systems
Figure 4.4 shows the various pump impeller profiles as a function of specific speed.
The following shows the type of impeller that would yield the best efficiency for
the indicated range of specific speeds in English units1:
Typical cooling water pumps with flow rates of from 1,000 to 10,000 gal/min
would achieve maximum pump efficiency at a specific speed of approximately
3,000.1,2 A centrifugal pump impeller may be replaced with a smaller or larger impel-
ler in the same bowl size, within limits.4
1 1
NQ 2 NQ 2
s 3
3
(4.2)
NPSHA 4
NPSHR 4
where
NPSHA = net positive suction head available, ft.
NPSHR = net positive suction head required, ft.
Pumps 31
The available value of “s” must equal or exceed that required value in order to
prevent cavitation. A high value of “s” at the operating point of maximum efficiency
indicates a good suction design.
For a vertical wet pit pump, NPSHA may be calculated as in Equation (4.3)
NPSHA Pb S Pv (4.3)
where
Pb = barometric pressure
S = submergence
Pv = vapor pressure at the cooling water temperature.
NPSHR is dictated by the pump design and is specified by the pump manufac-
turer. (See Figure 4.5 below.) A reasonable suction specific speed is 8,500 rev/min.2
50
30
20
10
0
0 50000 100000 150000 200000
CCW Flow Rate (gal/min)
Q H s.g.
BHP (4.4)
3960 p
where
s.g. = specific gravity of the cooling water
ηp = pump efficiency.
34 Engineering of Power Plant and Industrial Cooling Water Systems
240
200
69%
Total Head [ft]
7.5" Dia.
160
8.375" Dia.
12 BHP
14 BHP
120 16 BHP
50% Eff.
55% Eff.
60% Eff.
80 63% Eff.
65% Eff
67% Eff.
40
0 40 80 120 160 200 240 280 320 360 400
U. S. Gallons per Minute
FIGURE 4.7 Pump head and efficiency curves. (Courtesy FLOWSERVE Pump Division).
TABLE 4.1
Values of K for Equation (4.5)3
Pump Efficiency (%) SI Units English Units
70 1726 9.4
80 1210 6.3
90 796 4.3
Pumps 35
4.10 AIR VENTING
As shown in Figures 3.1 and 3.5, a check valve is normally located at the discharge
of a wet pit vertical turbine-type cooling water pump to prevent the entire cooling
water system from draining down each time a pump is stopped. When the pump
stops, normal practice is to bleed air into the pump column through a float-type air
release valve or through an inverted check valve as shown in the figures. When the
pump is restarted, the air in the pump column is gradually released through this valve
to control the rise of water in the pump column to avoid a water hammer as the col-
umn of water hits the closed check valve. (See Chapter 8.) Care must be taken in
sizing the air release mechanism, since if it vents the air too slowly, the remaining air
will pass through the discharge check valve with the water, and if too quickly, a water
hammer may occur. Although a float-type air release valve or inverted check valve of
suitable size may be available, most likely the correct air flow would be dictated by
an appropriately sized orifice as shown in the figures. The mass flow rate of air may
be determined by the volumetric flow rate of the pump at rated conditions times the
density of air. Equation (4.6) from Page 3–24 of Reference 7 shows the relationship
between the mass flow rate of air as a function of the diameter of the orifice in
English units.
where
w = mass flow rate of air, lbm/sec
Y = expansion factor (See Page A-21 of Reference 7)
d1 = orifice diameter, inches
C = orifice flow coefficient
ΔP = pressure drop across the orifice, lbf/in2.
The size of the piping and valves up stream of the orifice should be such that the
pressure drop through them should be no more than approximately 10% of the pres-
sure drop through the orifice.
36 Engineering of Power Plant and Industrial Cooling Water Systems
In an open CCW system, the siphon through the condenser is normally main-
tained when the CCW pumps are stopped. Refilling the system and reestablishing
condenser vacuum is a long and laborious process, so the system would not be
allowed to drain down by continuing to operate the condenser vacuum priming
pumps. The condenser vacuum is maintained by continuing to operate the condenser
vacuum pumps. If it becomes necessary to allow the water to drain from the MC, it
would be refilled by throttling the condenser discharge valves to raise the hydraulic
gradient sufficient to fill the condenser tubes as air is vented through the vacuum
priming system to control the rate at which the water rises in the tubes to avoid a
water hammer. (See Chapter 8.)
4.12 PUMP MOTORS
The required pump motor rated horsepower is defined in Equation (4.7).
BHP
MHP (4.7)
m
where
MHP = motor horsepower
ηm = motor efficiency.
The motor efficiency is typically 95%.
The cooling water system pump motor should be sized so that the MHP require-
ment is not exceeded at any point over the normal operating range. The service factor
of a motor is an indication of how much the nameplate rating of the motor may be
exceeded for short periods of operation.
The type of motor depends on the function of the cooling water system. Safety-
related cooling water pump motors are normally Nuclear Class 1E, totally enclosed,
with a service factor of 1.0. Non-safety-related cooling water pump motors are
normally National Electric Manufacturers Association MG1, open and drip-proof,
but if the cooling water system is an outdoor installation, the pump motor should be
weatherproof. The service factor for these pumps is normally 1.15. Motor cooling
water lines (if required) should be self-draining to preclude freezing.
Pumps 37
275.00
270.00 269.46
268.35
267.37
265.00
264.12 263.90
Head, feet of water
262.15
260.00 259.97
258.35 258.32
257.61 257.88
256.40 255.35
255.80 255.30
255.00 254.67
254.15
252.51 252.99
252.01
252.98
250.00 249.88
248.37
247.76
247.79 247.84 246.63
245.27
245.00 243.22 243.64 244.11
244.34
243.38 243.88 244.60
242.74 243.19242.74
243.09 243.22
242.27 241.16 240.62 240.87
240.00 240.46
240.64
238.12 237.38
237.15 236.70
236.02 235.54
235.00
230.00
07/03/1995 11/14/1996 03/29/1998 08/11/1999 12/23/2000 05/07/2002 09/19/2003 01/31/2005 06/15/2006 10/28/2007
Date of Test
FIGURE 4.8 Inservice test results for a cooling water pump at a flow rate of 9,500 GPM.
• The ability to test cooling water pumps is essential to diagnosing pump dete-
rioration and correcting problems. Therefore, provisions should be made in the
design of the cooling water system to be able to periodically test the pump.
These provisions should include means to measure the flow rate and to calcu-
late the total head of the pump and to provide a flow path capable of testing
near the normal flow rate.
• Prelubrication of vertical wet pit mixed flow pumps should be provided from
either down stream of the strainer shown in Figure 3.5 or from a separate seal
water system.
• Small water lines such as those required to provide prelubrication and cooling
water pump motor cooling should be protected by appropriate insulation
and/or heat tracing.
• If a semi-open impeller is employed, the line shaft and the pump column
should be of the same material. If the line shaft is of CS, disassembly can be
very difficult due to corrosion. Therefore, both the line shaft and the pump
column should be of SS.
• Considering the corrosive and erosive nature of RCW, serious consideration
should be given to employing SS materials for the pump bowl, impeller, col-
umn, line shaft, and discharge head. (See Chapter 6.)
Pumps 39
• Specify the appropriate heat treatment for each part to prevent stress corrosion
cracking.
• For pumps in unfavorable sump configurations, consider employing features
such as straightening vanes on the pump suction.
REFERENCES
1. Linsley, R. K. et al. Water-Resources Engineering, 4th ed., pp. 416–423, McGraw-Hill,
Inc., 1992.
2. Hydraulic Institute Standards for Centrifugal, Rotary, and Reciprocating Pumps, 14th
ed., p. 12, Hydraulic Institute, Parsippany, NJ, 1983.
3. Mays, L. W. Water Resource Engineering, 2nd ed., pp. 479–480, John Wiley & Sons,
Inc., 2011.
4. Shashi, M. Liquid Pipeline Hydraulics, CED Engineering.
5. Cameron Hydraulic Data, 16th ed., pp. 1–25, Ingersoll-Rand, Woodcliff Lake, NJ,
1981.
6. Guyer, P. J. Introduction to Pumping Stations for Water Supply Systems, CED
Engineering.
7. Crane Technical Paper No. 410, 24th Printing, Crane Co., King of Prussia, PA, 1988.
8. Operation and Maintenance of Nuclear Plants, ASME OM-2020, American Society of
Mechanical Engineers, New York, NY, 2020.
5 Piping and Valves
5.1 PIPING APPLICATIONS
The purpose of cooling water piping is to transport water from one point in the sys-
tem to another in an efficient and reliable manner for the life of the plant. The appli-
cations for cooling water piping may be broadly categorized as either buried pipe or
pipe that is hung from pipe hangers inside a structure. A material that may be suitable
for one application may not be suitable for the other.
5.2 PIPING MATERIALS
CS piping alone, though less expensive than some other alternatives, is generally a
poor choice in the long run for either buried or hung applications when compared
with other piping materials. As will be shown in Chapter 6, CS in cooling water sys-
tems is frequently not a suitable material to last for the life of the plant and must be
replaced due to corrosion or flow blockage. As will be shown in Chapter 7, the flow-
passing capability of CS piping in cooling water systems is often poor even in rela-
tively new piping systems when compared with other materials. Indeed, some studies
have shown that due to the tuberculation found in CS piping in cooling water sys-
tems, the line size required to pass the same flow rate with the same pressure drop
may be one size smaller for corrosion-resistant materials than for CS, and the installed
cost may be only a fraction more or less than for CS. CS pipe (typically ASTM A106
Grade B or A53 Grade B) has been used in all sizes up to more than 20 ft (6.1 m) in
diameter. Steel pipe in sizes 0.5 to 12-inch (1.27 to 30.5 cm) in diameter is often a
continuous tube formed by drawing over a mandrel. Larger steel pipe up to 48-inches
(122 cm) is normally fabricated from long, narrow steel plate that is bent to shape and
welded along a spiral joint.1
Suitable alternative materials, depending on where in the plant the piping is
located, may include SS, CPP, pre-lined ductile iron (PDI) pipe, and a variety of
plastic piping materials such as FRP, PVC, and HDPE pipe.
5.4 BURIED PIPING
A typical power plant has a large complement of cooling water piping buried in and
around the facility. CS piping has been the material of choice for piping systems
41
42 Engineering of Power Plant and Industrial Cooling Water Systems
buried in the plant yard. Such piping is normally coated on the exterior with a bitu-
minous coating and wrapped in fiberglass to protect against exterior corrosion.
Depending on the composition of the soil surrounding the pipe, a cathodic protection
system may be needed to supplement the exterior coating. As shown in Figure 5.1,
cathodic protection consists of a direct current power source with the positive termi-
nal connected to sacrificial anodes buried under ground. Other wires serving as cath-
odes are connected to the pipes. Any breach in the pipe coating provides a path for
the electricity to pass from the anodes through the ground, back to the pipe, and back
through the cable to the power source. The flow of electricity into the pipe limits the
corrosion, thus protecting the pipe from loss of metal. Although frequently viewed as
passive, cathodic protection systems require supervision. Excessive impressed volt-
age can cause disbanding of the pipe coating, resulting in an accelerated corrosion
rate. Plant engineers are often not familiar with these systems, and when equipment
fails (if it is discovered at all) it may be found to be obsolete and spare parts may not
be available.
Other materials such as CPP, PDI pipe, and plastic piping may be more suitable
for buried service. In recent years, there has been a trend toward using various plastic
piping systems.
the standard are 20 through 90-inch (50.8 through 229 cm). Operating pressures can
be as high as 260 lbf/in2 (1,793 kPa). Standard lengths are 12, 16, and 20 feet (3.66,
4.88, and 6.10 m).2
Prestressed concrete pipe consists of a thin steel cylinder with steel joint rings
welded to its ends. The cylinder is then lined with a dense coating of concrete and
high tensile strength wire is wound around the outside of the cylinder at a
predetermined stress. The pipes are manufactured according to AWWA C301. Sizes
covered by the standard are 16 through 96-inch (40.6 through 244 cm). Operating
pressure range for economical design is from 200 to 275 lbf/in2 (1,379 to 1,896 kPa).
Standard lengths are 16 and 20 feet (4.88 to 6.10 m).2
Pretensioned concrete pipe as shown in Figure 5.2 consists of a heavier steel cyl-
inder with steel joint rings welded to its ends. The cylinder is then lined with a dense
coating of concrete. High tensile strength wire is wound around the outside of the
cylinder at a predetermined stress, and the outside is coated with concrete. The pipes
are manufactured according to AWWA C303. Sizes covered by the standard are 10
through 36-inch (25.4 through 91.4 cm). Operating pressure range can be as high as
400 lbf/in2.(2,758 kPa). Lengths range from 24 to 40 feet (7.32 to 12.2 m).2
There has been considerable operating experience with all three of these types of
pipes, including some in nuclear seismic Category I applications. They are not
subject to either interior or exterior corrosion. However, special consideration should
be given to the joint details due to possible joint leakage.
length of a section of pipe by moving a lance while the pipe is spinning. In the latter
method, the mortar is sprayed or slung evenly onto the pipe wall by a rapidly revolv-
ing moving head inserted through the stationary pipe at the centerline. The lining is
then cured by either storing it in a moist environment, processing it through an ele-
vated temperature curing tunnel, or seal-coating it with a solvent-based paint. The
lining produced by either of these methods produces a dense, smooth, surface that
both inhibits interior corrosion and promotes flow. PDI is produced in accordance
with ANSI/AWWA C104/A21.4. The thickness of the lining is to be not less than
1/16-inch (0.159 cm) for 3 to 12-inch (7.63 to 30.5), 3/32 (0.238 cm) for 14 to 24-inch
(35.6 to 61.0), and 1/8-inch (0.318 cm) for 30 to 64-inch (76.2 to 163 cm) pipe.
Normally acceptable operating temperatures are up to the boiling point of water
unless seal coated in which case should not exceed 150°F (65.6°C). Sections of pipe
are joined by bell and spigot with an intermediate rubber gasket placed in a groove
inside the socket at the bell end.3
5.4.3 Plastic Pipes
The two main classes of plastic pipes are thermoplastics and thermosetting.
Thermoplastic pipes soften at elevated temperatures above the useful range and
become readily formable. On cooling, the material regains its original properties.
Production by extrusion is simple, and joining and field modification exploit the
softening and hardening ability. When heated to high enough temperature and pressed
together, pipe ends fuse into a serviceable joint.4
HDPE pipe is a thermoplastic pipe manufactured by the extrusion process.
Operating pressures can range from 50 lbf/in2 (345 kPa) for large pipes to 200 lbf/in2
(1,379 kPa) for small pipes. The operating temperature limit is 140°F (60.0°C). The
pipes are manufactured according to ASTM D2104, D2239, D2447, F405, and
F449.2 Sizes covered by the standards are 0.75 through 200-inch (1.91. through
508 cm). Standard lengths range from 20 to 40 feet (6.1 to 12.2 m) with coils 1000
feet (305 m) in length.2
Among the thermoplastics, PVC pipe is the most common used for small plastic
piping at power plants. It is also manufactured by the extrusion process. Operating
pressures can range from 150 lbf/in2 to 200 lbf/in2 (1,034 to 1,379 kPa). The operating
temperature limit is 140°F (60.0°C), but the strength is defined at 23°C (73.4°F) and
decreases at higher temperatures. The pipes are manufactured according to ASTM
D1785, D2241, D2321, D2412, D2672, and D3034.2 (See also AWWA C900.) Sizes
covered by the standards are 4 through 18-inch (10.2 through 45.7 cm).2 Standard
lengths range from 20 to 40 feet (6.1to 12.2 m) with coils 1000 feet (305 m) in
length.2
Thermosetting resins cannot be reversibly cycled over a wide temperature range.4
Thermosetting plastics require reinforcement, usually by fiberglass which forms a
composite wall in which each layer contributes to the desired overall qualities of the
pipe.4 Thermosetting resin pipe reinforced with fiberglass reinforcement is manufac-
tured by wrapping reinforcement fibers unbonded around the pipe surface and the
pipe is then heated until the thermal bonding occurs.4 Operating pressures can range
from 30 lbf/in2 (207 kPa) for large pipes to 250 lbf/in2 (1,724 kPa) for small pipes.
Piping and Valves 45
The maximum operating temperature limit is 125°F (51.7°C).2 The pipes are manu-
factured according to ASTM D2996 and ASTM 2997.2 Sizes covered by the stan-
dards are 14 through 168-inch (35.6 through 427 cm). Standard lengths range from
40 to 60 feet (12.2 to 18.3 m).2
FRP pipe is a composite material made from a thermosetting polymer matrix
reinforced with fibers.4 Operating pressures can range from 30 lbf/in2 (207 kPa) for
large pipes to 250 lbf/in2 (1,724 kPa) for small pipes.2 The operating temperature
limit is 140°F (60.0°C).2 The pipes are manufactured according to ASTM D3517 and
ASTM 3754.2 Sizes covered by the standards are nominal 8 through 144-inch (20.3
through 366 cm).2 Standard lengths range from 10 to 20 feet (3.05 to 6.10 m).2 In
some installations, the cost of the fittings to join the pipe runs may equal or exceed
the cost of the pipe. Older installations of FRP pipe have experienced failures due to
a lack of uniform soil compaction, manufacturing defects, and the use of unsuitable
resins.
Considerable operating experience exists with plastic pipe in a variety of applica-
tions in industry. Plastic pipe is not generally subject to corrosion, but if the cooling
water contains particles such as sand, erosion may occur mainly at turns. Plastic
pipes are light and easy to handle, but extreme care must be taken in their installation
in buried applications, as excess soil loading and/or ovalling of the pipe can be a
problem.5
access points is first impregnated with a liquid thermosetting epoxy resin and then
folded. The open end of the in situ tube is attached to an inversion tube extending
down from the surface to one end of the pipe. As the tube is filled with water, the in
situ tube is inflated by the water, causing it to be turned inside out and pressing the
resin-impregnated side of the in situ tube firmly against the inside wall of the pipe.
The water inside the in situ tube is then circulated through a boiler, causing the resin
to cure over a period of a few hours and changing the in situ tube into a hard, structur-
ally sound pipe-within-a-pipe. After the water is pumped out and the inversion tube
is removed, the ends of the in situ tube are cut off to match the ends of the pipe. This
method of lining may be applied to pipe diameters from 6 to 60-inches (15.2 to
152 cm). The thickness of the lining is a function of the diameter of the pipe and
depth of burial ranging from 0.1 to 1.45 inches (0.254 to 3.68 cm). No structural
strength is required of the host pipe, since the resulting epoxy coated pipe has con-
siderable strength, which is a function of the diameter to in situ tube thickness ratio.
Piping and Valves 47
effectively serving the purpose for which it was intended for many years. TVA sur-
veyed the use of CML not only in municipal applications but also in fossil and
nuclear power plants and discovered that CML had been successfully used in non-
safety-related applications at numerous fossil and nuclear plants7. In general, the
experience with in situ CML has been excellent when applied in accordance with the
applicable AWWA standard.9 However, experience with CML in salt water applica-
tions has not been encouraging. In situ CML should not be confused with pre-lined
pipe which is welded or bolted together in the field. The impact of applying CML on
the existing piping design is minimal, since the piping fittings and other access open-
ings are reinstalled as originally designed.
The technical feasibility of CML is a function of the size or piping to be lined and
the complexity of the system. Although pipe sizes as small as 4 inches (10.2 cm) have
been lined, TVA decided that for safety-related applications, only those lines that can
be accessed from inside the pipe should be candidates for CML. Since each valve and
fitting must be removed from the system prior to lining, CML lends itself to long runs
of large, buried piping.
The WBNP ERCW system is divided into two trains (A and B) with a WBNP
Unit 1 train A and train B and a WBNP Unit 2 train A and train B supply header and
a train A and train B discharge header serving both units. The portion of the WBNP
ERCW system lined with CML consists of the four supply headers extending from
the IPS to the plant auxiliary building and the two discharge headers from the auxil-
iary building to the cooling towers. The supply headers range in length from 5,600 to
5,900 feet (1,710 to 1,800 m) and in size from 24 to 36 inches (61.0 to 91.4 cm). The
two discharge headers are 1,200 and 1,700 feet (366 to 518 m) long. The first 153 feet
(46.6 m) of the supply header is 24-inch (61.0 cm). The balance is 30 and 36-inch
(76.2 and 91.4 cm). Discharge headers are 36-inch (91.4 cm) in diameter. The project
was divided into two halves with each half consisting of one of the supply headers
serving each unit and one of the discharge headers in the same train being lined at a
time so that a train of ERCW would be available to support construction at all times.
An interval between lining the two halves was provided to complete the curing of the
last section, closure, flushing, testing the first half, and unwatering, and opening the
first section of the second half.
The CML process is a highly specialized construction technique that should be
attempted only by those who are experienced in the practice. TVA allowed the CML
contractor the freedom to use the same methods which had proven so successful in
other applications. Every effort was made to minimize the impact on those techniques
due to the fact that the project was safety-related.
The locations of access openings were selected to excavate valves and fittings and
at high and low points in the piping and to ensure that no run of piping is longer than
a few hundred feet. Where possible, locations were selected to minimize the depth of
access holes. The excavations extended at least a foot below the pipe invert and
exposed at least 12 feet (3.66 m) of pipe.
After the piping system had been unwatered, the valves, fittings, or spool pieces
(which are referred to as closure pieces) were removed by cutting the pipe to permit
access to the piping for cleaning and lining equipment. Spool pieces removed from
straight runs of pipe were at least 8 feet (2.44 m) long. Each closure piece was
Piping and Valves 49
removed from the hole and set on the ground beside the hole. Where fittings were
removed, at least 2 feet (0.61 m) of pipe on the end or each run was exposed. After
the piping was cleaned, lined, cured, and inspected, TVA welded the closure piece
back into place. After the closure piece was welded into place and before the CML
was applied by hand to the interior of the weld joint, a vacuum box test was performed
on the weld.
After the access openings were created, the interior surface of the piping was
cleaned by dragging spring-loaded mechanical scrapers through the pipe. A mortar
mix consisting of Portland cement, Type II sand, and water was centrifugally applied
by machine to each run of pipe so as to achieve a densely packed and uniform lining.
The mortar mix was approximately one-to-one by volume, and the water/cement
ratio was kept as low as possible. The mortar application was followed in the same
pass by either a conical-shaped drag trawl or by rotating paddle trawls. Rotating
paddle trawls were found to be superior to the conical-shaped drag trawl. With a drag
trawl, the smallest piece of foreign material could be dragged through the pipe,
requiring repair by hand. As the trawling machine moved along at a rate of
approximately 4.5 ft/min (0.0229 m/s), the mortar was pumped to the machine
through a hose in front of the machine. The travel speed, hose pressure, and trawl
adjustments were set to achieve a 3/8-inch (0.952 cm) thick lining with a tolerance of
+1/8-inch (0.318 cm) and -1/16-inch (0.159 cm). In areas where machine lining was
not practical such as in fittings or closure weld joints, the lining was applied by hand.
Curing was begun immediately upon completion of a lining run. The goal of curing
was to maintain at least a 90% relative humidity inside the pipe. After the lining had
been inspected and repaired as required, the closure piece was installed by welding.
The heat-affected mortar was removed by chipping, and the weld joint was lined by
hand from within the pipe. A curing compound was used only on this weld joint
repair. Since CML does not rely upon its adhesion to the pipe but rather to the arching
action to keep the CML in compression, its use in noncircular transitions is question-
able without special design provisions.
TVA was responsible for opening and closing the holes and piping and keeping
holes unwatered except when the CML contractor was in the hole performing
cleaning lining activities. When the holes were backfilled, the same procedures were
used as in the original construction. This included controlling the quality of backfill
material and using vibrating compactors. Care was taken to ensure that the compactors
did not ride against the pipe. The backfill activity was delayed until the lined pipe and
closure piece had been cured for at least four days.
At points in the piping where the CML terminated, TVA installed termination
rings consisting of 3/8-inch (0.9525 cm) thick by one-inch (2.54 cm) wide rolled bar
stock that were fillet welded to the interior of the pipe before the CML was applied.
In this way, the end of the CML butted against termination rings rather than being
exposed to hydraulic forces. All ASME code activities were performed by TVA,
since the CML contractor was not an “N” stamp holder. (An “N” stamp holder is
authorized to perform work under ASME Section III at a nuclear facility.)
Proper curing is the most important step in the lining process. Curing was the
responsibility of the CML contractor until a section of pipe had been inspected and
accepted by TVA. Pipe end caps were used to keep the CML from drying too quickly.
50 Engineering of Power Plant and Industrial Cooling Water Systems
After the lining achieved initial set, sandbags were installed at the ends of the pipe
and water was added until it flowed steadily through the bottom or the pipe from one
end to the other. The end caps were secured on the ends of the pipe for a minimum of
four days with water being added daily in a similar manner. Any of the exterior
surfaces exposed to the sun were covered with burlap that was wetted hourly. The
closure pieces were capped, wrapped in plastic, and covered with wet burlap.
A total of 612, 13,083, and 12,238 feet (186.5, 3,988, and 3,730 meters) of 24, 30,
and 36-inch (61.0, 76.2, and 91.4 cm) piping were lined. A total of 31 access holes
were excavated to permit removal of 72 closure pieces. Approximately 200 cubic
yards (153 m3) of corrosion products were removed from the interior of the piping.
The project contractor cost in 1982 was $467,000. The cost of TVA support was
estimated to be approximately $1,000,000 which included the cost of excavating and
backfilling the access holes, cutting and welding the piping, curing the pipe, and
performing inspections.
5.5 HUNG PIPING
Unlike buried piping which is bedded and supported by the earth, hung piping is
simply supported by pipe hangers, and more rigid pipe are required to minimize the
number of hangers. In hung piping, dynamic and thermal loading are concentrated at
the hangers. If oversized CS piping is employed to compensate for the reduced flow-
passing capability, the result can be lower velocities, resulting in increased sedimen-
tation and corrosion. PDI pipe is generally not suitable for service in hung piping due
to a lack of flexibility of the cement lining in these piping systems and the increased
weight, especially at the joints where flanges are often employed. Similarly, CPP is
not normally employed in hung piping for much the same reasons. Neither PDI nor
CPP can be readily modified in the field, potentially resulting in schedule impacts
due to field changes.
Dipped and heat-fused plasticized PVC coated pipe has successfully controlled
corrosion in CS piping and fittings. Success depends on the proper procedures to
ensure a good application of the coating. When properly applied, PVC coating has
performed well due to its excellent adhesion characteristics. This tremendous
adhesion strength results in a coating providing bond strengths that may exceed the
tensile strength of the PVC itself. The coating does not delaminate or come off in
large pieces as has sometimes been the case with in situ epoxy coatings. Before the
coating is applied, the base metal is sand blasted to a near white metal finish and the
coating is seamlessly baked on to the pipe making it impervious to attack by saltwater
or chlorine. PVC coated pipe has had to be replaced in some areas subject to high
cavitation. Because PVC is a thermoplastic, it will distort under high heat and
pressure. If the lining is too thick on the flange face, it will possibly extrude into the
inside diameter of the pipe if excessive torques are used during the assembly process.
For this reason, the thickness on the flange face is kept as thin as possible. The PVC
material has a tendency to stick to itself, making disassembly of spool pieces
difficult.10
The use of CS piping clad with a corrosion-resistant alloy such as 300 series SS
or Inconel 625 might be a suitable choice for replacing CS hung pipe.11 Since the
Piping and Valves 51
allowable stresses and thermal expansion would be essentially the same as the CS
pipe, the material may be replaced like-for-like without requiring redesign and/or
reanalysis.11 For cooling water from rivers or lakes with hard water and low chloride
levels, the 300 series SS would be adequate, while those from brackish or salt water
may require a more corrosion-resistant material such as Inconel 625.7 The cladded
pipe is manufactured by a machine-gas arc welding and roll bonding process that
produces a metallurgically bonded alloy 80 to 100 mm thick internal cladding.7 The
CS piping constitutes the pressure boundary, while the cladding constitutes the cor-
rosion allowance. The root pass of field girth welds is made using the same alloy rod
as the cladding, so the surface exposed to the cooling water after welding is the same
as the cladding.7
Plasticized PVC coated pipe and alloy cladded pipe are normally flanged or
screwed fittings, since welding would destroy the coating or cladding Flanged joints
require more surrounding space for fitting up and tightening the bolts than do welded
joints.5
In light of its resistance to corrosion, SS is the preferred material for new hung
piping. Type 304 and 304L SS provide good service in many instances. In the
presence of sedimentation, algae, and oxidizing biocides such as chlorine, Type 316L
SS may be the preferred choice to deal with crevice corrosion and potential localized
high concentrations of chloride ions leading to pitting. Brackish or salt water
applications may require a more corrosion-resistant material such as Inconel 625.
Recently, plastic piping systems have been used inside power plants, but in
addition to requiring more hangers, they present a fire hazard. Figure 5.5 shows
HDPE supported by pipe hangers inside the Catawba Nuclear Station.
FIGURE 5.5 Cooling water HDPE supported by pipe hangers inside the Catawba Nuclear
Station.
52 Engineering of Power Plant and Industrial Cooling Water Systems
earthquake acceleration used for the design or TVA nuclear plants. The recorded
maximum peak-to-peak accelerations were 1.2g and 3.8g, respectively. Dominant
frequencies ranged from 15 to 70 Hz. For most large earthquakes, the dominant fre-
quencies are in the range of 0.5 to 10 Hz. Lower frequencies indicate a buried pipe
would experience fewer cycles of vibration during a real earthquake. No cracks due
to vibration were found in any of the CML after unloading, and it was concluded that
the lining had experienced more severe vibrations than from any potential earth-
quakes in terms of magnitude and number of cycles.
After the piping arrived at the laboratory, a 30-ft (9.14 m) section of 30 inch
(76.2 cm) pipe was subjected to bending, cyclic loading, and drop tests as seen in
Figures 5.7 and 5.8.
FIGURE 5.7 Cement-Mortar lining being subjected to cyclic loading and bending test.
54 Engineering of Power Plant and Industrial Cooling Water Systems
Cracks appeared in the lining only after the applied stress exceeded the tensile
strength of the mortar. No lining failure occurred.
2-foot (0.61 m) long sections of 30-inch (76.2 cm) pipe were subjected to cyclic
loading, torsion, drop, and impact tests as seen in Figure 5.8.
Cracks appear in the pipe at 15 foot (4.57 m) drop height. A 5-foot (1.5 meter)
length of 30-inch (76.2 cm) pipe was welded to each end of the 30-inch (76.2 cm)
elbow and it was subjected to bending tests shown in Figure 5.9
The elbow was loaded to 50,000 lb (22,700 kg) without failure. When the elbow
was loaded to 54,000 lb (24,500 kg), the lining failed, and the elbow was shortened
by 5 inches, 1.5 inches permanently.
Piping and Valves 55
piping such as headers are normally fabricated in the shop using saddles to reinforce
fabricated tees where required.
5.7.1 Valves
A valve is a device used to prevent, limit, or permit the flow of cooling water through
a portion of the system. Swing check valves as shown in Figure 5.11 prevent the
reverse flow of the cooling water and are most often found at the cooling water pump
discharge to prevent back flow through an adjacent idle pump. A disk is hinged at the
top of the valve, and flow through the valve keeps the disk open, while reverse flow
or gravity causes the disk to swing shut, shutting off flow.
Butterfly valves are the most common valves in a cooling water system because
they are simple, relatively inexpensive, weigh less, and are easier to operate and
maintain than many other types of valves. Butterfly valves use a circular disk to
rotate through 90° to go from full closed to full open and may be stopped at any point
in between to throttle the flow through the line. There is very little pressure drop
when the butterfly valve is wide open. Most butterfly valves in cooling water system
service have elastomer lining seats. They are controlled with either a hand wheel or
are operator powered using either an electric motor or pneumatic actuator. The com-
mon body types are lug style in which the lugs are threaded on each side to receive
bolts from adjacent flanges, wafer style where the body is clamped between two
pipeline flanges, and flanged ends.
Gate valves are used for applications requiring either fully open operation (requir-
ing minimum pressure drop) or fully closed operation (requiring a tight shut-off) and
should not be used for throttling. When operating, the disk moves up or down on the
end of a threaded valve stem, driven by an electric motor or pneumatic actuator. Gate
valves are either parallel type in which a disk slides between two parallel seats or
wedge-shaped, which has two inclined seats. When fully open, the disk is fully with-
drawn, making it possible for a pipe cleaning pig to pass unobstructed. The gate
valve has either a metal or rubber seat in a depression in the valve bottom. Since for
cooling water systems the potential exists for objects such as pebbles or mollusks to
hinder complete closure of the valve, a rubber seat may be required if tight shut-off
is required. Gate valves are more expensive than butterfly valves and require more
physical space.
Globe valves as shown in Figure 5.12 are used to regulate flow by passing the flow
through a spherical body in which the flow must pass through an internal baffled
opening, the size of which is adjusted by a movable plug that can be screwed up or
down. Typically, automated globe valves (control valves) use a smooth rather than
threaded stem which is opened and closed by an actuator assembly that may be air-
operated. Globe valves exhibit a relatively high pressure drop.
Ball valves are sometimes used in smaller lines where tight shut-off is impor-
tant. A ball with a hole in it controls the flow. When the hole is aligned with the
direction of flow, the pressure drop through the valve is insignificant, and when the
hole is positioned perpendicular to the direction of flow, the flow is shut off. By
positioning the ball in any intermediate position, the cooling water flow rate may
be controlled by changing the pressure drop through the valve. Ball valves are nor-
mally operated manually by a handle attached to a stem that controls the position
of the ball.
5.7.2 Fittings
Figure 5.13 shows a sampling of the cooling water system pipe fittings that are com-
mercially available. Long radius elbows are generally preferred because they require
less pressure drop than short radius; however, they require more space.
P Do
tm A (5.1)
2 SE Py
where
tm = minimum required wall, in
P = internal pipe pressure, lbf/in2
Do = outside diameter, in
S = maximum allowable stress, lbf/in2
E = joint efficiency (1.0 for seamless pipe)
y = temperature coefficient (0.4 for cooling water piping)
A = corrosion allowance, in (See Chapter 6).
Additional pipe wall thickness may be required to withstand external loads such
as gravity, thermal loads, torsion, and seismic effects, etc.
The formulae for ASME Section III, Class 3 piping are the same as Equation (5.1).
REFERENCES
1. Linsley, R. K. et al. Water-Resources Engineering, 4th ed., p. 378, McGraw-Hill, Inc.,
New York, NY, 1992.
2. Chandley, C. A. et al. Essential Raw Cooling Water (ERCW) System Piping Materials,
memorandum MEB ‘810413022, Tennessee Valley Authority, Knoxville, TN, 1981.
60 Engineering of Power Plant and Industrial Cooling Water Systems
3. Bonds, R. W. Corrosion Control – Cement-Mortar Lining for Ductile Iron Pipe, Ductile
Iron Pipe Research Association, Birmingham, AL, 2017.
4. O’Keefe, William. Corrosion-resistant Piping for Utility and Industrial Power Plants.
Power, Vol. 125, No. 4, pp. S1–S24, April 1981.
5. Chandley, C. A. et al. Nonsafety-Related Raw Water Systems Piping Materials, memo-
randum MEB ‘820107011, Tennessee Valley Authority, Knoxville, TN, 1982.
6. Bowman, C. F. and P.V. Guthrie, Jr. Corrosion in Carbon Steel Service Water Piping.
1994 ASME Pressure Vessel and Piping Conference, Phoenix, AZ, ASME, 1994.
7. Bowman, C. F. In Situ Cement-Mortar Lining of Safety-Related Service Water Piping
Systems. International Joint Power Conference, 94-JPGC-NE-6, 1994.
8. Miller, W. T. Durability of Cement-Mortar Linings in Cast-Iron Pipe. Journal AWWA.
American Water Works Association, Denver, CO, June 1965.
9. AWWA Standard C602-76. Cement –Mortar Lining of Water Piplines – Inch and
Larger – In Place, American Water Works Association, Denver, CO, 1976.
10. Robinson, L. K. and P. C. Fritchman. Lining of Raw Water Piping with Plasticized PVC,
EPRI Service Water Systems Reliability Improvement Seminar, Electric Power Research
Institute, New York, NY, 1994.
11. Chakravarti, Bhaven. Use of Clad Piping Products for Solving Nuclear Plant Service
Water Systems Corrosion, 91-JPGC-NE-12. International Power Generation
Conference, ASME, 1991.
12. Hubble, J. D. Operating Experience for Alternative Raw Water Piping Materials,
Memorandum MEB 810720032, Tennessee Valley AuthorityKnoxville, TN, 1981.
13. Sun, C. N., et al. Full Scale Testing and Qualification of Cement-Mortar Lined Carbon
Steel Pipe, CEB-82-8, Tennessee Valley Authority - Division of Engineering Design –
Civil Engineering Branch, Knoxville, TN, 1982.
14. Regulatory Guide 1.26: Quality Group Classifications and Standards for Water, Steam,
and Radioactive-Waste-Containing Components of Nuclear Power Plants, Rev. 4,
Nuclear Regulatory Commission, Washington, DC, 2007.
15. Watts Bar Nuclear Plant SSER 4. Report of the Advisory Committee on Reactor
Safeguards, Section 19, pp. 19–1 to 19–2, 1982.
16. ASME B31.1-2001. Power Piping: ASME Code for Pressure Piping, B31.1 – American
National Standard, The American Society of Mechanical Engineers, New York, NY,
2001.
6 Corrosion and Fouling
61
62 Engineering of Power Plant and Industrial Cooling Water Systems
Sevier (JS), Watts Bar (WB), Widows Creek (WC), Kingston (K), and Cumberland
(CU) and nuclear plants including BFNP and SNP. The sections of piping removed
from the various raw water systems were kept hydrated and delivered for analysis to
the TVA Power Service Center Laboratories in Chattanooga, Tennessee. A measured
length of a piping sample was sealed at one end and filled with water. The volume of
water contained in the sample was compared with the original volume as calculated
from the nominal dimensions of a new pipe. The percent volume occupied by the
deposit thus determined represented the average loss in pipe cross-sectional area and
was related to an average decrease in pipe diameter. A 4-inch (10.2 cm) length of
each pipe was split lengthwise, scraped, and acid cleaned in inhibited hydrochloric
acid. The sections were weighed and compared to the weight calculated for new pipe
of nominal size. The change in pipe weight was then directly related to the change in
pipe wall thickness. A visual inspection of each piping sample was made after
cleaning to identify the deepest pit or area of maximum wall thinning. The remaining
wall thickness in the deepest pit was measured with a dial micrometer with a
1/32-inch (0.079 cm) diameter anvil. The deposit in each sample was analyzed for
various constituents.
Figure 6.1 is illustrative of the amount of corrosion products and other material
found inside of the piping. Although such pictures are very common in the technical
literature today, when the piping was removed and examined by the author in the late
1970s the implications were staggering.
Observed and calculated data for the piping samples are shown in Table 6.1. The
data in Table 6.1 is sorted by the number of years that the piping has been in service.
Samples that had been in constant flow service are noted as “C” and those that had
been in mostly stagnant flow service are noted as “S”.
Figure 6.2 shows the average and maximum wall thinning from Table 6.1. As one
may see, whereas the average wall thinning appeared not to be a strong function of
age, the maximum wall thinning (i.e. pitting) was. The average ratio between the
average and maximum wall reduction was approximately 3.
FIGURE 6.1 3-inch pipe removed from widows creek fossil unit 8.
Corrosion and Fouling 63
TABLE 6.1
Analysis of Samples Taken from Deposits in Raw Water Piping
Ave. Max. Ave. Pitting
Sample Flow Age Red. Red. Rate Rate Ratio Fe3O3 SiO2 S Mn3O2
ID Cond. (Years) (in) (in) (MPY) (MPY)
SNP-1 C 2.0 0.010 0.036 5.10 18.00 3.53 87.5 0.4
CU-7 C 5.0 0.014 0.057 2.80 11.40 4.07 89.0 9.0 0.4 1.9
CU-6 C 5.0 0.025 0.019 5.00 3.80 0.76 81.2 17.0 0.4 2.7
CU-2 S 5.0 0.011 0.064 2.20 12.80 5.82 88.9 8.0 0.6 1.5
CU-8 C 5.0 0.023 0.055 4.60 11.00 2.39 78.0 14.0 0.3 1.5
CU-4 C 5.0 0.014 0.027 2.80 5.40 1.93 85.2 9.0 .05 1.4
CU-1 C 5.0 0.020 0.014 4.00 2.80 0.70 88.5 8.0 0.4 1.8
CU-5 C 5.0 0.021 0.075 4.20 15.00 3.57 74.0 21.0 0.6 2.0
WC-17 C 10.0 0.035 0.064 3.50 6.40 1.83 86.0 7.0 0.1 2.5
K-4 S 12.0 0.018 0.038 1.50 3.17 2.11 82.5 6.6 1.6
K-5 S 12.0 0.033 0.068 2.75 5.67 2.06 79.8 4.5 1.0
K-6 S 12.0 0.032 0.07 2.67 5.83 2.19 71.5 4.3 1.3
WC-4 C 12.1 0.014 0.046 1.12 3.80 3.38 90.4 0.5
WC-23 C 13.8 0.019 0.095 1.38 6.91 5.00 81.0 8.1 2.4
WC-22 C 13.8 0.018 0.053 1.31 3.85 2.94 79.1 6.9 2.4
WC-21 C 13.8 0.035 0.067 2.55 4.87 1.91 65.0 20.1 3.7
WC-24 C 13.8 0.017 0.045 1.24 3.27 2.65 56.3 27.4 5.2
WC-19 C 17.0 0.039 0.063 2.29 3.71 1.62 70.0 10.0 0.1 3.5
WC-20 C 17.0 0.031 0.059 1.82 3.47 1.90 87.0 4.0 0.1 3.5
WC-16 S 17.0 0.021 0.062 1.24 3.65 2.95 90.0 6.0 0.1 3.0
WC-18 C 17.0 0.033 0.07 1.94 4.12 2.12 78.0 7.0 0.1 2.6
JS-2 S 17.7 0.020 0.061 1.11 3.45 3.10 75.8 0.5 2.2
G-1 C 17.8 0.022 0.077 1.26 4.33 3.44 88.1 0.8
G-2 S 19.5 0.028 0.138 1.44 7.08 4.93 78.2 9.9 1.9 1.5
G-3 S 19.5 0.024 0.16 1.23 8.21 6.67 74.8 10.3 1.8 1.6
G-4 S 19.5 0.024 0.092 1.23 4.72 3.83 82.6 8.3 2.5 1.4
G-5 S 19.5 0.031 0.102 1.59 5.23 3.29 75.5 8.2 2.2 1.4
JS-1 C 21.5 0.016 0.079 0.72 3.67 5.10 3.7 0.1 72.4
C-1 C 22.2 0.027 0.073 1.20 3.29 2.74 82.9 0.3
JS-6 S 23.0 0.045 0.086 1.96 3.74 1.91 89.5 7.0 1.1 1.4
K-8 S 23.0 0.007 0.042 0.30 1.83 6.00 79.4 4.8 1.1
JS-7 C 23.0 0.048 0.096 2.09 4.17 2.00 69.0 9.0 0.4 3.7
JS-8 C 23.0 0.028 0.04 1.22 1.74 1.43 44.0 13.0 0.3 4.2
K-7 S 23.0 0.017 0.143 0.74 6.22 8.41 81.8 5.4 1.3
JS-3 S 23.0 0.024 0.044 1.04 1.91 1.83
JS-4 S 23.0 0.040 0.046 1.74 2.00 1.15 91.0 6.0 1.3 0.6
JS-5 S 23.0 0.061 0.096 2.65 4.17 1.57 85.6 6.0 0.7 1.3
K-10 S 23.0 0.025 0.128 1.09 5.57 5.12 90.3 4.2 0.9
K-9 S 23.0 0.022 0.044 0.96 1.91 2.00 80.2 3.4 0.8
WC-2 C 23.8 0.030 0.122 1.24 5.13 4.12 38.6 0.6
WC-15 S 25.0 0.006 0 0.24 0.00 0.00 63.4 11.0 .4 3.2
WC-6 C 25.0 0.026 0.065 1.04 2.60 2.50 89.0 133.0 0.4 3.1
WC-13 C 25.0 0.022 0.036 0.88 1.44 1.64 77.9 7.0 0.3 2.4
WC-7 C 25.0 0.018 0.06 0.72 2.40 3.33 80.8 8.0 0.5 2.3
WC-8 C 25.0 0.016 0.129 0.64 5.16 8.06 72.3 15.0 0.8 2.8
WC-10 C 25.0 0.015 0.052 0.60 2.08 3.47 80.0 7.0 0.7 1.6
WC-11 C 25.0 0.054 0.095 2.16 3.80 1.76 72.5 7.0 0.4 1.9
WC-9 C 25.0 0.012 0.045 0.48 1.80 3.75 71.5 18.0 0.9 2.8
WC-12 C 25.2 0.027 0.046 1.07 1.83 1.70 77.8 5.0 0.4 1.5
WB-7 C 33.0 0.028 0.079 0.85 2.39 2.82 90.0 7.0 0.8 1.3
(Continued)
64 Engineering of Power Plant and Industrial Cooling Water Systems
Sample Flow Age Red. Red. Rate Rate Ratio Fe3O3 SiO2 S Mn3O2
WB-6 C 33.0 0.024 0.057 0.73 1.73 2.38 81.8 8.0 0.3 1.5
WB-2 C 34.1 0.035 0.1 1.02 2.93 2.88 84.4 1.0
WB-3 C 35.0 0.016 0.057 0.46 1.63 3.56 93.7 4.0 0.3 1.0
WB-5 C 35.0 0.011 0.019 0.31 0.54 1.73 89.7 5.0 0.5 1.2
WB-4 C 35.0 0.018 0.13 0.51 3.71 7.22 92.5 5.0 0.4 1.2
Average 3.05 78.1 11.6 0.6 3.5
C = Constant flow.
S = Normally stagnant flow.
0.18
0.16
0.14
Wall Thining (in)
0.12
0.10
Ave.
0.08
Max.
0.06
0.04
0.02
0.00
0 5 10 15 20 25 30 35 40
Years Service
From Table 6.1, it can be seen that JS-5, WC-1, JS-7, and JS-6 had the highest
values of average wall reduction. Samples JS-5, JS-6, JS-7, and WC-11 all had vary-
ing degrees of exterior corrosion. This exterior corrosion also affects the maximum
wall thinning calculations so that the maximum thinning for these samples would
have been somewhat reduced if the exterior corrosion had been controlled. Varying
degrees of exterior corrosion were noted on all these samples with JS-5 being the
worst. Control of exterior corrosion would allow these values to be discarded. Data
from stagnant lines were seen to fall within the same areas as the continuously flow-
ing samples. Large differences in the average wall reduction are seen in samples
removed from a given site and even between samples removed from a given
pipeline.
Samples WC-15, WC-20, WB-8, WB-9, and WB-10 were removed from galva-
nized lines. Galvanizing appears to be more effective in controlling maximum wall
thinning than in controlling average wall reduction. Much more data from galvanized
Corrosion and Fouling 65
lines would be necessary before any conclusions could be made, however. The gal-
vanized sample data should be used with caution since the maximum wall thinning
values are calculated from the remaining wall thickness measured by a micrometer.
The calculated values are underestimates of the actual thinning since the assumed
initial wall thickness of the pipe does not account for the additional wall thickness
due to the zinc coating. This results in negative values of maximum wall thinning for
some samples. WB-8 was found to be a unique galvanized sample. Removing the
insulation from the piping exterior to obtain the sample revealed a 0.4-inch (1.02 cm)
diameter hole rusted through the pipe wall. It is speculated that the zinc coating was
defective at this point, exposing the CS to the stagnant water in the line. The corro-
sive galvanic attack was accelerated due to the small area of CS pipe exposed to the
galvanized portion of the line.
As seen on Figure 6.2, large variations in maximum wall thinning were found
with the variations in data for samples from one site or from one pipeline at the same
site and even greater than that for the average wall thinning data. Values of maximum
wall thinning up to 0.160-inch (0.406 cm) were found in the observed data. The larg-
est values of maximum wall thinning were seen in some of the 8-inch (20.3 cm)
samples at G (G-2 and G-3) and the 6-inch (15.2 cm) samples from K (K-7 and
K-10). Tubercles approaching 2 inches (5.1 cm) in height were found in these sam-
ples. It was found that areas of maximum wall thinning were usually found beneath
the large tubercles, indicating that maximum wall thinning is a function of tubercle
size. The average diameter reduction of these samples was less than some of the
smaller diameter samples due to only isolated instances of the large tubercles.
Figure 6.3 shows a plot of the average and pitting corrosion rate for each specimen
as determined by the method described above.
As one may see from Figure 6.3, both the average corrosion rate and the pitting
corrosion rate appear to decline with age, suggesting that cleaning the pipe without
adding an inhibitor may accelerate the rate of corrosion. The average corrosion rate
was 1.7 MPY.
20
18
16
Corrosion Rate (MPY)
14
12
10
Ave.
8
6 Pitting
4
2
0
0 5 10 15 20 25 30 35 40
Years Service
The scope of the 1979 TVA study was not intended to predict a 40-year design
value of average wall reduction or maximum wall thinning (i.e. corrosion allowance
“A” in Equation 5.1) or the impact on system design of the reduced wall thickness but
only to report the observed data and to make any comments regarding trends or pecu-
liarities. It was observed that the samples having large values of average wall reduc-
tion also had varying degrees of exterior corrosion. If all samples are considered,
average wall reductions reaching 0.0625 inches (0.159 cm) were seen. Discarding
samples with obvious extreme exterior corrosion drops the maximum value of the
average wall reduction to 0.040 inches (0.102 cm). Values of maximum wall thinning
up to 0.160 inches (0.406 cm) were found in the observed data. It is noted that only
one sample was found with through-wall leaks, since they would normally have
already been replaced. Therefore, the maximum wall thinning could be much higher
than indicated by the 1979 study. No significant differences were observed in the
corroded condition of horizontal versus vertical runs of pipes as long as the pipes
were completely full of raw water.
In 1980, some of the results of the TVA investigation focusing on the flow-passing
capability of the piping were reported by Bowman and Bain.2 (See Chapter 7.)
Figure 6.4 from Reference 2 shows the effective decrease in diameter of the pipes
due to material buildup as determined by the method described above as a function
of years of service.
One may see that the degree of material buildup varied greatly from sample to
sample, but generally it appeared to be progressive with the age of the pipe. In
stagnant, continuously pressurized piping systems, the rate of material accumulation
is generally lower than that found in raw water piping systems where water flows in
a continuous or nearly continuous manner, thereby replenishing the oxygen supply
which can then induce further corrosion. However, data from some stagnant lines fall
within the same areas as the data from flowing lines.
From the scatter of data seen on Figure 6.4, it can be seen that age was not the only
parameter influencing corrosion product buildup. Large variations in buildup are
seen for piping removed from a given site at a given age (e.g. WC and WB) and in
some cases large variations can be seen from samples removed from a single pipeline
(e.g. WC-21 through WC-24 and G-2 through G-5). It was found that the average
buildup in 8-inch (20.3 cm) diameter piping (G-2 through G-5) and 6-inch (15.2 cm)
diameter piping (K-7 through K-10) was on the same order of magnitude as the
buildup in the 2, 3, and 4-inch (5.1, 7.6, and 10.2 cm) lines taken at JS and WC.
Buildup did not appear to be dependent on pipe diameter.
Large differences in the appearance and consistency of the corrosion product
buildup were found. In some cases, materials other than corrosion products were
found on the pipe interior. At JS, some of the samples were found to have a large
amount of manganese deposit. Sample WC-24 was found to have a higher level of
silica than other samples. Most of the samples had a relatively uniform buildup with
a very rough surface like that shown in Figure 6.1. However, some samples such as
K-10 had almost no average buildup but had large, randomly spaced isolated tuber-
cles. The samples removed from WB appeared to not be any worse than those
removed from WC and JS even though the WB piping had been installed approxi-
mately 20 years earlier. However, It should be noted that WB was out of service for
a significant period of time (10–15 years) and the status of the piping during that
period is not known. The effective age of the piping at WB could actually be less than
that shown. It can be seen, in most cases, that the diameter reduction in galvanized
lines is less than that of the other samples. It can be seen from Figure 6.2 that age
effect is only one part of the explanation for material buildup and that the worst
buildup observed actually occurred between 20 and 25 years of service.
Reference 1 concluded that although the appearance and consistency of the
buildup on the inside wall of the pipe samples varied, iron oxide was virtually always
the principle constituent, and the primary mechanism was always corrosion of the
steel piping by the aerated raw water with redeposition of the corrosion products onto
the inside wall of the pipe in the form of irregular tubercles. The entire process was
determined to be induced or at least influenced by sulfur-reducing bacteria (SRB).
Corrosion of raw water piping and the resultant redeposit of ions of corrosion product
onto the inside of the pipe were found to a significant degree at all plants that were
sampled. Under each tubercle was almost invariably found an area of reduced pipe
wall thickness. The results of the study indicated that at the end of the 40-year life of
a plant in the TVA system, CS raw water piping will experience an average reduction
in the inside diameter of 0.40 inch (1.02 cm), an average reduction in the pipe wall
thickness of 0.065 inch (0.165 cm), and a maximum wall thinning of at least 0.160
inch (0.406 cm) due to corrosion. As a result of the 1979 TVA study (Reference 1)
TVA issued References 3 by J. R. Alley as guidance for design engineers in dealing
with CS piping in raw water service.
Reference 1 also presented the results of pressure drop tests performed in straight
sections of CS raw water piping at three TVA power plants. These tests conducted to
determine the impact of corrosion products buildup on the interior pipe wall on the
flow-passing capability of the pipe are addressed in Reference 2 and in Chapter 7.
68 Engineering of Power Plant and Industrial Cooling Water Systems
be calculated. The approach was an appropriate adaptation for raw water piping of
the procedures found in ASME Section XI (IWB-3640) for evaluating flaws in
austenitic SS piping in ASME Section III, Class I systems, which provides convenient
but overly conservative means of evaluating MIC damage. In this approach, all MIC
indications must be added together in the circumferential direction and evaluated as
a single flaw oriented in the direction of the primary bending to produce the weakest
net sectional properties. Additional refinements have been developed to eliminate
this conservatism as required on a case-by-case basis. The approach taken is to
establish a screening criteria of allowable total length of MIC defects based on the
IWB-3640 methodology for a given line size and enveloping load magnitudes for a
given system. All welds with a total MIC damage indication of less than this value
are structurally adequate. Welds with greater MIC damage were evaluated
individually, first by using the methodology with location-specific loads and then
with the less conservative methods if required. It should be noted that all methods of
evaluation assumed that all MIC indications were completely through-wall and make
no allowance for sound metal that may exist above the MIC cavities. This approach
was required because existing methods of NDE did not permit reliable evaluation of
MIC damage in the radial direction at the time the flaws were evaluated.
In 1987, TVA began investigating corrosion rates by means of corrosion coupons.
Although this technique cannot predict the long-term corrosion rate, it is useful to
determine the relative short-term corrosion rate as a function of time, temperature,
and various water treatments. TVA conducted tests at the SM&E Laboratory during
which CS coupons were exposed in a once-through service water flow loop drawing
water from the Tennessee River at Knoxville, Tennessee. The results of these tests are
shown in Table 6.2.
These data are shown in Figure 6.6.
Blackburn and Mullin12 reported on the corrosion rates measured in a condenser
waterbox at the BFNP in 1987–1989. Figure 6.7 shows the corrosion rates measured
at BFNP by an array of different durations of coupon exposure. As with Figures 6.3
and 6.6, the same trend of lower corrosion rates with time is observed. Although the
magnitude of corrosion as a function of duration of coupon exposure rates varies
considerably between the three studies, the data consistently suggest that the average
corrosion rate is a function of service life and that the rate decreases with time.
TABLE 6.2
Coupon Corrosion Tests in Cooling Water
Start End Time Corrosion Rate
Date Date (Days) (MPY)
10/22/1987 11/23/1987 32 5.35
11/24/1987 1/4/1988 41 3.60
1/8/1988 2/12/1988 35 5.94
11/24/1987 3/21/1988 120 2.78
2/24/1988 4/7/1990 773 1.59
11/22/1987 4/7/1990 898 1.86
Corrosion and Fouling 71
5
Corrosiom Rate (MPY)
0
0 200 400 600 800 1000
13
12
11
Average Corrosion Rate (MPY)
10
5
30 40 50 60 70 80 90 100 110 120 130
Duration of Coupon Exposure (Days)
Figure 6.8 shows the corrosion rates measured at BFNP by 60-day coupons as a
function of the service water temperature. This study suggests that the corrosion rate
increases with increased cooling water temperature.
Although the average corrosion rates reported above are useful in assessing the
various factors that influence corrosion, the pitting corrosion rate is the parameter
that is of more interest to the designer. Unfortunately, much of the published litera-
ture reports on corrosion monitoring performed with weight loss coupons which nor-
mally do not reflect pitting corrosion rates. Figure 6.3 shows the corrosion rate
calculated based on the deepest pit observed in the piping samples removed from the
nine different TVA power plants as discussed above. When compared with average
corrosion rates, pitting corrosion appears to occur at about three times the average for
the same specimens. Although the general trend of corrosion rates declining with
service life appears to hold true for pitting corrosion, caution should be exercised in
drawing conclusions regarding an appropriate pitting corrosion rate based on
Figure 6.3. Piping specimens that have experienced through-wall pits are not included
in this sampling, since they have long since been replaced. Through-wall leaks began
to occur in the EECW and fire protection piping at BFNP after approximately 13
years of service. The first leaks occurred in 3-inch (7.6 cm) standard wall piping,
which implies a pitting corrosion rate of 16.6 MPY. These initial leaks were followed
by 80 to 100 additional leaks over the next few years before several hundred feet of
piping were replaced in 1988. In 1993, a through-wall leak occurred in a 16-inch
(40.6 cm) standard weight pipe at BFNP, implying a pitting corrosion rate of 16.3
MPY. WBNP reported leaks in small-bore [2 to 6-inch (5.1 to 15.2 cm)] standard
weight piping after about 14–17 years of service resulting in calculated pitting
20
18
Average Corrosion Rate (MPY)
16
14
12
10
0
50 55 60 65 70 75 80 85
Average Service Water Temperature (F)
corrosion rates of 8 to 16 MPY. In 2001, several leaks were discovered in the 12-inch
(30.5 cm) standard wall [0.375-inch (0.9525 cm)] WBNP fire protection supply
header from the IPS after 23 years of service for a pitting corrosion rate of 16.3 MPY.
The entire header was subsequently replaced.
In 1993, TVA initiated a comprehensive assessment, repair, and replacement of
the raw water piping systems at the SNP. The results of the RT data for the SS butt
welds showed a large percentage containing small, randomly distributed MIC defects.
None of the 55 butt welds evaluated failed to meet the structural integrity criteria.
The SS butt welds inspected in the ERCW system that showed indications of MIC
were either monitored or replaced with Inconel 625 filler metal. Figure 6.9 shows the
location of the only socket weld inspected that showed possible indications of MIC.
An analysis of this weld at SM&E concluded that socket welds are less prone to MIC
due to the location of the fillet weld. Since full penetration does not normally occur,
the weld is not in contact with the cooling water.
Visual inspection of the interior of the SS butt welds where MIC damage had
occurred showed that a small tubercle existed at the interior of the pipe at the weld
joint. A water treatment program to eliminate or minimize the extent of attack at the
SS butt welds by preventing the formation of these tubercles is discussed in
Section 6.4.1.
Figure 6.10 shows the typical condition of the CS piping encountered at SNP.
Random leaks have occurred in low flow areas of 2-inch (5.1 cm) and smaller cooling
water and fire protection piping, and in some cases, when the corrosion products
were removed, pits were found to be through-wall. CS piping was inspected by UT.
The “as found” minimum pipe wall thickness was compared with the minimum wall
thickness required to provide structural integrity. If the thickness was less than the
required value, a specific minimum wall thickness calculation using point-specific
stresses was performed. The UT data indicated random pitting throughout the CS
systems. The more severe pits that were detected were small in diameter and clearly
FIGURE 6.10 Three-inch carbon steel RCW pipe from sequoyah nuclear plant.
isolated with considerably thicker base metal surrounding each pit. The study con-
cluded that gross degradation leading to structural failure of CS piping is unlikely,
but random leaks could reasonably be expected. The average corrosion rate in the
cooling water systems at SNP was determined to be 4 MPY after approximately
17 years of service. However, some locations exhibited corrosion rates as high as
13 MPY. Although this effort provided useful information on the condition of the
system, it did not preclude the possibility that pitting corrosion at even higher rates
were occurring at other points in the system.
In 1994, Bowman and Guthrie13 summarized the results of the TVA studies of CS
corrosion in cooling water systems and the implications for piping system designers
in selecting an appropriate corrosion allowance “A” in Equation 5.1 in the future.
Tuovinen, et al,14 recognized that tubercles resulted from pitting corrosion because
they consisted largely of iron oxides and were found overlying pits. Past studies sug-
gested that microorganisms accelerated the corrosion reactions and enhanced tuber-
culation. The bacteria found in most cooling water systems make them particularly
vulnerable to corrosion. Touvinen conducted an experiment in which cast iron cou-
pons were immersed in various test solutions for four weeks. These solutions included
tap water, distilled water, and a liquid medium inoculated with samples of red water
and ground tubercles. Although coupon surface reactions took place under all assay
Corrosion and Fouling 75
conditions, the corrosion was twice as great in the inoculated medium. This led
Touvinen to conclude that bacteria could be involved in the mechanism of corrosion.
There was some hope that most of the iron showing up in the tubercles had been
scavenged from soluble iron found in the raw water, as was the case with the silica
and manganese found in the deposits. However, that hope was refuted by a study
conducted by Vermont Yankee Nuclear Power Corporation and published by Metell15
in1986. In that study, the author conducted tests on removable spool pieces of CS
pipe over a five-year period. The masses of the pipe spools were determined before
and after the test. The deposits were removed and the pipe was weighed once again
to yield the mass of the pipe after the test and the mass of the deposits. A volume/
density test and molar/mass balance showed that the deposits were composed of 10%
base metal, 90% oxygen and water on a volume basis. A comparison was made
between the oxide deposit based on the base metal loss and the actual oxide deposit.
The good agreement between these values supports the conclusion of the study that
the oxide was almost exclusively from corrosion and not deposition of soluble iron
from the source stream. Further, the study observed that the deepest pits had the
largest tubercles, that the iron lost from the pipe wall ended up in the overlying
tubercle, and that the formed tubercle is approximately ten times larger than the
deepest pit.. Metell observed that mechanical cleaning to remove tubercles to improve
system flow characteristics promotes corrosion of the pipe wall.
In 1986, the American Nuclear Society published Reference 16 as an American
National Standard for nuclear safety cooling water systems in light water reactors.
The Standard stated that these systems should be constructed of corrosion-resistant
materials, be protected by corrosion inhibitors or cathodic protection, or have
sufficient wall thickness allowance to ensure the integrity of the system over the
design life of the plant. Considering the fact that by that time, construction of virtually
all of the nuclear plants in the United States had been completed, this document,
though useful for future plants, was rather like closing the barn door after the horse
had escaped.
In 1990, the NRC published Reference 17. For Code Class 3 piping, a licensee is
required to perform code repairs or request NRC to grant relief for temporary non-
code repairs on a case-by-case basis regardless of pipe size. Because of the rather
frequent instances of small leaks in some Class 3 systems such as cooling water
systems, the NRC provided guidance that would be considered by the NRC staff in
evaluating relief requests for temporary non-code repairs of code Class 3 piping. The
guidance consisted of assessing the structural integrity of the flawed piping by a flaw
evaluation and assessing the overall degradation of the system by an augmented
inspection. The document concluded that “temporary non-code repair of Class 3
piping that cannot be isolated without a plant shutdown is justified in some instances.
The rather frequent instances of small leaks in some Class 3 systems, such as service
water systems, could lead to an excessive number of plant start-up and shutdown
cycles with undue and unnecessary stress on facility systems and components if the
facilities were to perform a code repair when the leakage is identified.”17
In 1991, the ASME published Reference 18 as a guide for determining the remain-
ing strength for corroded pipelines (not power piping, e.g. B31.1). Unlike MIC in
butt-welded SS where the damage is preferential to the transverse axis of the pipe
76 Engineering of Power Plant and Industrial Cooling Water Systems
(i.e. the weld) making the pipe more vulnerable to seismic and dead weight loads, the
MIC damage in CS is random and catastrophic failures in the longitudinal direction
may be possible. Although Reference 18 is not applicable to power piping, per se, the
document contains guidance as to how to determine the maximum allowable longi-
tudinal extent of corrosion.
In 2007, INPO issued a Significant Event Report on inadequate design resulting
in cooling system leaks at several nuclear plants.
6.1.4 MIC Tubercles
In addition to the role that microorganisms play in corrosion of CS service water,
general corrosion and the differential aeration cells set up by the tubercles are also
factors.
General corrosion, present when CS is exposed to an oxidizing agent such as
aerated water, can increase when an oxidizing biocide such as chlorine is used to
control bacteria. (See Chapter 12.)1 This requires the designer to balance the benefits
that the biocide may provide in controlling the pitting corrosion from the MIC against
the increase in general corrosion.
Although differential aeration cells can be associated with any form of crevice, in
raw water they are most commonly associated with tubercles. Figure 6.11 shows a
typical tubercle in CS pipe.19
All tubercles have five structural features in common:
1. Outer crust
2. Inner shell
3. Core material
4. Fluid-filled cavity
5. Corroded floor.20
As discussed by Metell15 and Herro,19 much of the tubercle material is formed of cor-
rosion products from the underlying metal. The tubercle often contains an inner cav-
ity filled with fluid. As tubercles increase in size with age, free oxygen within
decreases and differential aeration cell activity is promoted. Anions concentrate
within the tubercle, lowering the pH of the fluid inside the tubercle even if the bulk
fluid pH is alkaline. Since both differential aeration cells and MIC cause pitting cor-
rosion, often occurring at the same site, distinguishing between the two in service
water is often difficult. MIC is considered by many experts to be the most serious
form of corrosion in service water systems. In the case of MIC, several types of bac-
teria often work together to attack the pipe. Slime-forming bacteria (psudemonas)
produce a biofilm which becomes the host for iron-reducing bacteria, which are aero-
bic. This iron-reducing bacteria then can provide a covering for SRB, which are
anaerobic. SRBs are often found inside tubercles and produce the characteristic odor
of hydrogen sulfide when the tubercle is penetrated while still wet. This discussion is
an oversimplification of the subject. All or none of the above may occur in a specific
case.
pitting corrosion should be considered. The pitting corrosion rate can be as much or
more than three times the average corrosion rate. All three TVA nuclear plants have
experienced through-wall leaks in CS piping. Based on the pipe wall thicknesses and
service life of piping, a pitting corrosion rate of 13–16 MPY or more for untreated
raw water is not unreasonable. Data obtained from an effective monitoring program
can be beneficial in making reasonable predictions as to pipe integrity and operability
at a given site. (See Section 6.4.)
The designer should seek to minimize the impact of MIC in designing the service
water system. The system operating water velocity is one parameter that the designer
should consider to help reduce the impacts of corrosion. Metell15 reported that fast
moving streams appear to interrupt tubercle formation, and that stagnant and low
velocity water appears to deprive the bacteria of required oxygen, reducing growth.
He stated that moderate velocities [2 to 7 ft/sec (0.61 to 2.1 m/s)] encourage bacteria
growth. Figures 6.12 and 6.13 show 24-inch (61.0 cm) headers in the SNP ERCW
system. In Figure 6.12, the normal cooling water velocity exceeds 10 ft/sec (3.05 m/s),
whereas the flow in the redundant header shown in Figure 6.13 is normally zero.
Exceedingly high normal velocities (over 10 ft/sec) (3.05 m/s) can lead to erosion in
CS cooling water piping.
Normally, the sedimentation that would be associated with velocities below
3 ft/sec (0.91 m/s) would promote the growth of the anaerobic SRB and so most
experts recommend that normally flowing systems be designed for at least 3 ft/sec
(0.91 m/s) to keep solids in suspension. Provisions for chemical treatment such as
injection points, special provisions to make sure that the chemicals will reach all
parts of the system, and provisions for side-stream monitoring or spool pieces should
be included in the system design.
FIGURE 6.12 24-inch cooling water header where velocity exceeds 10 ft/sec.
Corrosion and Fouling 79
FIGURE 6.13 24-inch cooling water header with normally zero velocity.
Depending on the desired service life, standard wall pipe thicknesses may not be
adequate for CS piping. This is especially true for piping 3-inch (7.6 cm) and smaller.
Socket welded SS pipe may be employed that is inherently much less susceptible to
MIC. If SS piping is used for larger piping requiring butt welds, an effective biocide
treatment designed to prevent the formation of MIC nodules over the welds is imper-
ative. (See Section 6.3.1.) For larger piping, CS may be acceptable for hung piping
systems as long as the size of the piping is increased to account for the increased
pressure drop due to MIC and the pipe wall thickness is increased to account for the
anticipated rate of pitting corrosion. (See Chapter 7.)
6.2.2 Asiatic Clams
The Asiatic clam (corbicula fluminae), an exotic freshwater bivalve mollusk, was
first discovered in North America near the mouth of the Columbia River in 193822
and has since spread throughout the United States. Unless precautions are taken,
Asiatic clams often enter the cooling water system as adults or larvae when the sys-
tem was initially flooded or soon after it began operation. Once in a cooling water
system, Asiatic clams can grow rapidly, as much as 1/10-inch (0.254 cm) per month,
and may grow to be 2 inches (5.1 cm) in size and can produce veligers throughout
the year.23 Adult Asiatic clams cannot attach to a surface and have limited mobility
with a single “foot”, so they are frequently found in low areas or areas of low veloc-
ity. As documented in Section 1.8, they have been a major concern to the NRC, as
they have been the cause of numerous challenges to safety-related cooling water
systems that are used only infrequently. The clams settle in upstream areas and grow
until the system is called upon to operate. They are then sometimes swept up in the
cooling water flow until they obstruct an important piece of equipment such as a
valve or HX. Asiatic clams elude periodic chemical treatment regimens, as they
sense the presence of the chemical and can close up until the danger passes. However,
veligers smaller than 1/32-inch (0.079 cm) have not yet developed a protective shell
and are thus susceptible to biocides. Asiatic clams spawn when the cooling water
temperature is above 60°F (15.6°C) and have been reported to spawn well below
65°F (18.3°C).23
6.2.3 Zebra Mussels
Unlike the Asiatic clam, the zebra mussel’s byssal threads can attach to almost any
surface.24 Zebra mussels have spread rapidly, as their planktonic (drifting) veliger
stage remains in the water for several weeks after release, allowing it to be carried
great distances before settlement. By 1991, zebra mussels were found in the TVA’s
Kentucky Lake near where the Tennessee, Ohio, and Mississippi Rivers converge. In
1994, EPRI predicted that zebra mussel infestations would eventually be found in
70% of the states. Presently, they may be found in 28 states or over 50% of the states.
Zebra mussels can be found where the pH is greater than 5.5 and the water tempera-
ture is between 54 and 90°F (12.2 and 32.2°C).24 Since they feed on suspended sol-
ids, zebra mussels have brought about great change in the ecology of bodies of water
such as the Great Lakes, resulting in a shift in species composition due to the increas-
ing clearing of the water.25
Corrosion and Fouling 81
Unlike the Asiatic clam, the zebra mussels attach to hard surfaces by byssal
threads to almost any surface.26 The zebra mussel can grow up to 2 inches (5.1 cm)
in length27 and are a serious hazard to cooling water systems, as they may be found
on IPS trash racks and forebays, system piping, and HXs.24 Fortunately, zebra mus-
sels may be controlled by a combination of monitoring and chemical treatment or
heat treatment. Sodium hypochlorite in doses of less than 1.0 ppm is effective in
controlling zebra mussels.28 However, areas that may be up stream of the biocide
injection point such as IPS trash racks and forebays pose a challenging problem.
0.12
0.10
Diameter Reduction, inches
0.08
0.06
0.04
No Treatment
0.02 Chlorination
Zinc Polyphosphate
0.00
0 2 4 6 8 10 12
Time Aftrer Start of Test, months
The observed high initial rate of buildup and lower rate later in the test are consis-
tent with the sample data described in Section 6.1.2 and plotted in Figure 6.4. The
study concluded the following:
• The rate of buildup was initially very rapid but had slowed dramatically by the
end of the test.
• The chlorinated line experienced more rapid buildup of deposits than the other
two lines.
• Zinc polyphosphate in the concentrations tested had little if any beneficial
effect under the test conditions.
• Corrosion-resistant materials would be needed in many instances instead of CS
because of the serious corrosion problems with CS and the lack of effective-
ness of corrosion inhibitors.1
6.4.2 Biocide Testing
Prior to implementing the proposed cooling water system chemical treatment regi-
men, TVA sponsored testing by various organizations to ensure the feasibility of the
proposed regimen. The questions that needed to be answered were as follows:
Toxicity tests were conducted by the Ecology Laboratory of the Oak Ridge National
Laboratory (ORNL) to provide the necessary technical information to support regu-
latory approval for the use of the biocide in the ERCW system at SNP. The biocide
tested was Actibrom 1338, a proprietary bromine and dispersant mixture manufac-
tured by Nalco Corporation. The tests were conducted with the Actibrom 1338 mixed
with sodium hypochlorite at a 1:1 molar ratio. Tests conducted included both a
Ceriodaphnia seven-day survival and reproduction test and a fathead minnow larval
growth test also of seven days’ duration. The Actibrom 1338/sodium hypochlorite
mixtures (1:1 molar ratios) did not result in increased mortalities at concentrations in
excess of 30 ppm.
Qualification tests were conducted by the SM&E Laboratory to evaluate the
potential adverse effects of candidate biocides on the material of construction of the
wetted parts of a typical cooling water system and to ensure that the introduction of
the biocide into the system does not cause the corrosion products buildup on the CS
piping to become detached from the surface of the pipe wall. A test was conducted in
which three samples of 2.5-inch (6.4 cm) CS pipe and three samples of 6-inch
(15.2 cm) SS pipe all containing corrosion products including tubercles were sub-
jected to a 30-day exposure. One sample each of carbon and SS was exposed to
untreated raw water, one each was exposed to a raw water solution treated with a
solution of generic sodium bromide activated by sodium hypochlorite, and one each
was exposed to raw water treated with Nalco Actibrom 1338 mixed with sodium
hypochlorite. The biocides were initially injected at 7.5 ppm of free available
Corrosion and Fouling 85
chlorine with a 1:4 molar ratio of bromine to chlorine. A visual and tactile inspection
of the SS specimens at the end of the test revealed an absence of slime on the surfaces
of biocide-treated specimens, but no significant amount of corrosion products was
removed from the CS specimens.35
Corrosion tests were conducted on materials typically found in ERCW systems to
determine the relative corrosivity of candidate biocides on these materials in a sterile
solution of simulated raw water. The primary purpose of this test was to determine if
the addition of bromine or bromine with a dispersant increases the corrosion rate
when compared with sodium hypochlorite alone. The test was accelerated somewhat
by employing a biocide level of 7.5 ppm, which was five times the anticipated level.
Biocides containing bromine did not appear to be more corrosive than sodium
hypochlorite alone. In fact, the addition of commodity sodium bromide resulted in a
corrosion rate decrease for all CS specimens tested, accompanied by an increase in
the amount of passivated surface area. The slight increase in the corrosion rate with
Actibrom 1338 appeared to be due to the dispersant in this solution acting to remove
corrosion products from the surface of the CS. All copper alloys tested exhibited
good protection in the simulated raw water without biocide and significant corrosion
rates when exposed to sodium hypochlorite. All of the copper alloys showed a
decrease in corrosion rate when bromine was present in the biocide. All of the
austenitic SS specimens and weld coupons exhibited very low corrosion rates.
However, all of the austenitic SSs except AL-6XN exhibited some susceptibility to
crevice attack in one or more of the solutions, and some of the austenitic stainless
welded coupons exhibited minor crevice attack in the solutions containing
bromide.36
A test was conducted to evaluate the potential degradation effects on Buna-N
rubber materials which are used as O-rings in the ERCW system. Some of the O-rings
tested were sandwiched between corrosion coupons used in the test described above
while others were stretched over the coupon assemblies to provide the compressive
force for the sandwiched O-rings. Physical property measurements were selected for
their response to potential degradation, due to exposure to the biocides and included
hardness, tensile strength, elongation, and modulus. The results of these tests,
performed in accordance with the appropriate industry standard, showed no physical
property degradation as a result of exposure to the biocide.37
Tests were conducted by the University of Tennessee’s Institute for Applied
Microbiology (IAM) to determine the effectiveness of various biocides at controlling
sessile and/or planktonic bacteria populations and on controlling MIC. An initial test
was conducted on MIC nodule on a 6-inch (15.2 cm) SS weld removed from the SNP
to determine if a biocide consisting of chlorine and a dispersant could penetrate the
nodules and provide growth inhibition of the corrosive microorganisms without
dissolution or removal of the nodule. The test was conducted in a re-circulating
system in which the test water was replaced with fresh lake water treated with biocide
at approximately 48-hour intervals to maintain a total available chlorine concentration
of approximately1 ppm. During the test, the pH varied between 7.4 and 8.75. No
significant reduction in the size of the nodules was observed. Biological tests
conducted by IAM concluded that although there remained a very diverse population
86 Engineering of Power Plant and Industrial Cooling Water Systems
of organisms in the nodules, their numbers were very low and those that were present
were in a dormant condition.38
A series of tests was conducted by IAM which were specifically designed to
determine the biocide composition, dosage, and application time required to be
effective controlling MIC-causing bacteria.38 In six identical test stands, CS and SS
specimens were exposed to a re-circulating sterile medium. Three of these test loops
were inoculated with a mixed consortium of six types of bacteria including FeRed,
FeCcpt, SRB, and Ps taken from TVA nuclear plants. Within a few days, sessile
bacterial colonies were formed as tubercles on the CS specimens in the inoculated
loops (tubercles did not form on the SS specimens). After the colonies were
established, two of the three inoculated loops were treated with a biocide, with the
third serving as a control. The first test loop was treated with NaOCI alone, the
second was treated with commodity NaBr/NaOCI. The same biocides were added to
two of the sterile loops with the third sterile loop left as a control. Direct electrical
measurements were made of the corrosion occurring in mohms, and microbes were
recovered after each test and the number of colony-forming units (CFU) was
determined. The activity of the biofilms was determined by measuring the C-14
acetate uptake by the microbial lipids on the specimens.
Two separate experiments were conducted. In the first experiment, both biocides
were fed to maintain a residual halogen of 2 ppm for one hour. This was followed in
24 hours with an additional exposure of 2 ppm for two hours. The NaBr/NaOCl
biocide was mixed at a 1:4 molar ratio and pH was maintained at 8.5. This treatment
regimen proved to be totally ineffective for both biocides. At the end of the second
biocide injection, the corrosion rates for the inoculated specimens that were treated
with biocides were higher than the control, and the viable organisms recovered from
the specimens showed no evidence of damage to the bacteria and in many cases there
was an increase in viable cells. These results suggest that ineffective or sub-lethal
pulses of biocide actually stimulate the bacteria. Each of the specimens, with and
without biocide additions, developed a corrosion products layer over the specimen
which when removed revealed a smooth surface. In contrast, those specimens that
were inoculated with bacteria exhibited severe pitting on the metal surface after
removal of the biofilm.
A second experiment was designed in which both biocides were fed at slug dose
of 16 ppm for two hours followed by a continuous residual halogen of 2 ppm for 24
hours. The NaBr/NaOCl biocide mix was changed to a 1:1 molar ratio, and the pH
was kept at 8.5. This second treatment regimen had a marked biological effect.
Although the presence of oxidants in the system increased the general corrosion rate
both with and without bacteria present, the test results shown on Figure 6.15 indicate
that both biocides were effective in killing bacteria, and that the NaBr/NaOC1
biocides may be slightly more effective on sessile (coupon) bacteria than NaOC1
alone. This result is to be expected since the pH for the test was selected to be
prejudicial against chlorine alone. The data also suggest that both biocides are
effective against a broad spectrum of bacteria. Figure 6.15 suggests that although a
biocide may lower the number of CFUs below 106/ml, thus rendering the biofilm
inactive, even bacteria that were suppressed below detectable levels were able to
partially recover within 24 hours after termination of biocide treatment. Micrographs
Corrosion and Fouling 87
22
sterile
20 unknown
HCl/Br
18 NaClO
no biocide
16
14
dpm (thousands)
12
10
0
0 10 20 30 40 50
time (hrs)
of the specimens tested showed that pitting corrosion characteristic of MIC is greatly
reduced when an effective biocide is employed support the numerical data.38
FIGURE 6.16 Halogen residual and corrosion rates in the SNP ERCW system.
FIGURE 6.17 WBNP carbon steel corrosion rate vs. cooling water temperature.
was added to sodium hypochlorite to produce hyprobromous acid and fed four hours/
day with a halogen residual (0.1–0.5 ppm). One reason that bromine activated by
sodium hypochlorite was preferred over straight chlorine is that it is less corrosive
than chlorine. Other advantages include better performance at elevated pH and less
persistence in the environment. However, hypobromous acid fed for a few hours at a
time has very limited effect on macrofouling by clams and mussels. The chemical
treatment program also included phosphate (1–1.8 ppm), zinc (0.2–0.25 ppm), and
Copolymer (0.28–0.35 ppm) fed continuously and Azol blend (3.5–4.0) 15 minutes
1–2 times/month, DMAD (0.5–0.62) fed for 30 minutes once a week, and Quat
(0.15–1.5 ppm) fed for 24 hours twice a week. BFNP reported that the results were
as good or better than expected.42
effective at pH > 7.5, and is less persistent in the environment. However, if the residu-
als are kept low and the cooling water is mixed with the CCW before being dis-
charged, a chlorine-only biocide is not normally offensive. Commercial biocides
such as Nalco’s Actibrome 1338 also contain a proprietary dispersant. Actibrome
1338 has been shown to clean up corroded CS piping over time. However, the result
may be a relocation of the iron and other constituents on the surfaces of HX tubes.
Handling and mixing liquid chlorine and bromine in the right proportions can be
challenging. In some locations where pH < 7.5, one may be able to achieve satisfactory
results with just sodium hypochlorite alone or in conjunction with a polyphosphate to
soften and remove MIC nodules over time and/or a copolymer dispersant to maintain
sequestered small particles in suspension to be removed by the flowing water if required.
By far the greatest impediment to a successful biocide treatment program is the
reliability of the chemical feed system. Adequate engineering must go into the design
of these systems to ensure reliable operation. Consideration should be given to
installing redundant components such as pumps, etc., or even full redundant trains of
equipment to achieve the required 100% availability. This job is often left to the
chemical manufacturer without adequate oversight.
Common practice is to suspend biocide treatment except during the mollusk
spawning season or to rely on periodic shock treatments. Biocide treatment programs
that rely on intermittent operations permit veligers to enter the cooling water system
where they hide out and grow the protective shell. Even if the periodic treatment is of
such duration as to starve the mussel, the result is a dead mussel in the system, which
is hardly better than a live one.
In areas where zebra mussels are a problem, one should control their growth
upstream of the point of biocide introduction. The use of antifouling paints such as
cuprous oxides, copper epoxies, or nontoxic coatings such as silicone rubber impreg-
nated with silicone oil should be considered. The system at WBNP of introducing
BCDMH (commonly used in swimming pools) upstream of the trash racks and/or
traveling screens is of interest in that it holds promise for controlling zebra mussels
as well as Asiatic clams. One might surmise that this arrangement could lead to accel-
erated corrosion of the traveling water screens if they are made of CS.
Unlike oxidizing biocides such as chlorine or bromine where the residual becomes
relatively inert when their demand is satisfied, non-oxidizing biocides such as Clam-
trol or DGH-QUAT are poisons that are long-lasting and very expensive. Their use in
open cooling water systems is highly problematic, generally requiring the system to
be shut down, isolated, and flushed after the mollusks have been killed.
The perfect is often the enemy of the good. In some cases, the cost of the chemical
treatment system has become so high as to become unaffordable, resulting in the
elimination of chemical treatment all together. Care should be taken to implement the
least costly system that is effective. In most instances, this will be determined by site-
specific conditions.
REFERENCES
1. Bain, W. S., et al. Corrosion in Carbon Steel Raw Water Piping, (TVA Ref.
ESS800416204) Tennessee Valley Authority, Knoxvville, TN, 1979.
92 Engineering of Power Plant and Industrial Cooling Water Systems
2. Bowman, C. F. and W. S. Bain. A New Look at Design of Raw Water Piping. Power
Engineering Magazine, Vol. 84, No. 8, pp. 73–77, August 1980.
3. TVA Mechanical Design Guide DG-M5.2.1. Corrosion/Erosion Allowance for
Determination of Minimum Pipe Wall Thickness in Carbon Steel Piping Systems,
Tennessee Valley Authority, Knoxville, TN, 1980.
4. IN 85-30. Microbiologically Induced Corrosion of Containment Service Water System,
Nuclear Regulatory Commission, Washington, DC, 1985.
5. Generic Letter 89-13. Service Water System Problems Affecting Safety-Related
Equipment, Nuclear Regulatory Commission, Washington, DC, 1989.
6. “Microbiologically Influenced Corrosion (MIC)”, Institute of Nuclear Power Operations
Significant Event Report SER 73–84, 1984.
7. Licina, George. Sourcebook for Microbiologically Influenced Corrosion in Nuclear
Power Plants, Electric Power Research Institute, Palo Alto, CA, 1988.
8. Pavinich, W. A. et al. Four-Point Bend Testing of MIC-Damaged Piping, (TVA Ref.
B45890825251) Tennessee Valley Authority, Knoxville, TN, 1989.
9. Deardorff, A. F., et al. Evaluation of Structural Stability and Leakage from Pits Produced
by MIC in Stainless Steel Service Water Lines. Corrosion 89, 1989.
10. Pavinich, W. A. et al. Mechanical Properties of Stainless Steel Weldments Degraded by
MIC, Paper No. 531. Corrosion 90, 1990.
11. TVA Civil Design Standard DS-C1.2.8, Structural Evaluation of Microbiologically Induced
Corrosion Degradation in Piping, Tennessee Valley Authority, Knoxville, TN, 1991.
12. Blackburn, F. E., and Mullin, L. J. Detection and Control of Bacterial Corrosion Using
Internal Corrosion Monitors. Microbially Influenced Corrosion and Biodeterioration,
MIC Consortium, Knoxville, TN, 1990, pp. S1–S24.
13. Bowman, C. F. and P.V. Guthrie, Jr. Corrosion in Carbon Steel Service Water Piping.
1994 ASME Pressure Vessel and Piping Conference, ASME, 1994.
14. Tuovinen, J. E., et al. Bacterial, Chemical, and Mineralogical Characteristics of
Tubercles in Distribution Pipelines. Journal AWWA, American Water Works Association,
Denver, CO, pp. 626–635, November 1980.
15. Metell, H. M. Corrosion from Iron Bacteria in Plant River Water Systems. Proceedings,
Workshop on Microbe Induced Corrosion, Electric Power Research Institute NDE
Center, Charlotte, NC, 1986.
16. ANSI/ANS-59.1-1986. Nuclear Safety Related Cooling Water Systems for Light Water
Reactors. American Nuclear Society, 1986.
17. Generic Letter 90-05. Guidance for Performing Temporary Non-Code Repair of ASME
Code Class 1, 2, and 3 Piping, Nuclear Regulatory Commission, Washington, DC, 1990.
18. ASME B31G-1991. Manual for Determining the Remaining Strength of Corroded
Pipelines, American Society of Mechanical Engineers, New York, NY, 1991.
19. Herro, H. M. Corrosion and Fouling in Nuclear Power Plant Service Water Systems,
Electric Utility Service Water System Reliability Improvement-A Compendiun of
Presentations, Electric Power Research Institute, Palo Alto, VA, 1993.
20. Herro, H. M. and R. D. Port, The NALCO Guide to Cooling Water Systems Failure
Analysis, McGraw Hill, Inc., New York, 1993.
21. Characklis, W. G., et al. Biofouling Control Technology: The Roll of Fouling Monitors.
Condenser Technology Symposium, Electric Power Research Institute, Providence, RI,
1987.
22. Jenner, H. A., et al. Hydroecologie Appliquee, Tome 10, Volume 1–2, Electricite de
France, 1998.
23. Derrworth, J. E., et al. Duke Power Company’s Development of a Biofouling Monitoring
Program at Two Nuclear Power Plants on the Southeastern Reservoirs. International
Macrofouling Symposium, Electric Power Research Institute, Orlando, FL, 1990.
Corrosion and Fouling 93
24. Mussalli, Y. G. Zebra Mussel Monitoring and Control Guide, Electric Power Research
Institute, Palo Alto, CA, 1992.
25. Jenner, H. A. Biomonitoring in Chlorination Anti-Fouling Procedures to Achieve
Discharge Concentrations as Low as Reasonable. International Macrofouling
Symposium, Electric Power Research Institute, Orlando, FL, 1990.
26. Armor, A. Zebra Mussels: The EPRI Response Update. International Macrofouling
Symposium, Electric Power Research Institute, Orlando, FL, 1990.
27. DeMoss, D., et al. Design Features to Mitigate Fish, Zebra Mussel, and Other
Macrofouling of Plant Components. International Macrofouling Symposium, Electric
Power Research Institute, Orlando, FL, 1990.
28. Matisoff, G., et al. Controlling Zebra Mussels at Water Treatment Plant Intakes II -
Velinger Dose/Response Static Tests. International Macrofouling Symposium, Electric
Power Research Institute, Orlando, FL, 1990.
29. Garbarino, L. N. Testing of Chemical Methods for Clam Control under Simulated Field
Conditions. International Macrofouling Symposium, Electric Power Research Institute,
Orlando, FL, 1990.
30. Isom, B. G. et al. Controlling Corbicula (Asiatic Clams) in Complex Power Plant and
Industrial Water Systems. American Malacological Bulletin, Special Edition No. 2. pp.
95–98, 1986.
31. Sommerville, D. C. and F. L. Steinert. Development of Alternative Macrofouling Control
Methods for the Diablo Canyon Power Plant. International Macrofouling Symposium,
Electric Power Research Institute, Orlando, FL, 1990.
32. Gross, A. C. Macrofouling Problems and Control Techniques in Marine water around
Long Island. International Macrofouling Symposium, Electric Power Research Institute,
Orlando, FL, 1990.
33. Kahabka, J. The Zebra Mussel: New York’s Experience. International Macrofouling
Symposium, Electric Power Research Institute, Orlando, FL, 1990.
34. Harwood, D. B. and D. J. Buda. Effective Zebra Mussel Control at Detroit Edison
Harbor Beach Power Plant. American Power Conference, Chicago, IL, 1993.
35. Guthrie, P. V., et al. Sequoyah Nuclear Plant Dipersion Tests on Carbon and Stainless
Steel Pipe Samples, Test 6 (R3), SME-COR-88-001, Singleton Materials Engineering
Laboratory, 1988.
36. Guthrie, P. V., et al. Sequoyah Nuclear Plant Evaluation of the Effects of Cl/Br Biocides
on the Corrosion of Metals within the ERCW, SME-COR-88-011, Singleton Engineering
Laboratory, 1988.
37. Guthrie, P. V., et al. Sequoyah Nuclear Plant Evaluation of the Effects of Cl/Br Biocide
Water Treatment on Buna-N Rubber, SME-COR-88-019, Singleton Engineering
Laboratory, 1988.
38. Van, A. et al. Accelerated Tests of Effects of Bromide Additions to Biocide Treatments on
Microbiologically Induced Corrosion (MIC) on Mild Steel, Institute for Applied
Microbiology, 1988.
39. Bowman, C. F. Solving Raw Water Piping Corrosion Problems. Power Engineering
Magazine, Vol. 98, No. 7, pp. 35–38, July 1994.
40. Hewette D. Utility Experience Report – Tennessee Valley Authority. Service Water Working
Group Meeting Proceedings, Electric Power Research Institute, Palo Alto, CA, 1989.
41. Riggle, K. TVA Watts Bar Nuclear Plant – Service Water Chemical Treatment Program,
Service Water Systems Reliability Improvement Seminar, Electric Power Research
Institute NDE Center, Charlotte, NC, 1993.
42. Garbarino, N., et al. Raw Water Treatment at the TVA Browns Ferry Nuclear Plant.
Service Water Reliability Improvement Seminar, Electric Power Research Institute,
Orlando, FL, 1997.
7 Pipe Flow
2
L Vpipe
hL , f = f (7.1)
di 2 g
where
hL,f = friction head loss
f = friction factor
L = length of pipe
di = inside diameter of pipe
Vpipe = water velocity in a pipe or tube
g = acceleration due to gravity.
Equation (7.2) is the value for the friction factor, f, determined from the Colebrook
equation2 as follows:
1 e 2.51
2 log10 (7.2)
f 3.7 D Re f
where
e = absolute roughness of pipe, ft
Equation (7.1) is more commonly expressed in terms of volumetric flow rate in
English units as follows:3
LQ 2
hL , f = 0.0311 f (7.3)
d5
where
Q = Flow rate, Gal/min
d = diameter of pipe, in.
7.1.2 Hazen-Williams Equation
Whereas the Darcy-Weisbach equation provides a more analytically based mathe-
matical solution to the head loss due to pipe friction, the empirical Hazen-Williams4
equation is more appropriate for power plant cooling water system applications. As
95
96 Engineering of Power Plant and Industrial Cooling Water Systems
shown in Chapter 6, the interior of cooling water piping systems is subject to deterio-
ration with age depending on chemical properties of the water and pipe material in
contact with the water. Scaling, corrosion, or bacterial attack can therefore adversely
affect the flow capacity of the system. Some provision must be made in pressure drop
calculations to account for this deterioration of the pipe interior surface. The most
readily available information for a quantitative expression of pipe surface condition
relative to operating experience and length of service life is the “C” factor used in the
Hazen-Williams equation shown in Equation (7.4).4
100 Q1.85
hL , f 0.002083 L 4.8655 (7.4)
C d
where
C = Hazen-Williams “C” factor
The Hazen-Williams formula is based on water at 60°F (15.6°C) having a kine-
matic viscosity of 1.13 centistokes. The kinematic viscosity of water can vary from 1.8
for water at 32°F (0°C) to 0.29 centistokes for water at 212°F (100°C), respectively.
However, this variation in kinematic viscosity for the normal range of cooling water
systems results in negligible changes in the friction head loss and may be ignored.
TABLE 7.1
Commonly Used Roughness Coefficients for Design Purposes
Type of Pipe C e
Cement asbestos 130, 140
5 4 0.00755
Bitumastic enamel-lined iron or steel centrifugally applied 1404
Smooth glass or plastic 135,5 1401 0.0055
Cement-lined iron or steel centrifugally applied 130,5 1404 0.00755
Cement mortar trawled in place 1255 0.0115
Copper, brass, lead, tin, or glass pipe and tubing 1304
Welded and seamless carbon steel 55-70,6 1001,4,5 0.0605
Welded and seamless stainless steel 1206
Wrought iron, cast iron 1001,4,5 0.0605
Tar-coated cast iron 1004
Galvanized iron 905 0.0125
Concrete, formed 80,5 100,4 1301 0.225
Spiral-riveted steel (flow with lap) 1004
Spiral-riveted steel (flow against lap) 904
Corrugated steel 604
Pipe Flow 97
V2
hL , F = k (7.5)
2g
where
hL,F = form head loss
k = resistance coefficient.
Tests have been conducted for most commercially available components of simi-
lar size and shape. The k factors for flanged pipe fittings shown in Figure 7.1 and
valves in Table 7.2 are from Reference 5.
The “k” factor for other components such as strainers and HXs must be obtained
from the manufacturer. (See Section 3.4 regarding S. P. Kenney strainers.)
7.2.2 Equivalent Lengths
When performing head loss calculations by hand, common practice is to express the
head loss through components in the cooling water piping system in terms of the
equivalent length of pipe that would produce the same head loss. Table 7.3 shows the
equivalent lengths of piping for an array of components from Reference 4.
The equivalent lengths were calculated for steel pipe carrying cold water. The
error for water in a steel pipe at 100°F (37.8°C) is about -5%. The error for epoxy-
coated or copper pipe is about 15% for water at 40°F (4.4°C) and 25% for water at
100°F (37.8°C). However, since these errors are in the conservative direction, they
are commonly neglected.2
As seen in Reference 6 by F. P. Carr and C. F. Bowman, a separate form of the
Hazen-Williams equation is required for form losses in piping components, since
they are not affected by changes in wall roughness. Therefore, in order to use the
equivalent length type analysis for form losses, the Hazen-Williams “C” factor asso-
ciated with the published data for such losses must be inserted into the equation as
seen in Equation (7.6).6
Q1.85
hL , F 0.001486 4.8655 (7.6)
d
98 Engineering of Power Plant and Industrial Cooling Water Systems
FIGURE 7.1 Recommended energy loss coefficient, k, for flanged pipe fittings.
Using the equivalent length approach, the head losses computed for form losses in
piping components using Equation (7.6) may be directly added to the head loss due
to the friction in the pipe using Equation (7.4) to determine the total head loss through
a run of cooling water piping.
Pipe Flow 99
TABLE 7.2
Recommended Energy Loss Coefficient, k, for Valves Fully Open
Valve type K
Angle 1.8–2.9
Ball 0.04
Butterfly
25-lb Class 0.16
75-lb Class 0.27
150-lb Class 0.35
Check valves
Center-guided globe style 2.6
Double door
8 in or smaller 2.5
10 to 16 in 1.2
Foot
Hinged disc 1–1.4
Poppet 5–1.4
Rubber flapper
V < 6 ft/s 2.0
V > 6 ft/s 1.1
Slanting discd 0.25–2.0
Swingd 0.6–2.2
Cone 0.04
Diaphragm or pinch 0.2–0.75
Gate
Double disc 0.1–0.2
Resilient seat 0.3
Globe 4.0–6.0
Knife gate
Metal seat 0.2
Resilient seat 0.3
Plug
Lubricated 0.5–1.0
Eccentric
Rectangular (80%) opening 1.0
Full bore opening 0.5
hL , f 100 Q1.85
0.2083 L 4.8655 (7.7)
100 C d
TABLE 7.4
Diameter Reduction in Flow Test Samples
Average Measured
Plant Diameter Reduction (in)
Widows Creek 0.405
Kingston 0.133
Gallatin
Section A 0.270
Section B 0.320
102 Engineering of Power Plant and Industrial Cooling Water Systems
where
hL,f /100 = friction head loss in feet per 100 ft of pipe.
Equation (7.8) is a least squares curve fit of the form of Equation (7.7).
hL , f
= a1 Q1.85 (7.8)
100
where a1 is a constant obtained from each set of test data. By setting Equation (7.7)
equal to Equation (7.8), one may solve for d as shown in Equation (7.9).
1
100
1.85
4.8655
d 0.2083 (7.9)
a1 C
For each set of data with a unique value of a1 a tabulation of values for d that satisfy
Equation (7.8) was created.
Per Figure 6.1, the fact that the flow through a CS cooling water pipe occluded by
corrosion products is a function of more than the roughness of the interior of the pipe
is obvious. Accordingly, a dimensionless parameter, d*, defined in Equation (7.10),
was found to be useful in correlating the values of d calculated from Equation (7.9)
with the measured values of diameter reduction. (See Section 6.2.1.)
d
dnom dCALC
(7.10)
d MEAS
where
dNOM = nominal inside diameter of new pipe
dCALCC = calculated inside diameter of pipe using Equation (7.9)
ΔdMEAS = diameter reduction corresponding to the percent volume reduction.
Figure 7.2 shows d* plotted as a function of “C” for all of the pressure drop tests.
The smallest variation of d* occurs at a value of “C” of approximately 57 at a
value of d* approximately equal to 2. Equation 7.11 shows the Hazen-Williams
equation modified by Bowman and Bain as discussed herein based on a slightly more
conservative value of “C” equal to 55 and a diameter reduction equal to twice that
measured.
hL , f 0.63 Q1.85
(7.11)
100
dNOM 2 d MEAS
4.8655
The Darcy-Weisbach equation can be written (for a pipe length of 100 ft) in the form
shown in Equation (7.12).
hL , f Q2
= 3.11 f (7.12)
100 d5
Pipe Flow 103
8
Gallatin 8 in. Section 1
Gallatin 8 in. Section 2
Kingston 6 in.
Windows Creek 3 in.
7
0
20 40 60 C 80 100 120
Equation (7.13) is a least squares curve fit of the form of Equation (7.12).
hL , f
= a2 Q 2 (7.13)
100
a2 d 5
f = (7.14)
3.11
Equation (7.15) is the expression for the friction factor in fully rough flow by Moody.9
Full rough flow is almost certain to exist at design flow in old, corroded piping.
1 3.7
= 2 log10 (7.15)
f e
d
where
“e” is in inches.
104 Engineering of Power Plant and Industrial Cooling Water Systems
10
Widows Creek 3 in.
Gallatin 8 in. Section 2
Gallatin 8 in. Section 1
Kingston 6 in.
0.1
0.01
0.0 0.5 1.0 2.0 1.5 2.5 3.0
d*, calculated diam. reduction/measured diam. reduction
e 3.7
(7.16)
d 1
10
2 f
For each pressure drop test with its unique value of a2, values of f were calculated for
different assumed d using Equation (7.14). Equation (7.16) was used to calculate e/d.
Figure 7.3 shows a plot of “e” vs d*.
The smallest variation in “e” appears to occur at a value of d* equal to 1.0 to 1.2
where e = 0.9 to 0.8 inches.
Equation (7.17) shows the Darcy-Weisbach equation as modified by Bowman and
Bain using a value of e = 0.9 inch and a calculated diameter reduction equal to the
measured value of diameter reduction (d* =1).
hL , f 3.11 f Q 2
(7.17)
100
dNOM d MEAS
5
where
2
f 2 log10 4.1 d NOM d MEAS (7.18)
As one may see from Table 7.1, highly regarded sources agree on the adoption of a
Hazen-Williams “C” of 100 as the commonly used value for the design of CS piping
Pipe Flow 105
FIGURE 7.4 Comparison of measured and predicted pressure drops for 6-inch pipe at
Kingston Fossil Power Plant.
FIGURE 7.5 Comparison of measured and predicted pressure drops for 3-inch pipe at
Widows Creek Fossil Power Plant.
in cooling water systems. Such was the case at TVA until it was proven otherwise.
Figures 7.4 through 7.6 show the raw data taken for various pressure drop tests along
with curves representing different methods of calculating pressure drop using the
Bowman–Bain equation.
These curves based upon the empirical evidence contained herein, illustrate the
inadequacy of an assumption of C = 100 for design purposes. The Bowman-Bain
Equations (7.11) and (7.17), account for not only the roughness of the inside surface
of the pipe but also the diameter reduction to predict pressure drop in piping.
At reasonable velocities, the Hazen-Williams equation as modified by Bowman
and Bain consistently predicts values of pressure drop greater than the modified
Darcy equation, perhaps because the large diameter reduction projected after 40 years
is doubled in Equation (7.11) but not doubled in Equation (7.17). As indicated in
106 Engineering of Power Plant and Industrial Cooling Water Systems
FIGURE 7.6 Comparison of measured and predicted pressure drops for 8-inch pipe at
Gallatin Fossil Power.
Figures 7.2 through 7.4, the resulting head loss comparison is based on C = 55 and
Δd = 0.4 inch (1.02 cm), since those are the values that resulted in a good correlation
for the three flow tests performed. Results may vary for other sites.
Like many power and industrial plants located on the interior, the Tennessee River
enjoys relatively soft water having an average pH of 7.3. For those plant sites that
have similar conditions, the results of this study should have a profound impact on
the design of future raw water piping systems, since the pressure drops calculated by
methods recommended herein are significantly greater than those which would be
calculated by presently recognized standard methods. It should be noted that these
results apply only to friction losses and should not be applied to form losses.
In 1986, the results of the TVA flow and pressure drop tests were presented at an
EPRI workshop on MIC.10 The presentation gained little notice.
hL P1 P2 Z1 Z 2 VH1 VH 2 (7.19)
where
hL = total head loss
P1 and P2 = gauge pressure
Z1 and Z2 = elevations of the gauge pressure
VH1 and VH2 = velocity head.
Pipe Flow 107
2
Vpipe
VH = (7.20)
2g
where
Vpipe = velocity in the pipe
Form losses, hL,F, are calculated based on the equivalent lengths and subtracted
from the total head loss to yield the friction head loss, hL,f . (See Section 7.1.)
At TVA’s SNP ERCW system flow tests were conducted annually from 1980 to
1993.11 These test data yielded information to calculate the apparent “C” factor in
two large headers between the IPS and the auxiliary building. Each of the two 4000-
foot (1,220 m) runs of piping includes 24-inch (61.0 cm), 30-inch (76.2 cm), and
36-inch (91.4 cm) diameter sections of piping in series with varying flow rates in the
different sections of piping.
For a run of piping with multiple line sizes in series, the Hazen-Williams equation
as modified by Bowman and Bain may be expressed as Equation (7.21).
1.85 s L
100 Qn1.85
hL , f
100
0.2083
C
d 2 d MEAS
4.8655
n (7.21)
100
n 1 NOM , n
where
s = number of pipe sections
Qn = flow in each section of pipe, gal/min
dNOM, n = nominal pipe diameter in each section of pipe, in
L = length of pipe in each section, ft.
Solving for “C” yields
1.85
s L 1
Qn1.85
C
0.2083 x 100
hL , f
d NOM ,n 2 d MEAS
4.8655
n
100
1.85
(7.22)
100
1
At TVA’s Sequoyah plant, flow tests were conducted on the ERCW system by mea-
suring the cooling water pressures at the IPS and at the auxiliary building. The
Sequoyah test data have yielded sufficient information to calculate the apparent “C”
factor in the two large headers between the IPS and the auxiliary building. Each of
the two runs of piping has varying flow rates in the different sections of piping.
Since it is impractical to remove a section of large-diameter piping to take a mea-
surement, a value of ΔdMEAS = 0.2 in. (0.51 cm) was assumed based on Figure 6.4 and
the age of the piping. However, the “C” factor calculated from Equation (7.22) is
relatively insensitive to the value of ΔdMEAS for such large diameter pipe.
Figures 7.7 and 7.8 show the results of these tests for headers 2A and 2B,
respectively.
108 Engineering of Power Plant and Industrial Cooling Water Systems
100
90
85
80
75
70
80 82 84 86 88 90 92 94
Test Year
FIGURE 7.7 Sequoyah Nuclear Plant ERCW header 2A Hazen-Williams “C” factor.
95
Hazen-Williams "C" Factor
90
85
80
75
70
65
80 82 84 86 88 90 92 94
Test Year
FIGURE 7.8 Sequoyah Nuclear Plant ERCW header 2B Hazen-Williams “C” factor.
The results are somewhat scattered even though these tests were performed with
calibrated instruments and the data was independently verified. However, this scatter
is to be expected, since the tests involved measuring pressures with separate pressure
gauges approximately one-half mile apart and measuring flows in 30-inch (76.2 cm)
piping with standard flow orifices.
The results are somewhat surprising, because the “C” factors do not appear to be
decreasing with age as expected. However, as discussed in Section 6.5, the piping
was first placed in service in 1977 and 1978. By 1982, the “C” factor had degraded
to approximately 90 for Header A and 70 for Header B when the biocide treatment
was implemented. The fact that Train A is normally operated, while Train B is not,
may be a consideration. (See Figure 6.13.)
Pipe Flow 109
TABLE 7.5
Watts Bar Nuclear Plant ERCW Header Hazen-Williams “C” Factors Before
and After Lining with Cement Mortar In Situ
“C” Factor “C” Factor
Supply Header for CS for CML
1A 74.6 163.7
2A 80.7 184.8
1B 77.1 219.5
2B 75.4 154.1
Average 77.0 181.5
In 1982, TV A conducted similar flow test on the supply headers at the WBNP
before and after the CML was applied as discussed in Section 5.4.5.12 The Hazen-
Williams “C” factor for the piping before and after the CML was applied is shown in
Table 7.5.
The increase in flow-passing capability of the piping is quite dramatic. The result
has been an increase header pressure in the ERCW system inside the auxiliary build-
ing. The average value for CML is even higher than the published Values of “C” =
130-140. (See Table 7.1.) The scatter in the results of the CML tests when compared
to the CS tests is due to the lower head loss measured relative to the test instrument
accuracy. These tests were conducted prior to completion and commercial operation
of WBNP, so each header was operated about the same amount of time and without
biocide treatment.
In 1983, a similar flow and head loss test was conducted on the BFNP EECW
system. The EECW system pressure was measured at the EECW pump discharge
and at the entrance to the emergency diesel generators. The flow to the diesel genera-
tor HXs was measured in the 14-inch (35.6 cm) and 18-inch (45.7 cm) CS pipes from
the pumps. The “C” factor calculated by the procedure described in this section was
C = 88 assuming Δd = 0.2 (0.51 cm) in.
hydraulic design standards provide appropriate default values for internal diameters
and roughnesses of piping, equivalent lengths of various fittings, and loss coefficients
for combining and dividing flow through tees. Available inputs include global or
local specifications of corrosion effects on pipe roughness and inner diameter values.
The network input data are saved in text format to a disk file that may be edited later
using either the editing capabilities available in MULTIFLOW or any text editor.
After all necessary input data are provided, MULTIFLOW solves the system and
provides output reports to a printer or to the monitor.
MULTIFLOW was developed and tested in accordance with the requirements of
TVA Nuclear QA criteria for computer software. The requirements included
validation by comparing results obtained using MULTIFLOW with results obtained
by hand calculations for an extensive set of problems exercising all of the capabilities
of MULTIFLOW. In addition to its adherence to TVA QA criteria and mechanical
design standards, MULTIFLOW has several input, solution, and output capabilities
that are not usually available in general-purpose network codes. The size of a network
solved using MULTIFLOW is limited only by available computer memory.
MULTIFLOW iteratively computes flows through tees using separate loss coefficients
for each flow path that depend on the ratio of flow through the path to total flow
through the tee. MULTIFLOW computes fluid temperatures throughout a network
based on specified supply flow temperatures and specified loads at HXs. For
condensate systems, fluid densities, viscosities, and vapor pressures are treated as
variable with temperature and pressure. MULTIFLOW allows the flow in a link to be
fixed at a user-specified value and computes the valve flow coefficient or pump total
head required to achieve the desired flow. Components handled by MULTIFLOW
include pipes, pumps, check valves, pressure regulating valves, relief valves, tees,
fixed flows, and various sources of energy loss (e.g., valves, elbows, reducers, etc.).
MULTIFLOW also contains built-in design diagnostic tools that flag unacceptable
conditions, such as pressures below the vapor pressure.
The RCW system for each nuclear unit at SNP takes its suction from the CCW supply
conduit upstream of the MC. There are four 20” (50.8 cm) RCW strainers and five
horizontal, centrifugal, dry-pit RCW pumps. One of the RCW pumps is an installed
spare. The RCW system serves innumerable non-safety-related HXs in the SNP such
as the turbine lube oil cooler, stator water cooler, hydrogen cooler, and a host of smaller
HXs serviced by small CS piping. The RCW system discharges back into CCW dis-
charge conduit at various points downstream of the MC. MULTIFLOW was utilized to
determine which CS RCW piping would be required to be replaced with SS.
Measurements of the RCW system pressures were made at the RCW pump suc-
tion and discharge and at 15 points in the system. Table 7.6 show the results of
MULTIFLOW runs for an array of Hazen-Williams “C” factors and values of Δd.
The results of the test implied that the Hazen-Williams “C” factor and the diameter
reduction that best modeled the actual pressures in the SNP RCW system are C = 80
and Δd =0.15 inch (0.381 cm), with an average difference between the measured pres-
sure and the pressure calculated using MULTIFLOW of only 0.3 psi (2.1 kPa).
TABLE 7.6
Sequoyah Nuclear Plant RCW System Pressure Difference* For an Array of
Hazen-Williams “C” Factors and Δd
Hazen-Williams Average
“C” Factor Δd ΔP (psi)
100 0 7.6
90 0.3 −1.0
85 0.2 −1.8
85 0.3 −0.5
80 0.15 0.3
80 0.2 0.5
80 0.3 0.3
70 0.3 2.3
TABLE 7.7
Sequoyah Nuclear Plant RCW System Piping Replacement
Line size (in) Length (ft) Elbows Gate Globe Reducer Butterfly
0.75 44 8 8 4 1
1.00 994 44 15 13 17
1.50 229 20 5 3 2
2.00 1803 58 14 18 4
2.50 573 68 20 1 12
3.00 471 25 3 6 4
4.00 379 26 2 1 2
6.00 76 7 1
14.00 104 4
Table 7.7 shows which CS RCW piping would need to be replaced with SS. The
RCW Pumps would also need to be replaced with higher head pumps.
REFERENCES
1. Linsley, R. K. et al. Water-Resources Engineering, 4th ed., pp. 347–349, McGraw-Hill,
Inc., 1992.
2. Hansen, E. G. Hydronic System Design and Operation-A Guide to Heating and Cooling
with Water, p. 61, 63, McGraw-Hill, Inc., 1985.
3. Crane Technical Paper No. 410, 24th Printing, Crane Co., King of Prussia, PA, 1988.
4. Cameron Hydraulic Data, 16th ed., pp. 3–7, 3–8, 3–20, Ingersoll-Rand, Woodcliff Lake,
NJ, 1981.
5. Mays, L. W., Water Resource Engineering, 2nd ed., pp. 473, 489–492, John Wiley &
Sons, Inc., 2011.
6. Mechanical Design Standard DS-M3.5.1, Rev. 7, Pressure Drop Calculations for Raw
Water Piping and Fittings, Tennessee Valley Authority, Knoxville, TN, 1999.
7. Bain, W. S., et al. Corrosion in Carbon Steel Raw Water Piping, (TVA Ref.
ESS800416204) Tennessee Valley Authority, Knoxville, TN, 1979.
8. Bowman, C. F. and W. S. Bain. A New Look at Design of Raw Water Piping. Power
Engineering Magazine, pp. 73–77, Vol. 48, No. 8, August 1980.
9. Moody, L. F. Friction Factors for Pipe Flow. Transactions of the ASME, Vol. 66, No. 8,
pp. 671–684, 1966.
10. Bowman, C. F. Microbe – Induced Corrosion of TVA Raw Cooling Water Piping.
Proceedings of the EPRI Workshop on Microbe Induced Corrosion (MIC), Electric
Power Research Institute, 1986.
11. Bowman, C. F. Solving Raw Water Piping Corrosion Problems. Power Engineering
Magazine, Vol. 98, No. 7, pp. 35–38, July 1994.
12. Bowman, C. F. In Situ Cement-Mortar Lining of Safety-Related Service Water Piping
Systems. International Joint Power Conference, 94-JPGC-NE-6, 1994.
13. Schohl, G. A., et al. MULTIFLOW, a Quality Assured Intuitive Computer Code for
Hydraulic Analysis of Pipe Networks. Proceedings of the 1995 International Joint
Power Generation Conference, Vol. 2, pp. 67–79, 1995.
14. Sequoyah Nuclear Plant §316(b) – §122.21(r)(10) – (13) Information, Appendix A to
Transmittal from TVA to Tennessee Department of Environment and Conservation,
June 29, 2018.
8 Cooling Water System
Engineering Pitfalls
100
Head (Ft)
Gauge pressure
Cooling HX
Water
50 Pump
Lake level
Cooling
water piping
113
114 Engineering of Power Plant and Industrial Cooling Water Systems
HX
100
Vacuum
Head (Ft)
Gauge pressure
Cooling
Water
50 Pump
Lake level
Cooling
water piping
150
Gauge pressure HX
100
Head (Ft)
Cooling
Water
50 Pump
Valve
Lake level
Cooling
water piping
8.2 AIR LIBERATION
Since the atmospheric gases (primarily nitrogen and oxygen) are soluble in water,
significant quantities of these gases can be absorbed and carried into the piping sys-
tem. These gases can also cause flow disturbances and reduced heat transfer rates in
HXs if they come out of solution inside the system.
Henry’s law relates the important variables affecting gas solubility as shown in
Equation (8.1).
Px
Nx = (8.1)
Kx
where
Nx = mole fraction of dissolved gas, x
Px = partial pressure of dissolved gas x
Kx = Henry’s Law coefficient for gas x.
This equation shows that the number of moles of gas that can be dissolved in a
given quantity of water is directly proportional to its partial pressure and inversely
proportional to its Henry’s law coefficient. For a particular gas, the latter coefficient
is primarily a function of temperature, increasing as the temperature increases. Thus,
water becomes less soluble to air as the pressure decreases or the temperature
increases. Since this is exactly what happens as cooling water passes through the
cooling water system, it is possible for gases to be released within the system.
Air liberation within the system can affect heat transfer of system HXs. For exam-
ple, if a HX were to operate with a sufficiently high temperature rise, or was located
so that the local pressure was sufficiently low, air liberation could occur. This would
not necessarily create any problems. However, if the geometry of the HX or the cool-
ing water piping were such that liberated air could be trapped within the HX, the air
could displace the water and effectively reduce the available heat transfer area. This
could occur in HXs with a bottom outlet or where the cooling water piping turned
down at the outlet nozzle.
Air liberation can also affect fluid flow if conditions are such that the flow is in the
so-called “slug” flow regime. In this regime, large bubbles of liberated gases are
periodically swept through the system, so the cooling water flow is not steady but
pulsing and unacceptable vibration can also result.
The preferred approach in initial design is to avoid air liberation entirely. The first
step to achieve this goal is to calculate the maximum quantity of air dissolved in the
cooling water inlet. Henry’s law may be used in the following combined form, which
includes the effect from all atmospheric gases as shown in Equation (8.2).
Pb
N air = (8.2)
K air
116 Engineering of Power Plant and Industrial Cooling Water Systems
where
Nair = mole fraction of all dissolved gases
Kair = Henry’s Law coefficient from Figure 8.4.
The barometric pressure should be the standard atmospheric pressure correspond-
ing to the elevation of the free surface water level. To maximize Nair, the Henry’s law
coefficient, Kair, should be based on minimum cooling water supply temperature.
The final factor, C, accounts for the degree of saturation of the inlet water. Since
it is common for bodies of water to approach 100 percent saturation in the winter,
“C” should not be less than 1.0. However, it is also known that the water can be
supersaturated with air downstream of dams or where the source of cooling water is
an evaporative cooling device such as a cooling tower or spray pond. (See Chapter 10.)
Evaporative cooling devices may therefore justify a “C” value of 1.5, whereas a cool-
ing lake may dictate a value of 1.0. Hydroelectric turbine operation can cause satura-
tion up to 100 percent, while spillways and evaporative cooling devices can cause an
increase to 150 percent. Having determined the mole fraction of dissolved air in the
inlet cooling water, the next step is to determine the minimum pressure required to
keep this air in solution. Again, use Henry’s law as shown in Equation (8.3).
N air max
Prequired ’
(8.3)
K air
12
10
Henry's Law Coefficient, K AIR (x104)
0
0 10 20 30 40 50 60 70 80
where
Prequired = minimum gauge pressure to keep air in solution
Nair-max = maximum mole fraction of air in the entering cooling water
K’air = Henry’s Law coefficient based on the HX outlet temperature from Figure 8.4.
The key difference is that K'air is based on the HX outlet temperature. The outlet
temperature may be calculated using Equation (8.4).
Q
Tout Tin (8.4)
m cp
where
Tout = HX outlet temperature
Tin = HX inlet temperature
Q = maximum HX heat load
m = cooling water mass flow rate
cp = constant pressure specific heat.
Since Tout is greater than Tin, K’air in Equation (8.3) will be greater than Kair in
Equation (8.2) as evident from Figure 8.4. Tout must be calculated for each HX and
Prequired be determined for each different value.
The next step is to determine the actual minimum gauge pressure, Pactual, on the
discharge side of each HX. This involves simply calculating the hydraulic gradient as
discussed in Section 8.1. If “Pactual” is less than “Prerquired”, the potential exists for air
to be liberated within the HX and/or downstream piping due to the increase in
temperature. The fact that air is released is not necessarily unacceptable. The flow
regime must be determined to make the evaluation of those having the potential for
air liberation by first calculating the Froude number with Equation (8.5) and then
consulting Figure 8.5.
V2
Fr = (8.5)
gD
where
Fr = Froude number
V = local velocity
g = acceleration due to gravity
D = pipe or tube inside diameter.
Next one must calculate the air-to-water volume ratio, Vr, of air liberated at the
pipe or tube section being investigated. To determine this ratio, one must first find the
actual mole fraction of air released. This will be the difference between the mole
fraction of dissolved air in the inlet water, Nair, and the mole fraction that local condi-
tions will permit to remain in solution, “N’air” shown in Equation (8.6)
P’
’
N air = ’
(8.6)
Pb K air
118 Engineering of Power Plant and Industrial Cooling Water Systems
where
N’air = mole fraction that local conditions will permit to remain in solution
P’ = local static pressure
K’air = Henry’s Law coefficient at local temperature (from Figure 8.4).
The volume of air liberated per unit volume of water, Ve, is then calculated by first
considering the ideal gas law shown in Equation (8.7) and (8.8).
PV = nRT (8.7)
nRT
V = (8.8)
P
where
P = pressure
V = volume
n = number of moles
R = universal gas constant
T = absolute temperature
Cooling Water System Engineering Pitfalls 119
The volume of air liberated per unit volume of water, Vr, may then be calculated
by Equation (8.9).
Vr
N air
N air
’
RT ’
(8.9)
P’
where
Vr = air-to-water volume ratio
T’ = absolute local temperature.
The values of “Fr” and “V” are then plotted on Figure 8.5. Those that fall within
the bubbly flow regime are generally acceptable. Those in the slug flow region may
require modification.
Many possibilities exist to correct HX loops found to be in the slug flow regime.
However, many of the solutions become increasingly difficult as design and
construction progress. Perhaps the simplest solution is to relocate the flow-balancing
valve beyond the region having the potential for air liberation as shown in Figure 8.3.
This will pressurize the critical area by the amount of the differential across the
valve, possibly eliminating the potential for air release or transforming it to bubbly
flow. Another possibility is to reroute the piping to eliminate problem high points. It
may even be possible to relocate a HX to a lower floor as shown in Figure 8.1.
Booster pumps to pressurize problem areas are also effective, particularly on the
supply side of the HXs.
8.3 FLASHING
The term “flashing” refers to the change of state from liquid to gas. It is generally
associated with the formation of large volumes of vapor as a result of heating, expan-
sion into a low pressure region, or both. Flashing might occur, for example, within a
HX, because of the temperature rise of the water. The effective heat transfer area
would thereby be reduced, leading to a further rise in temperature, more flashing, etc.
Eventually the HX could become completely filled with vapor and unable to remove
its design heat load.
Flashing can also occur in regions of low pressure. Such regions might exist
downstream of flow-balancing valves or automatic temperature control valves. For
this reason, such valves should generally be located downstream of their associated
HXs to preclude the possibility of collecting vapor within the HX.
The first step in evaluating the potential for flashing is to determine the HX outlet
temperature as shown in Equation (8.4). The saturation vapor pressure, Psat, corre-
sponding to “Tout” may then be read from the ASME Steam Tables.2,3 Next, the local
HX outlet pressure is calculated as described in Section 8.1. If Plocal < Psat, as illus-
trated in Section 8.2, flashing will occur. The outlet of flow-balancing valves or tem-
perature control valves should also be checked for flashing. Flashing should not be
allowed to occur within system HXs. Possible corrective measures include all of
those mentioned in Section 8.2 for air liberation. It might also be possible to prevent
flashing by increasing the design flow rate of the cooling water, thereby decreasing
120 Engineering of Power Plant and Industrial Cooling Water Systems
8.4 CAVITATION
Whereas flashing deals with the formation of vapor, cavitation deals with the damag-
ing effects as the vapor bubbles change back to liquid. The implosion of the vapor
cavities can generate extremely high local pressures. The shock wave itself is suffi-
cient to fracture the grain boundaries of metal surfaces, causing removal of whole
grains and leaving a roughened metal surface. Erosion may lead to structural failure
or leakage. Corrosion accelerates the process.
Cavitation is generally associated with throttling valves, orifice plates, venturis,
and other such devices that create a sudden change in local pressure. The propensity
for and severity of cavitation may be determined by calculating the “cavitation index”
shown in Equation (8.10).
Pd Psat
’
Ki (8.10)
Pu Pd
where
Ki = cavitation index
Pu = local upstream pressure
Pd = local downstream pressure
Psat = saturation vapor pressure at the maximum operating temperature.
The acceptable cavitation level or index, “Ki”, so calculated may then be inter-
preted from Figure 8.6. If unacceptable cavitation is indicated by this procedure, the
corrective actions in Sections 8.2 for air liberation and/or 8.3 for flashing may be
effective. Generally, the low outlet pressure is the major contributor to the cavitation
problem, and steps to increase it will be effective. Adding a multihole restricting
orifice downstream of the cavitating component will increase the backpressure of the
component and reduce or eliminate the cavitation. However, the effect on system
performance at off-design points and over the plant life must be carefully considered.
If other measures are not feasible, the use of a special anti-cavitation valve or multi-
ple orifices might be considered. Initial piping design should attempt to minimize the
required throttling in the high-flow HX loops.
If the cooling water system design uses vertical pumps, provisions should be
made for air and vacuum, release between the pump discharge and the discharge
check valve. (See Figure 3.1.) The vacuum relief valve is required when the difference
in pump discharge elevation and the design low water level is greater than
approximately 33 feet (10.1 m) to prevent column separation when a pump is shut
Cooling Water System Engineering Pitfalls 121
down. When the pump is restarted, the air in the piping must be vented to prevent air
from being forced into the cooling water system, which could degrade the perfor-
mance of HXs served by the system.
8.5 WATER HAMMER
The information in this section is largely taken from Reference 5 by G. C. Dunn and
J. D. Hubble.
A
H Ho
g
Vo V (8.11)
122 Engineering of Power Plant and Industrial Cooling Water Systems
where
H = pressure head
Ho = initial pressure head
A = wave speed
g = gravitational constant
V = fluid velocity
Vo = initial fluid velocity.
Equation (8.11) applies only for a simple wave propagation when the deceleration
in fluid velocity from “Vo” to “V” occurs over a period of time, T, where t < 2L/A,
where “L” is the length of pipe and where the wave speed, A, is much greater than
the initial fluid velocity, Vo. The pressure wave thus generated travels through the
pipe. The travel time required for the return of this wave is defined in Equation (8.12).
2L
T = (8.12)
A
Ew
A (8.13)
w
where
Ew = bulk modulus of elasticity of water
ρw = density of water.
The wave speed in a pipe depends on the material, wall thickness, and type of
construction as well as the fluid properties and temperature. Equation (8.14) (in
English units) shows how to compute the wave speed as a function of the particular
piping system.7
Ew 1
A x (8.14)
E D
1 w
Ep t
where
Ep = bulk modulus of elasticity of the pipe material
D = pipe diameter
t = thickness of the pipe wall.
Wave speeds for large steel pipe may be as low as 3,000 ft/sec (914 m/s) for small,
high-pressure steel pipe or as low as 4,500 ft/sec (1,372 m/s) in the absence of
ingested air.
To calculate the wave speed in a homogeneous mixture of air and water, Equations
(8.15) and (8.16) are used along with Equation (8.14).
Cooling Water System Engineering Pitfalls 123
Ew
EM (8.15)
VM a Ew
1 1
VMT Ea
VM a VM w
M a w VM (8.16)
VMT T
where
EM = bulk modulus of elasticity of the mixture of water and air
Ew = bulk modulus of elasticity of water
Ea = bulk modulus of elasticity of air
VMw = volume of water
VMa = volume of air
VMT = total volume
ρM = density of the mixture of water and air
ρw = density of water
ρa = density of air.
Measurements of wave speeds as low as 1000 ft/sec (305 m/s) with 0.4 percent air
(by volume) in water have been published which show good agreement with these
equations.
Therefore, the assumption that the wave speed, A, is much greater than the initial
fluid velocity, Vo, in Equation (8.11) is valid.
When a change in fluid velocity occurs over a time interval greater than the travel
time of the resulting pressure wave as expressed in Equation (8.12), the change is
considered slow, and the governing equations in a frictionless system are shown in
Equations (8.17) and (8.18).8
H Ho F f (8.17)
g
V Vo
A
F f (8.18)
where
F = the magnitude of the pressure wave generated by a change in water velocity
and whose direction is opposite to original water flow
f = the magnitude of the reflected pressure wave generated by a change in water
velocity and whose direction is that of the original water flow.
where “F” is a function of t-x/A and f is a function of t+x/A and “x” is the distance
along the pipe.
Note that “x” is positive in the direction opposite the initial fluid velocity, since it
measures the distance upstream from the point of initial disturbance in flow.
Equation (8.17) implies that at a time, t, at a point “x” feet from the initial distur-
bance, the head rise is equal to the algebraic sum of the pressure wave, F, and the
reflected wave, f. These waves are propagated in opposite directions in the pipe with
124 Engineering of Power Plant and Industrial Cooling Water Systems
a constant velocity of “A” feet per second. When an “F” wave passes an “f” wave,
neither wave is attenuated or undergoes a change in shape.
Equation (8.18) relates the magnitude of the pressure waves “F” and “f” to the
change in velocity which propagates the waves.
Water hammer is generally caused by changes in the mode of equipment operation.
This, in turn, is most often the result of valve operation, startup, shutdown, or
inadequate venting actions.
A
H Ho
g
V Vo 2 f (8.19)
Initially, “f” equals zero at the valve. It may be shown that for a wave reflected from
a reservoir, the first reflected wave at the valve is equal in magnitude but opposite in
sign to the direct wave which left the valve “T” seconds earlier.6
For slow valve operation, the severity of potential water hammer may be deter-
mined by approximating the actual valve closure by a series of successive instanta-
neous stepwise movements at some time intervals, Δt, where Δt < T.
In order to determine the changes in velocity for a chosen time interval, a
relationship is required between the percent valve opening with respect to time
(during valve operation) and the valve coefficient as a function of valve opening.
With this information, the change in flow and corresponding change in velocity may
be calculated for the specified time interval. Equation (8.19) is then used to calculate
H – HO for the selected interval. For each stepwise movement, the initial values of
“H” and “V” are taken as the final value calculated from the previous step. This
procedure is repeated until the valve reaches its final position. Given a specified
design, this procedure allows the effects of valve operation to be evaluated.
Long pipe lengths will require relatively long valve closure times in order to pre-
vent water hammer. Equation (8.2) reveals that this factor is usually negligible unless
there are several thousand feet of pipe. However, consideration must be given to the
transient resulting from an instantaneous valve closure due to a motor operator fail-
ure. If such a failure would result in an unacceptable impact on the system, snubbers
(dampers) should be furnished with the valve operator.
Unless properly designed, a cooling water system is likely to experience water
hammer during startup and shut down due to the acceleration and deceleration of
fluid columns inherent in these operations. By proper design and operation, water
hammer can be avoided by controlling the rate of change of fluid column velocity.
Cooling Water System Engineering Pitfalls 125
During a cooling water pump start, the acceleration of the fluid column may be
controlled by starting the pump against a closed or partially closed discharge valve
and then gradually opening the valve. The reverse procedure may be followed when
shutting down a pump. Spurious pump trips can result in column separation in the
pump discharge, with resulting water hammer. The vacuum generated gradually
overcomes the receding water column with a spring-like action, and then collapses as
the column of water is reunited. A vacuum breaker/air relief valve may be used on the
pump discharge to prevent formation of the temporary vacuum.9 Check valves or
automatic-closing butterfly valves located on pump discharges may also aid in
reducing the detrimental effects of column separation at high points in the system by
keeping the upstream leg of piping full of water following a pump trip.
High points in the system which would be pressurized under normal operating pres-
sures, will experience depressurization and column separation upon system shutdown
if the high point is more than 33 feet (10.1 m) above the hydraulic gradient with the
system depressurized. Upon startup, as the system is re-pressurized, the vapor column
will collapse. This results in a water hammer as the column of water is reunited.
Vacuum breaker/air relief valves should be provided at all such high points to prevent
water hammer as the column is reunited. Carefully located check valves in the system
will often provide protection against column separation at high points in the system by
keeping the upstream leg of piping full of water following a system shutdown.
During startup, the system should be filled carefully to vent all air pockets at high
points so that flow will not be impeded. Care must be exercised in the sizing of vent
valves, since the size of the vent valve establishes the velocity at which the column
of water rises at the high point as the air is displaced by water. If the vent valve is too
large, resulting in the water column rising at a relatively high velocity, the resulting
deceleration as the last of the air is released can be very significant. This problem can
be particularly serious in large tanks and HXs. An alternative to careful sizing of the
vent valve would be to place an orifice in the vent line sized to restrict the rate at
which the air may be vented.
It should be emphasized that the complexity and potential consequences of water
hammer lead to design as the preferred method for control of hydraulic transients.
However, a detailed water hammer analysis may be required if the system design
parameters violate one or more of the guidelines described herein.
REFERENCES
1. TVA Mechanical Design Guide DG-M6.3.3. General Design of Essential Raw Cooling
Water Systems, Tennessee Valley Authority, Knoxville, TN, 1986.
2. Meyer, C. A. et al. ASME Steam Tables, 6th ed., American Society of Mechanical
Engineers, New York, NY, 1993.
3. ASME Steam Tables Compact Edition, American Society of Mechanical Engineers,
New York, NY, 1993, 2006.
4. Tung, P. and M. Mikasinovic. Eliminating Cavitation from Pressure-Reducing Orifices.
Chemical Engineering, December 12, 1983.
5. TVA Mechanical Design Guide DG-M3.5.3. Analysis and Control of Water Hammer in
Large-Diameter Raw Water Piping Systems. Tennessee Valley Authority, Knoxville, TN,
1982.
126 Engineering of Power Plant and Industrial Cooling Water Systems
6. Streeter, V. and E. B. Wylie. Hydraulic Transients, McGraw-Hill, Inc., Newe York, NY,
1967.
7. Linsley, R. K. et al. Water-Resources Engineering, 4th ed., p. 367, McGraw-Hill, Inc.,
1992.
8. Paramakian, J., Water Hammer Analysis, Prentice-Hall, Inc, New York, NY, 1955.
9. TVA Mechanical Standard Drawing SD-M6.1.1, Typical System Air Release
Requirements, Tennessee Valley Authority, Knoxville, TN, 1981.
9 Heat Exchangers
where
hc-in = cold stream enthalpy in
hc-out = cold stream enthalpy out
hh-in = hot stream enthalpy in
hh-out = hot stream enthalpy out
mc = mass flow rate of cold stream
mh = mass flow rate of hot stream
Q = rate of heat transfer.
Since
h cp T (9.3)
127
128 Engineering of Power Plant and Industrial Cooling Water Systems
then
where
tc-in = cold stream temperature in
tc-out = cold stream temperature out
Th-in = hot stream temperature in
Th-out = hot stream temperature out
cp,h = hot stream specific heat
cp,c = cold stream specific heat.
Any one of the six parameters may be calculated if the other five are known. For
example,
mc c p c tc out tc in
mh (9.5)
c p h Th in Th out
Q = U Ah F LMTD (9.6)
where
U = overall heat transfer coefficient
Ah = effective hot-side HX surface area
F = LMTD correction factor
LMTD = log mean temperature difference
Heat Exchangers 129
where
t1 t2
LMTD (9.7)
t
Ln 1
t2
and
The accepted practice is to take the hot-side (shell-side) effective surface area, Ah, as
the HX reference surface area where
where
Ntubes = number of tubes per pass
Npass = number of passes
do = outside tube diameter
leff = effective tube length
The LMTD correction factor, F, is a function of the type of HX. The value of “F”
equal to one applies for counter-flow arrangements such as seen in Figure 9.1 and in
other counter-flow HX arrangements. (See Section 9.2 and 9.3.) A formula for the
value of “F” is available for a few other flow arrangements in the open literature.1
Another method of HX analysis is the effectiveness method as defined with refer-
ence to the cold stream as
tc out tc in
P (9.12)
Th in tc in
where effectiveness, P, as defined in the equation above is the cooling range divided
by the cooling potential.
A formula for the value of “P” is available for other flow arrangements in the open
literature.2
The overall heat transfer coefficient, U, may be expressed as the inverse of the
sum of the resistances to heat transfer through the following:
1 A A A
rh rf ,h h rw h rf ,c h rc (9.13)
U A
w A
c Ac
where
1 1
=rh = rc (9.14, 9.15)
hh hc
so that
1
U (9.16)
1 Ah A A 1
rf , h rw h rf ,c h
hh Aw Ac Ac hc
where
hh = hot-side convection coefficient
hc = cold-side convection coefficient.
Note that all fouling resistances are referenced to the hot side (i.e. the shell side)
of the HX tubes. The effective area of the wall and the wall resistance are shown as
follows:
Ao Ai
Aw (9.17)
A
ln o
Ai
do di
rw (9.18)
2 kt
where do and di are the tube outside and inside diameters and kt is the tube material
thermal conductivity.
The value of the cold-side convection coefficient, hc, is a function of the Nusselt
number, Nu, as follows:
k
hc Nu c (9.19)
di
where
kc = thermal conductivity of water.
Several equations are available for the value of the Nusselt number.1 The com-
monly used classic Colburn3 equation is as follows:
1
Nu = 0.023 Re 0t .8 Prt 3 (9.20)
Heat Exchangers 131
where
Ret = tube-side Reynolds number,
Re t vt d i / t (9.21)
and
Prt = tube-side Prandtl number,
where
ρ = density
μt = average tube viscosity
vt = tube velocity.
No such similar direct method for calculating the hot-side convection coefficient,
hh, exists, as it is a complicated function of the HX shell geometry such as the type
and spacing of the baffles, the leakage through the tube support plates, etc.
Manufacturers generally hold this data to be proprietary. If a manufacturer’s HX data
sheet is available, the most direct method for calculating hh is as follows:
1
hh, design (9.23)
1 Ah A A 1
rf , h rw h rf ,c h
U design Aw Ac Ac hc
where the value of “Udesign” is available or may be calculated from the data sheet.
If the design flow rate, inlet and outlet temperatures, number and size of tubes,
and the value of “F” are known, then “Udesign” may be calculated from Equation
(9.24).
Q
U design = (9.24)
Ah F LMTD
For HXs in cooling water systems, the value “hc” may vary considerably during
operation, as the cooling water flow and temperature often change seasonally as the
inlet water temperature changes. The value of “hh” may vary slightly from the design
value during operation, but the change is normally minor compared with the other
resistances in Equation (9.13), and in particular the tube-side fouling term that often
predominates. Therefore, it is often acceptable to assume that the value for “hh” and
thus “rh” remains constant in many cooling water system applications. However, if
that is not the case, consult Reference 2.
used to cool spaces inside power plants and other industrial plants and for many other
applications such as to control the impact of an accident in a nuclear plant. A familiar
example of an AWHX is the radiator in an automobile, and like that application, it is
typically attached to a fan which draws air through a series of serpentine coils. As
such it is classified as a cross-flow HX in which the LMTD correction factor “F” is
equal to 1 if there are 4 or more passes through the coils as shown in Figure 9.2.
The convection boundary resistance to heat transfer on the air side of an AWHX
can be as much as 20 to 30 times that on the tube side where there is turbulent flow
of water through the tubes. To compensate for the poor heat transfer on the air side,
fins are provided to increase the surface area on the air side by as much as 20 or more
times that of the water side. As a practical manufacturing consideration, these fins are
normally rectangular in shape. Accordingly, due to the resistance to conduction heat
transfer down the fin to the surface of the water, increasing the length of the fin
reaches a point of diminishing returns.2 The measure of this reduction in heat transfer
is referred to as the fin efficiency, ηfin. Some AWHX employ helical fins that are
brazed to the tubes while others employ plate fins that are typically analyzed as
equivalent fins.
The overall heat transfer coefficient at design conditions, Udesign, is calculated
similar to Equation (9.16) for STHXs as shown in Equation (9.25).
1
fin
U (9.25)
1 A A A 1
rf , h h rw h rf ,c h
hh Aw Ac Ac hc
Note that the only difference between Equation (9.19) and (9.25) is that the numera-
tor contains the term for fin efficiency. In most AWHX designs, the fin efficiency is
very nearly 1.0. If a more accurate analysis is required, consult Reference 2.
1 / fin
hh, design (9.26)
1 A A 1
rf , h rw h rf ,c h
U design Ac Ac hc
As with the STHX, it is often acceptable to assume that the value for “hh” and thus
“rh” remains constant in many cooling water system applications.
tube-pulling space required), and have higher coefficients of heat transfer. Therefore,
they require less cooling water flow to achieve the same degree of cooling. PHX are
primarily suited for liquid-to-liquid heat transfer, although working fluids involving
single-phase gases are possible.
Alfa Laval, a PHX manufacturer, suggests the following performance limits in
their literature:
The analysis of PHX is similar to that of other HX. The overall heat transfer coef-
ficient, U, may be expressed as the inverse of the sum of the resistances to heat trans-
fer as shown in Equation (9.27).
1 Q
U (9.27)
1
hc
1
hh
rw rfouling A F LMTD
where
rfouling = is the sum of the fouling resistance on both sides of the plate.
Flow through adjacent passages in a PHX is countercurrent. Therefore, the LMTD
correction factor, “F” is 1 for most PHX applications. The PHX consists of a single
type of plate in which the geometry of the plate is the same on both sides.
The geometry of a PHX is defined by the following parameters:
Since the plates are corrugated, the effective area of a plate is greater than the product
of the width times the height by the surface enlargement factor, ϕ, which can be as large
as 1.5, depending on the plate manufacture and can easily be measured with a flexible
tape measure. With this information, one may calculate the number of channel passes,
the effective area, the spacing between plates, and the hydraulic diameter as follows:
N cp N p 1 / 2 (9.28)
Aeff LW x LH (9.29)
Heat Exchangers 135
b Lc X (9.30)
Np
4 Lw b
De (9.31)
w 2b
2 L
hc hc C Re
3
4 Pr
1
3
k D
c
e
(9.32)
Re DeG / (9.33)
m
G= (9.34)
N p b Lw
cp
Pr (9.35)
k
These terms are equally applicable to both the hot and cold sides of the PHX.
In 1999, Bowman6 pointed out that since the geometry on both sides of the PHX
is the same, the expression for “h” for both the hot and cold side is similar. Therefore,
the value of “C” in Equation (9.26) is the same for both sides, and one may solve for
“C” for a clean PHX as follows:
A LMTD
U 1 1 rw (9.36)
hc hh Q
1 1 A LMTD
rw
k D k D
3 1 3 1
(9.37)
C Re c 4 Prc 3 c C Re h 4 Prh 3 h Q
e e
3 1 3 1
Re c 4 Prc 3 kc Re h 4 Prh 3 kh 1
C C (9.38)
De De A LMTD
rw
Q
136 Engineering of Power Plant and Industrial Cooling Water Systems
De De
3 1
3 1
Re c 4 Prc 3 kc Re h 4 Prh 3 kh
C (9.39)
A LMTD
rw
Q
This equation makes it possible to estimate the performance of a PHX at other than
design conditions by simply knowing the physical parameters and the predicted heat
transfer rate for a single set of design operating conditions (i.e. hot-side and cold-side
mass flows and inlet and outlet temperatures). If the design data are not available, the
value of C could be determined by conducting a series of heat transfer tests on a clean
PHX over a range of operating conditions.
1.0
not
recom’d
0.8
(Taborek)
fouling resistance m²K/kW
0.6
increasing levels of
chemical treatment
0.4
0.2
TEMA recommendation
0.0
0.5 1.0 1.5 2.0 2.5 3.0 3.5
flow velocity [m /s]
For raw water, the Tubular Exchange Manufacturer’s Association10 (TEMA) rec-
ommends a minimum design fouling value of 0.002 to 0.003 hr-ft2-oF/Btu (0.00036
to 0.00054 s-m2-oC/J) for tube-side velocities below 3.0 ft/sec (0.91 m/s) and 0.001
to 0.002 hr-ft2-oF/Btu (0.00018 to 0.00036 s-m2-°C/J) for velocities above 3.0 ft/sec
(0.91 m/s). However, Taborek10 noted that the fouling rate is also a function of tube
material and cooling water quality. Figure 9.4 shows the range of fouling rates rec-
ommended by Taborek, overlaid onto those recommended by TEMA for river water
as well as data reported in References 8 and 9. (Taborek10 stated that rf = f(V−1.75).
REFERENCES
1. ASME PTC 12.5-2000. Single Phase Heat Exchangers, September 2000.
2. Thomas, L. C. Heat Transfer- Professional Version, 2nd ed., Capstone Publishing Corp.,
Tulsa, OK, 1999.
3. Colburn, A. P. A. Method of Correlating Forced Convection Heat Transfer Data and a
Comparison with Fluid Friction. Transactions of AIChE, Vol. 29, pp. 174–219.
4. Rauj, K. S. N. and J. Chand. Consider the Plate Heat Exchanger. Chemical Engineering,
Vol. 87, No. 16, pp. 133–144, August 11, 1980.
5. Arpaci, Vedat S. Microscales of Turbulent Heat and Mass Transfer. In Advances in Heat
Transfer, Academic Press, Cambridge, MA, 1997, pp. 1–91.
6. Bowman, C. F. Plate Heat Exchangers. Electric Power Research Institute Service Water
System Reliability Improvement Seminar, Biloxi, MS, 1999.
7. Somerscales, E. F. C. Fouling of Heat Transfer Surfaces: An Historical Review. Heat
Transfer Engineering, Vol. 11, No. 1, pp. 19–36, 1990.
138 Engineering of Power Plant and Industrial Cooling Water Systems
10.1 REGULATORY REQUIREMENTS
In 1972, the United States Congress passed the CWA, establishing the basic structure
for regulating discharges of pollutants including heat through pipes or man-made
ditches into the waters of the United States. Under the CWA, the EPA was charged
with implementing these pollution control measures and with developing national
water quality criteria recommendations. The EPA has implemented the program
through the NPDES. Each state was required to establish limits for thermal discharge
in their state that are intended to protect the propagation of the receiving body of
water’s balanced indigenous population of fish, shellfish, and wildlife. These limits
address the following parameters outside a reasonable mixing zone near the point of
discharge from a plant:
Under Section 316(a) of the CWA, the permitting state may impose alternative efflu-
ent limitations for controlling thermal discharges in lieu of the effluent limits that
would otherwise be required if the organization receiving the permit can demonstrate
that the otherwise applicable thermal discharge effluent limit is more stringent than
necessary to assure the protection and propagation of the body’s balanced indigenous
population of fish, shellfish, and wildlife. Under the CWA, “new source performance
standards” set the level of allowable discharges from new industrial facilities. This
provision requires the EPA to determine the best available demonstrated control tech-
nology for a given industry that may be more stringent than the limits for existing
dischargers up to and including a “zero discharge” standard.
As stated in Section 3.3, Section 316(b) of the CWA requires power and industrial
plants drawing water from the waters of the United States to implement the BTA to
reduce injury or death of fish and other aquatic life and requires new plants at existing
facilities to install closed-cycle recirculating systems or to reduce actual intake flow
to a level commensurate with that attained by a closed-cycle recirculating system.
Therefore, future cooling water systems may require some method of rejecting
heat directly to the environment such as cooling towers or a spray pond to either
operate as a closed system or in a “helper” mode as discussed in Section 7.6.
10.2 COOLING TOWERS
10.2.1 Cross-Flow Mechanical Draft Cooling Towers
Figure 10.1 Illustrates a common type of cross-flow mechanical draft cooling tower
(MDCT).
139
140 Engineering of Power Plant and Industrial Cooling Water Systems
Air outlet
Fan stack
Fan
Fan gear
Fan motor
Hot water flume Hot water flume
Louvers
Drift eliminators
Air outlet
of the veil. When the power plant is not operating but there is still CCW flow to the
NDCT, there is less dense saturated air entering the veil, since the molecular weight
of water vapor (18) is less than that of air (29). Depending on the water loading on
the fill section, this may result in an increase in air flow as the lighter air tends to rise.
When the power plant is operating, the heat added to the CCW results in an even
greater air flow, as warm saturated air is even less dense. A canopy between the
donut-shaped heat transfer section around the veil containing the splash-type fill
material and the veil encloses the interior of the NDCT so that no air can bypass the
fill section.
ice buildup has begun. As a result, cross-flow cooling towers are in somewhat disfa-
vor where there is the potential for ice formation.
Air outlet
Drift eliminators
Water inlet
Air outlet
Drift eliminators
Air out
Air in
before falling to the basin below. Another type of cooling tower fill material shown
in Figure 10.7 is thin corrugated plastic glued together in a herringbone pattern
described as “egg crates” manufactured by Munters and Hitachi. This type of fill
material, though more efficient than that shown in Figure 10.6, may be susceptible to
clogging. If the surface of the plastic is permitted to be covered with pseudomonas
bacteria (i.e. slime), suspended solids in the cooling water tend to build up on the
surface of the plastic, eventually obstructing flow. Chemical treatment systems
employing oxidizing biocides such as chlorine are volatile, and the biocide and may
not control the buildup of pseudomonas on the fill material.
Heat Rejection 145
10.3 SPRAY PONDS
10.3.1 Advantages of Spray Ponds
A spray pond is a system of pipes and spray nozzles that spray water into the air to
cool the water. They are similar in this way to cooling towers in that they dissipate
waste heat to the atmosphere principally through evaporation. Much of the advance
in the understanding of the design of spray ponds has been gained because they play
a critical role in the safe operation of some nuclear plants.1 Unlike MDCT, spray
ponds need no fan power or fill maintenance. Spray ponds are less susceptible to ice
damage than cooling towers and can operate satisfactorily under cold conditions if
provided with a spray bypass to maintain minimum temperatures in the pond.
buoyancy of the warm air (which is of the same order of magnitude and is directed
vertically upward). Since the two forces acting on the air oppose each other, the
result is a reduced air flow rate through the spray region and a large increase in the
local wet-bulb temperature (WBT). Additionally with a large FBSP, the falling water
tends to block air flow into the central parts of the array, requiring an interference
factor to be applied to determine the local WBT as a function of the ambient WBT.1
FIGURE 10.9 Oriented spray cooling system at the Columbia Generating Station.
Heat Rejection 147
t1 t2
(10.1)
t1 tWB
where
η = spray efficiency
t1 = temperature of the water entering the spray nozzle
t2 = temperature of the sprayed water
tWB = ambient WBT.
Assuming a constant heat load and WBT one may solve for t2 as follows:
where
tWB-local = wet-bulb temperature at the spray nozzle.
70%
60%
50%
Efficiency
20%
10%
0%
40 50 60 70 80
FIGURE 10.10 Flat bed spray ponds and oriented spray cooling system efficiencies vs.
WBT.
148 Engineering of Power Plant and Industrial Cooling Water Systems
70%
60%
50%
40%
Efficiency
Rancho Seco
Okeelanta
30% Columbia
20%
10%
0%
0 5 10 15 20
Ambient Air Velocity (Mi/Hr)
FIGURE 10.11 Flat bed spray ponds and oriented spray cooling system efficiencies vs.
ambient air velocity.
OSCS at the CGS. One may see from Figure 10.10 that the spray efficiency increases
with increasing WBT. This is the case for any type of evaporative cooling device such
as a cooling tower.
Figure 10.11 shows the significant impact that ambient air velocity has on spray
ponds, as the spray efficiency increases with increased ambient air velocity. At zero
air velocity, the OSCS is seen to have a very significant advantage in efficiency,
because the OSCS creates its own wind.
REFERENCE
1. Bowman, C. F. and S. N. Bowman Thermal Engineering of Nuclear Power Stations:
Balance of plant Systems, CRC Press, Boca Raton, FL, 2021.
Nomenclature
Symbol Definition English Units SI Units
A corrosion allowance in m
A wave speed ft/sec m/s
a1 constant Dimensionless Dimensionless
a2 constant Dimensionless Dimensionless
A cross-sectional area ft2 m2
Aeff effective surface area ft2 m2
Ah effective hot-side heat exchanger surface area ft2 m2
BHP brake horsepower Hp Hp
C saturation factor Dimensionless Dimensionless
C Hazen-Williams “C” factor Dimensionless Dimensionless
cp specific heat Btu/lbm-oF kJ/kg-oC
cp,c tube-side specific heat Btu/lbm-oF kJ/kg-oC
cp,h hot-side specific heat Btu/lbm-oF kJ/kg-oC
D pump bell diameter ft m
d* dimensionless parameter Dimensionless Dimensionless
dNOM, n nominal pipe diameter in each section of pipe in m
dNOM nominal inside diameter of new pipe in m
dCALC calculated inside diameter of pipe in m
ΔdMEAS measured diameter reduction in m
D pipe diameter ft m
De hydraulic diameter ft m
Do outside diameter min
d diameter of pipe in
di inside diameter of a pipe or tube ft m
do tube outside diameter ft m
d1 orifice diameter in
EM bulk modulus of elasticity of the mixture of lbf/in2 Pa
water and air
Ep bulk modulus of elasticity of the pipe lbf/in2 Pa
Ew bulk modulus of elasticity of water lbf/in2 Pa
e absolute roughness of pipe in
f friction factor. Dimensionless Dimensionless
f magnitude of the reflected pressure wave lbf/in2 kPa
F LMTD correction factor Dimensionless Dimensionless
F magnitude of the pressure wave lbf/in2 kPa
Fd Froude number Dimensionless Dimensionless
g gravitational constant ft/sec2 m/s2
G flow rate gal/min l/s
hL total head loss ft m
hL,f friction head loss ft m
hc cold-side convection coefficient Btu/hr-ft2-oF J/s-m2-oC
hc-in cold stream enthalpy in Btu/lbm kJ/kg
hc-out cold stream enthalpy out Btu/lbm kJ/kg
hh hot-side convection coefficient Btu/hr-ft2-oF J/s-m2-oC
hh,design design hot-side convection coefficient Btu/hr-ft2-oF J/s-m2-oC
hh-in hot stream enthalpy in Btu/lbm kJ/kg
hh-out hot stream enthalpy out Btu/lbm kJ/kg
H pressure head ft kPa
(Continued)
149
150Nomenclature
Lw width of plate in m
m mass lbm kg
m cooling water mass flow rate lbm/hr kg/s
MHP Motor horsepower hp Hp
m mass flow rate lbm/hr kg/s
mc mass flow rate of cold stream lbm/hr kg/s
mh mass flow rate of hot stream lbm/hr kg/s
N rotational speed rev/min
Nair mole fraction of all dissolved gases Dimensionless Dimensionless
N’air = mole fraction that local conditions will permit Dimensionless Dimensionless
to remain in solution
Nair-max maximum mole fraction of air in the entering Dimensionless Dimensionless
cooling water
Nx mole fraction of dissolved gas, x Dimensionless Dimensionless
n specific speed Dimensionless Dimensionless
n number of moles Dimensionless Dimensionless
NHX number of PHX in service Dimensionless Dimensionless
Np number of plates Dimensionless Dimensionless
Npass number of passes Dimensionless Dimensionless
NPSHA net positive suction head available ft m
NPSHi cavitation inception ft m
NPSHR net positive suction head required ft m
Ntubes number of tubes per pass Dimensionless Dimensionless
Nu Nusselt number Dimensionless Dimensionless
P effectiveness Dimensionless Dimensionless
P pressure lbf/in2 kPa
Prequired minimum gauge pressure to keep air in lbf/in2 kPa
solution
P’ local static pressure lbf/in2 kPa
P1 gauge pressure 1 lbf/in2 kPa
P2 gauge pressure 2 lbf/in2 kPa
P internal pipe pressure lbf/in2 kPa
Pb barometric pressure lbf/in2A kPaa
Pd local downstream pressure lbf/in2 kPa
(Continued)
Nomenclature 151
T time sec s
t thickness of pipe wall in m
t temperature oF oC
153
154Index
coatings for zebra mussel control, 82 counter-flow natural draft cooling tower, 143
Colbert, 61 cross-flow mechanical draft cooling tower,
Colburn equation, 130 139–140
cold-water basin, 140 cross-flow natural draft cooling tower, 140–141
Colebrook equation, 95 Cumberland, 62
colony-forming units, 86 cuprous oxide, 82, 91
Columbia, 147–148 cylindrical wedgewire screens, 20–21
Columbia Generating Station, 146, 148
component cooling water, 5
concrete pressure pipe, 3, 41–42, 50 D
condenser circulating water, 1–3, 17–19, 21–22, Darcy-Weisbach Equation, 95, 101–102, 104
27–29, 31, 33, 33, 36, 82, 90, 110, 111, Deardorff, A. F., 69
140–141, 143 debris, 2, 4, 18, 21
condenser discharge valve, 36 density, 3, 10–11, 13, 21, 35, 52, 75, 122–123,
condenser vacuum, 36 131, 140, 143
condenser vacuum pump, 36 design deficiencies, 18
condenser waterbox, 70 design error, 5
containment, 3, 5, 68 design margin, 69, 77
containment air cooler, 5 Detroit Edison, 4, 82
containment spray, 5, 87 DGH-QUAT, 89, 91
control and analysis of water hammer, 124 Diablo Canyon, 5, 82
control of water hammer, 121 diesel generator, 3, 5, 7, 109
control room chiller, 5 differential aeration cell, 76–77
control valve, 4, 31, 58, 119 dispersant, 84–85, 88–91
conventional flat bed spray ponds, 145 dry-pit pumps, 27
convection coefficient, 130–131, 133 Dunn, G. C., 121
cooling coil, 5 dynamic viscosity, 11–12
cooling tower, 1–2, 19, 22, 27, 48, 116, 139–145,
148
cooling tower fill material, 2, 141–144 E
cooling tower makeup pump, 2
cooling water pump, 1–2, 5, 16–18, 16, 23, 24–25, earthquake, 52–53
27–28, 30–31, 33, 35–38, 57, 89, 113, effectiveness, 84–85, 129
113–114, 125 efficiency, 27, 29–31, 33–36, 34, 59, 132, 140,
cooling water system, 1–7, 9–10, 15, 18–20, 147, 147, 148, 148
22–25, 27, 31, 35–38, 41, 55, 57–58, emergency equipment cooling water, 61, 68–69,
68, 74–75, 77, 79–84, 89–91, 95–96, 72, 99, 109
105, 109, 113, 115, 120–121, 124, 127, engineering, 1, 5, 7, 9, 15
131, 133, 136, 139–140 Environmental Protection Agency, 19–21, 110,
copolymer, 89–91 139
copper, 3, 82, 85, 90–91, 96–97 epoxy coating, 3, 45, 50
copper epoxies, 82, 91 equivalent lengths, 97, 100, 107, 110
corbicula fluminae, 80 erosion, 6, 45, 56, 77–78, 120
corrosion, 2–6, 38–39, 41–45, 50–51, 56, 59, essential raw cooling water, 47–48, 56, 69, 73, 78,
61–62, 64–65, 65, 66–68, 70, 70, 71, 82, 84–85, 87–89, 107–108, 109, 109
72, 72, 73–79, 82–91, 96, 99, 101–102, evaporative cooling, 116, 148
110, 120 extensive properties, 11
corrosion allowance, 51, 59, 66, 74, 77 exterior corrosion, 42–43, 64, 66
corrosion in cooling water systems, 74, 77
corrosion inhibitor, 75, 82–84, 89 F
corrosion inhibitor testing, 82
corrosion of shaft, 2 Fahrenheit, 9
corrosion product, 3–4, 27, 47, 50, 62, 67, 73, 77, fan, 132, 140, 140–142, 142, 145
79, 83–86, 88, 99, 101–102 Farley, 3–4
corrosion rate, 42, 47, 65, 65, 68, 70, 70, 71, 72, fiberglass-reinforced plastic, 3, 41, 45, 55
72–74, 77–78, 85, 87–90 fill material, 2, 111, 140–144
counter-flow mechanical draft cooling tower, 142 fill section, 140–143
Index 155
fine mesh screens, 20–21 heat exchanger, 1, 3–7, 12, 18, 20, 31, 45, 56, 61,
fire protection piping, 72–73 79, 81, 87–91, 97, 99, 109–111, 113,
fire protection pumps, 2, 17 113–114, 115, 117, 119–121, 125,
fish, 2, 4, 18–24, 79–80, 110, 139 127–134, 136, 143
fish eggs, 21, 24 heat exchanger fouling, 5, 136
Fitzpatrick, 2–4 heat transfer, 6, 12, 18, 79, 88, 90, 115, 119,
flashing, 119–120 127–129, 132–136, 141
flat bed spray pond, 145–148 heat treatment, 5, 39, 81
floating boom, 21–22 heat treatments for zebra mussel control, 82
flow, 1–6, 11–12, 15–16, 17, 17, 19, 21–24, 27, Henry’s law, 115–116
29–31, 33, 35, 37–38, 41–42, 44, 47, Henry’s law coefficient, 115–118, 116
50, 57–58, 61–62, 63–64, 64, 66–68, Herro, H. M., 77
70, 73, 75, 77–80, 87–91, 95–97, 96, high density polyethylene, 3, 41, 44, 51, 55
99, 100, 101, 101, 102–103, 106–111, Hope Creek, 2
115, 117–120, 123–125, 127, 129, Horizontal centrifugal pump, 1
131–136, 137, 139–144, 146 Hubble, J. D., 121
flow and pressure drop tests, 5, 88, 106 hung piping, 50–51, 79, 90
flow test, 4, 47, 101, 101, 106–107, 109 hydraulic gradient, 36, 113–114, 117, 125
flow velocity, 77, 137 hydraulic pressure gradient, 113, 113–114
foreign objects, 2 hydrogen cooler, 111
form loss, 97–98, 106–107 hyprobromous acid, 88–90
form loss equation, 97
fouling, 4–6, 25, 61, 79–81, 90–91, 129–131, 134,
I
136, 137, 137
fouling resistance, 130, 134, 136, 137, 137 IN 2007-06, 7
frazil ice, 2, 18, 24 IN 2007-28, 5
friction loss, 15, 97, 99, 101, 106 IN 81-21, 4
Froude number, 15, 117 IN 83-46, 3
IN 85-24, 3
IN 85-30, 3
IN 86-96, 4
G
IN 88-37, 4
Gallatin, 61, 101, 101, 103–104, 106 IN 89-76, 4
galvanic pitting corrosion, 3 IN 90-26, 5
galvanized, 64–65, 67, 96 IN 90-39, 4
gate valve, 3, 57–58, 100 IN 92-49, 2
gauge pressure, 9–10, 10, 106, 108, 113, 113–114, IN 94-61, 3
117 IN 94-79, 3
general corrosion, 47, 68, 76, 86 Indian Point, 3
Generic Letter 89–13, 2, 6 Institute for Applied Microbiology, 85–86
Generic Letter 90–05, 3 Institute of Nuclear Power Operations, 18, 37,
Generic Letter 96–06, 5 68, 76
globe valve, 58, 100 intake, 1–2, 5, 15–16, 18–23, 82, 139
Grand Gulf, 2 intake blockage, 2
Guthrie, P. V., 47, 74 intake channel, 15, 23
intake pumping station, 1–3, 16–19, 22–25, 47–48,
73, 79, 81, 88–89, 107, 140, 142
H
intake structure, 2, 15, 18, 20–21, 23
halogen, 86–89 intensive properties, 11
Harbor Beach, 82 iron oxide, 61, 67, 74, 88, 101
Hazen-Williams Equation, 95–97, 102, 105, 107 iron-reducing bacteria, 77
head, 10, 22, 27, 29–31, 33, 33–34, 34–35, 37–38,
38, 44, 47–48, 56–57, 73, 78–79, J
87, 95–98, 101–102, 106–108, 108,
109–111, 113, 113–114, 122–124 John Sevier, 62–63
head loss, 27, 95–98, 101–102, 106–107, 109, 113 joint efficiency, 59
156Index
K N
Kelvin, 9 NaBr/NaOC1, 86
kinematic viscosity, 11, 96 National Pollution Discharge Elimination System,
Kingston, 62, 101, 101, 103, 104, 105 19–20, 139
natural draft cooling tower, 22, 110–111,
140–141, 143
L
net positive suction head, 30–31, 34
larvae, 21, 24, 80–81 nodules, 79, 85, 89, 91
leak, 3, 7, 20, 37, 43, 66, 68–69, 72–76, 78, 90, nondestructive examination, 69–70
120, 131 NRC oversight, 6
leaves, 2 Nuclear Regulatory Commission, 1–7, 55–56, 68,
Licina, G., 68 75, 80
Licensee Event Report 97-037, 3 nuclear safety, 5, 7, 18, 37, 47, 52, 75
Licensing Event Report 96-001-01, 5 NUREG 1275, 6
line shaft, 1, 5, 27–28, 36–38 Nusselt number, 130
line shaft bearing, 36
LMTD correction factor, 128–129, 132, 134 O
log-mean temperature difference method, 128
louver, 20, 140, 140, 141 oil spill, 18
lube oil cooler, 111 Okeelanta Florida Complex, 147
Ontario Ministry of the Environment, 4
open once-through, 1, 27
M
open recirculating, 1
macrofouling, 79–80, 90, 136 oriented spray cooling system, 146–148
main condenser, 1, 22, 27, 36, 71–72, 111 orifice, 16, 35, 101, 108, 120–121, 125
makeup, 1–2 orifice plate, 120
manganese, 67, 75 overall heat transfer coefficient, 128–129, 132,
manganese dioxide, 136 134
marsh grass, 2, 22 oxidizing biocide, 51, 76, 89–91, 144
mass, 22, 35, 75, 117, 127, 134–136 oxygen scavenger, 82
McGuire, 5 Oyster Creek, 2–3
Metell, H. M., 75, 77–78 oyster shell, 4
Metro Water District of Southern California, 52
microbiologically induced corrosion, 3, 7, 12, 25, P
47, 68–70, 73, 75–79, 82, 85–86, 88–91
microfouling, 5, 79–81, 90, 136 Palo Verde, 3, 5
microorganism, 61, 74, 76, 85 Pavinich, W. A., 69
MIC tubercles, 76 Peach Bottom, 4
Miller, W. T., 8, 56 Pickering, 2
Millstone, 2–3 pipe coating, 3, 6, 41–45, 50–52, 65, 82, 91
mils per year, 47, 63, 65, 65, 70, 71, 72, 72, pipe, concrete pressure, 3, 41–42, 50
73–74, 78, 90 pipe fitting, 45, 48–51, 56, 58–59, 97–98, 110
minimum wall thickness, 73 pipe flow, 95
mixed flow, 1, 15, 27, 30, 37–38 pipe form losses, 97–98, 106–107
modulus of elasticity, 52, 122–123 pipe friction, 95–96
mole fraction, 115–118 pipe hangers, 41, 50–51
molluscicide, 81 pipe, hung, 50
mollusk, 4, 58, 79–82, 90–91 pipe, in situ lined, 45
momentum diffusivity, 12 pipe lining, 41, 45–46
Moody diagram, 11–12 pipe, plastic, 44–45
Moody, L. F., 103 pipe, pre-lined ductile iron, 43
motor, 1-3, 16, 22, 23, 24, 27–28, 35–38, 57, 124, pipe wraps, 41
140, 140, 142, 142 piping, buried, 41, 47, 52–53
Mullin, L. J., 70 piping codes, 37, 47, 49, 52, 55, 58, 75, 77
MULTIFLOW, 109–111, 111 piping leak, 3, 7, 66, 68–69, 72–75, 78, 90
multi-pressure condenser, 22 piping materials, 3, 41–42, 45, 75, 84
Index 157
piping network analysis, 110 raw cooling water, 4, 38, 111–112, 112
piping, pre-lined ductile iron, 41, 43 reactor, 3–5, 37, 56, 75
piping standards, 44–45, 47, 55 reduction in pipe diameter, 66, 101
piping wall thickness, 58–59, 62, 65–67, 73, 75, regulatory requirements, 139
77–79, 122 relief valves, 110, 125
pitting, 3, 47, 51, 61–62, 63–64, 65, 65, 68, resistance coefficient, 97
72–74, 76–79, 86, 90 Reynolds number, 11, 131, 135
pitting corrosion rate, 65, 65, 72–74, 77–78, 90 Ristroph traveling screen, 20
planktonic, 80, 85 Robinson, 3, 68
plate heat exchanger, 133 room cooler, 5–6
Point Beach, 5 rototional speed, 29
polyphosphate, 82–84, 83, 89, 91 roughness coefficient, 96, 96
polyvinyl chloride, 3
potential improvements, 22, 37, 77
S
Prandtl number, 11–12, 131, 135
pressure, 1–5, 9, 9–10, 10–12, 19–20, 22, 24–25, Safety Evaluation Report, 56
30–31, 35, 37, 41–45, 49–51, 55, Salem, 4–5
57–59, 67, 77, 79, 88–89, 96, 101–102, San Onofre, 4
104–111, 111, 113, 113–114, 115–125, screen wash pump, 2, 16, 23–24
134, 136, 145–146 seagrass, 79–80, 136
pressure drop, 5, 11–12, 22, 25, 31, 35, 41, 57–58, seal water cooler, 4
67, 79, 88, 96, 101–102, 104–106, seaweed, 2, 18
113, 136 Section 316(a), 139
pressure wave, 121–124 Section 316(b), 19, 110, 139
properties of water, 9–10 sedimentation, 50–51, 78
psudemonas, 77 seismic qualification, 52, 56
pump capacity, 15 semi-open impeller, 27–28, 37–38
pump efficiency, 30, 33, 34, 35 Sequoyah Nuclear Plant, 25, 62, 63, 69, 73–74,
pump head, 31, 33, 33–34, 37 78, 82, 84–85, 87–88, 107–108,
pump head capacity curve, 31, 33 110–111, 111–112
pump head curve, 31 service factor, 36
pump impeller, 1–2, 27, 29–30, 34 Service Water Assistance Program, 68
pump impeller profile, 30 service water pump, 2, 17
pump in-service testing, 37 sessile, 85–86
pump line shaft, 1, 5, 27–28, 36–38 shell-and-tube heat exchanger, 127–128, 132–133
pump line shaft seal, 38 silica, 67, 75
pump margin, 37 silicone oil, 82, 91
pump minimum flow rate, 35 silicon oxide, 101
pump motor, 16–23, 35–36, 38 Singleton Materials & Engineering Laboratory,
pump run-out, 31 52, 70, 71, 73, 84, 88
pump shaft coupling, 2, 36 skimmer wall, 23
pump shut-off head, 31, 35 Slime-forming bacteria, 77
pump size, 15, 30, 33 snubber, 124
pump speed, 5, 29, 33, 36–37 socket weld, 56, 73, 79
pump suction, 1–2, 4, 15, 27, 29–31, 34, 39, 111 sodium bromide, 84–85
sodium hypochlorite, 81, 83–85, 88–91
Q sodium sulfide, 82
Somerscales, E. F. C., 136
qualification testing, 82 South Texas Project, 7
quality assurance, 7, 55, 110 spawning, 81, 89, 91
specific gravity, 13, 33
specific heat, 12, 117, 128
R
specific speed, 29–31, 33
radiographic testing, 69, 73 splash-type fill material, 140–141
rake, 2 spray nozzle, 145–147
Rancho-Seco, 147, 147 spray pond, 1, 116, 139, 145–148
Rankine, 9 spray pond test results, 147
158Index
spray tree, 146 tubercle, 61, 65, 67–68, 73–77, 83–84, 86, 101
stagnant flow, 62, 64 Tubular Exchange Manufacturer’s Association,
stainless steel, 3, 69, 96 137, 137
standard international, 9–10 Tuovinen, J. E., 74
stator water cooler, 111 turbine, 1, 3–4, 9, 15, 22, 27, 35, 111, 116
steam generator, 4
stop log, 2, 16, 23
U
strainer, 2–3, 23, 24–25, 36, 38, 81–82, 87–90,
97, 111 ultrasonic testing, 68, 73
submergence, 15, 24, 31 U.S. Fish and Wildlife Service, 4
suction specific speed, 30–31
sulfur-reducing bacteria, 67, 77–78, 86
sump, 2, 16, 17, 17, 39 V
Surry, 3
vacuum pressure, 9, 10
Suspended solids, 56, 79–80, 144
vacuum relief valve, 120
Swing check valve, 57, 100
valve, 3–6, 16–23, 31, 35–36, 41, 45, 48,
system head curve, 31
56–58, 80, 97, 99–100, 110, 114, 115,
119–120, 124–125
T vapor column, 125
veil, 140–141, 143
Taborek, J., 137, 137 veligers, 24, 80–82, 89–91
temperature, 5, 9–11, 13, 19, 22, 28, 31, 35, velocity cap, 19–22
44–45, 59, 70–72, 77, 80–82, 88–89, vertical runs, 66
109–111, 113, 115–116, 116, 117–120, vertical wet-pit, 1–2, 27, 29–31, 36, 38
122, 127–128, 131, 134, 136, 139, viscosity, 11–12, 96, 131, 135
145–147, 147 volume, 10–11, 35, 49, 62, 75, 82–83, 95,
temperature coefficient, 59 101–102, 117–119, 123
Temporary Instruction 2515/118, 7
Tennessee River, 56, 70, 106, 110
Tennessee Valley Authority, 47–50, 52–53, 55–56, W
61–62, 66–68, 70, 72–74, 78, 80–82,
84, 86–88, 99, 105–107, 109–110 wall resistance, 130
test, 3–7, 25, 37–38, 47–49, 52–56, 61, 67–70, 70, wall thinning, 61–62, 64–67
71, 74–75, 81–86, 83, 88, 91, 97, 99, water hammer, 6, 35–36, 121, 124–125
101–110, 108, 136, 146–147 waters of the United States, 19, 110, 139
thermal conductivity, 12, 130 Watts Bar, 62
thermal diffusivity, 12 Watts Bar Nuclear Plant, 47–48, 55–56, 68–69,
thermal discharge effluent limit, 139 72–73, 88–89, 91, 109, 109
thermoplastic, 44, 50 wave speed, 122–123
thermosetting, 44–45 wearing ring, 37
thermosetting epoxy resin, 46 wedgewire screens, 20–21
thin film-type fill, 143 wet-bulb temperature, 146–147, 147, 148
Thoma’s cavitation constant, 34 Widows Creek, 62, 101, 101, 104, 105
through-wall leak, 7, 66, 68, 72, 78, 90
through-wall pit, 68–69, 72 Z
total residual chloride, 81, 89
trash rack, 2, 15, 16, 18, 23, 25, 81, 91 zebra mussel, 4, 25, 80–82, 89, 91, 136
trash sluice, 16–23 zebra mussel control, 82
traveling screen, 2, 15, 16, 20–21, 23, 24–25, 89, 91 zero discharge, 139
traveling water screen, 2, 18–21, 23, 25, 91 zinc polyphosphate, 82–84, 83