Constr-001 Method Statements DATA PANEL INSTALLATION
Constr-001 Method Statements DATA PANEL INSTALLATION
Revision Number: 00
Document
Owner: MRQ
3. 3. Location of Activity
Low Voltage Room and Electrical Rooms
6. 5. Operation
7. Materials: Materials used will be as per the material submittal approved by the
engineer and will be as per the approved drawings in coordination with other services.
8. Storage / Protection: DB, SMDB, and MDB and Accessories shall be unloaded with
care to avoid any damages. If they are shipped in packs or pallets, each pack of pallet
shall be lifted individually with suitable lifting equipment. Every precaution shall be
taken to preserve their cleanliness before installation. Store in accordance with
manufacturer’s instructions, Properly protected from construction activities and
weather conditions.
9. Installation:
1. To make sure that the entire installation is in conformance and in accordance
with the design intent of the project for the Electrical and Low Voltage System
in addition to the specification and as per approved shop drawings and
comply.
2. with local and International Standards.
3. All the switchboards shall be fabricated at the manufacturer’s works.
4. Before beginning installation in any area, examine all parts of the adjoining
works into which applicable work is to be placed. Should any condition be
found which will prevent the proper execution of the work, installation shall
not proceed in that area until such conditions are corrected by the contractor.
5. Fix all equipment independently of wiring system. Use cadmium of zinc
electroplated bolts, nuts, washers and screw.
6. Mount single DB at 1800mm from finish floor level to top of equipment,
unless shown otherwise on drawing / schedules.
7. Ensures that clearance in front of switchgear is not less than 1m, or as
indicated.
8. Number terminals, cables and component parts to correspond with
manufacturer have certified drawings.
9. Terminate PVC, SWA PVC and MICS cables inside enclosure by securing
cables to switchboards with gland bracket; and enclosure with glanding plates
or fabricated steel extension boxes.
10. For flush installation, DB’s all conductors shall terminate behind the board in
an adaptable box. For surface mounting, trunking shall be fixed between the
board and ceiling or floor level, or conduit run directly into Trunking which
prevent correct installation of the Trunking lid. Adequate earth continuity shall
be made between the various components.
1. Project Manager
1. To ensure that all the preparation and application works are carried out
according to the Contract Specification.
2. To ensure that the progressing of works is carried out according to the planned
program and as per the approved method statement.
3. To ensure that all equipment and material required executing the work are
available according to the planned Construction Programme.
4. To co-ordinate with the Main Contractor, MEP co-coordinator, and Safety
Officer for a safe and proper execution of the works.
2. Site Engineer
1. To ensure that the works are carried out according to the Contract
Specifications approved method statement.
2. To provide all necessary information and distribute responsibilities to his
construction team.
3. To monitor the progress of work in relation with the work program and to
report to the Project Manager.
4. To co-ordinate with the safety officer and to ensure that the works are carried
out in safe practicing methods.
3. Foreman
1. The foreman will carry out his duties by maintaining continuous coordination
with the site engineer on daily basis, and ensure proper distribution of the
workforce in the required and planned locations.
2. To ensure that his assistant foreman/ charge hand are aware of the job
requirements and they have enough information to carry out their duties
properly.
3. To ensure in consultation with the site engineer that the manpower involved in
the works are moving as agreed and planned for the work.
4. To ensure that the daily work is progressing as planned and advise the Site
Engineer for any requirement of the additional resources.
5. To control disposal of waste materials to the instructions received from the site
engineer.
6. To ensure full coordination with the safety officer to maintain safe working
and proper house keeping of the site, following the approved safety measures
and further ensure that all his working team are aware of the same to prevent
accident and losses.
7. After completion of works, Foreman shall inform the site engineer for
inspection of works.
8. Distribution and the control of materials shall be monitored by foreman and
storekeeper.
4. Safety Engineer
1. Ensure the implementation of all the safety measures in accordance with the
HSE plan and everybody aware of it for it’s proper implementation.
2. Ensure all the implemented safety measures are adequate to maintain safe
working on the site.
1. Wire cutters
2. Measuring tape
3. Drill machine
4. Wooden hammer
5. Flat file
6. Screw drivers
7. Open and box spanners
8. Crimping tool
ATTACHMENTS
Risk assessment
Inspection and test plan
Quality control procedure