Blasting and Painting Procedure
Blasting and Painting Procedure
: SEU-005-QP-1002-0001
Construction Support Services Revision : 1
Contract
Page : 2 of 10
BLASTING AND PAINTING
RECORD OF REVISION
The revisions listed below have been incorporated in this copy of the document.
TABLE OF CONTENT
1. OBJECTIVE 5
2. GENERAL 5
2.3. Abbreviations 5
3. INTRODUCTION 5
4. PROCEDURE DETAILS 5
4.3. Painting 7
4.3.2. Mixing 7
4.3.3. Thinning 7
5. PAINTING APPLICATION 8
5.1. Inspection 8
6. INSPECTION 9
7. SAFETY MEASURES 10
8. REFERENCE 10
1. OBJECTIVE
This procedure covers the method to be followed for performing painting works on all external
surfaces of structural steel and piping.
2. GENERAL
2.3. Abbreviations
3. INTRODUCTION
SEU shall comply with this procedure, which shall be carried out in accordance with
manufacture’s recommendation and generally applicable company specification. Project
Manager is responsible for ensuring such compliance and SEU shall ensure that its own project
specific procedure incorporate all relevant aspects of, and are fully consistent with, the contents
of this document.
4. PROCEDURE DETAILS
Oil and grease contamination shall be removed with an approved degreasing and
water flushed prior to blast cleaning in accordance with SSPC-SP1 ″Solvent
Cleaning″. Salt Contaminant shall be removed with fresh water.
Offshore Welding, Fabrication and Doc. No. : SEU-005-QP-1002-0001
Construction Support Services Revision : 1
Contract
Page : 6 of 10
BLASTING AND PAINTING
All rough welds, burrs, weld spatter and all other sharp surface projection shall be
ground smooth prior coating preparation.
All surfaces to be coated shall be cleaned to SSPC in accordance with paint
system applied.
The anchor pattern profile shall correspond to KEANETATOR comparator
between 2.0 ~ 3.0 mils peak to peak.
Cleaning shall be discontinued each day in sufficient time to permit the surface
cleaned to be primed before the end of the working day or prior to any forecasted
detrimental weather.
Blast cleaned surface shall be primed on the same day to avoid rusting. If surface
preparation is authorized at night (exceptionally), the prepared surface shall be
wiped the next morning. They shall be freshened with light blasting before the
primer is applied.
Surface preparation shall not be performed at night and also if any of the following
occur:
The surface is likely to be humid after surface preparation and before painting.
The surface temperature is less than 5°F above the surrounding air dew point.
If the relative humidity exceeds 90%, permission from Company/Contractor must
be obtained to proceed with or continue with surface preparation. A sling
hygrometer must be provided to measure the air relative humidity and dew point
readings at blasting area.
One unit of air compressor 390 cfm, 100 psi, equipped with separator to
ensure that the compressed air supply is free of oil and moisture.
1 unit Blasting Pot 200 liter capacity C/W accessories.
Offshore Welding, Fabrication and Doc. No. : SEU-005-QP-1002-0001
Construction Support Services Revision : 1
Contract
Page : 7 of 10
BLASTING AND PAINTING
4.3. Painting
All paint and thinner containers shall be kept closed before use and store
under shelter.
Any paint that has gelled or settled during storage shall not be used.
Any paint for which the shelf-life is expired shall not be used.
4.3.2. Mixing
4.3.3. Thinning
Thinner are to be added only when necessary for proper application and
must never exceed manufacturer recommendations.
Steel surface temperature is less than 5°F (-15°C) above dew point.
The relative humidity for Inorganic Zinc Silicate not more 70% and for
the other paint 75 - 85%.
During rain or when the wind speed exceeds 15 miles per hour.
The time internal between coats is likely to exceed 48 hours.
Offshore Welding, Fabrication and Doc. No. : SEU-005-QP-1002-0001
Construction Support Services Revision : 1
Contract
Page : 8 of 10
BLASTING AND PAINTING
Brush type and quality shall enable proper application of paint. Round or
oval brushes are suitable for irregular/rough surfaces or pitted steel. Flat and
wide brushes are suitable for large flat surfaces.
Brush recommended for stripe coating and small areas, care must be taken to
achieve the specified dry film thickness.
5. PAINTING APPLICATION
5.1. Inspection
The damage paint and non-adherent paint shall be removed and the surface thoroughly
cleaned. The edge of the damaged area shall be smoothed. Surface preparation shall
extend approximately 1 inch into the sound coat. Mechanical cleaning as per SSPC
SP3 may be applied in case surface preparation by blasting is not possible. Repair of
damage area refer to section 5 COPI Spec. 84501-9200-1L-006 Rev.A2
(RAL 1021)
1 Primer Coat (P-01) Inorganic Zinc Silicate Jotun RESIST 86, CPA
(DFT 2.5 – 3 mils) + JOTUN ZINC
100, COMP B
6. INSPECTION
Inspection of surface preparation is carrying out by visual and compared with “Keane-
Tator” or “Surface profile Comparator”.
The air relativity humidity shall be measured with a hygrometer. Surface preparation
and/or paint application operations shall not commence if it is beyond the acceptable
limit. Relative Humidity shall be measured before commencement of work.
shall less than 80% of specified DFT required and average value of measurements
shall not be less than specified DFT required. The observations will be recorded in the
attached Painting Report Format.
7. SAFETY MEASURES
Safety to be ensured as the chemicals used in the painting procedure are highly inflammable
and hence must be stored and handled away from source of heat and spark
Avoid breathing of vapor or spray mist as it can lead to nausea and unconsciousness.
Inaccessible area for blasting and painting need adequate scaffolding erection.
8. REFERENCE
The requirements contained in the following standards shall form part of this specification in the
manner and extent specified here in:
1. Steel Structures Painting Council (SSPC) Specifications.
2. COPI Specification for Coating Structures Piping and Equipment (Doc. No.: 84501-9200-
1L-006 REV.2)
ATTACHMENT 1
INSPECTION & TEST PLAN
Offshore Welding, Fabrication and Doc. No. : SEU-005-QP-1002-0001
Construction Support Services Revision : 1
Contract
Page : Attachment
BLASTING AND PAINTING
ATTACHMENT 2
PAINTING REPORT FORMAT
Offshore Welding, Fabrication and Doc. No. : SEU-005-QP-1002-0001
Construction Support Services Revision : 1
Contract
Page : Attachment
BLASTING AND PAINTING
ATTACHMENT 3
NON-CONFORMITY REPORT FORM
Offshore Welding, Fabrication and Doc. No. : SEU-005-QP-1002-0001
Construction Support Services Revision : 1
Contract
Page : Attachment
BLASTING AND PAINTING
ATTACHMENT 4
PAINTING SPECIFICATION SHEETS (JOTUN)
Offshore Welding, Fabrication and Doc. No. : SEU-005-QP-1002-0001
Construction Support Services Revision : 1
Contract
Page : Attachment
BLASTING AND PAINTING
Offshore Welding, Fabrication and Doc. No. : SEU-005-QP-1002-0001
Construction Support Services Revision : 1
Contract
Page : Attachment
BLASTING AND PAINTING
Offshore Welding, Fabrication and Doc. No. : SEU-005-QP-1002-0001
Construction Support Services Revision : 1
Contract
Page : Attachment
BLASTING AND PAINTING
Offshore Welding, Fabrication and Doc. No. : SEU-005-QP-1002-0001
Construction Support Services Revision : 1
Contract
Page : Attachment
BLASTING AND PAINTING
Offshore Welding, Fabrication and Doc. No. : SEU-005-QP-1002-0001
Construction Support Services Revision : 1
Contract
Page : Attachment
BLASTING AND PAINTING
Offshore Welding, Fabrication and Doc. No. : SEU-005-QP-1002-0001
Construction Support Services Revision : 1
Contract
Page : Attachment
BLASTING AND PAINTING
Offshore Welding, Fabrication and Doc. No. : SEU-005-QP-1002-0001
Construction Support Services Revision : 1
Contract
Page : Attachment
BLASTING AND PAINTING
Offshore Welding, Fabrication and Doc. No. : SEU-005-QP-1002-0001
Construction Support Services Revision : 1
Contract
Page : Attachment
BLASTING AND PAINTING
Offshore Welding, Fabrication and Doc. No. : SEU-005-QP-1002-0001
Construction Support Services Revision : 1
Contract
Page : Attachment
BLASTING AND PAINTING
Offshore Welding, Fabrication and Doc. No. : SEU-005-QP-1002-0001
Construction Support Services Revision : 1
Contract
Page : Attachment
BLASTING AND PAINTING
Offshore Welding, Fabrication and Doc. No. : SEU-005-QP-1002-0001
Construction Support Services Revision : 1
Contract
Page : Attachment
BLASTING AND PAINTING
Offshore Welding, Fabrication and Doc. No. : SEU-005-QP-1002-0001
Construction Support Services Revision : 1
Contract
Page : Attachment
BLASTING AND PAINTING
Offshore Welding, Fabrication and Doc. No. : SEU-005-QP-1002-0001
Construction Support Services Revision : 1
Contract
Page : Attachment
BLASTING AND PAINTING
Offshore Welding, Fabrication and Doc. No. : SEU-005-QP-1002-0001
Construction Support Services Revision : 1
Contract
Page : Attachment
BLASTING AND PAINTING
Offshore Welding, Fabrication and Doc. No. : SEU-005-QP-1002-0001
Construction Support Services Revision : 1
Contract
Page : Attachment
BLASTING AND PAINTING
Offshore Welding, Fabrication and Doc. No. : SEU-005-QP-1002-0001
Construction Support Services Revision : 1
Contract
Page : Attachment
BLASTING AND PAINTING
Offshore Welding, Fabrication and Doc. No. : SEU-005-QP-1002-0001
Construction Support Services Revision : 1
Contract
Page : Attachment
BLASTING AND PAINTING