Tendernotice 1
Tendernotice 1
ENGINEERING DEPARTMENT
(B.C. DIVISION)
Office of BC Division,
2
5. Bidders with the following eligibility criteria only may participate:
Average Annual Turnover during the last three financial years ending with
March’ 2024 should not be less than Rs.14,64,935/- (Scanned copy of the
original audited balance sheets with Profit & Loss account sheets to be submitted
in proof of turnover along with the attested copy of turn over duly certified by
chartered Accountant having UDIN number).
5.2 Similar work executed criteria:
Scanned copy of original experience certificate(s) of having successful completion of
similar type of work during the last 07 (Seven) years ending last day of month
previous to the one in which applications are invited should either of the
followings:
a)Three similar completed works each costing not less than Rs.19,53,247/-.
(OR)
b)Two similar completed works each costing not less than Rs.24,41,559/-.
(OR)
c)One similar completed work costing not less than Rs.39,06,494/-
(1) Similar work in this case shall be defined as any civil engineering work.
(2) Scanned copy of Original TDS Certificate must be uploaded along with Technical Bid,
if the work certificate from any Private Organization is submitted for the above
purpose.
7. (a) For effecting the Bid, the online Bidder shall deposit the cost of Tender Document,
EMD separately to the A/C mentioned at 4.1(B)(Bid Information) through National Electronic
Fund Transfer (NEFT) / Real Time Gross Settlement (RTGS) and obtain the
acknowledgement of the said transaction. A self signed copy of these acknowledgements
should be uploaded by the Bidder while submitting the tender in respect of documents
regarding cost of Tender Document, The cost of tender document, EMD.
The Bidder should ensure that the transaction shall be within stipulated bidding period for
that tender. No previous dues of the bidder shall be adjusted towards the above transaction
of cost of Tender Document, EMD. The bidder shall not use the same transaction in more
than one tender. Otherwise his bid will be rejected.
The account from which the cost of Tender Document, EMD will be deposited should be
in the name of Contractor/authorized person of the firm who have digitally signed the bid.
Refund of EMD in respect unsuccessful bidders will also be made to that specific A/C of the
bidder.
(b) The exemption towards cost of Tender Document and EMD Fee shall be considered
from the bidders those who have registered with NSIC (National Small Industries
Corporation) / MSE (Micro and Small Enterprises 2012) registered with District Industries
Centre (DIC) / KVIC (Khadi & Village Industries Commission) / KVIB (Khadi & Village
3
Industries Board) / COIR Board / MOMSME ( Ministry of Micro, Small and Medium
Enterprises) / UAM (Udyog Adhar Memorandum). Such registration certificate must be
uploaded by the bidder along with the Technical Bid failing which the tender shall not be
considered.
(c) A standard form of refund of EMD/EASD is available in the tender documents at
APPENDIX-V, so as to facilitate the bidder for applying refund of EMD. Refund of EMD in
respect of unsuccessful bidders will only be made to that account from which it was
deposited by the Bidder.
9. The bidder must possess compatible Digital Signature Certificate (DSC) of Class-II or Class-
III.
10. All Bids are to be submitted online on the Websitehttps://eprocure.gov.in/eprocure/app. No
Bid shall be accepted off-line. The Bids shall be received only “on line” on or before
20/06/2024 upto 17:00 Hours.
11. The copies of the EPF & ESI Registration, GST Registration, PAN card, ITRs etc. should
be uploaded by the Bidder while submitting the Tender.
12. In the e-Tender System, after uploading the Bid; the bidder not to send any documents (Hard
copy) to the Tender inviting Authority before opening of Technical Bid (in case of Two Stage
Bid). After opening of the Bid, the Authenticity of the uploaded documents as per
requirement of the e-Tender document will be verified by the Tender Inviting Authority.
13. After evaluation of bid, all the bidders will get the information regarding their eligibility/pre-
qualification on website. Thereafter, a system generated e-mail confirmation will be sent to
all successful bidders. The bidders can check the same from the portal.
14. The Price-bid of the successful bidders (qualified in Technical-bid) will be decrypted and
opened on-line, on the scheduled date and after the pre-scheduled time by the Bid Openers
with their Digital Signature Certificate (DSC). The bidders can view bid opening remotely
on their personalized dash board under “Bid Opening (Live)” link. The bidders will get
the information regarding the status of their financial bid and ranking of bidders on website.
15. If there is a tie between two or more bidders for deciding the L-1 Offer then the designated
Tender Committee will finalize the tender by a transparent lottery system through video
recording in presence of the L-1 bidders or their authorized representatives. Even if any or all
L-1 bidders or their authorized representatives fail to be present at scheduled date and time
of lottery, duly informed to them, the lottery system shall be carried out by the committee to
finalize the L-1 bidder.
17. The authority will not be held responsible for any technical snag or network failure during on-
line bidding. It is the bidder‟s responsibility to comply with the system requirement i.e.
hardware, software and internet connectivity at bidder‟s premises to access the e-Tender
website. Under any circumstances, PPA shall not be liable to the bidders for any
direct/indirect loss or damages incurred by them arising out of incorrect use of the e-Tender
system or internet connectivity failures.
18. The authority reserves the right to reject any or all tenders without assigning any reasons
thereof and shall also not be bound to accept the lowest tender.
19. Bidder are advised to visit the site of work prior to submission of their bid. Bidder shall get
himself thoroughly familiarized with the site conditions, existing road facilities for carrying
materials etc before submission of the e-tender. He may contact the Executive Engineer, BC
Division or his authorized representative at his office at Administrative Building, Paradip Port
Authority, Dist – Jagatsingpur, Odisha -754142. In this regard. Non compliance of the same
4
will in no way relieve the successful bidder of any of his obligations in performing the work in
accordance with this Bid Document within the quoted price.
20. The Authority are not bound to accept the lowest or any tender and reserves the right to
accept a tender in full or in part and / or reject a tender in full or in part without assigning any
reason thereof.
21. Extra Additional Security Deposit (EASD): All the bidders who will quote
beyond 15% less over the estimated cost put to tender will mandatorily deposit
5% of the estimated cost put to tender through RTGS/NEFT in favour of FA & CAO,
PPT account prior to closing of the tender. The proof documents to be uploaded in
the 1st. Cover. After opening of the tender, if this amount exceeds the required
EASD amount, the balance will be refunded to the bidder after issue of work
order or will be adjusted against the ISD. If the bidder fails to deposit the above
5% value of the estimated cost put to tender and upload the proof within specified
time the bid of the said bidder will be treated as invalid/cancelled after opening
of the price bid. Then the tender will thereafter be processed for finalization
without considering the above invalid bidder. Bidders who are required to submit
balance EASD in addition to the mandatory 5% deposit according to their
respective quoted rates, then the lowest bidder after opening of the price bid will
be informed to deposit the balance EASD amount within 10 days time. In this case,
if the concerned bidder failed to deposit the balance EASD amount within the
stipulated time, the bid of the said tender will be treated as invalid/cancelled and
action as per tender condition will be initiated against the said bidder. Then the
tender will be processed for finalization excluding the above invalid bidder and
the next lowest bidder will be given chance to deposit the requisite amount. This
clause supersedes the earlier clause to this effect.
22. The bill of supplier of goods/services will be paid only after filing of GSTR-1 and
reflection of the same under GSTIN of PPA in the GST Portal
23. VALIDITY:
The Tender shall remain open for acceptance for a period of six months from the date of
opening of techno commercial bid. If before expiry of this validity period, the bidder amends
his quoted rates or tender, making them unacceptable to the Trustees and / or withdraws his
tender, the Earnest Money deposited shall be liable to forfeiture at the option of the Trustees
/ sanctioning authority.
Sd/-
Executive Engineer,
BC Division,
Paradip Port Authority
C.C. to:-1. The CE, PPA / C.V.O., PPA for favour of kind information.
2. The S.E.(T), PPA for favour of kind information.
3. E.E.(PD)/ All EEs under Engg. Deptt., PPA for favour of information.
4. PRO, PPA for information and necessary action. He is requested to arrange
publication in the Port Gazette & abbreviation form of e-TCN in Newspaper as per
norms.
5. Commandant, CISF, Paradip Port / Notice Board.
6. All HODs, PPA for information and with request to give wide publicity to the tender
call notice in the Notice Board.
7. All Asst. Executive Engineers /All AEs/ All JEs /Superintendent / Auditors of BC
Division, PPA for information.
5
CHECK LIST TO BE UPLOADED BY THE BIDDER
Name of Work: Providing, fixing of tiles to all rooms and renovation of the toilets of 06 Nos.
Type-C and 24 Nos. Type-B Port employees allotted Qtrs. at Nuabazar area.
Reference to Clause Uploaded If Yes,
Sl. No. (Yes/No) Page
Descriptions
No Reference
1 (a) Scanned copy of acknowledgement Clause No.6.1(A)
towards Cost of Tender Document/ of ITB
Exemption Document
(b) Scanned copy of acknowledgement Clause No.6.1(A)
towards EMD / Exemption document of ITB
3 Scanned copy of Audited Balance Sheet with Profit & Loss statement having UDIN number.
F.Y. - 2021-22
F.Y. - 2022-23 Clause No.6.1(A)
F.Y. – 2023-24 of ITB
4 Scanned copy of experience certificate of having successful completion of similar type of works
during the last seven years.
Three similar completed works costing not
a)
less than Rs. 19,53,247/- each OR
Two similar completed works costing not
b)
less than Rs. 24,41,559/- each OR Clause No.6.1(A)
c) One similar completed works costing not less of ITB
than Rs. 39,06,494/-
5 Scanned copy of Original TDS Certificate, if Clause No.6.1(A)
the work certificate is obtained from any of ITB
Private Organization.
6 Scanned copy of EPF Certificate Clause No.6.1(A)
of ITB
7 Scanned copy of ESI Certificate Clause No.6.1(A)
of ITB
8 Scanned copy of PAN Card Clause No.6.1(A)
of ITB
9 Scanned copy GST Registration Clause No.6.1(A)
of ITB
10 Scanned copy of Power of Attorney Clause No.6.1(A)
certificate, if any. of ITB
11 Copy of Income Tax Return (Last 03 Assessment years)
A.Y. - 2022-23
7
INFORMATION TO BIDDERS (ITB)
FOR e-PROCURMENT
1. GENERAL INFORMATION:
This section of the bidding documents provides the information necessary for bidders to
prepare online responsive bids, in accordance with the requirements of the Tender Inviting
Authority. It also provides information on online bid submission, opening, evaluation and
contract award.
8
2.0 QUALIFYING REQUIREMENT:-
The bidder shall upload the following documentary proof for fulfilling qualifying criteria as per
Clause No.5 of e-TCN.
i) Contact address of the organization/ Contact person with Mobile No., Land Phone
No., FAX No., Postal Address etc. who has issued such certificate(s).
3.0 BID VALIDITY: The validity of offer shall be 180 days from the date of opening of tender.
A bid valid for a shorter period may be rejected by the Trustee as being non responsive. In
exceptional circumstances, prior to expiry of the original tender validity period, the PPT may
request the bidder, in writing, for a specified extension in the period of validity.
4.0 The unit rates in Bill of Quantities shall be quoted strictly in figures only and macros must be
enable to see the word representation of figures.
5.0 EARNEST MONEY DEPOSIT: -
5.1 (a) The Bidder shall deposit EMD as mentioned in the e-TCN through NEFT/RTGS as
mentioned in Table No.4.1 (B).
(b) Any Firm registered with National Small Industries Corporation (NSIC)/ MSE
(Micro and Small Enterprises 2012) registered with District Industries Centre
(DIC) / KVIC (Khadi & Village Industries Commission) / KVIB (Khadi & Village
Industries Board) / COIR Board/MOMSME (Ministry of Micro, Small and Medium
Enterprises) / UAM (Udyog Adhar Memorandum), irrespective of relevance of the
product category is exempted towards deposit of cost of Tender Document and EMD
for the subject tender. Such registration certificate must be uploaded by the bidder
along with the Technical Bid failing which the tender shall not be considered.
9.4 The bidders; in their own interest, are advised to inspect and examine the site and its
surrounding and satisfy themselves, before submitting their tenders, in respect of the site
conditions including but not restricting to the following which may influence or effect the work
or cost thereof under the contract.
9.5 If any earlier fraud or corrupt cases was found against any bidder, the Trustees have the
right to cancel the bid for that corrupt /fraudulent bidder and may also debar him from
participating in future tenders.
b) The bank guarantee should preferably be issued from any of the branches of a
scheduled bank functioning at Paradip. In case the bank guarantee cannot be given from
a schedule bank functioning at Paradip then the bank guarantee should be en-cashable
in a branch of a schedule bank functioning at nearest possible branch of the bank to
Paradip. The bank guarantee itself should provide the encashability and be
countersigned by the branch in-charge on presentation of the bank guarantee.
c) Extra Additional Security Deposit (EASD): Extra Additional Security Deposit (EASD)
wherever applicable will be collected from the successful bidder along with the Initial
Security Deposit (ISD) after issuing the Letter of Intent (LOI). Back-out from the offer by
the participating bidder after opening of Technical Bid (in case of two stage bid) or price
bid (in case of single stage bid) OR non deposit of EASD by the successful bidder will
liable for forfeiture of EMD and suitable action shall be taken up against the bidder as per
decision of competent authority of PPA. EASD may be accepted in form of Demand
Draft, Bankers Cheque, Bank Guarantee in favour of Paradip Port Trust, IFSC:
ICIC0000776, Branch: Paradeep and must be drawn on any scheduled Bank located at
Paradip.
d) Extra Additional Security Deposit (EASD) & Its Calculation : Over and above the E.M.D,
tenderer quoting the rebate more than 15% on the cost of work put to tender shall have to
pay an ‘Extra Additional Security Deposit’ (E.A.S.D) separately. EASD wherever
applicable will be collected from the successful bidder along with the Initial Security
Deposit (ISD) after issuing the Letter of Intent (LOI). Back-out from the offer by the
participating bidder 20 after opening of Technical Bid (in case of two stage bid) or price
bid (in case of single stage bid) OR non deposit of EASD by the successful bidder will
liable for forfeiture of EMD and suitable action shall be taken up against the bidder as per
decision of competent authority of PPA. EASD may be accepted in form of Demand
Draft/Bankers Cheque/Bank Guarantee in favour of Paradip Port Trust, IFSC:
ICIC0000776, Branch: Paradeep and must be drawn on any scheduled Bank located at
Paradip. Extra Additional Security Deposit (E.A.S.D) = A x cost of work put to tender
100 Where A = Percentage rebate quoted on the cost of work put to tender by the tenderer
minus 15 (Fifteen). Example: If the tenderer desires to quote percentage rebate 25%
(Twenty five) percent, then the Extra Additional Security Deposit (E.A.S.D) shall be
worked out as under. E.A.S.D Amount = (25 – 15) x cost of work put to tender.
Note :1. The Demand Draft/ Banker’s Cheque/ Bank Guarantee shall be initially valid
upto scheduled completion and subsequently be extended upto actual completion. 2. The
E.A.S.D will be released on satisfactory completion of the work.
13
Scanned copy of PAN Card of the firm shall be uploaded along with the tender document
failing which the Bid may not be considered. Income Tax as per the Act shall be deducted
from the Bill of the contractor.
16.0 An amount of Cess calculated @1% of the billed amount shall be progressively recovered
from each running bill as well as from the final bill of the contractor for onward transmission
of the same by the appropriate authority. Other statutory deduction will also be made as
applicable at the time of payment.
17.0 TAX RECOVERIES AT SOURCE:
Any type of taxes applicable to the subject contract, duties, service charges, rents, etc. as
may be deductible would be deducted at source from the running payments of the
contractor/firm by Paradip Port Trust at the time of effecting payments as contained in the
provisions of relevant Acts/Laws.
As per law, if there is any provision for reimbursement/payment of any type of taxes by the
employer, the same shall be done accordingly.
18.0 RETIRED GOVERNMENT OR COMPANY OFFICERS:
No Engineer of Gazetted rank or other Gazetted officer employed in Engineering or
Administrative duties in Engineering Department of the State/Central Government or the
Paradip Port Trust is allowed to work as a contractor for the period of two years after his
retirement from Government service or from the employment of the Paradip Port Trust
without the previous permission of the State/Central Government/Paradip Port Trust, as the
case may be. The contract, if awarded, is liable to be cancelled if either the contractor or any
of his employee is found at any time to be such a person, who had not obtained the
permission of the State/Central Government or the Paradip Port Trust as aforesaid, before
submission of tender or engagement in the contractor‟s service as the case may be.
14
25. MISCELLANEOUS:
i) Bidders shall submit his offer for complete scope of work, strictly in accordance with the
tender document. Any deviation from the tender document and / or any in complete tender
shall not be considered.
ii) The bidder shall not impose his own terms and conditions in his offer or quote his rates
based on his own terms and conditions, such e-tenderers are liable to rejection at the option
of the trustees without further reference to the bidder.
„
iii) All materials shall have to be procured by the successful bidder and shall be of the best and
approved quality conforming to relevant specifications. The successful bidder shall also
arrange for supply of all labour, tools and plants as stipulated in the special conditions of the
contract, required for efficient execution of the work.
iv) all measuring units are in metric system and the rates and sums in the tender are in India
Currency. The language used throughout shall be in English.
v) the tender documents with all the enclosures, appendices, abstract form of tender and form
of tender shall be required to be complete, duly filled in and signed and uploaded.
vi) Contractor has to furnish a valid Mobile no.
vii) the bidder shall give a declaration about the names of their relations employed in Paradip
Port Trust. It is not to intention to debar the contractors from working if their relatives are
working in PPT but such a declaration is necessary in the interest of Trustees against any
possible lapses.
Sd/-
SIGNATURE OF THE TENDERER Executive Engineer,
BC Division
Paradip Port Authority.
Paradip- 754142
Dist- Jagatsinghpur
Odisha
15
CONDITIONS OF CONTRACT
CIVIL WORKS
2004
CONDITIONS OF CONTRACT
PART: 1 GENERAL CONDITIONS
DEFINITION AND INTERPRETATION
DEFINITIONS : 1.1 In the Contract (as herein after defined) the following words and
expressions shall have the meaning hereby assigned to them, except
where the context otherwise requires.
(a) “Employer” means the party named in Part-II who has called for Tenders
to build or construct, erect or deliver the works and who will employ the
Contractor and the legal successors in title to the Employer but not
(except with the consent of the Contractor) any assignee of the Employer.
(b) “Contractor” means the persons, firm or company whose tender has been
accepted by the Employer and includes the contractor‟s personal
representatives, successors and permitted assigns.
(c) “Engineer” means the Chief Engineer/Chief Mechanical Engineer/Chief
Engineer (Mech./Elect.) designated as such in Part-II).
(d) “Consultant” means the person or persons, firm or company designated
as such in Part-II.
(e) “Engineer‟s Representative” means any Representative or the Engineer
to perform such duties as mentioned in Clause 2.1 and 2.2. thereof
whose authority shall be notified in writing to the Contractor by the
Engineer.
(f) “Works” means the works to be executed in accordance with the
Contract.
(g) “Contract” means the notice inviting the tender, the tender and
acceptance thereof and the formal agreement, if any, executed between
the Employer and the Contractor together with the documents referred to
therein including these Conditions, with appendices and any special
conditions, the specifications, designs, drawings period schedule/bills of
quantities and schedule of rates. All these documents taken together shall
be deemed to from one contract and shall be complementary to one
another.
(h) “Contract Price” means the sum named in the Tender subject to such
additions there to or deductions there from as may be made under the
provisions hereinafter contained.
(i) “Constructional Plant” means all appliances or things of whatsoever
nature required in or about the execution, completion or maintenance of
the Works or Temporary Works (as hereinafter defined) but does not
include materials or other things intended to form or forming part of the
permanent work.
(j) “Temporary Works” means all temporary works of every kind required in
or about the execution, completion or maintenance of the work.
(k) “Drawings‟ means the drawings referred to in the specification and any
modification of such drawings approved in writing by the Engineer and
such other drawings as may from time to time be furnished or approved in
writing by the Engineer or in case of contractor‟s alternate designs,
drawings submitted by the contractor and approved by the Engineer.
(l) “Site” means the lands and other places on under in or through which the
works are to be executed or carried out and any other lands or places
provided by the Employer for the purpose of the contract together with
such other places as may be specifically designated in the Contract as
forming part of the Site.
(m) “Approved” means approved in writing including subsequent written
confirmation of previous verbal approval and “approval” means approval
in writing including as aforesaid.
16
(n) “Market Rate” means the rate as decided by the Engineer on the basis of
the cost of materials and labour to the contractor at the Site where the
works are to be executed, plus the percentage mentioned in schedule to
cover all overheads and profit.
(o) “Prime Cost” & “Prime Cost Sum” means the amount actually paid by the
contractor for any article, commodity or special work and shall include all
proper charges for packing, carriage and delivery to Site after deduction
of all trade discounts, rebates and allowance & the discount obtainable for
cash in so far as such discount for cash exceed 2½ percent.
(p) “Nominated Subcontractor” means all specialists, merchants, tradesmen
and others executing any special work or supplying any materials for
which provisional or prime cost sum are included in the contract, who may
have been or be nominated or selected or approved by the
Employer/engineer and shall be deemed to be employed by the
contractor.
(q) “Provisional Sum” or “Provisional Lumpsum” means a lumpsum included
by the Employer in the tender documents and shall represent the
estimated value of work for which details are not available at the time of
issue of tender.
(r) “Schedule(s) referred to in these conditions shall mean the relevant
Schedule(s) annexed to the tender paper issued by Employer.
(s) “A Week” means, seven days without regard to the number of hours
worked in any day in the week.
(t) “A Day” means a day of 24 hours from midnight to the next midnight
irrespective of the number of hours worked in that day.
(u) “A month” means month according to Gregorian Calendar.
Singular & Plural 1.2 Words Importing the singular only also include the plural and vice versa
where the context requires.
Marginal 1.3 The marginal headings or notes in these General Conditions shall not be
Headings or deemed to be part thereof or be taken into consideration in the
Notes interpretation or construction thereof or of the Contract.
ENGINEER’S REPRESENTATIVES
Duties and 2.1 The duties of the Engineer‟s Representative are to watch and supervise
Power of the works and to test and examine any materials to be used on
Engineer’s workmanship employed in connection with the works. He shall have no
Representative authority to relieve the contractor of any of his duties or obligations under
the contract nor except as expressly provided hereunder or elsewhere in
the contract to order any work involving delay or any extra payment by
the employer nor to make any variation of or in the works.
2.2 The Engineer may from time to time in writing delegate to the Engineer‟s
Representative any of the Powers and authorities vested in the Engineer
and shall furnish to the contractor a copy of all such written delegations of
powers and authorities. Any written instruction or approval given by the
Engineer‟s Representative to the contractor within the terms of such
delegation (but not otherwise) shall bind the contractor and the Employer
as though it had been given by the Engineer. Provided always as follows:-
(a) Failure of the Engineer‟s Representative to disapprove any work or
materials shall not prejudice the power of the Engineer thereafter
disapprove such work or materials and down, removal or breaking up
thereof.
(b) If the contractor shall be dissatisfied by reason of any decision of the
Engineer‟s Representative, he shall be entitled to refer the matter to the
Engineer who shall thereupon confirm, reverse or very such decision.
ASSIGNMENT AND SUBLETTING
Assignment Sub- 3.1 The contractor shall not assign the contractor or any part thereof or any
Letter benefit or interest therein or there under without the prior written consent
of the Employer.
3.2 The contractor shall not sublet the whole of the works, except where
otherwise provided by the contract, the contractor shall not sublet any
part of the works without the prior written consent of the Engineer (which
shall not be unreasonably withheld) and such consent if given shall not
17
relieve the contractor from any liability or obligation under the contract
and he shall be responsible for the facts defaults and neglects of any sub-
contractor, his agents, servants, or workmen, provided always that the
provisions of labour on piecework basis shall not be deemed to be a
subletting under this clause.
EXTENT OF CONTRACT
4.1 The contract comprise the construction, completion and maintenance of
the works and except in so far as the contract otherwise provides, the
provisions of all labour, materials, constructional plant, Temporary works
and everything whether of a temporary or permanent nature required in
and for such construction completion and maintenance so far as the
necessity for providing the same is specified in or reasonably to be
inferred from the contract.
CONTRACT DOCUMENTS
Languages 5.1.1 The language or languages which the contract documents shall be drawn
up shall be English.
Documents 5.1.2 Except if and to the extent otherwise provided by the contract the
Mutually provisions of the General conditions and conditions of particular
Explanatory applications shall prevail over those of any other document forming part
of the contract. Subject to the forgoing the several documents forming the
contract are to be taken as mutually explanatory of one another but in
case of ambiguities or discrepancies the same shall be explained and
adjusted by the Engineer who shall there upon issue to the contractor
instructions directing in what manner the work is to be carried out.
5.1.3.1 If there are varying or conflicting provisions made in any one document
forming part of the contract, the contract, the Engineer shall be the
deciding authority with regard to the intention of the document.
5.1.3.2 Any error in description, quantity or rate in schedule or works/items or Bill
of Quantities or any commission there from shall not vitiate the contract or
release the contractor from the execution of the whole or any part of the
works comprised therein according to Drawing and specifications from
any of his obligations under the contract.
Custody of 5.2.1 The Drawing shall remain in the sole custody of the Engineer but two
Drawing copies thereof shall be furnished to the contractor free of cost. The
contractor shall provide and make at his own expense any further copies
required by him. At the completion of the contract the contractor shall
return to the Engineer all drawing provided under the contract, if so
desired by the Engineer. The contractor shall give adequate notice in
writing to the Engineer or the Engineer‟s Representative of any further
drawing or specification that may be required for the execution of the
works or otherwise under the contract.
In case of alternative design submitted by the contractor is accepted by
the Engineer and works executed as per alternative design, the original
tracing and copies of drawings which may be with the contractor, shall be
handed over to the Engineer on completion of the work and such tracing
and drawing shall become the property of the Engineer.
One copy of 5.2.2 One copy of the drawings furnished to the contractor or prepared by the
Drawings to be contractor and approved by the Engineer in case of contractor‟s
kept on site alternative designs as aforesaid shall be kept by the contractor on the site
and the same shall at all reasonable items be available for inspection and
use by the Engineer and the Engineer‟s Representative and by any other
person authorised by the Engineer in writing.
Further Drawings 5.3 The Engineer shall have full power and authority to supply to the
and Instructions contractor by the Employer, from time to time during the progress of the
works such further Drawings and instructions as shall be necessary for
the purpose of the proper and adequate execution and maintenance of
the work and the contractor shall carry out and be bound by the same.
GENERAL OBLIGATIONS
Contract 6.1 The contractor will be required to enter in to a formal agreement with the
Agreement Employer incorporating the conditions of contract in the form prescribed
by the Engineer with such modifications as may be necessary at the cost
of contractor. All costs, charges and expenses including stamp duty
18
incurred in connection with the contract as well as preparations and
completion of agreement/shall be borne by the contractor. Until such
contact is executed the acceptance of the tender in terms of the contract
as defined in clause 1.1 (g) shall be binding upon the parties and shall be
contract.
Earnest Money 6.2.01 The amount of earnest money shall be 1% of the estimated cost put to
tender subject to the minimum of Rs.50 and maximum of Rs.20,000/-.
Security Deposit 6.2.1 A If the estimated cost of work does not exceed Rs.50,000/-
(i) A sum of worked out on the basis of 2% the accepted tender shall be
deposited by the contractor towards security in the form of cash,
irrevocable bank guarantee, Govt. Securities, approved bank deposit
receipts and other securities approved by the employer, within 14 days of
placement of work order. This will remain in force throughout the period of
contract including the maintenance period and will be refunded thereafter.
(ii) Further 2% retention money of the said accepted tender cost will be
deducted in installments at the rate of 2% from each of the Contractor‟s
running bills.
B If the estimated cost of work exceeded Rs.50,000/-
(i) A sum worked out on the basis of 5% of the accepted tender shall be
deposited by the contractor towards security in the form of cash,
irrevocable bank guarantee, Govt. securities, approved bank deposit
receipt and the others securities approved by the employer within 23 days
of placement of work order.
(ii) Retention money at the rate of 5% of the certified bill will be deducted
from each running bill subject to a maximum of 3% of the contract price.
(iii) Refund of the security deposit and the retention money to the contractor
will be made on the lines specified in clause 6.2.3 of conditions of
contract. Provided however, that contractor will have option to furnishing
irrevocable Bank Guarantee, Government securities, approved Bank
deposit receipt and other securities approved by the employer in lieu of
the retention money in cash referred to in sub-clause A (ii), B (ii) above.
Retention Money 6.2.2 A Percentage as stated in Part II will be deducted from each running bill
subject to a maximum accumulation of the sum stated in Part II.
6.2.3 The amount as stated in clauses 6.2.1 and 6.2.2 will not bear any interest.
Half of the above sum will be refunded to the contractor, if he so desires
on substantial completion and/or handling over of the work to the
satisfaction of Engineer, the balance being held in deposit as security for
a satisfactorily maintaining the works free from defects for a period of 6
months after the date of completion of works. If during this period of 6
months any defects are notified which in the opinion of the chief Engineer
are due to bad materials, used and or defective workmanship the
contractor shall be required to carry out at contractor‟s cost, such repairs
as the Chief Engineer considers necessary or in the event of contractor
failing to do this within a notified time, the Chief Engineer may arrange for
such repairs to be carried out and deducted the cost of such rectification
of the defects from the amount retained without prejudice to the recovery
of any amount that may have been spent in excess of the deposit. For
purpose of this clause, the period of 6 months shall count from the date of
handling over of the works by the Contractor to the Chief Engineer.
Inspection of Site 6.3 The Tender shall be deemed to have been based on such date regarding
hydrological climate and physical conditions nature of ground and
underlying strata as shall have been supplied by the Employer in the
documents furnished to the contractor by the Employer for the purpose of
tendering. The contractor shall never the less inspect and examine the
site and its surroundings and shall satisfy himself before submitting his
Tender as to the from and nature of the site the quantities and nature of
work and materials necessary for the completion of the work and the
means of access to the accommodation be may require and in general
shall himself obtain all necessary information as to risks contingencies
and other circumstances which may influence or effect his Tender.
Sufficiency of 6.4.1.1 The Contractor shall be deemed to have satisfied himself before
Tender tendering as to the correctness and sufficiency of his tender for the works
19
and of the Rates and prices stated in Price Bill of Quantities and the
Schedule of Rates and Prices (if any) which Rates and prices shall except
in so far as it is otherwise provided in the contract cover all his obligations
under the contract and shall cover matters and things necessary for the
proper completion and maintenance of the works.
6.4.1.2 If the contractor suggests alternative designs he shall be deemed to have
collected all relevant information and conducted all necessary tests
required for the proper execution of the work based on his alternative
design before tendering.
Work to be 6.5 The contractor shall execute complete and maintain the works in strict
Satisfaction of accordance with the contract to the satisfaction of the Engineer and shall
Engineer comply with and adhere strictly to the Engineer‟s instructions and
directions on any matter (Whether mentioned in the contact or not)
touching or concerning the works. The Contractor shall take instructions
and direction only from the Engineer or (Subject to the limitations referred
no in Clause 2 here of from the Engineer‟s Representative.
Programme to 6.6.1 The execution of the work shall be so planned as to cause little
be Furnished impediment as practicable to the working of the Port in General.
6.6.2 The contractor shall submit to the Engineer, within one month or further
period as may be permitted by the Engineer after receipt of the
acceptance letter for the tender, a detailed PERT/CPM network based
programme for completion of work in the form of a detailed network and
Bar Charts both in triplicate. The network shall include the various
activities involved in the execution of the work and their
interdependencies and the time required for completion of the different
activities. The progress of the work shall be periodically reviewed and the
network will be up-dated by the contractor every three months and three
copies of this shall be supplied expeditiously to the Engineer. The
contractor shall submit to the Engineer during the first week of every
calendar month the up-to-date progress and the progress made during
the previous month on important sections or portions of the work in
relation to the network programme.
6.6.3 The contractor shall submit the Engineer within one month or further
period as may be permitted by the Engineer after the receipt of the
acceptance letter for the tenders, a statement indicating his estimates,
based on the detailed and approved network, of the gross and the net
amounts that would become payable to him at the end of each month
during the progress of the works, to enable the employer to arrange for
the required funds. In case a revision of such an estimate is considered
necessary by the Contractor he will be allowed to furnish a revised
estimate based again on approved network, provided it is received
sufficiently in advance of the actual date payment of a monthly certificate.
6.6.4 The contractor shall submit to the Engineer for his approval full details
and drawings for the design or any Temporary works which he proposes
to construct sufficiently in advance as directed by the Engineer depending
on the nature of the work before work on the erection of any such
Temporary works commences on the site.
6.6.5 The submission to and approval by the Engineer or Engineer‟s
Representative of such programme or the furnishing of such particulars
shall not relieve the contractor or any of the duties or responsibilities
under the contract in connection with the works or Temporary Works.
Contractor’s 6.7 The contractor shall give or provide all necessary superintendence during
Superintendence the execution of the works and as long thereafter as the Engineer may
consider necessary for the proper fulfilling of the contractor‟s obligations
under the contract. The contractor or competent and authorized agent or
representative approved of in writing by the Engineer (which approval
may at any time be withdrawn) is to be constantly on the works and shall
give his whole time to the superintendence of the same. If such approval
shall be withdrawn by the Engineer the contractor shall as soon as is
practicable after receiving written notice of such withdrawal remove the
agent from the site and shall not thereafter employ him again on the site
in any capacity and shall replace him by another agent approved by the
20
Engineer such authorized agent or representative shall receive on behalf
of the contractor directions and instructions from the Engineer or (subject
to the limitations of clause 2 Hereof) the Engineer‟s Representative.
Contractor’s 6.8.1 The contractor shall provide and employ on the site connection with the
Employees execution and maintenance of the works.
(a) Only such technical assistants as are skilled and experienced in their
respective callings and such sub-agents foremen and leading hand as are
competent to give proper supervision to the work they are required to
supervise and.
(b) Such skilled, semiskilled and unskilled labour as is necessary for the
proper and timely execution and maintenance of the works.
6.8.2 The Engineer shall be at liberty to object to and require the contractor to
remove forthwith from the works and person employed by the contractor
in or about the execution or maintenance of the works who in the opinion
of the Engineer misconduct himself or is incompetent or negligent in the
proper performance of his duties or whose employment is otherwise
considered by the Engineer to be undesirable of the Engineer. Any
persons so removed from the works shall be replaced as soon as
possible by a competent, substitute approved by the Engineer.
6.8.3 The Employer shall be at liberty to terminate the contract if the successful
tender himself or any of his partners/employees or any of his directors
who having held class I post in the Port Trust prior to his retirement has
failed to obtained the Chairman‟s Port Trust specific permission to
undertake any outside employment before the expiry of two years from
the date his retirement, in accordance with the provisions of the
…………………………..…… Port Trust Class I employees. (Acceptance
of employment after retirement) Regulations 1975.
Setting Out 6.9 The contractor shall be responsible for the true and proper setting out of
the works in relation to original point lines and level of reference given by
the Engineer in writing and for the correctness (subject as above-
mentioned) of the position levels dimensions and alignment of all parts of
the works and for the provision of all necessary instruments appliances
and labour in connection therewith. If at any time during the progress of
the works any error shall appear or arise in the position levels dimension
or alignment of any part of the works the contractor on being required so
to do by the Engineer or Engineer‟s Representative shall at his own
expense rectify such error to the satisfaction of the Engineer or
Engineer‟s Representative. The Checking of any setting out or of any line
or level by the Engineer or the Engineer‟s Representative shall not in any
way relieve to contractor of his responsibility for the correctness thereof
and the contractor shall carefully protect and preserve all benchmarks
site-rails pages and other things used in setting out the works.
Borehole and 6.10 If at any time during the execution of the works the Engineer shall require
Exploratory the contractor to make boreholes or to carry out exploratory excavation
Excavation such requirement shall be ordered in writing and shall be deemed to be
an addition ordered under the provisions of clause 11.1.1 and 11.1.2
hereof unless a provisional sum in respect of such anticipated work shall
have been included in the Bill of Quantities.
Watching and 6.11.1 The contractor at his own cost shall make such provisions for the lighting
Lighting the works, materials and plant whether on shore or a float and shall
provide all such works and lights as may be required by Engineer or the
Employer or any other authority having jurisdiction in connection with the
site together with all labour stores and services required for their efficient
working and use at any item of day and night and all buoys and other
works required for the proper indication of submerged work and of
mooring for his vessels. He shall also provided at his own cost every
description of watching and maintenance required in connection with the
foregoing and all other services and for protecting and securing all places
dangerous whether to the contractor workmen or to other persons until
the work shall have been handed over to the Employer unless the
Engineer shall decide that such services are not longer required.
21
6.11.2 All lights provide by the contractor shall be placed or screened so as not
to interfere with any signal lights on the Employer‟s railways or with any
navigational lights or with any traffic or signal lights of any local or other
authority.
Care of Works 6.12.1 From the commencement to the completion of the works the contractor
shall take all responsibility for the care thereof and of temporary works
and in case any damage loss or injury shall happen to the works or to any
part thereof or to any Temporary works from any cause whatsoever (save
and except the Excepted Risk as defined in Clauses 6.12.2) shall at his
own cost repair and make good the same so that at completion the works
shall be in good order and condition and in conformity in every respect
with requirements of the contract and the Engineer‟s instructions. In the
event of any such damage loss or injury happening from any of the
Excepted Risks the contract shall if and to the extend required by the
Engineer and subject always to the provisions of clause 17 hereof repair
and make good the same as aforesaid at the cost of the Employer. The
contractor shall also be liable for any damage to the works occasioned by
him in the course of any operations carried out by him for the purpose of
complying with his obligations under clause 10.1.1 to 10.1.4 hereof.
6.12.2 The “Excepted Risk” are war hostilities (Whether war be declared or not)
invasion act of foreign enemies rebellion revolution insurrection or military
or usurped power civil war or (otherwise than amount the contractor‟s
own employee‟s) riot communion or disorder or use or occupation by the
Employer or any portion of the works in respect of which a Certificate of
completion has been issued or a cause solely due to the Engineer‟s
design of the works or any such operation of the forces of nature as
reasonable foresight and ability on the part of the contractor could not
foresee or reasonable provide against (all of which are herein collectively
referred to as “The Excepted Risks”)
Insurance of 6.13 Without limiting his obligations and responsibilities under Clauses 6.12.1
Works Etc. and 1.2.2 hereof the contractor shall insure in the joint names of the
Employer and the contractor against all loss or damage from whatever
cause arising (other than the Excepted Risks) for which he is responsible
under the terms of the Contract and in such manner the Employer and
Contractor are covered during period of construction the works and are
also covered during the period of Maintenance for loss or damage arising
from a caused occurring prior to the commencement of the period of
Maintenance and for any loss or damage occasioned by the contractor in
the course of any operations carried out by him for the purpose of
complying with his obligations under clauses 10.1.1 to 10.1.4 hereof.
(a) The works and the Temporary Works to the full value of such works
executed from time to time.
(b) The materials Constructional Plant & other things brought on the Site by
the Contractors to the full value of such materials Constructional Plant
and other things.
(c) As in case of sinking of constructional Plant and equipment for the cost of
salvage of the same to aggregate limit of Rs………………….. Lakhs.
6.13.1 The insurance applies only to contracts the estimated value of which is
Rs.25 lakhs or above. Such insurance shall be effected with an insurance
and in terms approved by the Employer & the Contractor shall whenever
required produce to the Engineer or the Engineer‟s Representative the
policy or policies of insurance and the receipts for payment of the current
premium provided always that without limiting his obligation and
responsibilities as aforesaid nothing in the Clause contained shall render
the Contractor liable to insure against the necessity for the repair or
reconstruction of any work constructed with materials of workmanship not
in accordance with the repairments of the contract.
Damage 6.14.1 The contractor shall (except if and so far as the specification provide
Persons and otherwise) indemnify and keep indemnified the employer against all
Property losses and claim for injuries or damage to any persons or any property
whatsoever (other than surface or other damage to land being or crops
22
being on the site suffered by tenants or occupiers) which may arise out of
or in consequence of the construction & maintenance of the works and
against all claims demands proceeding damages costs charges and
expenses whatsoever in respect of or in relation there to that nothing
herein contained shall be deemed to render the Contractor liable for in
respect of or to indemnify the employer against any compensation or
damages. Provided further that for the purpose of this clause the
expression “The Site” shall be deemed to be limited to the area defined in
the specification or shown on the drawings in which land and crops will be
disturbed or damaged as an inextensible consequence of the carrying out
of the Works.
Third Party 6.15.1 Before commencing the execution of the Works the contractor (but
Insurance without limiting his obligations and responsibilities under Clause 6.14.1)
shall insure against any damage loss or injury which may occur to any
property (including that of the Employer or to any person (including any
employee of the employer) by or arising out of the execution of the Works
or temporary works or in the carrying out of the Contract otherwise than
due to the matters referred to in the provision to clause 6.14.1 hereof.
Minimum 6.15.2 Such insurance shall be effected with an insurance and in terms
Amount of Third approved by the Employer and for at last the amount stated in the Tender
Party Insurance and Contractor shall whenever required produce to the Engineer or the
Engineer‟s Representative the policy or policies or insurance and the
receipt for payments of the current premiums.
Accident or 6.16.1 The Employer not be liable for or in respect of any damages or
Injury to compensation payable at Law in respect or in consequence of any
workmen accident or injury to any Workman or other person in the employment of
the Contractor any sub-contractor and the Contractor shall indemnify and
keep indemnified the employer against all which damages and
compensation and against all claims demands proceedings cost charges
and expenses whatsoever in respect thereof or in relation thereto.
Insurance 6.16.2 The contractor shall insure against such liability with an insurer approved
against accident by the Employer and shall continue such insurance during the whole of
etc., to Workman the time that any persons are employed by him on the Works and shall
when required produce to the Engineer or the Engineer‟s Representative
such policy of insurance and the receipt for payment of the current
premium. Provided always that in respect of any persons employed by
any subcontractor the Contractors obligations to insure as aforesaid
under this sub-clause shall be satisfied if the sub-contractor shall have
insured against the liability in respect of such persons in such manner
that the Employer is indemnified under the Policy but the Contractor shall
require such sub-contractor to produce to the Engineer or „Engineer‟
Representative when required such policy of insurance and the receipt for
payment or the current premium.
Remedy on 6.17 If the Contractor shall fail to effect and keep in force in insurance referred
Contractor’s to in Clause 6.13, 6.15 and 6.16 hereof or any other insurance which he
Failure to Insure may be required to effect under the terms of the contract then and in any
such case the employer may effect and keep in force any such insurance
and pay such premium or premiums as any be necessary for the purpose
and from time to time deduct the amount so paid by Employer with
interest as stated in part II as aforesaid from any moneys due or which
may become due to the contractor or recover the same as a debt due
from the contractor.
Giving of Notice 6.18.1 The Contractor shall give all notices and pay all fees required to be given
and Payment of or paid by any national or State Statute Ordinance or other Law or any
Fees Regulation or Bye-law of any local or other duly constituted authority in
relation the execution of the works or of any Temporary works and by the
rule regulations of all public bodies and companies whose property or
rights are affected or may be affected in any way by the works or any
Temporary works.
Compliance with 6.18.2 The Contractor shall conform in all respects with the provisions of any
Statutes such Statute Ordinance or Law as aforesaid and the Regulations or bye-
23
Regulations etc. laws of any local or other duly constituted authority which may be
applicable to the works or to any Temporary works and with such rules
and regulations of public bodies and companies as aforesaid and shall
keep the Employer indemnifying against all penalties and liability of every
kind for breach of any such statute Ordinance or Law Regulations or a
Bye-Law provided always that the Employer will repay or allow to the
contractor all such sums as the Engineer shall certify to have been
properly payable and paid by the contractor in respect of such fees, other
than fees which the contract requires the contractor to pay which fees
shall be included in the rates and prices entered in the price Bill of
quantities.
Fossils etc. 6.19 All fossils coins articles or value of antiquity and structures and other
remains or things of geological or archaeological interest discovered on
the site of the works shall as between the Employer and the contractor be
deemed to be absolute property of the Employer and the contractor shall
take reasonable precautions to prevent his workmen of any other persons
from removing or damaging any such article or thing and shall immediately
upon discovery thereof and before removal acquaint the Engineer‟s
Representative of such discovery and carry out at the expense of the
Employer the Engineer‟s Representative‟s order as to the disposal of the
same.
Patents Rights 6.20 The contractors shall save harmless and indemnify the Employer from and
and Royalties against all claims and proceedings for or on account of infringement of any
patent rights design trade mark or name or other protected rights in
respect of any constructional Plant machine work or material used for or in
connection with the works or temporary works or any of them and from
and against all claims demands proceeding damages costs charges and
expenses whatsoever in respect thereof or in relation thereto. Except
where otherwise specified the contractor shall pay all tonnage and other
royalties rent and other payments or compensation (if any) for getting
stones, and gravel, clay or other materials required for the works or
Temporary works or any of them.
Interference with 6.21.1 All operations necessary for the execution of the works and for the
Traffic and construction of any Temporary works shall, so far as compliance with
Adjoining requirements of the contract permits, be carried on so as not to interfere
Properties & unnecessarily or improperly with the public convenience or the excess to
antipollution use and occupation or private roads and footpaths or to or of properties,
measure Whether in the possession of the Employer or of any other person and the
contractor shall save harmless and indemnify the Employer in respect of
all claims demands proceedings damage costs charges and Expenses
whatsoever arising out of or in relation to any such materials in so far as
the contractor is responsible therefor.
6.21.2 The works and Temporary works shall be carried out in such manner as
not to interfere with ships or other vessels using the port or endanger
interfere with traffic whether by road rail or water and other normal
operation of the ports.
6.21.3 The Employer will afford the contractor reasonable facilities to enable him
to carry out the contract but the contractor must strictly observe any rules,
regulations or instructions which he may from time to time receive from the
Employer or the Engineer or any person or persons authouised by them
for the safety and protection of persons, traffic whether by road, rail or
water and property on the site or the land adjacent to the site.
6.21.4 The contractor shall take all possible precautions to secure the efficient
protection of the Docks, Harbours and all other waterways against
pollution of any kind during the execution, completion and maintenance of
the works and he shall ensure that no oil organic matter, refuse, rubbish or
other things of whatsoever nature are allowed to sweep or be supplied or
thrown into the water ways by him, his employees or sub-contractors or
any other agency or his.
Extra Ordinary 6.22.1 “The contractor shall use every reasonable means to prevent any of the
Traffic highways or bridges communicating with or on the routes to the site form
being damaged or injured by any traffic of the contractor or any of his sub-
24
contractors and in particular shall select routes choose and use vehicles
restrict and distribute loads so that any such extraordinary traffic as will
inevitable excise from the moving of plant and material from and to the site
shall be limited as far as reasonably possible and so that no unnecessary
damage or injury may be occasioned to such highways and bridges.
Special Loads 6.22.2 Should it be found necessary for the contractor to move one or more loads
of constructional plant machinery or reconstructed Units of parts of units or
work over part of highway or bridge failing with the jurisdiction of the
Employer the moving whereof is likely of damage any highway or bridge
unless special protection or strengthening is carried out then the
contractor shall before moving the load on to such high way or bridge give
notice to the Engineer of Engineer‟s Representative of the weight and
other particulars of the load to be moved and his proposals for protecting
or strength or the said highway or bridge. Unless within fourteen days of
the receipt of such notice the Engineer shall be counter-notice direct that
such protection or strengthening is unnecessary than the contractor will
carry out such proposal or any modification thereof that the engineer shall
require. At his own cost.
Waterborne 6.22.3 Where the nature of the works is such as to require the use by the
Traffic contractor or waterborne transport the foregoing provisions of this clause
shall be construed as though “highway” included a lock, dock, sea wall or
other structure related to a waterway and “vehicle” included craft, and shall
have effect accordingly.
Opportunities for 6.23 The contractor shall in accordance with the requirements of the Engineers
other afford all reasonable opportunities for carrying out their work to any other
Contractors contractors employed by the Employer and their workmen and the
workmen of the employer and of any other duly constituted authorities who
may be employed in the execution on or near the site of any work not
included in the contract of any contract which the Employer may enter into
in connection with or ancillary to the works. If however the contractor shall
on the written request of the Engineer of the Engineer‟s Representative
make available to any such other contractor or to the Employer or any
such authority any roads or ways for the maintenance of which the
contractor is responsible for to permit the use by any such of the
contractors scaffolding or other plant on the site or provide any other
service of whatsoever nature for any such the Employer shall pay to the
contractor in respect of such use or service such sum of sums as shall in
the opinion of the Engineer be reasonable provided also that if the
contractor avails of similar services from such other or the Employee the
Employer shall be entitled to recover from the contractor in respect of such
service such sum or sums as shall in the opinion the Engineer be
reasonable. The decision of the engineer shall be final.
Supply of Plant 6.24 Except where otherwise specified the contractor shall at his own expense
Materials & supply and provide all the Constructional Plant Temporary Works
labour materials both for Temporary and for permanent works labour (including
the supervision thereof) transport to or from the site and in and about the
works and other things every kind required for the construction
completion and maintenance of the works.
Materials to be 6.25.1 “Materials which the Employers is prepared to supply are shown in the
supplied by the schedule, soon after the acceptance or tender, the contractor shall give in
Employer writing a phased requirement of material according to the programme of
execution of works with regard to issue of materials.”
6.25.2 If the contractor desires the Employer to supply materials other than
those mentioned in the schedule, such as materials may be supplied by
the Employer. If available in the matter, at rates to be fixed by the
Employer.
Reservation or 6.32. The Employer reserves to himself the right any time or times to carry out
right to dredge any works he thinks necessary or proper in the vicinity of the site or
elsewhere.
Use of 6.33 Except as may be provided in the specification or approved by the
Explosives Engineer, the contractor shall not use explosives. The contractor shall
only permit handling and use of explosive to be carried by men fully
qualified and experienced in the storage, handling and use of the types of
explosive to be used. He shall comply with the provision of Indian
Explosive Act.
Customs and 6.34 The contractor shall comply with all the regulations imposed by the
security customs and port security Authorities in respect of the passage of plant
requirements vehicles. Materials and personal through Custom‟s barriers.
Use of Port Trust 6.35 In addition to the land at site of works proper, the contractor shall be
Land allotted suitable land for the purpose of lying out his work area, stores etc.
free or any rental charges as shown in the contractor drawing in case he
needs additional land the same would be given if it can be conveniently
spared and he will be charged rent for the additional land at the rates
27
fixed by the Engineer. The contractor, however, shall fix all electrical,
water supply and drawings installation, as per existing Municipal
regulations and pay charges for consumption of electrical energy and
water. On execution of the works the site shall be handed over to the
Engineer in good state with such a date as may be intimated to him by
the engineer.
Levels 6.36 The contractor shall provide all assistance. Instrument machines, labour
Soundings and materials as are normally required for taking levels & sounding for the
Charts preparation of level charts and corrections before commencement of work
and after execution of works. The contractor shall provide at his own
expense experienced attendants for the Engineer or the Engineer‟s
Representative to assist him in taking levels and checking of alignments.
Inflamable 6.37 The contractor shall comply with all central and local regulations in
Stores respect of safe storage of all Inflammable stores, or other materials
involving risk to third parties and shall take submit to the Engineer for
approval all drawings and documents required for the construction of
storage shed or other accommodation and shall build all such storage
sheds to the proper requirements.
Apprentices 6.38 The contractor shall during the term of this contract comply with the
provisions of the Apprentices Act. 1961 and maintain as part of his
organization a system or apprenticeship for training craftsmen. Failure on
the part of the contractor to observe the conditions and stipulations of this
clause shall be deemed to be a failure to employ a sufficient number or
proper and efficient workmen within the meaning of clause 6.8 above and
all the rights and remedies of the Employer there in provided including the
power to determine the contract shall applicable in such case.
LABOUR
Engagement of 7.1.1. The contractor shall make his own arrangements for the engagement of all
labour labour, local or otherwise, and save in so far as the contract otherwise
provides for the transport housing feeding and payment thereof.
Supply of Labour 7.1.2. The contractor shall so far as is reasonably practicable having regard to
local conditions provide on the site to the satisfaction of the Engineer‟s
Representative as adequate supply of drinking and other water for the use
of the contractor‟s staff and work people.
Alcoholic Liquor 7.1.3 The contractor shall not otherwise than in accordance with the statutes
of Drugs Ordinance and Government. Regulations or orders for the time being in
force import sell give barter or otherwise dispose of any alcoholic liquor or
drugs or permit or suffer any such important in sale gift barter or disposal
by his sub-contractors agents or employee.
Arms & 7.1.4. The contractor shall not give barter or otherwise dispose of to any person
Ammunition or persons any arms or ammunition of any kind or permit or suffer the
Festival & same as aforesaid.
Religious 7.1.5. The contractor shall allow his labour the Govt. notified National and local
Customs festival holidays and also such closed holidays for the Port declared by
the employer and also have due regard to local religious and social
customs in respect or labour employed by him.
Epidemics 7.1.6 In the event of any outbreak of illness or an epidemic nature the contractor
shall comply with and carry out such regulation orders and requirements
as may be make by the government or the local medical or sanitary
authorities for the purpose of dealing with and overcoming the same.
Disorderly 7.1.7 The contractor shall at all times take all reasonable precautions to prevent
Conduct, etc. any unlawful riotous or disorderly conduct by or amongst his employees
and for the prevention of peace and protection of persons and property in
the neighborhood of the works against the same.
Observance by 7.1.8 The contractor shall be responsible for observance by his contractors of
sub-contractors the foregoing provisions.
The contractor shall at all times during the continuance of the contract. So
Compliance with 7.1.9. far it may be necessary comply with all existing enactment‟s including
Regulations etc. central and state legislation as well as, any applicable bylaws of any local
authority regarding labour particularly the minimum wages Act. Factories
Act. Workmen‟s Compensation Act, Employees provident Fund and family
pension fund Act., Employees state insurance Act., Contract labour
28
(Regulation & Abolition) Act., Payment or wages Act. Maternity Benefit
Act. National Festival Holidays Act, Shop & Establishment Act, and shall
keep the employer indemnified against any action that may be taken
against him for the contravention of the provision of the above said
enactment‟s by the contractors. The rates quoted by the contractor in
schedule of quantities and Rates (SQ & R) shall be deemed to include all
expenses whatsoever the contractor may be require to incur for the
compliance with the provisions of the above said legislation. The
contractor shall make necessary arrangement for the employer to witness
the payments make by the contractor to his staff and labour.
Foreign 7.1.10 Should the contractor find that suitable qualified and Experienced
Personnel personnel required for the works are not available in India in sufficient
numbers and should the contractor wish to employ personnel Nationalities
other than Indian the contractor must obtain the necessary permits form
the central government to permit foreign personnel to enter India and to
work in India for this work. The contractor shall keep the employer fully
informed, of application made by him for the work permits for foreign staff
and/or approvals by the Indian authorities.
Fair wages 7.1.11 The contractors shall pay the labour engaged by him on the work not less
than fair wages which expression shall mean whether for the time or piece
work the labour rates or wages as fixed by the central Public works
Department as fair wage of the state payable to the different categories of
labours or those as notified under the Minimum wage Act. For the district
for corresponding employees of the employer of whichever may be higher.
That the contractor shall pay the labour engage by him on the work not
less than the minimum wages notified under any central or state law as
applicable to the Port and he shall not engage persons below the
minimum age fixed under any such law applicable.
Wage Records 7.1.12 The contractor shall maintain records of wages and other remuneration
paid to his employees in such forms as may be convenient and to the
requirements of the engineer & conciliation Officer, Central Ministry of
Labour, Government of India of such other authorised persons appointed
by the state Government. The contractor shall also exhibit the different
notices as required under the Minimum Wages Act. 1949, payment of
wages Act. 1936 and other Acts, Rules and Regulations make there under
from time to time.
Inspection of 7.1.13.1 The Engineer or the engineer‟s Representative or any other person
Wages Records authorised by them on their behalf shall have power to make inquiries with
a view to ascertain a proper observance of the Fair Wage Clause. He shall
have the power to investigate into any compliance regarding any default
made by the contractor sub-contractor regard to such provisions and also
the provisions made in the contract labour Act.
7.1.13.2 The Engineer shall have right to deduct from the moneys due to the
contractor any sum required or estimated to be required by making good
the loss suffered by a worker or workers by reason of non-fulfillment of the
conditions of the contract for the benefit of the workers, non-payment of
wages or of deductions make from his or their wage which are not justified
by their terms of the contract or non-observance of the regulations.
Accidents 7.1.14 The contractor shall within 24 hours of the occurrence of any accident at
or about the site or in connection with execution of the work report such
accidents to the Engineer/Engineer‟s Representative. The contractor Shall
also report such accidents to the competent authorities to whom such
report is required bye-law.
7.1.15 Any other conditions affecting labour and wages shall be as set out in
Part-II, in sub-clauses numbered 7.1.16, 7.1.17 etc. as may be necessary.
Wage book and 7.1.16 That the contractor shall maintain :
wage slips
(1) A wage book of each in such forms as may be convenient but the same
shall include the following particulars :-
(i) Rate of daily or monthly wages.
(ii) Nature of work on which employed.
(iii) Total number of days worked during each wage period.
29
(iv) Total amount payable for the work during each wage period.
(v) All deductions made from the wages with an indication in each case of the
grounds for which the deduction is made.
(vi) Wage actually paid for each wage period.
(2) A wage slip for each worker employed on the work provided that the
Engineer may grant exemption for the maintenance of the wage slip, if in
his opinion not more than 19 persons are likely to be employed directly on
the work, but in case he will have to maintain wage books as specified in
7.1.16. (1) above.
Preservation & 7.1.17 The wage books and wage slips shall be preserved for a period of not less
books & Slips than 12 months after the date of the last entry made in it.
Returns of 7.2 The contractor shall if required by the Engineer delivery to the Engineer‟s
Labour etc. Representative or at his office a return in detail in such from and at such
intervals as the Engineer may prescribe showing the supervisory staff &
the numbers of the several classes of labour from time to time employed
by the contractor on the site and such information inspecting
constructional plant as the engineer‟s Representative may require.
(b) Where work to which the provisional sum relates has been ordered by the
Engineer and executed by Nominated sub-contractor (as hereinafter
defined) the sum or sums actually paid (subject however to the provision
of clause 14.1.5) by the contractor to such sub-contractor on the direction
of the engineer and (if the contractor shall have added to the provisional
sum to which the work relates any sums in respect of charges and profits)
a sum in the same proportion to the sum so actually paid as the said
charges and profits bear to the said provisional sum.
Prime Cost Items 14.1.2 Every sum in the Bill of Quantities which contains either as the whole or
part of the sum a prime cost (P.C.) price for goods or materials to be
supplied for or for incorporation into the works shall be varied by the
substitution for the prime cost price of the actual price (subject however to
the provisions of clause 14.1.5. hereof) paid by the contractor for the
goods or materials on the direction of the Engineer and the contract price
shall be increased or decreased (as the case may be) by the amount by
which the sum to the bill of quantities is increased or decreased by such
substitution. No variation shall made to or in respect of any sum added for
labours to the prime cost price on account of the said actual price being
greater or less than the prime cost price but in respect of all order charges
and profit there shall be added or deducted as the case may be a sum
representing such percentage as is provided in the Bill of Quantities in
relation to the particular item or prime cost concerned or (if none) as is
inserted by the contractor in the form of Tender as the percentage for the
adjustment of prime cost sums.
Use of 14.1.3 All sums set out in the Bill of Quantities which shall be stated to be stated
provisional and to be provisional or for contingencies shall be used only at the direction
Contingency and discretion of the Engineer and if not used either wholly or part shall as
Items to the amount not used be deducted from the contract price.
14.1.4.1 The contractor shall when required by the Engineer produce all quotation
invoices, vouchers and accounts or receipts in connection with
expenditure in respect of provision or prime cost items.
Production of 14.1.4.2 If instructed by the Engineer the contractor shall obtain quotations from
Vouchers etc. approved sub-contractors or suppliers for the execution of the works under
a provisional sum or the supply of goods or materials under a prime cost
sum. The contractor shall submit these quotations to the Engineer
together with such other information as the engineer may required and
upon receiving instruction from Engineer he shall place his order for the
execution of such work of the supply of such goods or materials with the
subcontractor or supplier nominated by the Engineer.
Cash Discount 14.1.5 In so far any sum is paid by the contractor to a nominated subcontractor
(as hereinafter defined) by direction of the Engineer under clause 14.1.1
(B) or 14.1.2. before the contractor shall have received payment of that
sum from the Employer there shall for the purpose of adjusting the
contract price under clause 14.1.1 or 14.1.2 hereof (as the case may be)
added to the actual sum paid by the contractor as aforesaid 2.5% of the
amount of such actual payment and the benefit of any cash discount
whether availed off or not by the contractor allowed in respect thereof shall
be passed to the Employer.
Assignment Sub- 14.1.6 In the event of a Nominated Subcontractor (as hereinafter defined) having
contractors undertaken towards the contractor in respect of work executed or the
Obligations goods or materials supplied by such nominated sub-contractor any
continuing obligation extending for a period exceeding that of the period of
maintenance under this contract the contractor shall at any time after the
expiration of the period of maintenance assign to the Employer at the
39
Employer‟s request and cost the benefit of such obligation for the
unexpired duration thereof.
Nominated Sub- 14.2.1 All specialists merchants tradesmen and other executing any work or
contractors supplying any goods for which provisional or prime cost sums are included
in the Bill of Quantities who may have been or be nominated or selected or
approved by the Employer or the Engineer and all persons to whom by
virtue of the provisions of the Bill of Quantities of Specification the
contractor is required to subject any work shall in the execution of such
work or that supply of such goods be deemed to be sub-Contractors
employed by the contractor and are hereinafter referred to as Nominated
Sub-Contractors Provided always that the contractor shall not be required
by the Employer or the engineer or be deemed to be under any obligation
to employ any nominated subcontractor who shall decline to enter into a
sub-contractor with the contract containing provisions.
(a) That is respect of the work or goods the subject of the sub-contract
nominated sub-contractor will undertake towards the contractor the like
obligation and liabilities arises as are imposed upon the contractor towards
the Employer by the terms of the contract and will save harmless and
indemnify the contractor from and against the same and from all claims
demands proceedings damages cost charges and expenses whatsoever
arising out of or in connection therewith or arising out of or in connection
with any failure to perform such obligations or to fulfill such liabilities and.
(b) That the Nominated sub-contractor will save harmless and indemnify the
contractor from and against any negligence by the nominated sub-
contractor his agents workmen and servants and from and against any
misuse by him or them of any constructional plant or Temporary Works
provided by the contractor for the purpose of the contract and from all
claims as aforesaid.
Payments to 14.2.2.1 Before issuing under clauses 15.1.1 to 15.1.7 hereof any certificate which
Nominated Sub- includes any payment in respect of work done or goods supplied by any
contractors nominated sub-contractor the Engineer shall be entitled to demand from
the contractor responsible proof that all payments (less retentions)
included in previous in certificated in respect of the work or goods of such
nominated sub-contractor have been paid or discharged by the contractor
in default whereof unless the contractor shall.
(a) Inform the Engineer in writing that he has reasonable cause for
withholding or refusing to make such payment and
(b) Produce to the Engineer reasonable proof that he has so informed such
nominated sub-contractor in writings.
14.2.2.2 The Employer shall be entitled to such nominated sub-contractor direct
upon the certificate of the Engineer all payments (less retentions) which
the contractor has failed to make to such nominated sub-contractor and to
deduct by way of set-off the amount so paid by the Employer from any
sum due or which become due from the Employer to the contractor.
14.2.2.3 Provided always that where the Engineer has certified and the employer
has paid direct as aforesaid the Engineer shall in issuing any further
certificate in favour of the contractor deduct from the amount thereof the
amount so paid direct as aforesaid but shall not withhold or delay the issue
of the certificate itself when due to be issued under the terms of the
contract.
Final payment to 14.2.3 If the engineer desires to secure final payment to any nomination
Nominated Sub- subcontractor before final payment is due to the contractor and if such
contractor sub-contractor has satisfactory indemnified the contractor against any
latent defects than the Engineer may in certificate under clauses 15.1.1 to
15.1.7. of these conditions include as amount to cover the said final
payments and thereupon the contractor shall pay to such sub-contractor
the amount so certified and the limit of retention money named in the
appendix to the tender shall be reduced in proportion to the amount so
certified and the contractor shall be discharged from all liability for the
work or materials covered by such certificate except for any latent defects.
CERTIFICATES AND PAYMENTS
40
Monthly payment 15.1.1.1 The contractor shall submit to the Engineer each month on or before the
10th of the month, a statement on the standard printed form to be had an
application showing the estimated contract value of the permanent work
executed upto the end of the month (if such value shall justify the issue of
an interim certificate) and the contractor will be paid monthly on the
certificate of the Engineer. The amount due to him on account of
estimated contract value of the permanent work executed up to the end of
the previous month together with such amount (if any) as the Engineer
may consider proper on account of material for permanent works delivered
by the contractor on the site and in addition such amount as the Engineer
may consider fair and reasonable for any Temporary works or
constructional plants for which separate amounts are provided in Bill of
Quantities subject to a retention of the ………………… % named in the
tender unit the amount retained shall reach the “Limit of Retention Money”
named the tender (hereinafter called “The Retention Money”) provided
always that no interim certificate shall be issued for a sum less than that
named in the tender at one time.
15.1.1.2 80% of the net amount of interim certificate shall be paid by the Employer
within 10 days from the date of interim certificate and the balance within
30 days from the date of interim certificate.
15.1.2.1 One half of the Retention Money shall become due and shall be paid to
the contractor when the Engineer shall certify in writing that the works
have been substantially completed and other half shall be paid to the
contractor 14 days after the maintenance certificate has been delivered to
the Employer notwithstanding that at such time there may be outstanding
claims by the contractor against the Employer and provided always that if
at such time there shall retain to be executed by the contractor any works
ordered during such period pursuant to clause 10.1.1 to 10.1.4 and 1.2
hereof the Employer shall be entitled to with hold payment until the
completion of such works of so much of the second half of the retention
money as shall in the opinion of the Engineer represent the cost of the
works so remaining to be executed.
15.1.2.2 Provided further that in the event of different maintenance periods having
become applicable to different parts of the works pursuant to clause 9.8
hereof the expression” expiration of the period of Maintenance” shall for
the purposes of the clause be deemed to mean the expiration of the latest
of such period.
Time of payment 15.1.3.1 Payment upon each of the Engineer‟s Certificate shall subject to the
provision hereinafter be made by the Employer within the number of days
named in the Tender after such certificate has been issued by the
Engineer.
15.1.3.2 Delay in making such payments by the Employer due to exceptional
circumstances shall not nullify or vitiate in any way the other conditions of
the contract and contractor shall have no claim on this account.
Correction and 15.1.4 The Engineer may be any certificate make any correction or modification
with holding of in any previous certificate which shall have been issued by him and shall
Certificate have power to withhold any certificate if the works or any part thereof are
not being carried out to his satisfaction.
Indian Currency 15.1.5 Subject to the provision of clause 15.1.7 hereunder all payments made to
the contractor under the contract shall unless otherwise agreed be made
to the contractor in Indian currency.
Foreign currency 15.1.6 If the execution of the works shall necessitate material or equipment for
Required for incorporation in the permanent works which can bot be obtained in India,
permanent works an application for import Licence in each case is to be made-by the
contractor. The release of necessary foreign currency for such purpose
shall be arranged by the Employer and shall not be included in the amount
of foreign Exchange referred in Clause 15.1.7 hereunder. Such Foreign
currency will paid at the rate stated in the tender.
Foreign 15.1.7 The contractor shall insert in the tender the amount which he requires to
Exchange be paid in foreign currency in addition to payments under clause 15.1.6 for
Required for all all other purposes such as contractors plant overseas staff, expenses etc,
other purposes which shall be listed in detail. The contractor shall also insert in the tender,
41
the rate of exchange at the date of tendering upon which his tender is
based and the payment shall be made accordingly.
Advance for 15.1.8.1 The Employer shall pay to the contractor a lump sum advance as stated in
mobilisation part-II against Bank guarantee as a loan towards initial mobilization at the
interest started in Par-II. The advance shall be given immediately after the
execution of the contract agreement provided that the contractor shall
obtain and furnish at his own expenses towards security an advance
guarantee bond in the approved from as given in the tender documents for
a sum equal to the amount of the loan issued by a scheduled bank or the
Life insurance corporation of India.
Repayment of 15.1.8.2 The entire sum of the loan together with the interest accrued thereon shall
Advance for be recovered from the contractor from his monthly bills as stated in Part-II
mobilisation
Recovery of (i) Recovery of the sum loaned above shall be made from the payment
Loan certified in the interim certificate in proportion to the value of the work done
and certified by the Engineer after the value of the work reaches 25% of
the tendered value and all sums loaned shall be fully recovered by the
time the value of work completed reaches 75% of the tendered value and
the balance of loan, if any, remaining unpaid at that time shall forthwith be
paid up in cash by the contractor. The recovery of interest at the rate
referred to clause 16.2 (a) hereof on the loan shall be made monthly by
deduction from the interim certificates next due and the same shall be
calculated on the balance loans outstanding on the last day of each
previous calendar month.
(ii) The recovery of loan will normally be made according to the following
formula.
R=200 X P% of the gross value of the interim bill.
A
Where R=Recovery by which the total loan is to be reduced
P=Total amount of Loan(i.e. the amount of the loan
When 25% the contract price of the work has been Completed)
A= Contract value
If, however, the amount so arrived at, falls short of Rs.25,000/- the
contractors will have to make good the shortfall either by allowing
additional recovery from the bill or by payment in cash/by cheque, so that
an amount of Rs. 25,000/- is repaid every month.
(iii) The recovery of the installment of the loan and interest thereon will be
made proportionately from the 80% and 20% payments due to them
through their interim bill is due from/issued to them, the recovery of loan
according to the above formula may not be feasible. In that case, in order
to maintain the speed and continuity, of recovery the contractors will have
to pay an amount of Rs.25,000/- being the minimum amount towards
repayment of loan, and the interest due for that month before the end of
that month.
Advance for 15.1.9.1 If required by the contractor, an advance at an interest 3% over the
plant and Reserve Bank rate as announced from time to time by the Reserve Bank
Equipment’s of India under section 49 for the R.B.I. Act 1984 per annum may be paid
by the Employer as under.
(i) Up to 90% of the value of the new plants and equipment‟s considered
necessary for the work and the same procured and brought to site by the
contract for the work and.
(ii) 75% of cost as assessed by the Engineer in the case or old plant and
equipment‟s considered necessary for the work and brought to site by the
contract for the work.
FRUSTRATION
Payment in 18.0 In the event of the contract being frustrated whether by war or otherwise
Event of howsoever the sum payable by the Employer to the contractor in respect
Frustration of the work executed shall be the same as that which would have been
payable under clause 17 hereof if the contract had been terminated under
the provisions of clause 17 hereof.
NOTICES
Service of 20.1 Any notice to be given to the contractor under the terms of the contract
Notices on shall be served by sending the same post to or leaving the same at the
Contractor contractor‟s principal place of business (or in the event of the contractor
being a company to or at its registered office) or at contractor‟s site office
or elsewhere as approved by the Engineer.
Service of 20.2 Any notice to be given to the Employer under the terms of the contract
Notices on shall be served by sending the same by post to or leaving the same at the
Employer Employer‟s last known address (or in the event of the Employer being a
company to or at his registered office).
Major Economic 21.2 In the event of there being subsequent to the date of Tender such a major
Dislocation economic dislocation within the country in which the works are being or
are to be constructed as to result in the imposition by the Government or
that country or currency restrictions or in devaluation of the currency of
46
that country the Employer shall pay to the contractor any increased cost
of or incidentals to the execution of the works which is howsoever
attributed to or consequent on or the result of or in any way whatever
connected with such economic dislocation provided always that nothing in
this clause contained shall prejudice the right of the contractor to always
that noting in this clause contained shall prejudice the right of the
contractor to exercise any other rights or remedies to which the contractor
may be entitled in such event.
Registration with 21.3 The contractor shall register with the Employer‟s Dy. Conservator/
Board’s D.PLC. Dy. Port Conservator/Director Marine Department all his floating crafts
of the employed in the execution of this contract and no floating craft which has
contractor’s not been so registered shall be allowed to be employed in execution of
this contract. No exemption whatsoever shall be grant granted in this
regard.
Floating crafts 21.3 The contractor shall be interpreted and have effect in accordance with the
used in the law of India and any suit or other proceedings relating to this contract
execution of shall be filed or taken by the contractor in a court of law only (in Cuttack,
contract works Orissa)
21.4 The successful tenders should furnish information before the award of the
contract whether he himself or any of his partners directors or employees
has held class-1 post in the Port Trust within the period of last two years.
Income Tax 21.5 The tenderers are required to submit Income Tax clearance certificate
Clearance alongwith their tender.
CONDITIONS OF CONTRACT
Employer (a) The Employer (hereinafter called “Board”) means to Trustees of the Port of
PARADIP. A body corporate under the Major Port Trust Act 38 of 1963
represented by the Chairman.
Engineer (b) The Engineer is the Chief Engineer of the PARADIP PORT TRUST
Consultant (c) The „consultant‟ is M/s
…………………………………………………………… whom the
consultancy Agreement has been entered in to by the Employer on
…………
Earnest money The amount of Earnest Money shall be 1% of the estimated cost put to
6.2.01. tender subject ot the minimum of Rs.50/- and maximum of Rs. 20,000/-
Security Deposit (See at Page-19 amended) A, B
6.2.1.
Retention Money 5% of the amount of certified bill up to a limit 3% of the contract price.
6.2.2.
48
SPECIAL CONDITIONS OF CONTRACT
TABLE OF CONTENTS
49
SPECIAL CONDITIONS OF CONTRACT
1. GENERAL
1.1 Special Conditions shall be read in conjunction with the General Conditions of Contract,
specification, Drawings and any other documents forming part of this contract wherever the
context so requires.
1.2 Notwithstanding the Sub-division of the documents in to these separate section and volume
every part of each shall be deemed to be supplementary to and complementary of every
other part and shall be read with and into the Contract so far as it may be practicable to do
so.
1.3 Where any portion of the General Conditions of Contract is repugnant to or at variance with
any provisions of the Special conditions, the provisions of the Special Conditions shall be
deemed to over-ride the provisions of the General Conditions of contract and shall to the
extent of such repugnancy of variations, prevail.
1.4 Where it is mentioned in the Specification that the contractor shall perform certain work or
provide certain facilities, it is understood that the Contractor shall do so at his own cost.
1.5 The materials, design and workmanship shall satisfy the relevant Indian standard, the
specification conditioned herein and codes referred to. Where the specifications stipulate
requirement in addition to those contained in the Standard codes and specifications these
additional requirements shall also be satisfied.
2. THE WORK:
2.1 Scope of work: Furrow cutting, Spray grouting, 50mm bituminous macadam, 20mm
thick premix carpeting, seal coating, blinding the road surface, etc.The contractor will have
to execute the work strictly as per the direction of Engineer-in-charge
2.2 NATURE OF WORK: As detailed out in Bill of Quantities (BoQ) as per specifications and
drawings under this contract
3. THE SITE:
3.1 Site information.
3.1.1 The datum of soundings (chart datum) is Low Water Ordinary Spring Tide and all soundings
in drawings are referred to this Datum.
3.1.2 The following are the particulars of certain tide levels referred to the above „DATUM‟
TIDE CHART DATUM
Highest High Water +3.25 M
Lowest Low Water +0.40 M
Indian Mean Sea Level +1.55 M
3.1.3 Climate is tropical with high humidity. The maximum temperature is 102 degree F and the
minimum 51 degree F. The average annual rainfall is 55” which falls mostly during the South
West monsoon prevailing during the months of June – October.
The wind during the monsoon months of June to September is predominantly from South-
west and the strength varies between 3 and 5 on the Beanfort Scale. But there are certain
periods when the force increased to 6 or still higher.
3.2 Inspection of Site.
3.2.1 The intending tenderers are expected to visit the site and satisfy themselves on the actual
site conditions, meteorological and oceanographic data before tendering. Whatever
information regarding climatological data given in the tender documents is only intended as a
general guidance for the contractor and no warranty is given for the correctness of the same.
3.3 Access to Site: The contractor should examine the access to site before submitting his offer.
3.3.1 At present the work site is approachable by road from Cuttack Railway Station, a distance of
about 90 Kms. Cuttack is on Howrah-Madras Railway line. The site is also accessible by sea
from Calcutta, Visakhapatnam or any other Port.
50
4. PROGRAMME AND PROGRESS OF WORK
4.1 The contractor shall submit to the CE a realistic Bar Chart Schedule within 15 days from the
date of issue of work order showing the dates of commencement and completion of the
several parts of the work including anticipated dates for delivery, erection etc. of the various
sections of the work for this contract. The details Bar Chart Schedule shall be updated and
submitted by the contractor every three months.
4.2 The contractor shall submit to the CE in the first week of each month or any such period as
the CE may from time to time direct, a progress report for the proceeding period showing up-
to-date progress and progress during the previous period on all important items of each
section of portion of the work, in relation to and in consideration of detailed Bar Chart
Schedule.
5. SURVEYS AND LEVELS TO BE AGREED:
5.1 Before the works of any part thereof begun, the Contractor‟s agent and the CE‟s
representative shall together survey and take levels of the site of the works both above and
below water level, and agree all particulars on which the measurements of the works are to
be based. Such particulars shall be plotted by the Contractor and after agreement, the
drawings shall be signed by the CE or his authorized representative.
5.2 Failing such surveys and agreements being prepared and/or signed by the contractor, the
survey of the CE shall be final and binding on the Contractor.
5.3 The contractor shall be entirely responsible for the horizontal and vertical alignment, the
levels and correctness of every part of the work and shall rectify any errors or imperfection
therein. Such rectification shall be carried out by the contractor, at his own cost.
6. SETTING OUT THE WORKS:
The Contractor shall be responsible for the true and proper setting out of the works and for
the correctness of the position, levels, dimensions and alignment of all parts of the works and
for the provision of all necessary instruments appliances and labour in connection therewith.
If at any time during the progress of the works any error shall appear or arise in the position,
levels, dimensions or alignment of any part of the works, the contractor on being required so
to do by the CE shall at his own expenses rectify such error to the satisfaction of the CE
unless such error is based on incorrect data supplied in writing by the CE in which case the
expenses of rectifying the same shall be borne by the Board. The checking or any setting out
or of any line or level by the CE shall not in any way relieve the contractor of his
responsibility for the correctness thereof and the contractor shall carefully protect and
preserve all bench-marks, site nails, pegs and other things unused in setting out the works.
7. ORDER OF WORKS:
The order in which the works are to be carried out shall be to the approval of the CE and
shall be such as to suit the detailed method of construction, adopted by the contractor as
well as the realistic Bar Chart schedule. The works shall be carried out in such a manner so
as to enable the other contractors to work concurrently so that the entire project may be
brought into use immediately after the completion of works.
8. CO-ORDINATION AND INSPECTION OF WORKS:
The Co-ordination and inspection of the day-to-day work under the contract shall be the
responsibility of the Engineer and / or his representative. The written instructions regarding
any particular work will be normally passed by the Engineer and / or his representative.
.
51
9. CONTRACTOR’S TECHNICAL STAFFS.
The Contractor shall provide all necessary technical supervisor / Staff during the execution
of the works and as long thereafter as the Engineer and / or his representative may consider
necessary for the proper fulfilling of the contractor‟s obligations under the Contract. The
Contractor‟s representative approved by the Engineer and / or his representative is to be
constantly present on the works and shall give his whole time for supervision of the same
and shall make himself available whenever called for by the Engineer and / or his
representative. If such approval shall be withdrawn by the Engineer and / or his
representative the Contractor shall as soon as practicable after receiving written notice of
such withdrawal; remove the agent from the site and shall not thereafter employ him again
on the site in any capacity and shall replace him by another agent approved by the Engineer
and / or his representative. Such authorized agent or representative shall receive on behalf
of the Contractor directions and instructions from the Engineer and / or his representative.
9.1 The names of training and experience of the Contractor‟s agent or representative and other
supervisory site staff shall be submitted to the CE for approval before they are appointed.
9.2 The Contractor shall provide and employ on the site in connection with the execution and
maintenance of work ;
a) Only such technical assistants as are skilled and experienced in their respective
calling and such sub-agent foremen and leading hands as are competent to give
proper supervision to the work they are required to supervise, and
b) Such skilled, semi-skilled labour as is necessary for the proper and timely execution
and maintenance of the works.
9.3 The Engineer and / or his representative shall be at liberty to object to and require the
contractor to remove forthwith from the works any person employed by the contractor in or
about the execution or maintenance of the works who in the opinion of the Engineer and / or
his representative misconducts himself or is incompetent or negligent in the proper
performance of his duties or whose employment is otherwise considered by the Engineer
and / or his representative to be undesirable and such person shall not be again employed
upon the works without written permission of the Engineer and / or his representative. Any
person so removed from the works shall be replaced without delay.
10. WORK IN MONSOON:
The execution of the work shall continue in the monsoon also. The Contractor must maintain
sufficient labour force, plant machineries and coverings etc. as may be required for the work
and to execute the construction according to the prescribed schedule. NO special rate will be
considered for such work in monsoon.
10.1 Holiday or Sunday work:
Generally, work on Sundays and Holidays are not allowed. However subject to provision in
local Acts and any statute of the State, the Contractor may have to arrange for work on
Holidays and Sunday after obtaining permission for concern division, whenever so desired
by the Engineer or his representative to expedite progress and complete the works in time.
The contractor shall not be entitled to any additional payment for taking up works on
Holidays and Sundays.
11. CONTRACTOR’S WORKING AREA:
11.1 The contractor would be given necessary working area/open space as per requirement and
necessary rent will be paid by the contractor towards Temporary Camp Shed, Labour
Shed, Stores only. The contractor shall pay charges for this area at the rates indicated in
Annexure-VII. The working area/open space for temporary sheds as above shall be jointly
measured by the department & contractor monthly and a report to this effect shall be
produced to the division office for recovery of ground rents. A suitable working programme
shall be furnished with the Tender. The decision of the Chief Engineer/or any Competent
Authority regarding allotment of open space for above purpose to different contractor shall
be final and binding on the contractor.
11.2 The contractor shall remove all temporary works and clear the site at his cost to the
satisfaction of the Chief Engineer before the site is returned to the Port Trust.
52
11.3 The contractor shall provide fencing all round his working area and after completion of the
contract shall remove the same and restore and level the area to its original profile to the
satisfaction of Engineer and / or his representative.
12.. Accessibility for Checking and Supervision.
The engaged Contractor is to provide necessary arrangements for free access to the PPT
Officer‟s and personnel for supervision and checking of the subject work at his own cost.
13. Responsibility of the Contractor for methodology of works:
i) The contractor shall be solely responsible for the methodology and detailed working
for the whole of the works keeping in mind the site conditions and shall supply to the
Engineer such particulars thereof as he may require from time to time.
ii) The contractor shall submit within the time stipulated by the Engineer in writing, the
details of actual methods that would be adopted by the contractor for the execution of
each item of the work supported by necessary details.
iii) Approval, for the drawings and sketches, if necessary including those of the plant and
machinery that would be used, their locations, arrangements for conveying and
handling materials etc. should be obtained from the Engineer well in advance for
starting each item of work. The Engineer reserves the right to suggest modifications
or make concrete changes in the methods proposed by the contractor whether
accepted previously or not at any stage of the work, to obtain the desired accuracy,
quality and progress of work, which will be final and binding on the contractor
14. Quality Control:
Quality control is an essential part in the construction of and must be based on proper
objective and qualitative measurement. The contractor will have the full responsibility for
quality control and delivering the acceptable quality in the field. Regular appraisal of the
quality control to the Engineer or his representative should be made for effecting
improvements in the construction techniques to ensure satisfactory quality of work. The
quality control function shall include but not be limited to the following items
i) Sampling and Testing of Construction Materials:
Essentially to be carried out on the materials brought to site for construction work
unless permitted otherwise by the Engineer or his representative.
ii) Sampling and Testing of work at various stages of Construction:
Essentially to be carried out at any approve laboratory as per tender conditions or any
from Govt approved organization unless permitted otherwise by the Engineer at the
cost of the contractor.
15. TEMPORARY WORKS, OFFICE, JETTY, ETC.
15.1 The contractor shall submit to the CE for his approval, drawings and proposals for any
temporary works such as batching plant, storage yard, office, store, false work and
temporary platforms, pre-casting yard, workshop, etc. which he intend to construct for the
execution of the contract and no such work shall be constructed before obtaining the written
approval of the CE.
15.2 The Contractor shall obtain permission for any temporary work and would ensure that during
execution of works the statutory requirements of the concerned authorities such as Paradip
Port Trust, Police, etc. would be compiled with.
15.3 Not less than one month before the date when the contractor intends to start erecting any
part of the temporary works and staging required for carrying out the works he shall furnish
to the CE complete drawings of that part of the temporary works and staging with a proper
design. The contractor shall at the same time, if so required by the CE furnish calculations in
respect of such temporary works. The contractor shall also furnish to the CE drawings
showing the method proposed for the erection of the various parts of the work. The
furnishing to the CE any design for any temporary works and staging shall not relieve the
Contractor from any liability or obligation under the contract in respect of such temporary
works and staging. All temporary works shall remain the property of the Contractor.
16. OPERATIONS OF THE BOARD AND OTHERS:
53
16.1 The ordinary business and works of the Board and others as carried out on and in the vicinity
of the site will be continued during the construction, completion and maintenance of the
works and the execution of the contract shall be conducted in such a way as to avoid
interference with traffic of every kind by land and by water and with any other works in
progress in vicinity.
16.2 The Contractor‟s attention is drawn to the fact that other contractors employed by the Board
may be working in the vicinity.
16.3 The Contractor shall where so directed by the Engineer and / or his representative be
required to work to other contractor‟s drawings where-so-ever drawings for work not included
in this Contract are related to particular details of works.
16.4 The Contractor shall from time to time as the Engineer and / or his representative may direct,
provide attendance on the other contractors and carry out minor works in connection with
such contracts. The cost of provision of such attendance and work as may be so required will
be charged to the appropriate provisional sum in the Bill of Quantities.
17. PORT TRUST RULES:
17.1 The Contractor shall observe the conservancy rules relating to the Harbour, Township area
and shall always take such necessary additional steps to keep the harbour waters free of
noxious or unhygienic matters coming from his works as are required by the Board. Under no
circumstances shall inflammable material be allowed to spill to the Harbour area/any water
bodies.
17.2 The Contractor shall always observe and comply with the working rules and regulations of
the Port Trust in force or as issued from time to time.
18. EXISTING SERVICES:
18.1 Drains, pipes, cables, overhead-wires and similar services encountered in the course of the
work shall be guarded from injury by the Contractor at his own cost, so that may continue in
full and uninterrupted use to the satisfaction of the owners thereof, or otherwise occupy any
part of the site in a manner likely to hinder the operation of such services.
18.2 Should any damage be done by the Contractor to any mains pipes, cables or lines (whether
above or below ground). Whether or not & shown on the drawings the Contractor must make
good or bear the cost of making good the same without delay to the satisfaction of the
Engineer and / or his representative of the owners.
19. ENTRY ON PRIVATE OR OTHER PROPERTY:
The Contractor shall not enter upon or commence any work in or upon, across or through
any land, building or place being private property until authorized in writing by the Engineer
and / or his representative or other competent authority to do so.
20. NOTICE OF OPERATIONS:
No important operations shall be commenced nor shall work outside the usual working hours
be carried out without the consent of the Engineer and / or his representative in writing or
without full and complete notice also in writing being given to him.
54
21.4 The Contractor shall give every facility to the authorized safety officers of the Board to
inspect the works whensoever required, and shall observed and abide by any instructions
given by the Engineer and / or his representative in regard to the use of Plant, equipment
and temporary works in respect of General Safety. Compliance with such requirement shall
not be used as the basis of a claim against the board.
21.5 The Contractor shall at his own expenses provide and maintain upon the works to the
satisfaction of the Engineer and / or his representative. Proper and efficient life-saving and
First-Aid appliances which shall at all times be available at work site for use.
The Contractor will be required to take entry passes to the restricted area of Port for all
personnel, labourers, vehicles, machineries, equipment etc. No claim whatsoever on this
account will be entertained.
22. (a) LAW GOVERNING CONTRACT:
The Contract shall be interpreted and have effect in accordance with the Law of India and no
suit or other proceeding relating to this Contract shall be filed or taken by the contractor in
any court of Law except in Kujang Court.
(b) ARBITRATION AND NOTICE: As per arbitration act of Govt of India.
55
before the other or others and thereupon the Engineer and / or his representative or his
certificate in respect thereof.
24.4 If any reason or any default on the part of the contractor a completion certificate has not
been issued in respect of every portion of the works within one month after the date fixed by
the contract for the completion of the works, on any portion thereof in respect of which a
completion certificate has not been issued, provided that the works or the portion thereof, so
used as aforesaid shall be reasonably capable of being used and that the contractor shall be
afforded reasonable opportunity for completing these works for the issue of completion
certificate.
25. PERIOD OF MAINTENANCE /Defect Liability Period:
Unless otherwise mentioned specifically, the period of maintenance /defect liability period of
work after completion will be 06(six) months from the actual date of completion of the work.
In these conditions, the expression “period of maintenance” shall mean the period of
maintenance named in the form of the tender calculated from the date of the completion of
the work certified by the Engineer and / or his representative in accordance with clause
10.1.1 of GCC hereof of in the event or more than one certificate having been issued by the
Chief Engineer under the said clauses from the respective date show certified and in relation
to the period of maintenance the expression “the works” shall be construed accordingly. The
security deposit for the work will be released after completion of defect liability period
/maintenance period.
26. Performance Guarantee period : Nil
27 WORKING PERIOD:
Normally the work will be carried out between 8 AM to 5 PM on working days only. However,
the tenderer should note that he/they might be required to carry out the job on Sundays,
Holidays and after normal working hours and at night in addition to the normal working hours
to expedite the progress of the work if permitted by the competent authority. The tenderer
should include in his rates the cost, if any, involved on those accounts.
28. BANK GUARANTEE in lieu of Cash Security Deposit:
Security Deposit shall be recovered from the R/A bill of the contractor as per Tender
Conditions of contract. However, Bank guarantee may be considered in lieu of cash security
deposit. In that case the contractor shall have to submit to the division, a performance bond
in the form of an irrevocable guarantee from any scheduled bank at Paradip.
29. POSSESSION PRIOR TO COMPLETION:
The CE shall have the right to take possession of or use any completed or partially
completed work or part of the work. Such possession or use shall not deem to be an
acceptance of any work completion in accordance with the contract agreement. If such prior
possession or use by the CE delays the progress of work, on equitable adjustment in the
time of completion will be made and the contract agreement shall be deemed to be modified
accordingly.
30. COMPLETION DOCUMENTS:
31. WATER AND POWER SUPPLY:
31.1 WATER SUPPLY:
The Board may supply to contractor with reasonable quantity of fresh water at one point near
the site subject to availability of fresh water as per prevailing rate.
Water to the extent possible will be made available by the Port Trust. The connection and
extension to the working area shall be arranged by the contractor at his own cost. The
contractor shall also provide a water meter at his cost for metering the quantity of water
used. Charges for the consumption of the water will be paid by the contractor at the
applicable rates indicated in Appendix-VII or as per charges fixed from time to time by Port
Trust during contract period.
31.2 ELECTRICITY SUPPLY: The Board may supply to the contractor with electricity at the site of
the contractor‟s working area at one point. The Contractor will be required to pay for the
electricity towards consumption/used on Meter basis at rates in force during the contract
period, PPT does not guarantee the continuity of power supply. In the event of power failure,
56
the contractor shall be required to make its own arrangement for the provision of Electric
Power.
Drawing of power lines etc. from the point of supply of power by the Trust Board to the actual
work spot shall be arranged by the contractor at his own cost. Temporary lines and
connections by the contractor shall be approved by the authorized Agencies before drawing
the power. The contractor shall indicate his requirement of power to the concerned Executive
Engineer at the time of tendering or prior to work execution.
The contractor shall pay the Electricity charges at the applicable rates indicated in
Appendix-VII or as per charges fixed from time to time by Port Electrical Division.
N.B – The contractor will pay the required charges for water & power supply at the
rates fixed by PPT from time to time during the construction period only. The
charges for water & power consumption during the O&M shall be borne by the Board.
32. ABNORMAL RATES:
The Contractor is expected to quote rate for each item after careful analysis of cost involved
for the performance of the completed item considering all specifications and conditions of
contract. In case it is noticed that the rates quoted by the tenderer for any item are unusually
high or unusually low, it will be sufficient cases for the rejection of the tender unless the CE is
convinced about the reasonableness of the rates. For scrutiny the analysis for such rate is to
be furnished by the tenderer on demand.
33. DISPUTE IN MODE OF MEASUREMENT:
In case of any dispute as to the mode of measurement not covered by the contract to be
adopted for any item of work, mode of measurement as per relevant Indian Standard
Specification (Latest revision) shall be followed.
34. LIABILITY AND GUARANTEES:
34.1 The Contractor is responsible to carry out works as per specifications.
34.2 Of the Contractor feels that any variation in work or in quality of materials or proportions
would beneficial he shall bring this to the notice of Engineer and / or his representative in
writing.
34.3 The work will not be considered as complete and taken over by the Board until all the
temporary work for labour shed, store shed, site office and staff colonies etc. constructed by
Contractor are removed and work site cleaned to the satisfaction of Engineer and / or his
representative.
57
37. PUBLICITY:
No information or photographs concerning the works maybe published.
38. PRICE ADJUSTMENT PAYEMENT/ESCALATION:
In case of Contract in which the estimate cost of work put to tender as per Tender Call Notice
is more than Rs.1.00 (One) Crore and stipulated completion period is beyond 12 (Twelve)
months (both criteria to be satisfied). The Contractor will be allowed overall price variation in
accordance with the following formula.
V = (R – C) X I- Io
Io
Where V = Amount of overall variation payable for a value of R of work done.
R = Value of work done during the period under reference.
C = Value of materials supplied by the Employer at the stipulated rates and consumed in the
work plus the secured advance paid against the material brought at site.
I = All India Average Consumer price index (Base 2001 = 100) for industrial workers declared
by the Labour Bureau, Government of India for the period covered by a bill does not coincide
with a calendar month, then weighted time average for the period will be taken for I.
Io = All India average consumer price index (Base 2001 = 100) for industrial workers
declared by the Labour Bureau. Government of India, as prevailing for the month of the
tender opening.
The price variation shall be subject to the following conditions:
(a) The price variation shall be claimed by the contractor through a supplementary bill
along with interim measured bill in every cycle & after the index for any month is
officially published by the concerned authorities.
(b) No variation will be allowed for work done beyond the stipulated completion date.
(c) Escalation will not be payable on extra items/substituted items.
39. NO COMPENSATION IN CASE OF ALTERATION OR RESTRICTION OF WORKS:
If at any time from the commencement of the work the CE shall for any reason whatsoever
not require the whole work or part thereof a specified in the tender to be carried out, the CE
shall give notice in writing of the fact to the Contractor, who shall have no claim to any
payment or compensation whatsoever on account of any profit or advantage which he might
have derived from the execution of the works in full, but which he did not derive in
consequence of the full amount of the works not having been carried out neither shall he
have any claim for compensation by reason of any alterations having been made in the
original specification, Drawings, designs and instructions which shall involve any curtailment
of the works as originally contemplated. Provided always that in all such cases the
Contractor shall be entitled to payments according to adjustments in Contract Price as
allowed under the Provisions of the Clause-11.2.1 of GCC.
(a) Joint Venture (JV) firms are allowed to participate in the tenders having the estimated cost
put to tender more than Rs.5.00 Crores.
(b) No. of Joint Venture partners would be limited to three (including the lead partner) with at
least 26% equity holding by each member in case of a Company. In case a Joint Venture is
formed for the specific work only, each of the Joint Venture partner including the lead partner
shall have work experience of minimum value not less than 26% for at-least one single work
58
of the estimated cost put to tender as indicated in TCN to become eligible to be a member of
Joint Venture. One of the partners shall be nominated as Lead Partner for signing
Agreement with Paradip Port Trust and shall be authorized to incur liabilities and receive
instructions for and on behalf of any and all the partners of the joint venture. This
authorization shall be evidenced by submitting registered power of attorney signed by all the
partners.
(c) All partners of the joint venture shall be liable jointly and severally during the bidding process
and for the execution of the contract in accordance with the provisions of contract and a
statement to this effect shall be included in the authorization as above. The bid shall be
signed so as to legally bind all the partners jointly and severally.
(d) Joint Ventures must comply with the following requirements:
The joint venture must satisfy collectively the eligibility criteria as described in this section.
For this purpose, the following information of each member of the joint venture may be
submitted which will be added together to assess the collective eligibility criteria:
(i) Average Annual Turnover
(ii) Specific work Experience
(iii) Capacity of key Personnel
(iv) Ability to own / lease relevant equipment
Each JV Partner including the lead partner shall meet not less than 26% of the following
criteria:
(i) Average Annual Turnover
(ii) Specific work Experience
(e) All the partners together shall satisfy 100% of the criteria.
A copy of the joint venture agreement (JVA) specific to this work, if entered into by the
partners shall be submitted along with the Bid. Alternatively, the Memorandum of
Understanding (MoU) to execute a JVA in the event of successful bid shall be signed by all
partners and submitted with the bid. In any case, it is mandatory that a JV agreement is
entered into before the award of the work.
Pursuant to the foregoing, the Joint Venture Agreement shall include among other things, the
joint venture objectives, the proposed management structure, the contribution of each
partner in the joint venture, the commitment of the partners to joint and several liability for
due performance, recourse / sanctions within the joint venture in the event of default or
withdrawal of any partner and arrangements for providing the required indemnities.
(f) Similar Work Experience for Joint Venture (JV) Firm:
The partners of Joint Venture shall individually or jointly meet the similar work experience
criteria and the relevant work experience documents shall be furnished. Each JV partner
including the lead partner shall have work experience of minimum value not less than 26%
for at least one single work of the estimated cost put to tender as indicated in TCN. The
single work/two works / three works as indicated in the eligibility criteria shall not be spilt
which means in case of a single work one JV partner should have executed the single work
in full on his own as specified in Tender Call Notice and in case of two works / three works, if
JV partners proposed to collectively meet the experience then they should have individually
done each of the works in full on their own as per example given below.
Example-
A joint venture is constituted by three firms namely A, B & C and the estimated Cost of the
work put to tender is Rs.10,00,000/-. Then the eligibility criteria for meeting similar work
experience shall be
(i) Single work of value 80% equal to Rs. 8,00,000/-
(ii) Two works of value 50% each equal to Rs.5,00,000/-
(iii) Three works of value 40% each equal to Rs.4,00,000/-
JV may meet the similar work experience criteria either any one of the following categories.
(i) For single work category of value Rs. 8,00,000/-
59
Any one Joint Venture Partner should have executed the Single work of value Rs.8.00 lakh
in full individually on his own.
(ii) For two works category of value Rs.5,00,000/- each.
Value of each work executed by JV Partner shall be Rs.5.00 lakh in full individually on his
own.
(iii) For three works category of value Rs.4,00,000/- each
Value of each work executed by JV Partner shall be Rs.4.00 lakh in full individually on his
own.
g. Financial Turnover: The average annual turnover of each partner of the JV individually shall
not be less than 26% of average annual turnover as indicated in the eligibility criteria in TCN
/ Tender Document. Turnover of individual partner of the JV will be added together for each
financial year to meet eligibility criteria of the Average Annual Turn Over..
As per the letter No.AD/IR-22/2010/3026 Dtd.28th July, 2010 and letter of Govt. of Orissa
No. LL-I-(iii)-98/09/720(56)/L.E., Bhubaneswar, Dtd.27th January, 2009, Cess @ 1% of the
executed value will be deducted. The deduction will be @ 1% of gross bill value from each
running bill / final bill of the contractor. This deduction will be in respect of building and other
construction works i.e. construction, alteration, repairs, maintenance or demolition, of or, in
relation to, buildings, streets, roads, railways, tram ways, airfields, irrigation, drainage,
embankment and navigation works, flood control works (including storm water drainage
works, generation, transmission and distribution of water), oil and gas installations, electric
lines, wireless, radio, television, telephone, telegraph and overseas communications, dams,
canals, reservoirs, water courses, tunnels, bridges, viaducts, aqueducts, pipelines, towers,
cooling towers, transmissions towers and such other work as may be specified in this behalf
by the appropriate Government by Notification, but does not include any building or other
construction work to which the provisions of the Factories Act, 1948 (63 of 1948) or the
mines Act, 1952 (35 of 1952) apply.
43. EPF Code under Employees’ Provident Fund & Miscellaneous Provisions Act, 1952
and ESI Code under Employees’ State Insurance, 1948
The Tenderer must have EPF Code under Employees‟ Provident Fund & Miscellaneous
Provisions Act, 1952 and ESI Code under Employees‟ State Insurance, 1948 to cover all the
workers working under the Contractors. The successful tenderer, on award of the work must
ensure all the workmen, employed by the Contractors in relation to the contract work should
be cover under EPF and ESI Act‟ and other statutory benefits.
If asked for by the employer, the contractor will be required to submit photocopy of all
payment challans and produce the original for verification to the representative of the
Principal Employer, i.e. concerned Executive Engineer.
44. The quantities given in the bill of quantities are estimated quantities for work. During
execution of work, quantity may vary as per site condition and as directed by the Engineer or
his representative. The payment to the contractor will be made as per the actual work done.
TECHINICAL SPECIFICATION
1.0 These specifications establish and define the Material and constructional requirements for
Civil and Structural works. Specification will be followed for the execution of work as per
the latest BIS/ISI relevant to the item of work, materials supplied, testing, surveying,
measurements and scope of work and workmanship.
2.0 Methods of Measurements are indicated in these specifications. Where not so specified,
latest version of IS: 1200 shall be applicable.
3.0 Providing and operating necessary Measuring and Testing devices and Materials including
all consumable are included in the scope of work. No separate Measurement or payment for
testing the work shall be made but rates quoted for various items shall be deemed to
include the cost of such tests which are required to ensure achievement of specific quality.
60
4.0 Wherever referred to in this Tender Document, only the latest revision which shall be in
force till the completion of work of specifications, codes of practice and other publications
of the Bureau of Indian Standards shall be applicable.
5.0 In case of conflict amongst the provisions of Schedule of Rates, Specifications and Drawings,
all of them shall be read in conjunction with each other and clarification shall be obtained
from the CE whose decision shall be final and binding.
6.0 MATERIALS:
6.1 INDIAN STANDARDS
All materials shall, as far as possible, be of Indian Origin and conform to the latest additions
of the Indian Standards. Standard issued elsewhere may be used only if approved by the CE
and for these materials only for which appropriate Indian standards do not exist.
6.2 STORAGE OF MATERIALS
All the materials used in the permanent works shall be properly stored to prevent
deterioration or damage from any causes whatsoever to the entire satisfaction of the CE.
Cost for shed for storing of materials and deployment of watchman, etc. will be borne by the
Contractor and the same is deemed to be included in the offer. The Department is not
responsible for the theft/loss of materials at site.
7.0 CONSTRUCTION SCHEDULE:
The contractor shall furnish a detailed construction schedule to complete the work within
the stipulated period as mentioned in the Special Conditions of Contract (SCC) of tender
document.
8.0 TOOLS AND PLANTS:
The contractor shall deploy sufficient number of Tools, Plants, machinery etc. for timely
completion of the work.
9.0 DRAWINGS:
All the working drawings shall be prepared by the contractor.
10. STANDARDS & METHODS OF MEASUREMENTS:
The work shall conform to latest edition of the Indian Standard specifications.
Any part of the work not covered by the Standards shall conform to the relevant Indian
Standards. Where Indian Standards are not available, the foreign Standard such as British,
American, German, etc. as accepted by CE shall be allowed.
11. LIKELY SOURCES OF AGGREGATES:
11.1 The source of fine aggregate is near Cuttack at a distance of about 100 Kms. from the
work site and the materials can be brought by the road transport. Sand quality should
conform to Zone-II as recommended in IS 383.
11.2 The Coarse aggregate can be obtained from the Haridaspur Quarry located at a distance
of about 100 Kms. from the Port and is connected by road.
11.3 The Contractor shall check the sources, quality of material the availability, transportation
etc. before tendering the work.
12. The contractor shall be responsible for the true and proper setting out of work in
relation to original points, lines and levels of reference and providing with all
necessary instruments, appliances and labour in connection therewith.
13. Steel, Cement and all other materials required for the work shall be supplied by the
contractor at his own cost confirming to latest BIS Code. Reinforcement of
SAIL/RINL/VIZAG/TATA make confirming to Fe-500 shall only be used.
14.OPC/PSC cement of RAMCO/Dalmia/Ambuja/ Birla /JayPee/ Lafarge/Ultra Tech
/ACC/ Mahashakti or any other brand of 50 kg. per bag approved by the Engineer-in-
charge shall be used for the work.
15. Testing of Materials & Port approved Laboratories.
(a) The testing of the materials to the used in works shall be done in the following
5(Five) laboratories/institutions as per test requirement, as per standards as
decided by the agency engaged by PPT for work supervision or by the Engineer.
61
There should be no repetition of tests in the same laboratory. Other laboratories
/institutions as found suitable also may be approved by Chief Engineer depending
on the requirement.
i) Central Laboratory, Bhubaneswar, Sachivalaya Marg, Unit-IV, Bhubaneswar,
Dist: Khurda.
ii) Central Laboratory, OMP Square, P.O.: Chauliaganj, Cuttack.
iii) College of Engineering & Technology, Civil Engineering Department, CET,
Ghatikia, Kalinga Nagar, Bhubaneswar.
iv) Testing Laboratory, Directorate of Export Promotion & Marketing, Industrial
Estate, Madhupatna, Cuttack.
v) IIT, Bhubaneswar.
(b) The acceptance or rejection and accordingly, the eligibility for payment of works
executed will be dealt as per the provisions in the above standards. In case of any
discrepancy or any issue in this regard, the same shall be decided by the
supervising agency engaged by PPT or the Chief Engineer, PPT, which will be final
and binding.
(c) Contractor has to undertake the following tests at any Port approved laboratory
during the course of construction as approved by the Engineer. All the expenses for
testing shall be borne by the contractor.
Control tests for RCC:
Sl. Type of material & test Relevant Indian
Frequency
No. details standard
(1) (2) (3) (4)
Physical and chemical tests IS : 269 Once for each source of supply
of Cement IS : 455 and occasionally when called for
IS : 1489 in case of long/improper storage.
01
IS : 8112 Besides the contractor also will
IS : 12269 submit the Test Certificate on
cement released by Manufacturer.
All physical and chemical IS : 1786 Once for each source of supply
02 tests of Steel reinforcement and occasionally when desired by
(Fe-500). Engineer in charge.
Coarse & Fine Aggregates: One test for every week work of
(i) Gradation IS : 2386 each fraction of coarse aggregate
and fine aggregate, initially.
(ii) Deleterious constituents IS : 2386 (Pt-2) -do-
(iii) Water absorption IS : 2386 (Pt-3) Regularly as required, subject to a
03 minimum of one test a day for
coarse aggregate and two tests a
day for fine aggregate. This data
shall be used for correcting the
water demand of the mix on a
daily basis.
62
Note: Contractor has to conduct the day to day in-situ test by any Govt. approved private
laboratory during the execution of work in presence of the Engineer. All the expenses for
testing shall be borne by the contractor.
BILL OF QUANTITIES
1. GENERAL INSTRUCTION:
1.1 This Bill of Quantities must be read with the drawings, conditions of Contract and the
Specifications and the contractor shall be deemed to have examined the Drawings,
specifications, conditions of contract and to have acquainted himself with the detailed
description of the works to be done and the way in which they are to be carried out.
1.2 Notwithstanding that the work has been sectionalized every part of it shall be deemed to be
supplementary to and complementary to every other part and shall be read with it or into it
so far as it may be practicable to do so.
1.3 The detailed description of work and materials given in the specifications are not
necessarily repeated in the Bill of Quantities.
1.4 The quantities given in the Bill of Quantities are approximate only and are given to provide
a common base for tendering. Payment will be made according to the actual quantities of
work indicated on the drawings or ordered and carried out as measured by the Chief
Engineer and valued at the rates and prices quoted in the Bill of Quantities so long as the
total cost of works does not vary from the contract price by + twenty five percent (25%).
Any increase or decrease in the individual item shall not form the basis for alteration of the
rates quoted and accepted.
2. RATES AND PRICES TO BE INCLUSIVE:
2.1 Rates and prices set against items are to be the full inclusive value of the finished work in
accordance to the construction drawings and or described in the Specifications and
condition of contract. The rates shall include all elements of costs and expenses, which may
be required in and for completion of work as specified together with all costs and expenses
in complying with all general risks, liability and obligations together with every contingent
cost and charge whatsoever as set forth in the contract documents, including (but not by
way of limitation) all plant, machinery and appliances labour and other dues, establishment
charges including those from various statutory authorities, rents, taxes, insurance, testing
charges of different materials, supervision and overhead charges, profits, incidental
expenses if any and also include stoppage of work. The rates shall be inclusive of every
kind of temporary work executed or used in connection with proper completion of
permanent works (except those items in respect of which provision has been separately
made in the Bill of Quantities) and all such works as necessary for proper completion and
maintenance of the works.
2.2 The rates are intended to cover the supply of material including transport to site of works
and the execution of all works necessary to complete the work. Should there be any details
of construction materials which have not been referred to in the specifications or in the Bill
of Quantities and drawings but the necessity for which may be reasonably be implied and
inferred there from or which are usual or essential to the completion of the all works in all
trades, the same shall be deemed to be included in the rates and prices named by the
contractor in the Bill of Quantities. The rates and prices are to cover the item as described in
the Bill of Quantities and if there is inconsistency between the Bill of Quantities,
Specifications or Drawings, the description in the Bill of Quantities shall prevail.
2.3 Each individual item in the Bill of Quantities is to be priced. If any items are not priced, it is
to be indicated under which item or items the value of the work has been included. Items,
the Prices of which are the same shall not be bracketed. If the contractor omits to price an
item, the cost of the work of such item will be held to be spread over and included in the
prices given for other items. He shall not mark items “included” when the rate is asked for.
3. SUBSTITUTION:
If substitution found necessary at the time of execution for some items of work submitted by
the Contractor and agreed to by the Chief Engineer, the specifications for the materials
used, if not covered under the other items shall be as specified by the Chief Engineer and
the mode of measurement shall also be desired by the Chief Engineer.
63
OTHER IMPORTANT INFORMATIONS:
1. The bill of quantities shall be read in conjunction with the tender documents including
Notice Inviting Tender, Information to the Bidders for e-procurement, General Conditions of
Contract, Special Conditions of Contract, Technical Specifications, Drawings, etc.
2. Descriptions given in the items are not exhaustive and the contractor’s rate should be
inclusive for finished item of work and completed in all respect as per the item of work and
also its specification.
3. The contractor shall have to pay a sum of Rs.500.00 (Rupees five hundred) towards the
cost of a certified copy of agreement.
4. All the quantities mentioned in the schedule are combined for all works unless otherwise
specified.
5. The tender is valid for SIX months. However, the tenderers may specify their validity not
less than six months from the date of opening of tender.
6. The contractor should at all times, during execution of work, keep Paradip Port Trust
indemnified against all loses/expenses etc. on account of compensation payable to the
contractors workers, cost of any law suit etc. and the contractor shall have to bear all such
expenses.
7. The contractor shall at his own cost provide all materials required for the work. All materials
to be provided by the contractor shall be conformity with the specification laid down in the
contract and the contractor shall if required furnish the proof regarding the specification at
his own cost to the Engineer-in-charge.
8. The contractor shall have to use own equipment for the execution of the work.
9. No mobilization & demobilization charges for any plant/machineries is payable under
this contract.
64
APPENDICES
TABLE OF CONTENTS
VIII DRAWING
IX INTEGRITY PACT
65
APPENDIX-I
NOTES: The Appendix forms part of the Tender. Tenderers are required to be fill up all the
blank spaces in this Tender Form and Appendix.
PROFORMA OF AGREEMENT
Gentlemen,
1. In this Agreement, words expressions shall have the same meanings as are respective
assigned to them in General Conditions of Contract, hereinafter referred to.
2. The following documents shall be deemed to form and he read and construed as part of this
Agreement viz:-
3. The Contractor hereby covenant with the Trustees to execute, complete and maintain the
work till handing over to the Board in conformity in all respects with the provisions of
Contract.
66
4. The Trustees hereby covenants to pay to the contractor in consideration of such execution
completion and maintenance of the works the Contract Prices at the times and in the manner
prescribed by the Contract.
IN WITNESS whereof the parties hereto have caused their respective Common Seals to be
hereunto as fixed (or have set their respective hands and seals) the day and year first above
written.
Have executed these presents on the day and year first above written.
CHIEF ENGINEER
PARADIP PORT AUTHORITY
For & on behalf of the PPA
Signature of the Contractor
Witnesses: 1)
2)
67
APPENDIX-II
To
The FA &CAO, PPT
68
DETAILED INFORMATION ABOUT BANK GUARANTEE
a) The Bank Guarantee (BG) must be issued by a scheduled Bank. If the issuing Bank has a
branch at Paradip, then it has to ensure that the BG can be encashed at Paradip only. In case
the issuing Bank does not have a Branch at Paradip, it has to ensure that the BG can be
encashed at the nearest possible branch of the bank to Paradip. The issuing Branch of the
bank must ensure that the BG is encashed immediately on invocation without any delay and
demur. In encashing the BG the bank must strictly adhere to the RBI Guidelines issued from
time to time. The issuing Branch of the bank must clearly mention the complete address of the
Branch where the BG can be encashed when required.
b) The original BG should be sent by the issuing Branch of the bank to the beneficiary directly
under Registered Post/Speed Post/Courier cover with Acknowledgement. In exceptional cases
only, where the BG is handed over to the customer for any genuine reasons, the issuing
Branch of the bank should immediately send an unstamped duplicate copy of the BG by
Registered Post/Speed Post/Courier to the beneficiary with a covering letter requesting the
beneficiary to compare the original BG received from the customer and conform that it is in
order.
c) One officer should be specially designated by respective department with the responsibility for
verification timely renewal and timely encashment of B.Gs.
d) In this regard, the revised BG format is enclosed and the same is to be made as a part of the
Tender Document being issued henceforth. Also, in the case of tenders already floated where
the leftover time for submission of offer is 7 days or more, necessary corrigendum may be
issued to incorporate the new BG format. In all other cases the existing practice is to be
followed.
Further, if any deviation I the BG submitted by the participant is noticed when compared to the
format made available in the tender, the offer is not to be considered.
69
APPENDIX –III
TO
M/s._____________________________
_________________________________
_________________________________
Yours faithfully,
CHIEF ENGINEER,
PARADIP PORT AUTHORITY
70
APPENDIX –IV
TO
M/s._____________________________
_________________________________
_________________________________
Dear Sirs,
Yours faithfully,
CHIEF ENGINEER,
PARADIP PORT TRUST
71
APPENDIX –V
Executive Engineer,
BC Division
Paradip Port Authority.
Received Rs.
(Rupees ). only
72
APPENDIX –VI
1. Name of work :
3. Date of Commencement :
4. Date of Completion :
5. Was the work completed in time? :
If not, whether the compensation
recoverable was under the
contract has been waived or
recovered already may please be
indicated.
6. If the work done satisfactorily?
7. Agreement No. and Date.
8. Payment Vr. in which recoveries :
now proposed to be refunded
were made.
9. Amount to be refunded. :
10. Indicate, if the final bill was paid if :
so quote Vr. No.
11. Was any defect found during :
maintenance ?
12. State whether :
13. Remarks, if any. :
M.B. No.
In
Page No.
Certified that no dues are outstanding against the Contractor for recovery.
Passed for Rs………………………………………………………………………………… only.
Asst. Executive Engineer (C)/
Executive Engineer.
Executive Engineer,
BC Division
Paradip Port Authority.
Receipt Rs………………….………. (Rupees ………………………………………………………..
………………………………………………) only.
Signature of the Contractor.
APPENDIX –VII
73
SCHEDULE OF PORT TRUST RECOVERY RATES
NB: The rates are subject to change from time to time as approved by Paradip Port or the
appropriate Authority.
74
APPENDIX –VIII
INTEGRITY PACT
Between
Preamble: The Principal intends to award, under laid down organizational procedures,
contract/concession for Tender No.
……………………………………………………………………………… The Principal values full
compliance with all relevant laws and regulations, and the principles of economic use of resources,
and of fairness and transparency in its relations with its Bidder. The Central Vigilance Commission
(CVC) has been promoting Integrity, transparency, equity and competitiveness in Government/PSU
transactions and as a part of vigilance administration and superintendence. CVC has, through its
Office Orders No. 41/12/07 dated 04.12.07 and 43/12/07 dated 28.12.07 and Circulars No. 18/05/08
dated 19.05.08 and 24.08.08 dated 05.08.2008, recommended adoption of Integrity Pact and
provided basic guidelines for its implementation in respect of major procurements in the Government
Organizations In pursuance of the same, the Principal agrees to appoint an external independent
Monitor who will monitor the execution of the contract for compliance with the principles mentioned
above.
(2) If the Principal obtains information on the conduct of any of its employees which is a criminal
offence under the relevant Anti-Corruption Laws of India, or if there be a substantive suspicion in
this regard, the Principal will inform its Vigilance Office and in addition can initiate disciplinary
actions.
a. The Bidder/Contractor will not, directly or through any other person or firm, offer, promise or
give to any of the Principal's employees involved in the execution of the contract or to any
third person any material or immaterial benefit which he/she is not legally entitled to, in order
to obtain in exchange any advantage of any kind whatsoever during the execution of the
contract.
b. The Bidder/Contractor will not commit any offence under the relevant Anticorruption Laws of
India; further the Bidder/Contractor will not use improperly, for purposes of competition or
personal gain, or pass on to others, any information or document provided by the Principal
as part of the business relationship, regarding plans, technical proposals and business
details, including information contained or transmitted electronically.
(2) The Bidder/Contractor will not instigate third persons to commit offences outlined above or be an
accessory to such offences.
Section 3 - Disqualification from or exclusion from future Contracts
If the Bidder, before award of contract has committed a transgression through a violation of Section
2 or in any other form such as to put its reliability as Bidder into question, the Principal is entitled to
disqualify the Bidder from the tender process or to terminate the contract, if already signed, for such
reason.
75
1. If the Bidder/Contractor has committed a transgression through a violation of Section 2 such as to
put its reliability or credibility into question, the Principal is entitled also to exclude the
Bidder/Contractor from future contract award processes. The imposition and duration of the
exclusion will be determined by the severity of the transgression. The severity will be determined by
the circumstances of the case, in particular the number of transgressions, the position of the
transgressions within the company hierarchy of the Bidder and the amount of the damage. The
exclusion will be imposed for a minimum of 6 months and maximum of 3 years.
2. The Bidder accepts and undertakes to respect and uphold the Principal's Absolute right to resort
to and impose such exclusion and further accepts and undertakes not to challenge or question such
exclusion on any ground, including the lack of any hearing before the decision to resort to such
exclusion is taken. This undertaking is given freely and after obtaining independent legal advice.
3. If the Bidder/Contractor can prove that it has restored/recouped the Damage caused by it and has
installed a suitable corruption prevention system, the Principal may revoke the exclusion
prematurely.
1. If the Principal has terminated the contract according to Section 3, or if the Principal is entitled to
terminate the contract according to section 3, the Principal shall be entitled to demand and recover
from the Contractor liquidated damages equivalent to 5% of the contract value or the amount
equivalent to Security Deposit/Performance Bank Guarantee, whichever is higher.
2. The Bidder agrees and undertakes to pay the said amounts without protest or demur subject only
to condition that if the Bidder/Contractor can prove and establish that the termination of the contract
after the contract award has caused no damage or less damage than the amount or the liquidated
damages, the Bidder/Contractor shall compensate the Principal only to the extent of the damage in
the amount proved.
2. If the Bidder makes incorrect statement on this subject, it can be declared disqualified for the
purpose of the contract and the same can be terminated for such reason.
1. The Principal shall appoint competent and credible external independent Monitor for this Pact.
The task of the Monitor is to review independently and objectively, whether and to what extent the
parties comply with the obligations under this agreement.
2. The Monitor is not subject to instructions by the representatives of the parties and performs his
functions neutrally and independently. He reports to the Chairperson of the Board of the Principal.
76
3. The Bidder/Contractor accepts that the Monitor has the right to access without restriction to all
Project documentation of the Principal including that provided by the Contractor. The
Bidder/Contractor will also grant the Monitor, upon his request and demonstration of a valid interest,
unrestricted and unconditional access to its project documentation. The same is applicable to
Subcontractors. The Monitor is under contractual obligation to treat the information and documents
of the Bidder/Contractor/Subcontractor with confidentiality.
4. The Principal will provide to the Monitor sufficient information about all meetings among the
parties related to the Project provided such meetings could have an impact on the contractual
relations between the Principal and the Bidder/Contractor. The parties offer to the Monitor the option
to participate in such meetings.
5. As soon as the Monitor notices a violation of this agreement, he will so inform the Management of
the Principal and request the Management to discontinue or heal the violation, or to take other
relevant action. The Monitor can in this regard submit non-binding recommendations. Beyond this,
the Monitor has no right to demand from the parties that they act in a specific manner, refrain from
action or tolerate action.
6. The Monitor will submit a written report to the Chairperson of the Board of the Principal within 8 to
10 weeks from the date of reference or intimation to him by the 'Principal' and, should the occasion
arise, submit proposals for correcting problematic situations.
7. If the Monitor has reported to the Chairperson of the Board a substantiated suspicion of an
offence under relevant Anti-Corruption Laws of India, and the Chairperson has not, within
reasonable time, taken visible action to proceed against such offence or reported it to the Vigilance
Office, the Monitor may also transmit this information directly to the Central Vigilance Commissioner,
Government of India.
Section 9 - Pact Duration This Pact begins when both parties have signed it. It expires 12 months
after the last payment under the Concession Agreement. If any claim is made/ lodged during this
time, the same shall be binding and continue to be valid despite the lapse of this pact as specified
above, unless it is discharged/determined by Chairperson of the Principal.
4. Should one or several provisions of this agreement turn out to be invalid, the remainder of this
agreement remains valid. In this case, the parties will strive to come to an agreement to their original
intensions.
Date .:……………………
77
SPECIAL TERMS AND CONDITIONS OF TENDERERS
Make in India & sharing land border with India conditions:
INTIMATION TO TENDERERS:
i) Format of certificate for Local content declaration & Self declaration under Rule
153(iii) of the General Financial Rules (GFR‟s) 2017 .
ii) ii) Format of certificate for tenders for works under Rule 144(xi) in the General
Financial Rules (GFRs) 2017 .
iii) Accordingly 06 nos. of Annexures are attached. Bidders-
(d) “Class-II local supplier will not get purchase preference in any procurement,
undertaken by procuring entities.
B. Restrictions under Rule 144 (xi) of General Financial Rules 2017 (order Public
Procurement No.1) of DOE, Public Procurement Division, No.F.No.6/18/2019-PPD)
dated 23.07.2020) and amendments / clarifications issued subsequently by DOE.
The provisions contained in Order (Public Procurement No.1of DOE, Public
Procurement Division No.F.No.6/18/2019PPD) dated 23.07.20 and as amended /
clarified from time to time shall be applicable to this tender.
i) Any bidder from a country which shares a land border with India will be eligible to bid
against the tender only if the bidder is registered with the Competent Authority
specified in Annexure II of Order (Public Procurement No.1) dated 23.07.2020.
ii) "Bidder" (including the term tenderer, 'consultant' or 'service provider‟ in certain
contexts) means any person or firm or company, including any member of a
consortium or joint venture (that is an association of several persons or firms or
companies), every artificial juridical person falling in any of the descriptions of
bidders stated herein before including any agency branch or office controlled by
such person, participating in procurement process.
iii) "Bidder from a country which shares a land border with India" for the purpose of this
order means:
a. An entity incorporated, established or registered in such country : or
b. A subsidiary of an entity incorporated, established or registered in such a country : or
c. An entity substantially controlled through entities incorporated, established or
registered in such a country : or
d. An entity whose beneficial owner is situated in such a country : or
e. An Indian (or other) agent of such an entity :or
f. A natural person who is Citizen of such a country :or
g. A consortium or joint venture where any member of the consortium or joint venture
falls under any of the above.
iv) The beneficial owner for the purpose of (iii) above will be as under:
79
1. In case of a company or Limited Liability Partnership, the beneficial owner is
the natural person(s), who, whether acting alone or together, or through one or
more juridical person, has a controlling ownership interest or who exercises
control through other means.
Explanation
a) “Controlling ownership interest" means ownership of or entitlement to more than
twenty five percent of shares or capital or profits of the company;
b) “Control" shall include the right to appoint majority of the directors or to control the
management or Policy decisions including by virtue of their shareholding or
management rights or shareholder's agreements or voting agreements.
2. In case of a partnership firm, the beneficial owner is the natural person(s) who,
whether acting alone or together, or through one or more juridical person, has
ownership of entitlement to more than fifteen percent of capital or profits of the
partnership;
3. In case of an unincorporated association or body of individuals, the beneficial
owner is the natural person(s) who, whether acting alone or together, or
through one or more juridical person, has ownership of or entitlement to more
than fifteen percent of the property or capital or profits of such association or
body of individuals.
4. Where no natural person is identified under (1) or (2) or (3) above, the
beneficial owner is the relevant natural person who holds the position of senior
managing official;
5. In case of a trust, the identification of beneficial owner(s) shall include
identification of the author of the trust, the trustee, the beneficiaries with fifteen
percent or more interest in the trust and any other natural person exercising
ultimate effective control over the trust through a chain of control or ownership.
v.An agent is a person employed to do any act for another, or to represent another in
dealings with third person.
vi. [To be inserted in tenders for works contracts, including turnkey contracts] The
successful bidder shall not be allowed to sub-contract works to any contractor from a
country which shares a land border with India unless such contractor is registered with the
Competent Authority.
80
Annexure-I
Annexure-II
Model Certificate for Tenders
“I have read the clause regarding restrictions on procurement from a bidder of a Country
which shares a land border with India; I certify that this bidder is not from such a country, or
if from such a country, has been registered with the Competent Authority. I hereby certify
that this bidder fulfils all requirements in this regard and is eligible to be considered. [where
applicable, evidence of valid registration by the Competent Authority shall be attached].
Authorized signatory
(Name of the Firm entity).
81
Annexure-III
MODERL CERTIFICATE FOR TENDERS FOR WORKS INVOLVING POSSIBILITY OF
SUB-CONTRACTING
“I have read the clause regarding restriction on procurement from a bidder of a country
which shares a land border with India and on sub-contracting to contractors from such
countries; I certify that this bidder is not from such a country or, if from such a country, has
been registered with the Competent Authority and will not sub-Contract any work to a
contractor from such countries unless such contractor is registered with the Competent
Authority. I hereby certify that this bidder fulfils all requirements in this regard and is liable to
be considered (where applicable, evidence of valid registration by the Competent Authority
shall be attached).
Authorized signatory
(Name of the firm entity)
Annexure-IV
Model Certificate for GeM
I have read the clause regarding restrictions on procurement from a bidder of a country
which shares a land border with India; I certify that this vendor/ bidder is not from such a
country, or if from such a country, has been registered with the Competent Authority. I
hereby certify that this vendor/ bidder fulfils all requirements in this regard and is eligible to
be considered for procurement on GeM [where applicable, evidence of valid registration by
the Competent Authority shall be attached].
82
ANNEXURE-V
Local content Declaration & Self Certification as per the Government of India Order towards Public
Procurement (preference to Make in India) vide Letter No. P45021/2/2017-PP(BE-II), (revised)
Dated.16.9.2020)
(TO BE PROVIDED ON BIDDERS COMPANY/FIRM LETTER HEAD)
I, ___________________(Name of the Person(s),S/o. at (Address), working as _____________
(Designation and name of the firm/Company/partnership/Joint venture),and I have been authorized to
sign the Declaration/Self-Certification on behalf of firm /Company/partnership/Joint venture do
hereby solemnly affirm and declare as under:
That I will agree to abide by the terms and conditions of the policy of Government towards Public
Procurement (preference to Make in India) vide Letter No. P-45021/2/2017-PP(BE-II)
(revised)Dated.l6.9.2020.
That the information furnished hereinafter is correct to be of my knowledge and belief and I
undertake to produce relevant records before the procuring entity or any authority so nominated for
the purpose of assessing the Local Content.
That the local content for all inputs which constitute the said equipment has been verified by me and
I am responsible for the correctness of the claims made therein.
That in the event of the domestic value addition of the product mentioned herein is found to be
incorrect and not meeting the prescribed value addition norms based on the assessment of an
authority so nominated for the purpose of assessing the Local Content, action will be taken against
me as per the notification P-45021/2/2017-PP(BE-II), (revised) Dated.16.9.2020.
I agree to maintain the following information in the company's record for a period of 8 years and
shall make this available for verification to my statutory authority.
The Details of the location(s) at which the local value addition is made
i. Name and details of the Domestic manufacture
ii. Date on which this certificate is issued
iii. Product for which the certificate is produced
iv. Percentage of local content
83
Annexure-VI
Tenderers shall submit Declaration as per Annexure VIII in their technical bid
Format of Certificate for Tenders for Goods/Services/Works under Rule 144(xi) in the General
Financial Rules (GFRs),2017
To
((Name and address of Tender Inviting Authority)
DECLARATION BY AUTHORISED SIGNATORY OF THE FIRM
Dear Sir.
Ref: Your Tender No.____________ dated ____________
1.I/ We the undersigned_________________, (full name), do hereby declare, in my capacity as
_________ of M/s. _____________(name of bidder entity),that:
2.I / we certify that M/s.______________ (name of bidder entity).
a)is not from such a country, I hereby certify that this bidder fulfils all requirements in this regard and
is eligible to be considered. OR
b)is from such a country(strike out whichever is not applicable) and has been registered with the
Competent Authority. I hereby certify that this bidder fulfils all requirements in this regard and is
eligible to be considered.[Where applicable, evidence of valid registration by the Competent
Authority is attached).
3.I / We the Bidder agree and undertake that if the contract is awarded to us, we will not sub-contract
or outsource any work and / or any part thereof to a contractor from such countries, unless such
contractor is registered with the Competent Authority and proof of same is obtained. I / we hereby
certify that this bidder fulfils all requirements in this regard and is eligible to be considered and I /
We submit the proof of registration herewith
[Wherever applicable, evidence of valid registration by the Competent Authority shall be attached]
4.I understand that the submission of incorrect data and / or if certificate / declaration given by M/s.
(name of bidder / entity) found to be false, this would be a ground for immediate termination and
further legal action in accordance with law as per Clause 12 of Public Order on Restrictions under
Rule 144 (xi) of the General Financial Rules (GFR's),2017.
5.This declaration cum undertaking is executed by us through our Authorized Signatory/ies after
having read and understood the Office Memorandum and Order (Public Procurement No.1,2,3) dated
23rd and 24thJuly 2020 of Ministry of Finance, Department of Expenditure, Public Procurement
Division, Government of India including the words defined in the said order which shall have the
same meaning for the purpose of this declaration cum undertaking.