Abstract of 16 Check Dams

Uploaded by

bhaskar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
48 views

Abstract of 16 Check Dams

Uploaded by

bhaskar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 4

Name of the work: "Construction of 16 No's of Check Dams Across 1.

Pedda Vagu near Perumalla (V) of Lingampet (M), 2. Pedda Vagu near
Shetpally (V) 2 Nos of Lingampet(M), 3. Pedda Vagu near Nallamadugu
(V) of Lingampet (M), 4. Pedda vagu near Mathsangham (V) 3 Nos of
Gandhari (M) , 5. Gandhari vagu near Gandhari (V&M) 2 Nos,6. Mudholi
Vagu near Mudholi(V), Gandhari(M) 2 Nos, 7. Mallupet Vagu at Mallupet
(V), Sadashiva nagar(M), 8.Atti vagu( Khannapur -Gudem Vagu) near
Khannapur(V), Ramareddy (M),9.Bheemeshwarji Vagu(Gundaram Vagu)
near Gundaram (V) of Rajampet(M) 2 Nos, 10.Kalyani Vagu near
Advilingal(V) , Yellareddy (M) under Yellareddy Constituency of
Kamareddy District”

GENERAL ABSTRACT
S L No Description Total Amount
1 Check dams 356870810
Total Work 356870810
LS ITEMS:
1 Provision towards GST @ 12 % 42824497.00
2 Provision towards NAC Charges @ 0.1 % 356871.00
3 Seigniorage charges 5745997.00
4 Provision for SMET & DMF @ 32% on Seigniorage 1838719.00
charges (Statement Enclosed)

5 LS provision for SID and preparation of estimate 1100000.00


booklets
6 LS provision for trial pits 1100000.00
7 LS for infiltration Charges 1300000.00
8 LS Provision for Design Mix of Concrete, & Material 2100000.00
Testing Charges)

9 LS Provision for Tender Publication Charges, 700000.00


preparation of Agreement documents Photographic
Computerising and Xerox Charges
10 63106.00
LS for other unforssen &Rounding off
LS Total Amount Rs. 57129190.00

414000000
TOTAL Rs.

Dy.Executive Engineer, Executive Engineer,I&CADD.,


IB.Sub-Division, Yellareddy. IB Division, Kamareddy.
Name of the work: "Construction of 16 No's of Check Dams Across 1. Pedda Vagu near Perumalla (V) of Lingampet (M), 2. Pedda Vagu near Shetpally (V) 2 Nos of Lingampet(M), 3. Pedda Vagu near Nallamadugu (V) of Lingampet (M), 4. Pedda vagu near Mathsangham (V) 3 Nos of
Gandhari (M) , 5. Gandhari vagu near Gandhari (V&M) 2 Nos,6. Mudholi Vagu near Mudholi(V), Gandhari(M) 2 Nos, 7. Mallupet Vagu at Mallupet (V), Sadashiva nagar(M), 8.Atti vagu( Khannapur -Gudem Vagu) near Khannapur(V), Ramareddy (M),9.Bheemeshwarji Vagu(Gundaram
Vagu) near Gundaram (V) of Rajampet(M) 2 Nos, 10.Kalyani Vagu near Advilingal(V) , Yellareddy (M) under Yellareddy Constituency of Kamareddy District”

LINGAMPET(M) GANDHARI(M) SS NAGAR(M) RAMAREDDY(M) RAJAMPET(M) YELLAREDDY(M)

CHECK DAM CONSTRUCTIO CONSTRUCTIO


ACROSS CHECK DAM N OF N OF
CHECK DAM CHECK DAM CHECK DAM CHECKDAM CHECKDAM
CHECK DAM PEDDA CHECK DAM CHECK DAM ACROSS CHECK DAM CHECK DAM CONSTRUCTION OF
ACROSS ACROSS ACROSS CHECK DAM ACROSS ACROSS
ACROSS CHECK DAM VAGU AT ACROSS ACROSS GANDHARI ACROSS ACROSS CHECKDAM CONSTRUCTION OF
PEDDA PEDDA MUDHOLI ACROSS BHEEMESHWE BHEEMESHWE
PEDDA ACROSS CONFLUENC PEDDA PEDDA VAGU ON GANDHARI MUDHOLI ACROSS ATTI CHECKDAM ACROSS Total
VAGU NEAR VAGU NEAR VAGU NEAR MALLUPET ARJI ARJI Rate Per Amount
S. VAGU NEAR PEDDA E POINT OF VAGU NEAR VAGU NEAR UPSTREAM VAGU NEAR VAGU NEAR VAGU(KHANNAPU
VAGU(GUNDA VAGU(GUNDA
KALYANI VAGU Quantity
SSR Code Description of item NALLA BALANTHA PUTTI VAGU NEAR R -GUDEM VAGU) UNDER POCHARAM
NO TALLA REVU
POCHAMMA MADUGU
VAGU AT POTANGAL GANGAMMA GUNDU OF BAMAN POKALA
POCHAIAH NH-44 BRIDGE NEAR VADLOLLA RAM VAGU) RAM VAGU)
AT NALLAMADU VAGU AND TEMPLE AT REVU AT SANGHAM REVU AT ENCHA AT PROJECT COMMAND
TEMPLE AT AT FIELDS AT AT MALLUPET NEAR NEAR
PERUMALLA GU (V), GANDHARI MATHSANG MATHSANG REVU AT GANDHARI MUDHOLI REVU, NEAR ADVILINGAL(V)
SHETPALLY SHETPALLY MUDHOLI (V) GARMAN YELLAPUR
(V), VAGU AT HAM (V) HAM (V) GANDHARI (V&M) (V)
KHANNAPUR(V)
FIELDS AT TANDA AT
(V), (V), (V)
MATHSANG (V&M) GUNDARAM GUNDARAM
HAM (V), (V) (V)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty
Clearing thick jungle growth ( less than 50 percent
IRR-PMW-1- open space ) including bushes upto 30 cm /
1 135000 117000 98000 100000 143000 48000 50000 42000 44000 79200 89600 40000 52500 101250 38000 80150 1257700 2.9 sqm 3647330.00
2 parthenium and other weeds including burning or
disposing off the same as directed etc., complete.
Excavation in all kinds of soil including boulders upto
0.30 m dia for field channels, seating of embankment
for field channels etc., including dressing of bed and
IRR-CAW-1- sides to required profile, cost of all materials,
2
machinery, labour, placing the excavated stuff for
307 687 341 575 295.35 127.35 127.35 127.5 107.35 127.35 248 128 291 60 3549.25 58.9 cum 209051.00
2
formation of service road / embankment as directed
etc., complete with lead upto 10 m and lift upto 3 m.
IRR-CAW-1-2
Excavation for foundation in hard rock of all
toughness by blasting including boulders above 1.2 m
dia. for dam, spillway, intake structure and other
IRR-DAW-1-
3 appurtenant works and placing the excavated rock 1395 1395 476.4 cum 664578.00
4A
neatly in dump area or stack yard including levelling
as directed etc., complete with initial lead upto 1 km
and all lifts.IRR-DAW-1-4 (a)
Excavation for Structures- Mechanical Means
( Data adopted from MORTH)

Earth work in excavation in all kinds of soils of


IRR-CCDW- foundation of structures as per drawing and technical
4 specification, including setting out, construction of 5074.00 3126.00 5106.00 1505.00 5054.00 5795.00 6176.00 4424.00 4265.00 4949.00 5178.00 3479.00 5407.00 3368.00 3394.00 4622.00 70922 102.70 cum 7283689.00
1-2
shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom and
backfilling with approved material. ( depth upto 3
meters)
Providing and laying insitu vibrated M-15 ( 28 days
cube compressive strength not less than15 N /sq
mm ) grade cement concrete using 40 mm down size
approved, clean, hard, gradedaggregates for
foundation filling including cost of all materials,
machinery, labour, formwork,cleaning, batching,
IRR-CCDW- mixing, placing in position, levelling, vibrating,
5 3869.00 2414.00 2944.00 1525.00 1583.00 2119.00 2256.00 1627.00 1569.00 1815.00 1898.00 1272.00 1955.00 2028.00 2036.00 1686.00 32596 5842.50 cum 190442130.00
2-3 finishing, curing etc.,complete with initial lead upto 50
m and all lifts. (Cement content: 260 kg / cum with
use of super plasticiser(0.4% by wt. of cement),CA :
0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40
cum) IRR-CCDW-2-3

Providing and laying insitu vibrated M-15 ( 28 days


cube compressive strength not less than15 N / sq mm
) grade cement concrete using 20 mm down size
approved, clean, hard, gradedaggregates for sub-
structure / super- structure works including cost of all
materials,machinery, labour, formwork, scaffolding,
IRR-CCDW-
6 cleaning, batching, mixing, placing in 1243.00 1201.00 1194.00 1030.00 1054.00 903.00 935.00 755.00 742.00 801.00 820.00 642.00 835.00 864.00 866.00 741.00 14626 6483.10 cum 94821821.00
2-10
position,levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
(Cement content: 280 kg / cum with use of super
plasticiser(0.4% by wt. of cement),CA : 0.80cum,
Blending Ratio of CA--65:35, FA : 0.45 cum) IRR-
CCDW-2-10
Providing and laying insitu M- 20 ( 28 days cube
compressive strength not less than 20 N / sqmm )
grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for
wearing coat including cost of all materials,
machinery, labour, formwork, cleaning, batching,
IRR-CCDW- mixing, placing in position in alternate panels,
7 575.00 322.00 508.00 226.00 259.00 316.00 338.00 240.00 226.00 266.00 280.00 184.00 300.00 322.00 323.00 233.00 4918 6003.90 cum 29527180.00
2-26 levelling, compacting, finishing, curing, packing joints
with asphalt mortar etc., complete with initial lead
upto 50 m and all lifts. (Cement content: 330 kg /
cum with use of super plasticiser(0.4% by wt. of
cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.45 cum)
Name of the work: "Construction of 16 No's of Check Dams Across 1. Pedda Vagu near Perumalla (V) of Lingampet (M), 2. Pedda Vagu near Shetpally (V) 2 Nos of Lingampet(M), 3. Pedda Vagu near Nallamadugu (V) of Lingampet (M), 4. Pedda vagu near Mathsangham (V) 3 Nos of
Gandhari (M) , 5. Gandhari vagu near Gandhari (V&M) 2 Nos,6. Mudholi Vagu near Mudholi(V), Gandhari(M) 2 Nos, 7. Mallupet Vagu at Mallupet (V), Sadashiva nagar(M), 8.Atti vagu( Khannapur -Gudem Vagu) near Khannapur(V), Ramareddy (M),9.Bheemeshwarji Vagu(Gundaram
Vagu) near Gundaram (V) of Rajampet(M) 2 Nos, 10.Kalyani Vagu near Advilingal(V) , Yellareddy (M) under Yellareddy Constituency of Kamareddy District”

LINGAMPET(M) GANDHARI(M) SS NAGAR(M) RAMAREDDY(M) RAJAMPET(M) YELLAREDDY(M)

CHECK DAM CONSTRUCTIO CONSTRUCTIO


ACROSS CHECK DAM N OF N OF
CHECK DAM CHECK DAM CHECK DAM CHECKDAM CHECKDAM
CHECK DAM PEDDA CHECK DAM CHECK DAM ACROSS CHECK DAM CHECK DAM CONSTRUCTION OF
ACROSS ACROSS ACROSS CHECK DAM ACROSS ACROSS
ACROSS CHECK DAM VAGU AT ACROSS ACROSS GANDHARI ACROSS ACROSS CHECKDAM CONSTRUCTION OF
PEDDA PEDDA MUDHOLI ACROSS BHEEMESHWE BHEEMESHWE
PEDDA ACROSS CONFLUENC PEDDA PEDDA VAGU ON GANDHARI MUDHOLI ACROSS ATTI CHECKDAM ACROSS Total
VAGU NEAR VAGU NEAR VAGU NEAR MALLUPET ARJI ARJI Rate Per Amount
S. VAGU NEAR PEDDA E POINT OF VAGU NEAR VAGU NEAR UPSTREAM VAGU NEAR VAGU NEAR VAGU(KHANNAPU
VAGU(GUNDA VAGU(GUNDA
KALYANI VAGU Quantity
SSR Code Description of item NALLA BALANTHA PUTTI VAGU NEAR R -GUDEM VAGU) UNDER POCHARAM
NO TALLA REVU
POCHAMMA MADUGU
VAGU AT POTANGAL GANGAMMA GUNDU OF BAMAN POKALA
POCHAIAH NH-44 BRIDGE NEAR VADLOLLA RAM VAGU) RAM VAGU)
AT NALLAMADU VAGU AND TEMPLE AT REVU AT SANGHAM REVU AT ENCHA AT PROJECT COMMAND
TEMPLE AT AT FIELDS AT AT MALLUPET NEAR NEAR
PERUMALLA GU (V), GANDHARI MATHSANG MATHSANG REVU AT GANDHARI MUDHOLI REVU, NEAR ADVILINGAL(V)
SHETPALLY SHETPALLY MUDHOLI (V) GARMAN YELLAPUR
(V), VAGU AT HAM (V) HAM (V) GANDHARI (V&M) (V)
KHANNAPUR(V)
FIELDS AT TANDA AT
(V), (V), (V)
MATHSANG (V&M) GUNDARAM GUNDARAM
HAM (V), (V) (V)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Providing homogeneous embankment using soil from
approved borrow area in layers of 25 to 30 cm before
compaction including cost of all materials, machinery,
labour, all operations such as excavation, sorting out,
transportation, spreading soil in layer of specified
IRR-DAW-5-
8 thickness, breaking clods, sectioning, watering, 1737.00 4134.00 2071.00 3026.00 1474.00 686.00 686.00 686.00 686.00 686.00 1291.00 686.00 1538.00 177.00 19564 292.40 cum 5720514.00
5
compacting to density control of not less than 95
percent or as stipulated using Sheep foot roller /
Vibratory roller/ 8 to 10 tonne power roller etc.,
complete with initial lead upto 1 km and all lifts.

Providing and constructing contraction joints by fixing


31 cm wide central bulb type PVC water stop in single
line supported by 10 mm dia steel dowel rods on
IRR-DAW-4-
9 either side at 1 metre interval including cost of all 260.00 203.00 204.00 60.00 144.00 140.00 145.00 122.00 120.00 129.00 132.00 109.00 111.00 138.00 116.00 125.00 2258 252.40 Rmt 569919.00
5 Modified
materials, machinery, labour, valcunising joints etc.,
complete with all leads and lifts.

Providing and constructing 30 cm thick dry rubble


stone pitching including cost of all materials, labour,
IRR-CAW-8-
10 hand packing, finishing etc., complete with initial lead 2728.00 1964.00 4322.00 1616.00 2752.00 2946.00 2043.00 1964.00 2319.00 2437.00 1573.00 2555.00 2752.00 2752.00 2161.00 36884 577.80 Sqm 21311575.00
4
upto 50 m and all lifts.(with no pin headers)( rubble
stones : 0.33 cum/sqm)
Providing, fabricating and placing in position

reinforcement steel bars for RCC works including

cleaning, straightening, cutting, bending, hooking,


IRR-CCDW-
11 lapping, welding wherever required,tying with 1.25 4267.00 5528.00 3324.00 3561.00 2330.00 2610.00 2803.00 2945.00 1962.00 3210.00 2402.00 3520.00 2435.00 40897 60.30 Kg 2466089.00
2-1
mm dia soft annealed steel wire, including cost of all

materials, machinery, labour etc., complete with initial

lead upto 50 and all lifts. IRR-CCDW-2-1


Providing and fixing 25 mm dia 3 m long cold twisted
deformed steel dowel bars with one end driven into
45 to 50 mm diameter 1.50 m deep hole drilled in bed
rock and other end provided with L-bend for
embedding in concrete / masonry of over flow / non-
IRR-DAW-1-
12 over flow blocks and other appertenant works 210.00 210 985.40 No's 206934.00
13
including cost of drilling and cleaning hole, filling hole
with cement mortar 1 : 1 proportion, driving anchor
rod, cost of all materials, machinery, labour etc.,
complete with initial lead upto 1 km and all lifts.IRR-
DAW-1-13

356870810.00

Dy.Executive Engineer, Executive Engineer,I&CADD.,


IB.Sub-Division, Yellareddy. IB Division, Kamareddy.
STATEMENT SHOWING THE SEIGINORAGE CHARGES, DMF AND SMET CHARGES
Name of the work: "Construction of 16 No's of Check Dams Across 1. Pedda Vagu near Perumalla (V) of Lingampet (M), 2. Pedda Vagu near Shetpally (V) 2 Nos of Lingampet(M), 3.
Pedda Vagu near Nallamadugu (V) of Lingampet (M), 4. Pedda vagu near Mathsangham (V) 3 Nos of Gandhari (M) , 5. Gandhari vagu near Gandhari (V&M) 2 Nos,6. Mudholi Vagu
near Mudholi(V), Gandhari(M) 2 Nos, 7. Mallupet Vagu at Mallupet (V), Sadashiva nagar(M), 8.Atti vagu( Khannapur -Gudem Vagu) near Khannapur(V), Ramareddy
(M),9.Bheemeshwarji Vagu(Gundaram Vagu) near Gundaram (V) of Rajampet(M) 2 Nos, 10.Kalyani Vagu near Advilingal(V) , Yellareddy (M) under Yellareddy Constituency of
Kamareddy District”

Sand Metal Earth Gravel & stone


Sl Seignio Seignio Seigni Seigni
Item Total Qty Coeffici rage Coeffici rage Coeffi orage Coeffici orage
No. Qty Amount Qty Amount Qty Amount Qty Amount
ent Charge ent Charge cient Charge ent Charge
s s s s
1 M-15 using 40 mm sub structure 32596.00 0.40 13038.40 40.00 521536.00 0.90 29336.40 75.00 2200230.00 0.00 0.00 30.00 0.00 0.00 0.00 30.00 0.00
2 M-15 using 20 mm Super structure 14626.00 0.45 6581.70 40.00 263268.00 0.80 11700.80 75.00 877560.00 0.00 0.00 30.00 0.00 0.00 0.00 30.00 0.00
3 M- 20 using 20 mm for Wearing coat 4918.00 0.45 2213.10 40.00 88524.00 0.80 3934.40 75.00 295080.00 0.00 0.00 30.00 0.00 0.0000 0.00 30.00 0.00
4 Providing and constructing 30 cm thick 36884.00 0.00 0.00 40.00 0.00 0.00 0.00 75.00 0.00 0.00 0.00 30.00 0.00 0.33 12171.72 75.00 912879.00
dry rubble stone pitching including
cost of all materials, labour, hand
5 Embankment 19564.00 0.00 0.00 40.00 0.00 0.00 0.00 75.00 0.00 1.00 19564.00 30.00 586920.00 0.00 0.00 75.00 0.00
packing, finishing etc., complete with

TOTAL 873328.00 3372870.00 586920.00 912879.00

ABSTRACT
Item Amount DMF & SMET @
32%
Sand 873328.00 279464.96
Metal 3372870.00 1079318.4
Earth 586920.00 187814.4
Gravel & Stone 912879.00 292121.28
TOTAL 5745997.00 1838719.04
Or say 5745997.00 1838719.00

Dy.Executive Engineer, Executive Engineer,I&CADD.,


IB.Sub-Division, Yellareddy. IB Division, Kamareddy.