Cemtg Horizontal Well - Final
Cemtg Horizontal Well - Final
/HORIZONTAL WELLS
DRILLING TECHNOLOGY SCHOOL
TRAINING DEPARTMENT- IDT
Introduction
Most of the horizontal wells are generally completed without cementing. The
horizontal section is often completed as an open hole without some method of lining or
sometimes lined with a slotted liner, perforated liner or in some cases, wire wrapped sand
control liners. However in such wells, the formation rock must have sufficient integrity to
prevent collapse or sloughing, particularly when approaching depletion. Though the
horizontal section is not cemented but the cementation of the previous intermediate casing
is very critical as this is frequently highly deviated and achievement of good quality
cementation against this casing for proper zonal isolation is must for successful completion
of the well. This is because the primary motive of drilling horizontal drain holes in the
producing interval are to achieve improved productivity and the failure to achieve proper
zonal isolation in the upper cased off zones in such cases can greatly upset the production
economics because of reduced production of hydrocarbon and the need to dispose of large
quantities of unwanted fluids/gas. For this reason it is essential to achieve good
cementation against the highly deviated intermediate section for successful completion of
horizontal wells.
Completion Procedure
1
DRILLING TECHNOLOGY SCHOOL
TRAINING DEPARTMENT- IDT
produced fluids and to provide isolation between the upper cased off zones and
the lower producing intervals. Often, however, there are horizontal well
completion and production circumstances which dictate that casing must be run
and some form of isolation initiated. Some of these are listed below: -
ii. When "gas coning" and "water coning" control problems are foreseen
due to the borehole penetrating or being too close to the gas cap or
water table. This may result from loss of directional control causing the
bore holes to meander or simply penetration of the gas cap prior to
entering the oil producing zone.
1. Open hole.
2
DRILLING TECHNOLOGY SCHOOL
TRAINING DEPARTMENT- IDT
3
DRILLING TECHNOLOGY SCHOOL
TRAINING DEPARTMENT- IDT
4
DRILLING TECHNOLOGY SCHOOL
TRAINING DEPARTMENT- IDT
4 23
6 14
9 50
17 79
23 58
25 67
28 99
36 100
47 100
At a yield point of 28lb/100 sq. ft, the solids channel was eliminated.
However lowering the value to 25 lbs/100sq.ft resulted in only 67% bottom
5
DRILLING TECHNOLOGY SCHOOL
TRAINING DEPARTMENT- IDT
45 15
60 20
85 28
90 30
A summary of the data collected to date has led to two major conclusions: -
1. There appears to be a thresh hold value of mud yield point below which
a continuous solid channel will occur.
2. The yield point value required preventing this channel from forming
decreases with a decrease in deviation angle.
Slurry stability
Stability of the cement is always important, more so in a deviated well bore. Two
properties determine the stability of the slurry i.e. free water and sedimentation. It is well
known that good displacement practices minimizes the occurrence of inter zonal
communication channels, which are produced when cement bypasses the mud during
6
DRILLING TECHNOLOGY SCHOOL
TRAINING DEPARTMENT- IDT
primary cementing. Perhaps not so well known is the fact that communication channels can
also be created after the cement has been displaced but while it is still fluid. This channel
arises from cement slurries that are unstable and causes sedimentation and production of
large quantities of free fluid when static.
However, unstable slurry may also cause zonal isolation problem in vertical wells
but it will be particularly harmful in a deviated or horizontal well. In vertical wells, any
free water released by the cement will migrate to the top of the cement column, resulting in
potential formation of fluid channels and poor well bore isolation. Unless the free water
generation is very high, this effect does not greatly influence isolation in vertical well. In
high angle wells where the top of cement column runs the full length of the well bore, the
free fluid can collect along the high side of the annulus and sedimentation can result in a
highly porous, low strength & low density channel (Fig-1), which in turn may contribute to
zonal communication and gas migration.
Therefore by designing stable slurry the risk of annular communication and gas
migration can be minimized. Although free water and sedimentation can occur together
yet, one can occur without the other. Therefore testing should be conducted to assure that
neither occurs.
7
DRILLING TECHNOLOGY SCHOOL
TRAINING DEPARTMENT- IDT
Free water
Free water should be maintained at zero. The earlier API procedure for
measurement of free water percentage at ambient conditions was illustrated to
be inadequate for horizontal/high angle well conditions. Slurries which are
tested to have close to 1% free water at ambient conditions were shown to have
as much as 7% when tested under heated deviated condition. The most realistic
evaluation can be made by preconditioning the slurry to bottom hole
circulating temperature and pressure for a simulated placement time and then
pour it into a test cylinder-deviated to at least 45 0 angle and placed in a oil
filled heating chamber maintained at BHCT throughout the duration of testing.
This realistic procedure for free fluid determination has been incorporated in
the latest API Recommending Practice for Testing Oil Cements API RP 10B,
1997.
Sedimentation
8
DRILLING TECHNOLOGY SCHOOL
TRAINING DEPARTMENT- IDT
9
DRILLING TECHNOLOGY SCHOOL
TRAINING DEPARTMENT- IDT
TESTING PROCEDURE
Condition the slurry by applying the pressure and heat as per the thickening time
schedule which most closely simulates actual field conditions.
Poured the cement slurry in the settling tube which is preheated to 85 0C in the
curing chamber.
Heat up the tube to the desired BHCT in curing chamber under sufficient pressure
to prevent boiling of the slurry.
Cured for minimum 24 hours or until set.
Free water and settling determined by observing the difference in the level of the
cement column before and after curing and by determining the density of the top,
middle and bottom portion of the set cement. The variation in density from the top
to the bottom of the tube gives a clear identification of the amount of settlement
10
DRILLING TECHNOLOGY SCHOOL
TRAINING DEPARTMENT- IDT
experienced. For high angle wells this variations must be less than 1.5% of the
design density.
The BHCT is used as the test temperature since settlement can only occur while the
cement is fluid. These development of the slurry stability testing facilities has now made
possible design of a stable slurry at elevated temperature and pressure condition which will
be of immense value in achieving zonal isolation in deviated wells.
Fluid loss
Cement slurry should have higher gel and yield strength than the mud
unless this prohibits use of turbulent flow. Density control of the slurry and
uniform additive concentration are particularly important to assure that the
cement properties will be consistent through out the cemented interval. Batch
mixing of the slurry should be performed if possible.
11
DRILLING TECHNOLOGY SCHOOL
TRAINING DEPARTMENT- IDT
Mud Circulation
Correct use of spacers and flushes is required for the most efficient
cement placement. The most effective results are obtained where large
volume of low viscosity spacers and flushes are pumped ahead of the
cement slurry. Experimental results indicate that a 40 bbl water spacer
resulted in 94% efficiency on the low side, where as a 40 bbl viscous
spacer attained only 66% efficiency. The additional flow energy at
equivalent rates makes the thinner fluids more effective due to their
turbulent action. Also the degree of centralization affects the velocities of
these spacers and flushes in the narrow side of the annulus. This low-side
velocity must be determined to characterize spacer efficiency for low side
12
DRILLING TECHNOLOGY SCHOOL
TRAINING DEPARTMENT- IDT
Flow rate
Several studies have shown that regardless of flow regime present, the
higher the annular velocity, the better will be the displacement efficiency.
Maximizing flow rate during the cement job contributes to hole cleaning and
cement placement. Test data in the below mentioned table shows the effect of
velocity in displacement efficiency when displacing a 12ppg water base mud
with a 16.8ppg cement slurry.
13
DRILLING TECHNOLOGY SCHOOL
TRAINING DEPARTMENT- IDT
Not every case will be this dramatic, but when holding all factors
constant except flow rates, increasing the flow rate causes increase in
displacement efficiency. Even though higher annular velocities are desired, it
is equally desired not to break down the well bore with excessive circulating
pressure. It is recommended that a pre job cement placement simulator be run
to optimize flow rates for these jobs so that well bore integrity is maintained.
Optimal placement of cement slurry for casing protection and zone
isolation requires enhanced planning of cement placement operations. Correct
physical and chemical design of all fluids (drilling fluid, spacer and cement)
pumped in the annulus does not completely guarantee adequate placement.
Thus the higher completion cost of horizontal/ERD wells with possibility of
greatly increased production warrant the use of a cement job simulator as a
design tool. Using the program prior to actually conducting a job can identify
any problems (such as lost circulation or fluid invasion) before they occur, and
provide an opportunity to modify the planned design. The simulators generate
critical information that provides the most efficient design of surface flow
rates, therefore allowing maximum mud removal downhole. Information
required for this analysis includes all fluid properties and well bore
geometries (casing and hole sizes, deviation and depths) as well as location
and value of weak formation zones. The program output provides downhole
circulating pressures at critical zones of interest through out the job, and
accounts for free fall and predicts flow rate out of the well with a given
input rate.
MECHANICAL DEVICES/ACTIONS
Centralization
14
DRILLING TECHNOLOGY SCHOOL
TRAINING DEPARTMENT- IDT
15
DRILLING TECHNOLOGY SCHOOL
TRAINING DEPARTMENT- IDT
centralizer. One type specially designed for horizontal loading, the rigid
bores. However the bow type centralizers have to overcome the down hole
forces which include the weight of the pipe (which is lying on the low side of
16
DRILLING TECHNOLOGY SCHOOL
TRAINING DEPARTMENT- IDT
the open hole with little or no buoyancy) along with the weight of high density
cement slurry before it leaves the casing. This extra strain on the restoring
force results in each centralizer contributing less to the “lift” of the casing or
liner from the low side of the well bore and sometimes may cause the
centralizers that are not be limited by restoring forces, are mostly used in
17
DRILLING TECHNOLOGY SCHOOL
TRAINING DEPARTMENT- IDT
Pipe movement :
due to moving the pipe has been shown to improve cuttings and filter cake
removal, and helps break down gelled pockets of mud. These advantages
angle wells. Rotation is preferred in gauge holes because the rotational forces
on the fluid will cause it to be swept entirely around the annulus and thus
providing a mechanical means of ensuring that cement is placed under the low
in washed out holes as it provides the fluid velocity and pressure surges to
including, high slack-off drag, which may prevent the casing from returning to
bottom, perhaps leading to a liner not being set where designed . In addition,
may be countered and in long casing strings, movement at the drill floor may
not be transmitted to where it is needed due to pipe stretch. For this reason
worldwide, most liners in high angle/ horizontal wells are only rotated by use
severely eccentric as is the case in most high angle wells, rotation appears to
18
DRILLING TECHNOLOGY SCHOOL
TRAINING DEPARTMENT- IDT
RPM, and reciprocation should be in 10 to 20ft (3-6m) strokes, with one to two
strokes every one to two minutes. Movement should begin with initial mud
19
DRILLING TECHNOLOGY SCHOOL
TRAINING DEPARTMENT- IDT
torque values due to the increased contact with the well bore.
Casing/hole sizes :
well bore configuration. For vertical wells, the optimum annular clearance has
been suggested as 0.75 inch (i.e. 7" linear in 81/2 inch hole). In horizontal
20
DRILLING TECHNOLOGY SCHOOL
TRAINING DEPARTMENT- IDT
and heavier cement in combination with the lack of hydrostatic driving forces
make it necessary to enlarge this clearance for the best narrow side cleaning.
Testing has shown that at least 1.5 inch of annular clearance should be
5
maintained (5” liner in 8.5” hole) for high angle wells. Normally this will
provide ample clearance for displacement (assuming minimum 70% stand off)
minimum annular clearance of 1.5 inch between casing & hole to achieve
adequate mud removal and proper cement placement in the narrow side of the
hole.
Floating equipments :
spring loaded or positive closure valve should be used. The other type of
floating equipment will not function properly due to high deviation angle.
21