Pile Design
Pile Design
CONTRACTING
Tel: + 971 2 6213668
MIDDLE EAST FOUNDATION DRILLIND & CONTRACTING Fax: +971 2 6213667
E-mail: [email protected]
P.O. Box: 28840 - Abu Dhabi Mob: + 971 50 5291904
PILE DESIGN
CONSULTANT: Transco.
CONTENTS:
1.0 GENERAL
1
MIDDLE EAST FOUNDATION DRILLIND &
CONTRACTING
Tel: + 971 2 6213668
MIDDLE EAST FOUNDATION DRILLIND & CONTRACTING Fax: +971 2 6213667
E-mail: [email protected]
P.O. Box: 28840 - Abu Dhabi Mob: + 971 50 5291904
1.0 GENERAL
Project : power substation and water pumping
Consultants : Transco.
References :
Principles of Foundation Engineering - Braja M Das
Pile Design and construction practice - M J Tomlinson, Third edition
Elements of Soil Mechanics for Civil and Mining Engineers
- By G N Smith
Pressure Meter and Foundation Engineering
- By F Baguelin, J F Jezequel, D H Shields
Tests :
2
MIDDLE EAST FOUNDATION DRILLIND &
CONTRACTING
Tel: + 971 2 6213668
MIDDLE EAST FOUNDATION DRILLIND & CONTRACTING Fax: +971 2 6213667
E-mail: [email protected]
P.O. Box: 28840 - Abu Dhabi Mob: + 971 50 5291904
2 2
fcu = 40 N/mm , Ac = 280933.7815 mm (Net Area)
2 2
fy = 460 N/mm , As = 1809.557368 mm
N = 5119237.795 N Or 511.92 TONS
Load Factor : 1.4
3.3 Bending Moment calculations in Pile due to H-force and constructional allowances:
Since the piles are restrained by the pilecaps and Tie Beams the pile head shall be considered to be
restrained from rotational moment. Hence the moment on the pile occurs mainly due to horizontal
force at the pile head.
Elastic Analysis:
Reese and Matlock have established a series of curves for normally consolidated and cohesionless soils
for which the elastic modulus of the soil Es is assumed to increase from zero at the pile head in direct
proportion to the depth assuming that the pile behaves as an elastic beam on a soil which also behaves
elastically. Refer pages 219 to 223 of " Pile Design And Construction Practice by M J Tomlinson Third
Edition; 1987
MF = Bending Moment
Fm = Bending Moment Coefficient from figure 6.39b
T = Stiffness Factor
5
= EI/nh
E = Reference: BS 8110:1997 Part 2, Table 7.2
= 28000 MN/m² or N/mm²
4
I = 0.006361725 m
nh = Coefficient of subgrade modulus variation
= 28 MN/m3 (Refer figure 6.20)
T = 1.45
Zmax = L/T
L = Pile length
Zmax = 4.48 5
3
MIDDLE EAST FOUNDATION DRILLIND &
CONTRACTING
Tel: + 971 2 6213668
MIDDLE EAST FOUNDATION DRILLIND & CONTRACTING Fax: +971 2 6213667
E-mail: [email protected]
P.O. Box: 28840 - Abu Dhabi Mob: + 971 50 5291904
hs = 418 mm
418
Then hs /h = = 0.70
600
For the Ultimate State Design apply a load factor of 1.4 for working load:
1.4 N M
= 0.54 ; = 0.47
h² h3
From Chart 13 for design of circular columns to ACI318-08 , for this condition:
Area of Steel required Areq = 0.40%
Area of Steel provided As = 0.64% Therefore safe
Proposed reinforcement:
Main Bars, 9 Nos, Dia: 16 mm
Area = 0.64% of concrete Therefore O.K.
Links 8 mm @ 150 mm
14 x 10000
Working stress = = 0.495148712 N/mm2
p/4 x 600 ²
From the above results it can be inferred that stressses in the concrete are acceptable
4
MIDDLE EAST FOUNDATION DRILLIND &
CONTRACTING
Tel: + 971 2 6213668
MIDDLE EAST FOUNDATION DRILLIND & CONTRACTING Fax: +971 2 6213667
E-mail: [email protected]
P.O. Box: 28840 - Abu Dhabi Mob: + 971 50 5291904
1/3 1/4
Shear Stress = vc = 0.79 x (100 x As/(b x d)) x (400/ds) /gm
2
= 0.576 N/mm for concrete grade 25
vc = 0.576 [40/25]
1/3
= 0.674 N/mm2 for concrete grade 40
Hw
Working Shear Stress in pile = v =
p/4 xf ²
67.11 x 103
v = = 0.237 N/mm² (Ultimate)
p/4 x 600 ²
As v < vc the permissible shear stress is more than the actual shear stress, No Shear reinforcement is not required.
however we provide nominal 8 mm links @ 150 mm
0.95 x 460
< 100.53 mm² Therefore safe.
5
MIDDLE EAST FOUNDATION DRILLIND &
CONTRACTING
Tel: + 971 2 6213668
MIDDLE EAST FOUNDATION DRILLIND & CONTRACTING Fax: +971 2 6213667
E-mail: [email protected]
P.O. Box: 28840 - Abu Dhabi Mob: + 971 50 5291904
Length of Piles:
It should be emphasized that the length of pile assumed in these calculations is based on Lower cut-off
levels, Loadings and results of tests run on a few boreholes carried out by a third party. At any rate such
information contained in the Boreholes results affecting the design may not be exactly representative of the
whole area and particularly that the hard strata reported may differ from pile location to the other. The
length of pile(s) shall be determined on site while boring by our supervisor on site as he is the best judge of
the soil conditions because he watching every bore all the time.Of course the attention of the Engineer's
Representative shall be drawn to each case as it arises and a decision taken regarding where to found the
pile in each case.
Qu = Qb + Qs = Ab qb +As qs = 9 Cb Ab + a Cs As
Qb = 282743.3388 x 0 = 0 N 0.00%
Qs = 5183627.878 x 0.32 = 1658760.921 N 100.00%
Qu = 1658760.921 N = 165.88 Tons
6
MIDDLE EAST FOUNDATION DRILLIND &
CONTRACTING
Tel: + 971 2 6213668
MIDDLE EAST FOUNDATION DRILLIND & CONTRACTING Fax: +971 2 6213667
E-mail: [email protected]
P.O. Box: 28840 - Abu Dhabi Mob: + 971 50 5291904
qb = 2 Nf quc (4.26)
Where Nf = tan² (45 + f/2) For UCS of 0 kN/m² ;
f = 27 °, Nf = 2.66 ;
Shaft Frictional Resistance of Pile in Rock according to Tomlinson (After Williams & Pells):
qs = ab quc Where,
Shaft Frictional Resistance of Pile in Rock according to according to Tomlinson (After Rosenberg & Journeaux) :
qs = ab quc ; a = 0.20 ;b= 1.00 ;
qs = 0.2 x 1 x 1600 = 0.32 N/mm²
From the above comparative calculations it can be inferred that the minimum values are:
qb = 0.00 N/mm² ; qs = 0.31 N/mm²
Therefore
Qb = 282743.3388 x 0 = 0 N 0.00%
Qs = 5183627.878 x 0.31 = 1617291.898 N 100.00%
Qu = 1617291.898 N = 161.73 Tons
From the above comparative calculations it can be inferred that the minimum value for bearing in rock is:
Qu = 161.73 Tons
4.2.2 Shaft Frictional Resistance of Pile in Soil above Rock Layer: Not Considered
Friction angle of shaft in the Soil Layer : 27.0 (see annex - page 1)
Length of Pile shaft in Soil Layer : 0.0 m
qs = 0.00 kN/m²
Qs (S) = 0 x 0 = 0 N= 0 Tons
7
MIDDLE EAST FOUNDATION DRILLIND &
CONTRACTING
Tel: + 971 2 6213668
MIDDLE EAST FOUNDATION DRILLIND & CONTRACTING Fax: +971 2 6213667
E-mail: [email protected]
P.O. Box: 28840 - Abu Dhabi Mob: + 971 50 5291904
In compression :
F.S = 3 ; Qallow = 53.91 Tons
> 14 Tons ; Therefore safe
In Tension :
Q u = Qs = 162 Tons ; The weight of pile is not considered
F.S = 2.5 ; Qallow = 64.69 Tons
> 1 Tons ; Therefore safe
Nomenclature:
S = Total pile settlement = S1 + S2 + S3
S1 = Settlement of pile shaft
S2 = Settlement of pile caused by the load at end bearing
S3 = Settlement of pile caused by the load transmitted along the pile shaft
4.3.3 Settlement of pile caused by the load transmitted along the pile shaft :
S3 = Qws x D x (1- µS2) Iws
pLe Es
p = perimeter of the pile = 1884.96 mm
Le = embedded length of pile = 2.75 m
Iws = influence factor = 2 + 0.35 Le / D (Vessic, 1977) = 3.06 mm
S3 = 0.07 mm
We cannot predict residual settlements as these should better be left to the actual testing of piles.