0% found this document useful (0 votes)
50 views8 pages

Test Plan Performance Test Weclever

Uploaded by

trancham46
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
50 views8 pages

Test Plan Performance Test Weclever

Uploaded by

trancham46
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 8

Performance Test Plan

weClever v2.0.5

EWOOSOFT

Author : Sandy
2024-09-05

Copyright © 2023 VATECH Networks | All Rights Reserved. / Confidential


Document History
Date of Revision Details Author Approved
2023-09-05 First Written Document Sandy

2023-10-05 Update after reviewing by team Sandy

Table of Contents
1. Test overview......................................................................................................................................................................... 3

Copyright © 2023 VATECH Networks | All Rights Reserved. / Confidential


1.1 Test items..................................................................................................................................................................... 3
1.2 Test purpose............................................................................................................................................................... 3
2. Test scope............................................................................................................................................................................... 3
3. Out of scope of test............................................................................................................................................................. 3
4. Performance Test Requirements.................................................................................................................................... 3
4.1 Non-functional Requirements.............................................................................................................................. 3
4.2 Test cases.................................................................................................................................................................... 4
5. Test entry criteria.................................................................................................................................................................. 4
6. Test completion criteria...................................................................................................................................................... 5
7. Acceptance criteria.............................................................................................................................................................. 5
8. Test schedule......................................................................................................................................................................... 5
8.1 Full schedule.............................................................................................................................................................. 5
8.2 Detailed Schedule.................................................................................................................................................... 5
9. Test strategy........................................................................................................................................................................... 5
10. Test environment................................................................................................................................................................ 6
10.1 Test URL.................................................................................................................................................................... 6
10.2 Test PC....................................................................................................................................................................... 6
10.3 Test tool...................................................................................................................................................................... 6
11. R&R......................................................................................................................................................................................... 6
12. Test risk & mitigation......................................................................................................................................................... 6
Risks...................................................................................................................................................................................... 6
13. Cooperation details........................................................................................................................................................... 7

Copyright © 2023 VATECH Networks | All Rights Reserved. / Confidential


1. Test overview

1.1 Test items

Test Product Name Version Project Key(VTS)


weClever V2.0.5 EVNWCL

Key Test Items Remarks


Performance Test NFR

1.2 Test purpose

Details Remarks
Make sure the product performance meets requirement or not.

2. Test scope
- All the reviewed Non-functional requirements (Refer to 4. Performance test requirements).

3. Out of scope of test


- Any work other than stated in Test Scope.

4. Performance Test Requirements


4.1 Non-functional Requirements

NFR Type /
No Category NFR Description Customer expectation
Performance - User Peak Load: The system must be able to support
1 Current avg concurrent users: 1400
load 1400 active users.

Performance - The system response time on peak load for user


2 Responsiveness requests, shall be less than 2 seconds for any Less than 2 seconds
individual request
Performance - The system upload time on peak load for user
Upload time requests, shall be less than 50 seconds for any Less than 50 seconds
3 individual request with file <= 40Mb Documents, file: .docx, pdf, etc.
Image: BMP, DCM, Png, Jpg,

Performance - The system download time on peak load for


Download time user requests, shall be less than 10 seconds for Less than 10 seconds
4 any individual request with file <= 40Mb Documents, file: .docx, pdf, etc.
Image: BMP, DCM, Png, Jpg...

Performance - The dental chart's loading time shall be less


Loading time than 4-5 seconds EVNWCL-1338/EVNWCL-855
5
Performance - First The first loading time to display the Drug base
Loading time connection status shall be less than 4-5 EVNWCL-1541
6 seconds
Performance - Memory saturation does not happen when there
Memory saturation were many reminders (tested on several EVNWCL-691
7 hundred chargeback reminders)

4.2 Test cases

No NFR Description Steps Expectation

Copyright © 2023 VATECH Networks | All Rights Reserved. / Confidential


1 Login
1400 users login 2.Add patient 1.Login & do actions
and do some 3.Add act in actual successfully
1
actions on patient 4. Payment (Collection) 2. Respond time less
1. Peak Load: The page than <2s
system must be able
to support 1400 1400 users login 1.Login & do actions
active users. and do some 1 Login successfully
2
2. Performance - actions on Agenda 2.Add Appointment 2. Respond time less
Responsiveness page than <2s
1400 users login 1.Login & do actions
and search patient 1. Login successfully
3
2. Search patent 2. Respond time less
than <2s
The system upload 1400 users login,
1 Login
time on peak load for create patient and
2. Add patient
user requests, shall upload document
3.Import document .docx, .pdf Upload time is less
4 be less than 50 or image
files (file <=40Mb) than 50 seconds
seconds for any
4. Import image bmp, dcm,
individual request
png files (file <=40Mb)
with file <= 40Mb
The system 1400 users login,
1 Login
download time on search patient and
2. Search patient
peak load for user download
3.Download
requests, shall be document or image Upload time is less
5 document .docx, .pdf files (file
less than 10 seconds than 50 seconds
<=40Mb)
for any individual
4. Download image bmp, dcm,
request with file <=
png files (file <=40Mb)
40Mb
The dental chart's 1400 users login,
1 Login Dental chart's loading
loading time shall be search patient and
2. Search patient time shall be less than
less than 4-5 open patient file
3.Open patient file 5 seconds
6 seconds
The first loading time 1400 users login,
to display the Drug open drug base
1 Login . Respond time less
base connection page
2. Open Drug base than < 5 seconds
status shall be less
7 than 4-5 seconds
Memory saturation
1 Login
does not happen
2.Accounting
when there were
3.Unpaid No problem with
many hundred Manual check: user
4.Relaunches with >200 memory
chargeback select Relaunches
patients
reminders) reminders functions with >
5. Check memory
8 (tested on several 200 patients

Note: Internet connection depends on France office.

5. Test entry criteria

Status
Items Remarks
(O/X/-)
Test is requested from stakeholders O
Test schedule, test scope, out of scope, test environments, test
O
strategy, test resource are defined and confirmed.
Non-functional requirements (NFRs) are defined and confirmed O
Test Pass/Fail Criteria is defined and confirmed. O
Test data, test scripts, test tool and test environment are prepared. O
Information of most recent development output from project (SRS,
O
VTS issues, etc.) is provided.
Product is deployed for testing from development team. O Link

Copyright © 2023 VATECH Networks | All Rights Reserved. / Confidential


6. Test completion criteria

Items Remarks
If "Not Test, N/A" item exists,
When prepared test items are all proceeded corresponding reason will be
informed to test process task
When test was requested to stop by PM, Test Manager
When test cannot be progressed due to unexpected problems.

7. Acceptance criteria

Pass Conditions Remarks


Non-functional requirements (NFRs) meet the requirements

8. Test schedule

8.1 Full schedule

Classification Performance test Tester Resource (MD)


Sandy, Kent
Schedule 2024/05/13 ~2024/05/17

8.2 Detailed Schedule


Date Details Output Tester MD
2024/05/13 Data,
~2024/05/14
Prepare data, environments Sandy
environment
2024/05/14 Tools, test
~2024/05/15
Prepare tools, test scripts Sandy, Kent
scripts
Sandy
2024/05/16
~2024/05/17
Run test scripts Test Result

2024/05/17 Create Test report Test report Sandy, Kent


Total 2

9. Test strategy

Key Point Remarks


Non-functional - Create the test scripts corresponding with the defined testcases
requirements (NFRs) - Run test scripts by tool

10. Test environment

10.1 Test URL

Remarks
URL
https://test.weclever-dental.com/ Preproduction

Copyright © 2023 VATECH Networks | All Rights Reserved. / Confidential


10.2 Test PC

OS Screen resolution Remarks Tester


Browsers
(Bit, Lang) (pixels)
Window 11, Ram Sandy, Kent
1920 x 1080 (Full HD) - Remote PC
8GB (64, English)

10.3 Test tool

Tool Version
JMeter 5.6.3

11. R&R
Role Contact Person Responsibility
Manage product.
Product Support product requirements.
Planner Wonbin Review schedule/cost, documents, defects, decide on major
(VDV) issues of project unit, and monitor the detailed activity of
project.
Project Manage project, schedule/cost.
manager Snow Review test output (Plan, Result), decide on major issues of
(EVN) project unit, and monitor the detailed activity of test
Developer
LTS team Develop product.
(LTS)
Test Test plan, test result approval, technical support for test,
Manager Kelly support for test process, monitor/manage the entire activity
(EVN) of test
Test Leader
Sandy Create NFRs and plan, run, create test report
(EVN)
Automation
Team Kent Review NFRs and plan, support to testers finish test
lead(EVN)

12. Test risk & mitigation

No Risks Impact Action/Mitigation Remark


1 NFR is changed High Re-design the performance test scenario,
delay in performance
2 NFR is hard to High Re-design the performance test
performed scenario, delay in performance
3 Server has problems High Delay in performance
4 Internet speed has High Delay in performance
problems

13. Cooperation details

Copyright © 2023 VATECH Networks | All Rights Reserved. / Confidential


Contents Remarks
VTS QA Task EVNWCL-1554

Copyright © 2023 VATECH Networks | All Rights Reserved. / Confidential