KXD OFFICE (MsProject) (Kenhxaydung - VN) (Dzungtv) CHATGPT

Uploaded by

lethangts3
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
26 views3 pages

KXD OFFICE (MsProject) (Kenhxaydung - VN) (Dzungtv) CHATGPT

Uploaded by

lethangts3
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

ID Name Duration PredecessoOutline Level

1 ESTIMATION & CONTRACK SCHEDULE 560 days 1


2 Tài liệu dự án 0 days 1
3 Khởi công 0 days 1
4 PERMISSION SCHEDULE 225 days 1
5 LAND ISSUE (DONRE) 70 days 2
6 Document Pereparation 30 days 2 3
7 Letter from DONRE to HPC 0 days 6 3
8 Document Pereparation 40 days 7 3
9 Letter from HPC to DOC 0 days 8 3
10 LOCAL PLANNING (DPA) 225 days 2
11 Document 40 days 3
12 Document Pereparation 40 days 2 4
13 Letter from DPA to POC 0 days 12 4
14 Original BD 35 days 3
15 Review 25 days 13 4
16 Adjustmen 10 days 15 4
17 Original TD-BP 30 days 3
18 Review 25 days 16 4
19 Adjustmen 5 days 18 4
20 Approval 0 days 19 4
21 Resumission - Fire Fighting 60 days 3
22 Pre F.F Evaluation 25 days 20 4
23 Adjustmen 15 days 22 4
24 F.F - Application 20 days 23 4
25 Approval 0 days 24 4
26 ReSUMISSION - BD 30 days 3
27 Review 25 days 25 4
28 Adjustmen 5 days 27 4
29 Approval 0 days 28 4
30 ReSUMISSION - TD-BP 30 days 3
31 Review 25 days 29 4
32 Adjustmen 5 days 31 4
33 Approval 0 days 32 4
34 DESIGN SCHEDULE 235 days 1
35 TD & FORCON Drawing (Original Plan) 105 days 2
36 TD & FORCON Drawing Adjustment 70 days 2 3
37 Explanation of Coordinated items 0 days 36SS+6.43 3
38 DR3 Update 0 days 36 3
39 Issue FORCON R2 0 days 20 3
40 Changing Layout 235 days 2
41 BD1 60 days 2 3
42 Kick off 0 days 41SS+6.43 3
43 BD2 65 days 41 3
44 TD & FORCON Drawing Confirmation 50 days 43 3
45 DR3 No.2 0 days 44SS+5w 3
46 TD & FORCON Drawing Adjustment 10 days 44 3
47 Issue FORCON R3 0 days 46 3
48 VECD/Adjustment 40 days 41 3
49 Procurement/ Shop Drawing 60 days 44 3
50 Fabrication/ Delivery 45 days 3
51 Material delivery to site and starting installation work 0 days 3
52 Elevator Work 85 days 58FF 1
53 Installation & test 4 Lifts 45 days 52 1
54 Hoist remove 10 days 53 1
55 Facade closing 20 days 54 1
56 Final finishing 35 days 70FF,55 1
57 Main Building 1 days 1
58 Roof 21 days 59 1
59 PH room 14 days 60 1
60 Level 12 14 days 61 1
61 Level 11 14 days 62 1
62 Level 10 14 days 63 1
63 Level 9 14 days 64 1
64 Level 8 14 days 65 1
65 Level 7 14 days 66 1
66 Level 6 14 days 67 1
67 Level 5 14 days 68,88 1
68 Level 4 14 days 69 1
69 Level 3 14 days 85,72 1
70 Level 2 140 days 71 1
71 Level 2 7 days 83 1
72 Level 2 14 days 84 1
73 Sub-structure 1 days 1
74 TEST PILE (COMPLETED 2019/June) 1 days 1
75 Pile & Diaphragm Wall 133 days 1
76 Preparation + Guide wall 28 days 2
77 Diaphragm wall 63 days 76 2
78 Bored pile (Including Test Pile) 42 days 77 2
79 Underground Structure Work 427 days 1
80 Capping beam & preparation 14 days 78 2
81 1st Excavation (1FL-2.1m) 14 days 80 2
82 Cast 1FL 126 days 71 2
83 Cast 1FL 7 days 87 2
84 Cast 1FL 35 days 81 2
85 2nd Excavation (FL-2.1m ~ FL-5.1m) 21 days 84FS+1.43 2
86 Cast B1 & Cure 140 days 82FF 2
87 Cast B1 & Cure 7 days 93 2
88 Cast B1 & Cure 35 days 85FS-0.71 2
89 3rd Excavation (FL-5.1 ~ FL-9.6m) 35 days 88 2
90 Cast B2 & Cure 154 days 82FF 2
91 Cast B2 & Cure 35 days 89FS-1.43 2
92 PIT & Foundation Excavation (FL-9.6~FL 63 days 91FS-0.71 2
93 Cast PIT & Foundation 49 days 92FS-2.14 2
94 Concrete Grouting for Col 28 days 93FF 2
95 VMU/PMU 1 days 1