Analysis of Load Profile Generated in 10 Different Research-Papers Using MATLAB GUI
Analysis of Load Profile Generated in 10 Different Research-Papers Using MATLAB GUI
TABLE OF CONTENTS
Abstract ..........................................................................................................................2
Introduction ...................................................................................................................2
LOAD PROFILES ANALYSIS .....................................................................................5
GRAPHICAL USER INTERFACE ON MATLAB OF LOAD PROFILES.................15
LOAD FACTOR COMPARISON ...............................................................................20
POWER PLANT DESIGNING AND ECONOMIC ANALYSIS FOR TWO WORST
CASES.........................................................................................................................20
MODELLING OF POWER STATIONS .....................................................................26
NUCLEAR POWER PLANT 3D VIEW (SKETCHUP)........................................... 26
DIESEL POWER PLANT 3D VIEW (SKETCHUP) ............................................... 27
DIESEL POWER PLANT 2D VIEW (AUTOCAD) ................................................. 28
NUCLEAR POWER PLANT 2D VIEW (AUTOCAD) ............................................ 28
References....................................................................................................................29
Page | 1
Power System Analysis Complex Engineering Problem
Abstract
The report first provides an introduction to generating stations and their various
types. It then briefly defines economic and technical parameters on which we have
done the analysis of 10 practical load profiles. After discussing in detail 10 such real-
world load profiles we have attached manual as well as MATLAB calculations for
technical factors.
In such manner, the report proposes a plan for two creating stations including their
3D models, details and financial aspects for driving the two case profiles.
Introduction
The conversion of energy available in different forms in nature into electrical energy
is known as generation of electrical energy.
Electricity has become an indivisible part of our life today. It is required for many
domestic, commercial as well as industrial purposes, and the requirement is still
increasing day by day. This bulk demand for electric power is supplied by huge
electric power-generating stations or power plants. Some fuel source, such as coal,
oil, natural gas, or nuclear fuel produces heat, which is then used to boil water to
create steam. The steam under high pressure is used to spin turbine coupled with the
shaft(s) of one or more alternators or generating units. Generators then provide
electric power to the grid through a transmission and distribution system. Indeed,
generating stations are the source of all power.
Page | 2
Power System Analysis Complex Engineering Problem
Technical Analysis
Base Load: The minimum load that must always be supplied by a generating
Station
Load Factor: The ratio of average load to the maximum demand during a
given period is known as load factor i.e.,
Load factor = Average load / Max. Demand
The ideal load factor is 1 which represent load is drawing the maximum
Possible Power from a generating station,
Page | 3
Power System Analysis Complex Engineering Problem
Economical Analysis
Page | 4
Power System Analysis Complex Engineering Problem
TIME kW
00:00 190
01:00 200
02:00 220
03:00 180
04:00 230
05:00 185
06:00 230
07:00 380
08:00 470
09:00 420
10:00 360
11:00 310
12:00 460
13:00 370
14:00 340
15:00 385
16:00 360
17:00 390
18:00 490
19:00 910
20:00 620
21:00 730
22:00 575
23:00 460
Units Consumed = 9705 kWh
Explanation: The demand increases during the night time (7 PM to 11 PM) because of
lighting load. The demand stays capped at around 400 KW during the day time (6AM to 6
PM), with only occasional peaks. During the sleeping hours (after 12 AM to 5 AM) the
demand is the lowest at 200 KW.
Page | 5
Power System Analysis Complex Engineering Problem
Time kW
00:00 3700
01:00 3500
02:00 3520
03:00 3570
04:00 3580
05:00 3650
06:00 3680
07:00 3900
08:00 3950
09:00 4100
10:00 4500
11:00 4650
12:00 4580
13:00 4710
14:00 4750
15:00 4900
16:00 4700
17:00 4710
18:00 4400
19:00 4340
20:00 4200
21:00 4300
22:00 4600
23:00 4300
Units Consumed = 104990 kWh
Explanation: The demand during the (12 AM TO 9 AM) is almost around 400KW.
The peak demand of the airport is 4900KW which is at (3PM).the demand during the (9 AM
to 12AM) is varies.
Page | 6
Power System Analysis Complex Engineering Problem
Time kW
00:00 950
01:00 1020
02:00 980
03:00 970
04:00 975
05:00 1310
06:00 1700
07:00 3020
08:00 3800
09:00 4650
10:00 5650
11:00 6450
12:00 6590
13:00 6800
14:00 6900
15:00 7050
16:00 7100
17:00 7010
18:00 7200
19:00 7350
20:00 7020
21:00 7025
22:00 6130
23:00 2950
Explanation: Shopping centers operate from 09:30 to 22:00 and their major utilities and
lighting systems are started up at 07:00, after which the electrical load keeps rising until
22:00.
Page | 7
Power System Analysis Complex Engineering Problem
Time MW
00:00 5900
01:00 5100
02:00 4700
03:00 4600
04:00 4750
05:00 6200
06:00 7300
07:00 8700
08:00 8800
09:00 6500
10:00 4900
11:00 4100
12:00 3600
13:00 3000
14:00 3200
15:00 4000
16:00 5150
17:00 7850
18:00 8200
19:00 8250
20:00 8000
21:00 5000
22:00 4750
23:00 5050
Units Consumed = 104990 kWh
Explanation: The peak demand of UK is achieved during the time (6AM to8AM) is
8800MW and then from (9AM to 4PM) is low. Then in the evening during the time (5PM to
8PM) again peak demand is achieved. The demand during the night time is lowest which
moves around 6000MW.
Page | 8
Power System Analysis Complex Engineering Problem
Time kW
00:00 0.38
01:00 0.29
02:00 0.25
03:00 0.3
04:00 0.26
05:00 0.22
06:00 0.21
07:00 0.30
08:00 0.41
09:00 0.37
10:00 0.28
11:00 0.24
12:00 0.14
13:00 0.24
14:00 0.23
15:00 0.22
16:00 0.28
17:00 0.30
18:00 0.39
19:00 0.40
20:00 0.53
21:00 0.51
22:00 0.44
23:00 0.42
Units Consumed = 8.02 kWh
Explanation: The demand during the sleeping time is low which moves around 300W. The
peak demand of the building is 530W (8PM) because of high lighting load.
Page | 9
Power System Analysis Complex Engineering Problem
Time kW
00:00 500
01:00 520
02:00 600
03:00 500
04:00 600
05:00 400
06:00 500
07:00 600
08:00 1500
09:00 3000
10:00 2700
11:00 2900
12:00 3000
13:00 2600
14:00 2800
15:00 2700
16:00 2900
17:00 3000
18:00 1500
19:00 400
20:00 500
21:00 600
22:00 400
23:00 500
Explanation: The load between the night time (12AM to 7AM) is very low. The demand
between the peak working hours of industry is around 3000KW. The demand of industry
during the night is again low as the heavy industrial load is not working in night.
Page | 10
Power System Analysis Complex Engineering Problem
Time kW
00:00 0.15
01:00 0.14
02:00 0.15
03:00 0.13
04:00 0.14
05:00 0.15
06:00 0.16
07:00 0.22
08:00 0.30
09:00 0.31
10:00 0.22
11:00 0.23
12:00 0.19
13:00 0.18
14:00 0.20
15:00 0.20
16:00 0.19
17:00 0.17
18:00 0.16
19:00 0.20
20:00 0.31
21:00 0.41
22:00 0.38
23:00 0.30
Units Consumed = 5.38 kWh
Explanation: The demand increases during the night time (8 PM to 11 PM) because of
lighting load. The demand moves around 3100 W during the day time with only occasional
peaks. During the sleeping hours (after 12 AM to 5 AM) the demand is the lowest at 150W.
Page | 11
Power System Analysis Complex Engineering Problem
Time kW
00:00 23
01:00 24
02:00 22
03:00 21
04:00 40
05:00 31
06:00 37
07:00 49
08:00 53
09:00 59
10:00 64
11:00 63
12:00 62
13:00 61
14:00 61
15:00 59
16:00 56
17:00 58
18:00 57
19:00 56
20:00 54
21:00 37
22:00 36
23:00 35
Explanation: The peak demand of the building during the time (8AM to 8PM) is around
64KW. The demand during the night time (8PM to 7AM) moves around 49KW.
Page | 12
Power System Analysis Complex Engineering Problem
Time MW
00:00 11100
01:00 10100
02:00 9700
03:00 9400
04:00 9200
05:00 9300
06:00 9700
07:00 10800
08:00 11900
09:00 12200
10:00 12250
11:00 12200
12:00 12500
13:00 12150
14:00 12100
15:00 12050
16:00 12150
17:00 12200
18:00 12900
19:00 12900
20:00 12300
21:00 11800
22:00 11100
23:00 11000
Explanation: The peak demand of whole Belgium is moves around 12300MW during the
day time or working hours. The demand during the night time is lowest around 97000MW.
Page | 13
Power System Analysis Complex Engineering Problem
Time kW
00:00 5
01:00 5
02:00 5
03:00 5
04:00 5
05:00 5
06:00 5
07:00 15
08:00 15
09:00 15
10:00 15
11:00 15
12:00 20
13:00 20
14:00 20
15:00 20
16:00 20
17:00 20
18:00 20
19:00 5
20:00 5
21:00 5
22:00 5
23:00 5
Units Consumed = 280 kWh
Explanation: The peak demand of the building is achieved during the time (12PM to 6PM)
that is 20KW. The demand during the sleeping time is stays around 5KW. The demand
during the time (7AM to 11AM) stays around 15KW.
Page | 14
Power System Analysis Complex Engineering Problem
LOAD PROFILES
Page | 15
Power System Analysis Complex Engineering Problem
Page | 16
Power System Analysis Complex Engineering Problem
Page | 17
Power System Analysis Complex Engineering Problem
Page | 18
Power System Analysis Complex Engineering Problem
Page | 19
Power System Analysis Complex Engineering Problem
The Blue shaded region show the load profile with most poor load factor
(worst scenario) and we will be considering it for proposing it more efficient
power generating station design for them.
Page | 20
Power System Analysis Complex Engineering Problem
Generator Sizing
Improvement Method
For this Load profile, we have adopted peak shifting method. The peak which was
occurring at 7 pm is evenly distributed from 4 pm to 11 pm. In this way average load
increases which lead to increase the load factor which ultimately reduces per unit
generation cost of the electricity. The improved load factor is beneficial for both customer
and utility.
Page | 21
Power System Analysis Complex Engineering Problem
So A= 9,73,000
= Rs 11,537,560
Page | 22
Power System Analysis Complex Engineering Problem
The above is the cost per unit generated which is much more optimized and economical than the
original one
Household Level.
CASE 2:
Generator Sizing
Page | 23
Power System Analysis Complex Engineering Problem
Improvement Method
For this Load profile of industrial load, we have adopted peak shaving method. The peak
demand of 3000kW is shaved and is shifted to the time where there is less electric
demand. Industry is advised to increase its working hour so that demand gets evenly
distributed.. In this way average load increases which lead to increase the load factor
which ultimately reduces per unit generation cost of the electricity.
Page | 24
Power System Analysis Complex Engineering Problem
So A= 35,520,000
= Rs 74,204,160
The above is the cost per unit generated which is much more optimized and economical than the
original one
Page | 25
Power System Analysis Complex Engineering Problem
Front Layout
Top View
Page | 26
Power System Analysis Complex Engineering Problem
Front Layout
Top View
Page | 27
Power System Analysis Complex Engineering Problem
Page | 28
Power System Analysis Complex Engineering Problem
References
[1] Evora-Gomez, Jose & Kremers, Enrique & Cueva, SM & Hernandez, M & Hernandez, Jose J & Viejo,
Pablo. (2011) “Agent-based modelling of electrical load at household level”. Cosmos 2011: Proceedings of the
2011 Workshop on Complex Systems Modelling and Simulation. “Research Gate.
[2] R.S. Adhikari, N. Aste, M. Manfren, “Optimization concepts in district energy design and management – A
case study”, Energy Procedia, Volume 14, 2012,Pages 1386-1391, Science Direct
[3] R. Biyanto, Totok & Alhikami, Akhmad & Nugroho, Gunawan & Hantoro, Ridho & Bayuaji, Ridho &
Firmanto, Hudiyo & Waluyo, Joko & Sonhaji, Agus. (2015). “Thermal Energy Storage Optimization in
Shopping Center Buildings ”. Journal of Engineering and Technological Sciences. 47. 549-567. Research Gate.
[4] Brian Drysdale, Jianzhong Wu, Nick Jenkins,” Flexible demand in the GB domestic electricity sector in
2030”, Applied Energy,Volume 139,2015, Science Direct.
[5] L. Chuan, D. M. K. K. V. Rao and A. Ukil, "Load profiling of Singapore bu ildings for peak shaving," 2014
IEEE PES Asia-Pacific Power and Energy Engineering Conference (APPEEC) , Hong Kong, 2014, pp. 1-6, doi:
10.1109/APPEEC.2014.7065998.
[6] TY - JOUR, AU - Hasanbeigi, Al Price, Lynn 2021/01/22 “Industrial Energy Audit Guidebook: Guidelines
for Conducting an Energy Audit in Industrial Facilities” Research Gate.
[7] Amit Garg, P.R. Shukla, Jyoti Maheshwari, Jigeesha Upadhyay, "An assessment of household electricity
load curves and corresponding CO2 marginal abatement cost curves for Gujarat state, India"
Energy Policy,Volume 66, 2014, Pages 568-584. Science Direct
[8] Hart, Craig & Wright, Jarrad. (2016). Impact of novel and disruptive approaches/technologies on a
distribution utility: A Kenyan case study. 10.13140/RG.2.1.4234.3920.
[9] Bayram IS, Saffouri F, Koc M, Generation, analysis, and applications of high resolution electricity load
profiles in Qatar, Journal of Cleaner Production (2018), doi: 10.1016/ j.jclepro.2018.02.084.
[10] Atănăsoae, Pavel; Pentiuc, Radu D. 2018. "Choosing the Energy Sources Needed for Utilities in the Design
and Refurbishment of Buildings" Buildings 8, no. 4: 54. https://doi.org/10.3390/buildings8040054
Page | 29