Project Closure
Project Closure
Closure
Objectives
Structure
14.1 Introduction
14.2 What is a Project Audit?
14.3 When to Audit?
14.4 How to Audit
14.5 Who should Audit?
14.6 Audit Report
14.7 Project Closure
14.8 Types of Project Closure
14.9 Project Closure Process
14.10 Performance Evaluation
14.11 Let Us Sum Up
14.12 Self-Assessment Exercises
14.13 Further Readings
14.1 INTRODUCTION
In this unit, the foundations of auditing, auditing, and project conclusion will
be covered. Here, we will discuss the characteristics, categories, definitions,
and meanings of audit, auditing, and project completion. You will also learn
the goals, procedures, and steps of auditing and how to close a project.
This unit will explain what audit, auditing, and project closure mean from
different points of view. As a result, you can apply your experiences to the
relevant audit, auditing, and project closing. In addition, distinctions have
221
Project Closure been made between successful and unsuccessful initiatives and between
normal and premature project conclusions. The overall objective of this unit
is to offer several conceptual inputs, both western and Indian, to make project
audit and closure appropriate to the context of developing countries. Also,
words like audit, auditing, and projects are tried to be explained. Describe the
process of performance evaluation, team evaluation, and project conclusion
using examples from India.
Audits differ from conventional project reviews in that they are undertaken
by a party external to the project team and command structure. A designated
audit department, steering committee, or external auditor typically performs
the project audit.
In this unit, we use the word "project" to mean "a unique, temporary effort
undertaken to achieve planned goals", according to the Association for
Project Management(APM) Body of Knowledge, 6th edition. Different
techniques will be needed to audit programmes and portfolios. The auditing
of a project should be seen in the context of how the APM Body of
Knowledge defines the project, program, and portfolio (P3) assurance. P3
Assurance is the process of giving stakeholders Assurance that projects,
programmes, and portfolios will meet their scope, time, cost, and quality
objectives and realize their benefits.
Project Audit Components: Review of the selection criteria for the project.
The project's place in the organization's priorities is being reevaluated by
Checking the organizational culture to see if it supports the kind of project
being carried out, a review of the project team's performance and the number
of staff members needed to meet its needs. A review of outside factors that
might alter the project's direction or level of importance. A review of all
elements important to the project and project management in the future.
Although audits are not legally necessary for privately held businesses, they
are still carried out to give banks, investors, and other stakeholders
assurances about the company's financial standing. Various financial
statements are examined during an audit, including the income statement and
the cash flow statement. Statement of Cash Flows. A company's balance
sheet and cash flow statement both include data on how much cash was
generated and used during a specific period.
Information about how money is earned and spent during the course of the
fiscal year is provided to stakeholders and regulatory organizations by the
audit. An audit may take anywhere from a few months to a year, depending
on the size of the business. At the conclusion of the engagement, the auditor
offers a qualified opinion regarding the accuracy of the financial reporting
completed.
Stages of an Audit
• Depending on the complexity of the case and the size of the corporation,
different auditing procedures may be used. An audit typically has four
main stages, though:
• The first stage is the planning stage. This engagement stage, in which a
corporation works with an auditing firm to establish details such as the
level of engagement, procedures, and objectives.
• The second stage is the internal controls stage. Auditors gather financial
records and any other information required to conduct audits at this
stage. To assess whether the financial statements are accurate,
information is required.
• The fourth stage is the reporting stage. The auditors prepare a report that
expresses an opinion on the accuracy of the financial statements after
finishing all the tests.
224
The objective of a project management audit is to establish the actual status Project Audit and
Closure
of work accomplished on a project and its conformity with the project's
statement of work, including time and cost limits. It is a methodical, unbiased
evaluation of the condition of affairs undertaken by a qualified examiner
(Ruskin & Estes, 1984).
The allocated team should have a diverse set of abilities, including audit,
project management, and controls, as well as industry and subject area
experience. Audits cannot be completed by a single person since they require
assessment and permission. Even if that manager or supervisor is far away,
the oversight must be done. A good audit team will make a report with useful
suggestions while causing the project and business as little trouble as
possible.
In most cases, the audit report is accompanied by the annual report of the
company. Banks, financial institutions, investors, creditors, and regulators all
require an audit report. If the auditor issues a clean report, it means that the
financial statements of the company have been determined to be completely
compliant with accounting standards.
225
Project Closure Types of Audit Reports
Section/Heading Description
Title Report of the Independent Auditor. Simple and the word
"independent" should appear in the audit report's title.
This suggests that an impartial, impartial, and external
third party conducted the audit.
Addressee The report will state clearly to whom it is addressed.
Example: To the Company Name's Shareholders or
Directors
Introduction This would be a declaration that lists the name of the
organization undergoing the audit as well as the dates of
the financial period—typically the fiscal year—that the
audit will cover.
226
Project Audit and
Responsibilities Both the auditor and the board of directors of the Closure
of directors and company being audited have their responsibilities stated
auditors in this section. It states that the company's management
and directors have agreed to fulfil their obligation to give
the auditor all necessary financial records for the audit.
To the best of the director's knowledge, it also affirms
that the supporting documentation is true and accurate.
According to the statement, the auditor's duty is to
examine the company's financial statements.
Additionally, it states that the auditor's judgement must
be based on the data presented.
Opinion This section clearly states the auditor’s opinion.
Basis of opinion The audit was carried out in accordance with the
standards, and the section outlines the resources and audit
process. This section might be a little longer than the
others.
Other reporting If there are any additional reporting obligations, such as
responsibility statutory or regulatory requirements, they are listed here.
Signature of the Signed by the auditor
auditor
Date and place The date and city where the report was signed by the
auditor.
What will happen if a project is not closed properly? When a project is not
properly closed, the opportunity to learn from its process and outcomes is
lost. The likelihood of encountering the same challenges and maybe less
motivated teams increases the next time we begin a project.When we fail to
properly end a project, no lessons are learnt, and team efforts are not
227
Project Closure recognized and honoured. Whether the project is intended for an internal
audience or an external organization, it is likely that our customers may be
less pleased with the results. This is true regardless of how well it meets
project criteria or how quickly our client receives our deliverables.
iv) Failed Projects:Far too often, projects fail. Project failure can have
many different reasons. The project may be permanently killed if the
client runs out of money, which happens frequently.
ii) Learning Phase: The project closing learning phase is time allocated to
team reflection on what you've done, how you've done it, and what
you've learned now that the project is finished. There are several
approaches to project closing that emphasize learning and growth for
both the company as a whole and individual team members.
iii) People Phase: The people phase makes you feel things. The project
deliverables were made possible by the team. Recognizing their work
and the need for emotional closure will make everyone feel good and
ready for whatever comes next.