Lab3 - CPM
Lab3 - CPM
ACTIVITY A B C D E F G H
PREDECESSOR - - - A,B,C A,B,C D D,E D,E
DURATION 4 3 2 5 6 7 6 9
EARLY START 0 0 0 4 4 9 10 10
EARLY FINISH 4 3 2 9 10 16 16 19
SUCESSOR D,E D,E D,E F,G,H G,H I J K
LATE START 0 1 2 5 4 16 15 10
LATE FINISH 4 4 4 10 10 23 21 19
SLACK 0 1 2 1 0 7 5 0
CA YES YES YES
CRITICAL PATH A E H
Time Schedule
A 0 4 4
E 4 10 6
H 10 19 9
K 19 27 8
B 0 4 4
C 0 4 4
D 4 10 6
F 9 23 14
G 10 21 11
I 16 27 11
J 16 27 11