Project
Project
Which of the following is typically not included in the project final report?
A) Administrative performance.
B) Project performance.
C) Organizational structure.
D) Project teamwork.
E) Risk analysis and risk management.
ANSWER: C
Which of the following is not a primary mechanism by which the PM exerts control?
A) Reviews.
B) Personnel assignments.
C) Audit reports.
D) Resource allocation.
E) All of the above are mechanisms by which the PM exerts control.
ANSWER: C
Which of the following is a guideline to stop a project from having long, dreaded
meetings and possibly slow down the project schedule?
A) Hold “Weekly Progress Report” meetings.
B) Have excessive formality at project meetings.
C) Always attribute remarks to individuals in the minutes.
D) Distribute a written agenda in advance of the meetings.
ANSWER: D
Which of the following statements is not true about the project charter?
A) It determines the scope of the project.
B) It names the project manager for the project.
C) It authorizes the project manager to use organizational resources to perform
project activities.
D) It provides a high-level product description.
ANSWER: A
Activity D on a CPM network has predecessors B and C, and has successor F. D has
duration 6. B's earliest finish is 18, while C's is 20. F's late start is 26. Which
of the following is definitely true?
A) B is a critical activity.
B) C is completed before B.
C) D has no slack but is not critical.
D) D is critical and has zero slack.
E) F is critical and has zero slack.
ANSWER: D
Which of the following is not a rule for controlling/reducing the scope creep in a
project?
A) Consult PM on all proposed changes.
B) Include a change control system.
C) Fighting change.
D) Introduce a change order.
ANSWER: C
You are looking into strategies to deal with the negative risks in your project.
Which of the following is not a strategy that you can use to deal with negative
risks?
A) Avoid.
B) Transfer.
C) Mitigate.
D) Audit.
ANSWER: D
Which of the following terms is most closely associated with a task required by the
project?
A) Activity.
B) Event.
C) Milestone.
D) Network.
E) Path.
ANSWER: A
In which of the following project states is the value of the project audit of
rather limited usefulness?
A) Master schedule.
B) Initiation.
C) Feasibility study.
D) Preliminary plan/schedule budget.
E) The value of the project audit is very useful in all of the above project
states.
ANSWER: A
You are using a cause and effect diagram to find real causes of a problem by
exploring all the possible causes. Which quality process are you performing?
A) Quality assurance.
B) Quality planning.
C) Quality control.
D) Auditing.
E) Inspection.
ANSWER: C
The final project report typically does not include the organizational structure.
A) TRUE
B) FALSE
ANSWER: A
Audit reports are not a key method for a project manager to exert control.
A) TRUE
B) FALSE
ANSWER: A
A known limitation of the Gantt Chart is that it might require detailed technical
knowledge of the project's technologies.
A) TRUE
B) FALSE
ANSWER: A
Gathering benchmark data from similar projects is not a usual step in a project
audit.
A) TRUE
B) FALSE
ANSWER: A
The project charter does not determine the scope of the project.
A) TRUE
B) FALSE
ANSWER: B
If activity D in a CPM network has predecessors B and C and successor F, with F's
late start being 26, then D is critical and has zero slack.
A) TRUE
B) FALSE
ANSWER: A
A key result of the project launch meeting is the temporary fixing and
understanding of the project's scope.
A) TRUE
B) FALSE
ANSWER: A
Incorrectly assigning the technical team is not a fundamental reason for project
failure.
A) TRUE
B) FALSE
ANSWER: A
Completing the project final report is not one of the main duties of the
termination manager.
A) TRUE
B) FALSE
ANSWER: A
In the master schedule phase, the project audit's value is quite limited.
A) TRUE
B) FALSE
ANSWER: A
Using a cause and effect diagram to explore all possible causes of a problem is an
aspect of quality control.
A) TRUE
B) FALSE
ANSWER: A
It is false that the project manager must rely solely on the accounting department
for special project accounting rules.
A) TRUE
B) FALSE
ANSWER: A
The overall budget cost in top-down budgeting is generally not very accurate.
A) TRUE
B) FALSE
ANSWER: B
The business case for the project should be included in the project charter.
A) TRUE
B) FALSE
ANSWER: A
Traditional statistics assume that the paths are independent, which is a reason to
use simulation instead.
A) TRUE
B) FALSE
ANSWER: A
Which of the following statements is not true about a firm and its project
accounting?
A) Each firm has its own rules with regard to the allocation of overhead.
B) Most firms must comply with the Sarbanes-Oxley Act.
C) The project manager must rely on the accounting department to make special.
D) Most firms have their own accounting idiosyncrasies.
E) Unexpected charges may suddenly appear when the PM least expects it.
ANSWER: C
Which of the following is NOT one of the items addressed in a “Project Final
Report”?
A) Project teamwork.
B) Organizational structure.
C) Project performance.
D) Project manager performance.
ANSWER: D
The five process groups in project management are initiating, planning, executing,
monitoring, and closing.
A) TRUE
B) FALSE
ANSWER: A
A valid weakness of the Gantt Chart is that what appears on the chart may require
intimate knowledge of the project's technologies.
A) TRUE
B) FALSE
ANSWER: A
Auditing the project after completion is not a typical step in a project audit.
A) TRUE
B) FALSE
ANSWER: A
Collecting benchmark data from other similar projects is not a typical step in a
project audit.
A) TRUE
B) FALSE
ANSWER: A
Activity D on a CPM network, given its predecessors B and C, and successor F, with
F's late start being 26, is critical and has zero slack.
A) TRUE
B) FALSE
ANSWER: A
Naming the wrong technical team is not a fundamental reason for project failure.
A) TRUE
B) FALSE
ANSWER: A
Completing the project final report is not a main duty of the termination manager.
A) TRUE
B) FALSE
ANSWER: A
The value of the project audit is of rather limited usefulness in the master
schedule project state.
A) TRUE
B) FALSE
ANSWER: A
Using a cause and effect diagram to find real causes of a problem by exploring all
the possible causes is performing quality control.
A) TRUE
B) FALSE
ANSWER: A
The project manager must rely on the accounting department to make special project
accounting rules is not true about a firm and its project accounting.
A) TRUE
B) FALSE
ANSWER: A
Project manager performance is not one of the items addressed in a “Project Final
Report”.
A) TRUE
B) FALSE
ANSWER: A
The overall budget cost is generally not very accurate in top-down budgeting.
A) TRUE
B) FALSE
ANSWER: B
The business case for the project should always be included in a project charter.
A) TRUE
B) FALSE
ANSWER: A
The Traditional way assumes that the paths are independent is a valid reason for
using Simulation instead of Traditional Statistics.
A) TRUE
B) FALSE
ANSWER: A
What are the five process groups in project management?
A) Initiating, planning, executing, monitoring, and controlling
B) Initiating, planning, executing, monitoring, and closing
C) Initiating, scoping, executing, monitoring, and closing
D) Initiating, planning, executing, testing, and closing
ANSWER: B
Which of the following is not a primary mechanism by which the PM exerts control?
A) Reviews
B) Personnel assignments
C) Audit reports
D) Resource allocation
ANSWER: C
What is a guideline to stop a project from having long, dreaded meetings and
possibly slow down the project schedule?
A) Hold “Weekly Progress Report” meetings
B) Have excessive formality at project meetings
C) Always attribute remarks to individuals in the minutes
D) Distribute a written agenda in advance of the meetings
ANSWER: D
Which of the following statements is not true about the project charter?
A) It determines the scope of the project.
B) It names the project manager for the project.
C) It authorizes the project manager to use organizational resources to perform
project activities.
D) It provides a high-level product description.
ANSWER: A
Activity D on a CPM network has predecessors B and C, and has successor F. D has a
duration of 6. B's earliest finish is 18, while C's is 20. F's late start is 26.
Which of the following is definitely true?
A) B is a critical activity.
B) C is completed before B.
C) D has no slack but is not critical.
D) D is critical and has zero slack.
ANSWER: D
Which of the following is not a rule for controlling/reducing the scope creep in a
project?
A) Consult PM on all proposed changes
B) Include a change control system
C) Fighting change
D) Introduce a change order
ANSWER: C
You are looking into strategies to deal with the negative risks in your project.
Which of the following is not a strategy that you can use to deal with negative
risks?
A) Avoid
B) Transfer
C) Mitigate
D) Audit
ANSWER: D
Which of the following terms is most closely associated with a task required by the
project?
A) Activity
B) Event
C) Milestone
D) Network
ANSWER: A
In which of the following project states is the value of the project audit of
rather limited usefulness?
A) Master schedule
B) Initiation
C) Feasibility study
D) Preliminary plan/schedule budget
ANSWER: A
You are using a cause and effect diagram to find real causes of a problem by
exploring all the possible causes. Which quality process are you performing?
A) Quality assurance
B) Quality planning
C) Quality control
D) Auditing
ANSWER: C
Which of the following statements is not true about a firm and its project
accounting?
A) Each firm has its own rules with regard to the allocation of overhead
B) Most firms must comply with the Sarbanes-Oxley Act
C) The project manager must rely on the accounting department to make special
project accounting rules
D) Most firms have their own accounting idiosyncrasies
ANSWER: C
Which of the following is NOT one of the items addressed in a “Project Final
Report”?
A) Project teamwork
B) Organizational structure
C) Project performance
D) Project manager performance
ANSWER: D