Babita Shrestha Estimation July 2
Babita Shrestha Estimation July 2
0.00
7 Parking Tile work Sqft 0.00 210.00 -
H Section 9: Skill Special treatment and waterproofing works
1 Membrane Sheet layering sqft 1,155.73 110.00 127,129.75
2 PMM insertion sqft 539.27 30.00 16,178.22
3 Skill's DPC Bitumenous coating sqft 294.60 30.00 8,838.00 202,995.94
4 2K Coating Treatment sqft 1,155.73 30.00 34,671.75
5 Zero Side Polymer Coating Treatment sqft 539.27 30.00 16,178.22
2 Commode
Commode : 1 Set Per Bathroom 1 18,500.00 18,500.00
3 Wall Mixture
All Floor Wall Mixture : 1 Set Per Bathroom 1 6,800.00 6,800.00
Total No of Bathroom 2
Sub-Total 106,300.00
10 Buying And Installation of Pipe and Fitting 77,000.00
0 0
Total 3109.500 388.8 Total 0
Total Volume to excavate From original ground level : 3109.500 cuft
Total Back Fill 388.8 cuft
Soil Cutting 1165.5 cuft
1554.3 cuft
Section 4 Foundation Preparation Works
S.no Description unit Nos Depth Volume
A Protection Works
Necessary arrangements of sheet piling for protection works 1 LS
B Soil Compaction Works
Necessary compaction works in foundation 1 LS
Column Estimator
Discription Sectional Area Height Perimeter Nos VOL(cuft) Area(sqft) No of storey
Up To Plinth
C1 1.36 4.75 4.67 9.00 58.19 199.50
Up To Top
C1 1.36 8.33 4.67 22.00 249.44 855.21
Slab Estimator
Discription Slab Area(sqft) Thickness Total Volume(cft) Area For formwork(sqft)
Ground Floor 777.000 0.417 323.750 777.000
First Floor 837.000 0.417 348.750 837.000
Second Floor 0.000 0.417 0.000 0.000
Top Floor 280.310 0.417 116.796 280.310
STAIRCASE 135.420 0.417 56.425 135.420
Total 845.72 2029.73
1320.900
Beam Estimator
S.N Strap Beam Lower Tie Beam Upper Tie Beam Ground Floor Beam First Floor Beam Second Floor Beam Stair Secondary Top Floor
Size 14 9 9 9 9 9 9 9
22 12 12 10 10 10 10 10
Section 2.139 0.750 0.750 0.625 0.625 0.625 0.625 0.625
Summary
S.N Description Qty (cuft) Formworks (sqft) Remarks
A Footing 540.00 360.00
B Beams 493.24 1256.03
C Columns 307.62 1054.71
D Slabs 845.72 2029.73
F Sill and Lintel 147.79 549.77
Total 2334.38 5250.25
Deduction Deduction
in Brick in wall Deduction
Associated Wall Masonary plasters in Paintings
S.N Description thickness N0 L B H Area(sqft) Walls (cft) (sqft) (sqft)
DOOR
1 MAIN DOOR MD1 0.750 1 4.000 1.000 8.000 32.000 24 64 64
2 MAIN DOOR MD2 0.750 0 3.500 1.000 8.000 0.000 0 0 0
3 D1 0.417 6 3.000 1.000 7.000 126.000 52.5 252 252
4 D2 0.417 2 2.500 1.000 7.000 35.000 14.5833333 70 70
WINDOW 193.000
1 W1 0.750 8 6.000 1.000 4.000 192.000 144 384 384 48
2 W2 0.750 0 5.000 1.000 4.500 0.000 0 0 0 0
3 V1 0.750 2 2.000 1.000 2.000 8.000 6 16 16 4
3 W3(Staircase Window) 0.750 1 4.000 1.000 7.830 31.320 23.49 62.64 62.64 4
4 SD1 0.750 2 6.000 1.000 8.000 96.000 72 192 192 12
5 SD2 0.417 0 6.000 1.000 7.500 0.000 0 0 0 0
65.000 327.320 56
Brick Masonary
S.N Description unit Nos Length Breadth Height Volume
A Brick Masonary Walls
a Under the plinth (Toe Walls) nos
1 Total walls area from cad cft 147.30 4.75 699.68
Summary
Brick Masonary
S.N Description (cft) Plaster Paint
1 Toe Wall 699.68 8920.25 8920.25
2 Ground floor 949.68
3 First Floor 767.73
4 Second Floor 0.00
5 Top Floor 360.29
6 Parapet walls 147.12
8 Deduction from opening schedule 336.573333333 1040.64 1040.64
Total 2,587.92 7879.61 7879.61
External
L H A(Sqft)
GF 172.70 9.33 1611.87
FF 152.50 9.33 1423.33
SF 0.00 9.33 0.00
Top Floor 57.67 9.33 538.25
Lower Parapet 113.70 2 227.40
Upper Parapet 53.20 3 159.60
Varahanda 6.00 2 12.00
Deduction in zero side 28.90 18.66 539.27
Total 3433.18
Internal RFF
Walls Celling Beam
L H A(Sqft) A(Sqft) A(Sqft)
GF 172.70 8.33 1439.17 777 927.5
FF 152.50 8.33 1270.83 0
SF 0.00 8.33 0.00 0
Top Floor 57.67 8.33 115.34 280.31
Staircase 47.5 8.33 142.50 135.42
Lower Parapet 113.70 2 227.40
Upper Parapet 53.20 3 159.60
Varahanda 6.00 2 12.00
Total 3366.84
TOTAL 6800.01933 1192.73 927.5
Screeding , Punning , Tiles , Marbles , Granite , Parqueting
2 inch
S.no Description unit Nos Length Breadth Area Tiles(sqft) Marble(sqft) Granite(sqft) Parqueting (sqft) Screeding(sqft) Punning(sqft)
A Ground Floor
1 Guest Room 1.00 117.50 117.50
2 Kitchen/Dining 1.00 151.90 151.90 151.90
3 Living 1.00 163.39 163.39
4 Stair Passage 1.00 161.65 161.65 161.65
B First Floor
1 Bedroom 1 1.00 112.90 112.90
2 Bedroom 2 1.00 126.43 126.43
3 Bedroom 3 1.00 141.39 141.39
4 Living 1.00 118.06 118.06
5 Balcony 1.00 120.57 120.57 120.57
E Upper Terrace
1 Floor 1.00 837.00 837.00
2 Skirting 1.00 49.00 49.00
E Lower Terrace
1 Floor 1.00 0.00 0.00
2 Skirting 1.00 0.00 0.00
E1
Granite Work on Window Base
Total Lenght of Window 1.00 65.00 1.08 70.42
Lower Terrace 1.00 113.70 1.08 123.18
Upper Terrace 1.00 53.20 1.08 57.63
F Staircase
(With Nosing)(Double Moulding)
1 Risers 30 70 70.00
2 Trades 16 53.333333 53.33
3 Landing 2 44.4 44.40
4 Skirting 1 16.666667 16.67
184.4
F Bathrooms
1 Ground Floor
a Common T/B
Floor 1.00 33.67 33.67
Wall 1.00 208.25 208.25
2 First Floor
a Common T/B
Floor 1.00 33.67 33.67
Wall 1.00 208.25 208.25
G Parking Tiles
Parking Tiles 1.00 0.00 0.00
Summary
S.N Description Area(sqft)
1 Tiles Works 1,642.31
2 Granite Works 346.05
3 Marble Works 0.00
4 Screeding 781.00
5 Punning 0.00
6 Parqueting Works 0.00
Section 9 Special Treatment and Waterproofing
Summary of Works
S.N Description of works Quantity
1 Membrane Sheet layering 1,155.73
2 PMM insertion 539.27
False Ceilling
Floor Discription Unit Rate Area Price(Rs)
GF
Living + Dinning sqft 210.00 0
FF
Master Bedroom sqft 210.00 1.00 210
TF
Living Room sqft
Total 210
Section 10 Railing Works
Toughned
S.no Description unit Steel Wood Glass Iron
A Staircase
Provision of Railing in
staircase Rft 13.81
B At Balcony
Provision of Railing in
Balcony RFT 32.00
B At Lower terrace
Provision of railing RFT 0.00
D At Upper terrace
Summary of Works
S.N Description of works Quantity Unit
1 SS Steel Railing 131.41 Running Feet
2 MS Railing
3 Wooden Railing 0.00
4 Toughned glass Railing 32.00
Boundary wall
S,N Description of work unit no Length Breadth height qty ( cu.ft)
1 Earth work cu.ft 1 137.60 1.5 2.5 516
2 soling work sq.ft 1 137.60 1.5 0.25 51.6
3 pcc work cu.ft 1 137.60 0.75 0.25 25.8
4 Stone / Brick work up to ground level cu.ft 1 137.60 0.75 2.6 268.32
5 Brick work upto 4 ft above ground level cuft 1 137.60 0.75 4 412.8
s.n Description of work unit Qty ( ft) Qty ( m) Rate Amount Remarks
1 Earth work cu.ft 516 14.61 23 7540.53
2 soling work cuft 51.6 1.46 80 4128.00
3 pcc work cu.ft 25.8 0.73 400 10320.00
4 stone work up to ground level cu.ft 268.32 7.60 450 120744.00
5 Brick work upto 4 ft above ground level cuft 412.8 11.69 446 184108.80
6 Railing work Rft 137.6 137.60 450 61920.00
6 Plaster Work 1100.80 1100.80 70 77056.00
6 Paint Work 1100.80 1100.80 25 27520.00
Total 493,337.33
UNDER GROUND WATER TANK INTERNAL FINAL
Total 233580.86983125
SOAK PIT
S,N Description of work Unit No Length Breadth height qty ( cu.ft)
1 Earth work cu.ft 1 4 4 4 64
2 soling work sq.ft 0 0 0 0
3 pcc work cu.ft 0 0 0 0 0
4 BRICK WORK UP TO GROUND cu.ft 1 4 4 4 64
5 RCC WORK cuft 1 4 4 0.33 5.28
6 REINFORCEMENT KG 1 11
7 PIPE ( 2 PIC 6 INCH) PIC 2 2
S.N Description of work unit Qty ( ft) Qty ( m) Rate Amount Remarks
1 Earth work cu.ft 64 1.812517700368 721 1306.825261965
2 soling work sq.ft 0 0 750 0
3 pcc work cu.ft 0 0 15747 0
4 BRICK WORK UP TO GROUND cu.ft 64 1.812517700368 15000 27187.76550552
5 RCC WORK cuft 5.28 0.14953271028 17944.56 2683.298691589
6 REINFORCEMENT KG 11 150 1650
7 PIPE ( 2 PIC 6 INCH) PIC 2 4000 8000
Total 39177.88945908
Final Rate Analysis / No Change
1.Soil Excavation
1.1Hard Clay and soft type gravel mix soil up to 30 cm depth, transported up to 10 m. and lift 1.5 m.
Rate Nrs.
Nrs.
1.2 Soft and silts type clay excavation, transported 10 m lead and 1.5m lift
1 Labors
1.1 Unskilled No.
2 Materials
2.1 Hand Equipments3% of unskilled
Rate Nrs.
Nrs.water and compacted by lab
Earth filling by ordinary soil in 15-cm. Layer spraying sprinkling
2 distant.
Rate Nrs.
Nrs.
2 Materals
Rate Nrs.
Nrs.
4 First
Brickfloor
workand above, chimney made brick, making mix (1:4) C/S mortar, transportation of ma
4.1 cu. m.)
Rate Nrs.
Nrs.mortar, transportation of ma
First floor and above, chimney made brick, making mix (1:6) C/S
4.1 cu. m.)
Rate Nrs.
Nrs.
5 Stone Masonry Works
5.1 Rubble stone masonry wall, making mix (1: 6) C/S mortar transported of martial s up to 10 m.
Rate Nrs.
Nrs.
5.2 Stone filling on foundation plinth, leveled, transportation of material up to 30 m.
Rate Nrs.
Nrs.
6 Plain Cement Concrete (PCC)
6.1 For foundation, wall, transportation up to 30 m. PCC (1:3:6)
Rate Nrs.
Nrs.
Rate Nrs.
Nrs.
6.3 PCC (1:2:4) on superstructure, deck, slab, beam on cement concrete, up to 30 m. transportatio
Rate Nrs.
Nrs.
Rate Nrs.
Nrs.
8
,mmmmmmmmmmmmmm,,,,,,,,
No Change
Per 1 per.Cu.m.
Quantity Rate Per Unit Amount Remarks
1.5 0 0
4.2 0 0
1 2787.12 2787.12
0.1 2787.12 278.71
0.106 20000 2120
0.47 3400 1598
Total 6783.83
6783.83 per.Cu.m.
192.25 per.Cu.Ft.
terial up to 30 m.
Per 1 per.Cu.m.
Quantity Rate Per Unit Amount Remarks
1.5 0 0
1 2787.12 2787.12
0.2 2787.12 557.42
Total 3344.54
3344.54 per.Cu.m.
94.78 per.Cu.Ft.
Per 1 per.Cu.m.
Quantity Rate Per Unit Amount Remarks
1 0 0
4 0 0
1 0 0
4 0 0
Per 10 per.sq.m.
Quantity Rate Per Unit Amount Remarks 52100
1.72 0 0
2.56 0 0
cum 4400
cum 4400
cum 210798
cum 45687.6
mt 86000
kg 100
kg 100
kg 26.375
kg 65
lit. 250
lit. 268
kg 180
NO. 67
NO. 107
NO. 28
NO. 43
set. 32
NO. 227
sqm 710.0544
sqm 559.4368
NO. 125
NO. 3
rm 59.04
sqm 237
sqm 281
sqm 294
sqm 370
rm 100
rm 100
NO. 30
NO. 2
NO. 15
sqm 1400
NO. 60
9500
95
3383.072455
:3) on superstructure, deck, slab, beam on cement concrete, up to 30 m. transportation
Per 1 per.Cu.m.
Unit Quantity Rate Per Unit Amount Remarks
No. 0.8 0 0
No. 7 0 0
5 Rubble
Stone Masonry Works wall, making mix (1: 6) C/S mortar transported of martial s up to
stone masonry
5.1 10 m.
Per 1
S.N. Description Unit Quantity Rate Per Unit Amount
1 Labors
1.1 Skilled No. 1.5 0 0
1.2 Unskilled No. 4.2 0 0
2 Materals
2.1 Block stone cum 1 2787.12 2787.12
2.2 Bond stone cum 0.1 2787.12 278.71
2.3 Cement M.T 0.106 20000 2120
2.4 Sand cum 0.47 3400 1598
Total 6783.83
Rate Nrs. 6783.83 per.Cu.m.
Nrs. 192.25 per.Cu.Ft.
5.2 Stone filling on foundation plinth, leveled, transportation of material up to 30 m.
Per 1
S.N. Description Unit Quantity Rate Per Unit Amount
1 Labors
1.2 Unskilled No. 1.5 0 0
2 Materals
2.1 Block stone cum 1 2787.12 2787.12
2.2 Bond stone cum 0.2 2787.12 557.42
Total 3344.54
Rate Nrs. 3344.54 per.Cu.m.
Nrs. 94.78 per.Cu.Ft.
6 Plain Cement Concrete (PCC)
6.1 For foundation, wall, transportation up to 30 m. PCC (1:3:6)
Per 1
S.N. Description Unit Quantity Rate Per Unit Amount
1 Labors
1.1 Skilled No. 1 0 0
1.2 Unskilled No. 4 0 0
2 Materals
2.1 Cement M.T 0.22 20000 4400
2.2 40mm cum 0.65 4400 2860
Aggrigate
2.3 20 mm cum 0.24 4400 1056
Aggrigate
2.4 Sand cum 0.47 3400 1598
Total 9914
Rate Nrs. 9914 per.Cu.m.
Nrs. 280.95 per.Cu.Ft.
16 Snocempaint kg 65
17 Enamel paint lit. 250
18 Astar (Primer) lit. 268
ater and compacted by 19 Gum kg 180
20 150mm chukul NO. 67
per.Cu.m. 21 300mm chukul NO. 107
Remarks 22 100mm hing/kabja NO. 28
23 75mm hing /kabja NO. 43
24 Handle set. 32
25 250 mm locking set NO. 227
26 4 mm glass sqm 710.0544
27 3 mm glass sqm 559.4368
28 Hold fast NO. 125
29 Screw nail NO. 3
Sq.m. 30 Listic rm 59.04
Remarks 31 26 gauge CGI sheet sqm 237
32 24 gauge CGI sheet sqm 281
33 26 Gauge CGI sheet (color ) sqm 294
34 24 gauge CGI sheet ( color ) sqm 370
35 26 gaugeCGI sheet ridge ( color)rm 100
36 CGI sheet ridge rm 100
37 7mm nut and bolt NO. 30
38 bitween washer NO. 2
39 8mm J K hook NO. 15
40 porcelin glazed tiles sqm 1400
ortar, transportation 41 100mm chukul NO. 60
per.Cu.m.
Remarks 100 9500
95
3383.072455
ortar, transportation
per.Cu.m.
Remarks
4120
700
95 12652
ed of martial s up to
per.Cu.m.
Remarks
l up to 30 m.
per.Cu.m.
Remarks
per.Cu.m.
Remarks
per.Cu.m.
Remarks
, up to 30 m.
PCC (1:1.5:3) on superstructure, deck, slab, beam on cement concrete, up to 30 m
per.Cu.m.
Remarks S.N. Description Unit Quantity
1 Labors
1.1 Skilled No. 0.8
8100 1.2 Unskilled No. 7
2 Materals
750 2.1 Cement M.T 0.4
750 2.2 40mm Aggrigate cum 0
9500 100 2.3 20 mm Aggrigate cum 0.57
2.4 10 mm Aggrigate cum 0.29
2.4 Sand cum 0.425
8950.495733 Total
Rate Nrs. 12854
Nrs. 330
per.sq.m.
Remarks 52100
b
Remarks
16000 45030.5
n cement concrete, up to 30 m. transportation
Per 1 per.Cu.m.
Rate Per Unit Amount Remarks
0 0
0 0
18000 7200
4400 0
4400 2508
4400 1276
4400 1870
12854
per.Cu.m.
per.Cu.Ft.