Paraslim Parapet Formwork
Paraslim Parapet Formwork
1.0 Introductio n
Paraslim is a modular formwork system for use
in the construction of bridge deck cantilevers.
The system allows formwork to be erected and
dismantled quickly either piecemeal or in
modular panels.
This document is not to be used as a working
method statement. It is the customer’s
responsibility to assimilate this information into a
document specific to the site conditions.
This guidance note shall be read in conjunction
with the RMD Kwikform (RMDK) drawings.
It is assumed that work with RMDK equipment is
undertaken or supervised by personnel familiar
with the products. Where necessary product
familiarisation can be provided by RMDK.
2.0 References
Please refer to RMDK Paraslim brochure,
Paraslim Technical Data Sheets and the
attendant RMDK Risk Assessment. Reference
should also be made to the contract method
statement and construction drawings provided
by the contractor for specific details and
sequence.
Figure 1.
7.0 Erection
• For single use projects attachment of Paraslim frames to bridge beams may be carried
out piecemeal whilst the beams are at ground level. More usually and especially when
multiple use is envisaged, several Paraslim frames are pre-assembled into modular
panels complete with soffit members and ply for erection by crane. The dismantling
operation is nearly always carried out in modular panels by crane.
• Prior to any erection, grease the Paraslim Ties and assemble them with the Stripping
Cones. Insert the lower end of the assembly through the Paraslim Support Brackets
from above.
• Place the greased Paraslim Porthole Bearings in the correct Soldier porthole and pass
the safety chain tee through one of the small web holes to ensure the unit cannot
accidentally become dislodged.
• Ensure that all of the Paraslim Tilt Plates are in contact with the girder webs.
8.0 Checks
The customer should satisfy himself or herself that the equipment has been correctly
erected prior to any loading of the structure.
Lifting Points
Lashing Points
Side Stabilisers
For details of the load rating, assembly and adjustment of the Folding C-Hook refer to
Equipment Guidance Note UIX10606. For the majority of Paraslim modules there should
be no need to extend the two forks. The side stabilisers can be extended to provide
additional width to the C-Hook if required.
In the following sequence, photos referred to show a different version of the C-Hook but
apply equally
• Adjust the length of the legs on the Chain Assembly so that the angle of the C-Hook
forks approximately matches that of the soffit
• Lift the C-Hook into position. Working from a safe access on the deck and using tag
lines, guide the C-Hook forks into the Paraslim module between the secondaries and
the scaffold tube lacers. See Plates 2-7
• Secure the Paraslim module to the C-Hook lashing points using (lashings are not
supplied) See Plate 8.
• Lengthen the adjustable chain to move the centre of lift towards the combined centre of
gravity of the C-Hook plus the module. Keep the weight of the C-hook on the crane and
gently lift the Paraslim C-Hook until the forks are tight under the secondaries.
• Use the smaller Ratchet Spanner or the central hole on the Multispanner to undo all of
the ties in the module. When the tie thread is free from each porthole bearing withdraw
the ties upward through the cast deck. The C-hook now supports the module. See
Plates 9-12.
• Lower the C-hook, complete with the module and crane away from the bridge. Some
persuasion may be required if the module is stuck to the soffit. Take care not to allow
the equipment to foul or snag any part of the girders to avoid damage to the paintwork.
See plates 13-18.
• Lower the module to the ground for inspection and maintenance prior to immediate re-
erection with the C-hook, adjustment, storage or dismantling.
• Where Paraslim modules are to be stored before re-erection, attach temporary scaffold
tube legs with right angle couplers to the tube lacer at the end of the frames. Adjust the
length of the legs so that the module can be landed with the soffit slope matching that
used on the bridge to facilitate ready removal of the Paraslim C-Hook.
• Repeat for successive modules adjusting the point of lift to balance the load throughout
11.1. Access
Access below the soffit is required for this brief period where all tie holes can be filled in a
single operation. Access can be provided from scaffolding, cherry picker or scissor lift
working from below, or an underbridge inspection unit working from above.
11.2. Procedure
• Withdraw the projecting Flexihoses by hand from the soffit. Insert RMDK tie stoppers
to seal the hole from below. Pour RMDK Adogrout into the holes from above and
allow curing.
• Remove the tie stoppers from below for re-use and make good from below with RMDK
Adopatch mortar.