ITTOs, Formula
ITTOs, Formula
PV=FV/(1+ i)n
Present value of money
Future value
Interest
Years
Present value
Build or Buy
Build Cost
Monthly Build Cost
Buy Cost
Monthly Buy Costs
Predict how much more the remainder of the project will costs
Build or Buy
100000
12000
85000
11000
15000
1000
15
mulas:
Equation Indication
BAC/CPI
AC + BAC – EV
AC + [BAC-EV/(CPI x SPI)]
EAC-AC
Greater than 1 – harder to complete and meet BAC
(BAC-EV)/(BAC-AC)
Less than 1 – easier to complete and meet BAC
Greater than 1 – harder to complete and meet EAC
(BAC-EV)/(EAC-AC)
Less than 1 – easier to complete and meet EAC
Formula components
100000
1.06
1.191016
Formula components
625000
1.06
1.3382255776
Hover over the red dots for notes.
Answer these questions first and the formulas will be calculated for you.