Electrical Upgrade Gantt Chart
Electrical Upgrade Gantt Chart
WEEK 1
WEEK 2
WEEK 3
WEEK 4
WEEK 5
WEEK 6
WEEK 7
WEEK 8
WEEK 9
Item No. Description Wt (%)
Actual % Wt.
2.1 Main MCBB 13.00% 0.00% 0.00% 3.00% 4.00% 3.00% 3.00%
2.3 Feeder Line 54.00% 0.00% 0.00% 11.00% 10.00% 11.00% 11.00% 11.00%
2.4 KFC & Café France Submersible Pump Electrical Works 2.00% 0.00% 0.00% 1.00% 1.00%
3.1 Concrete Cutting, Breaking , Excavation, Backfilling and Reconcreting Works 4.00% 0.00% 1.00% 1.00% 2.00% 1.00%
3.4 Construction of Admin Office (Con Van Type), including foundation/pedestal 3.00% 0.00% 0.00%
100.00% 8%
100.00%
11.00%
28.00%
45.00%
61.00%
74.00%
86.00%
97.00%
Projected Cummulative Accomplishment
5.00%
0.0%
Actual Accomplishment
0.00%
8.00%
3.50%
38.00%
2.17%
1.17%
9.00%
0.33%
2.67%
0.80%
1.25%
2.00%
0.00%