KERC Regulation
KERC Regulation
2.65 “YEAR‟ means year commencing on 1st of April of any year and ending
on 31st of March of the succeeding year.
NOTE: The words and expressions used and not defined above but defined in
the Act / KER Act shall have the meanings as assigned to them in the
relevant Acts. In case of inconsistency in the words and expressions
used between the Act and KER Act, 1999, the provisions in the Act shall
always prevail.
CHAPTER-III
For arranging power supply, the following system and classification shall be
applicable.
(i) All installations (other than motive power) upto & inclusive of
5 KW of sanctioned load.
Note: The Consumer has the option to avail himself of supply at High
Tension even if the requisitioned load is less than 50 KW. The minimum
C.D. in such cases shall be 25 KVA.
Note: - In case the power supply is given at13.2 KV, the transformer
provided by the Consumer shall be designed for change over to11
KV, when the Licensee’s supply line is converted to 11 KV.
All installations with a contract demand above 7,500 KVA and up to and
inclusive of 35,000 KVA
Note: - 1) The Standard supply voltages for various contract demands are
as follows:
Supply
Contract demand
voltage
Up to 2,000 KVA 11/13.2 KV
Above 2,000 to 7,500 KVA 33 KV
Above 2,000 to 20,000 KVA 66 KV
Above 7,500 to 35,000 KVA 110 KV
Above 20,000 KVA 220 KV
3) If the C.D. is more than 2000 KVA, Supply shall be arranged at the
appropriate voltage levels depending upon the system network
available in the area.
4) As a special case, Railways are entitled to get power on two phases only
for traction purposes, subject to conditions that may be specified by the
Licensee.