Concrete Method Statement
Concrete Method Statement
TableofContents
1. Scope
2. Purpose
3. Responsibilities
4. Equipments
5. Material
6. Shop Drawings
7. Procedure
7.2 Formwork
8.9 Repair
1. SCOPE
The scope of this method of statement is to cover concrete works activity which includes
( Formworks installation, rebars supply and installation, concrete supply and placement, water
proofing, etc.) d supply for cast in situ Concrete in the project. In accordance with contract
requirements and approved project specification, project safety procedure and approved issued for
construction drawings.
2. PURPOSE
The method statement shall address the precedence of physical operations applicable for the
supply and placing Structural / nonstructural Concrete on the project.
This Method Statement is to ensure that concrete works activity will be expedite in an efficient
and safe manner in accordance with all relevant contract documents, (Specification and
Drawing) and international accepted methods, utilizing proven methods and procedures, as
detailed herein and was implemented on previous projects.
This Method Statement is for submittal to Consultant / Employer for their concurrence.
This Method Statement will, if deemed necessary, be revised as and when required to
accommodate circumstantial requirements that cannot be foreseen at this page.
3. RESPONSIBILITIES:
Project Director / Project Manager have the responsibilities for overall the project
activities including safety measures.
To ensure that the surveyor has completed setting out with reference points complying
with the approved for construction drawings.
Ensure that all parties who are required to make any kind of test / inspection are
suitably informed as to the overall program of the works and daily inspection testing
requirements.
The QC Engineer or his designee (QCI) shall be responsible for the following:
Review all relevant documentation and test reports issued by parties involved and
submit records to consultant.
Ensure that all discipline activities that require to be inspected in the concreting
operation has been inspected and approved.
Organized and allocate inspection works to the Quality Control Inspectors (Civil).
To issue NCR’s / DR’s, when and where required and to check that the construction
department provides timely appropriate corrective and preventive action.
Sign off and obtain signatures from the Consultant on the forms and verifying
documents as required.
Keeping a daily log of all the inspection Request submitted by the SE.
Carry out statistical analysis of the inspection and test result to improve quality control operation
on site, to verify testing compliance and to advise the SE of the results.
Filling and compiling controlled copies of all test reports under the supervision and instructions
of the QC Engineer.
Sampling and conducting field testing according to the instruction of the consultant and
QC Manager and in accordance with the Specifications.
The ITL ( Independent Testing Laboratory ) to ensure that the required numbers of samples are
taken from concrete works for the evaluation of quality and Durability of Concrete works.
The Laboratory technician / Engineer shall be responsible to test all concrete aggregates
constituent for quality ensuring it complies with specifications requirements and abide with the
prequency stipulated in the specification.
Ensure that all tests required specified for fresh concrete Production is completed. Issuing,
Compilation and filling all laboratory Test Forms / RFI for Certification submitting all records to
QC department.
Safety Inspector: To ensure all safety precautions has been taken into consideration before
commencing the concrete works.
All heavy equipment operators such as excavators cranes, forklift, etc, should have third party
license.
4. EQUIPMENTS:
4.8 Level
5. MATERIAL:
5.2 Timber
5.3 Scaffolding
6. SHOPDRAWINGS.
7.1ExcavationandBackfilling\
All the areas where excavation is required, the surveyor will give the information to
the excavation foreman to start the excavation to the levels indicated in the ifc
drawings.
After the excavation is completed, the surveyor will check the final grade of the
excavation and the grade will be adjusted accordingly.
Slight trimming will be carried out when and where required before the placing of
polyethylene plastic sheet.
Cast in situ elements shall be constructed in accordance with IFC drawings and line
with project specification.
Surveyor shall mark the location of structural member ( foundation, wall, Column,
etc.) as per approved drawings.
Excavation shall be carried out up to bottom level of blinding, leveled, sprayed with
water, compacted and tested as per relevant specification and approved drawings.
Where construction joints detailed on the drawing, width of concrete element warrant
establishment of construction / expansion joints, or concrete placement to be
stopped due to an avoidable circumstances on site, Construction joints shall be
made, Concrete surfaces will be roughened cleaned to establish a good joint
between old and new fresh concrete, QC inspection, Consultant approval is required
before concrete placement continue in concrete member.
Cleaning of Starter Bars shall be carried out following concrete placement completed
in preparation for the next concrete pouring.
7.2 Formwork
Concrete placement will not commence before Engineer Approval of Formwork and
Rebar Installation.
The design and construction of formwork shall take account of safety and of the
surface finish required. The formwork will be sufficiently rigid and tight to prevent loss
of grout or mortar from the fresh concrete and stand concrete Vibration (Excreted
Hydrostatic Pressure) without Movements. Form work and its supports to maintain
the correct position and to maintain correct shape and profile.
The formwork for foundation, beam connection, column neck and manholes etc. will
be made of either traditional formwork (plywood and timber and supported by tie rod
and steel support ) or DOKA system which a combination of DOKA wooden beams,
plywood and DOKA steel supports system with tie rod.
Formwork will be placed and aligned fixed to the required dimensions as detailed in
issued for construction drawings by the carpentry crew.
Formwork shall be rigid / sturdy and fixed in such a way to retain the structure
members dimensions.
QC Inspector will check the formwork installation and safety officer to ensure safety
of the work.
Before placing the steel reinforcement, an approved form release agent will be
applied to the internal face of the formwork.
For columns, walls shutter will not be closed before QC and consultant releases.
Based on the issued bar bending schedule, steel cutting and bending will be carried
out either in site fabrication shop / supplier fabrication work shop delivered to site
and assembled on site as per approved IFC drawings.
Reinforcement will be placed above ground not in touch of soil, either using wooden
blanks or concrete base to comply with project specification and international
accepted procedures.
Upon the arrival of steel rebar to site fabrication shop, the rebar fabrication crew will
cut and bend rebar in accordance with project specification and IFC drawings.
Before placing the fabricated rebar inside the formwork or mold, the formwork shall
be clean, blown out by air with air compressorvand coated with approved releasing
agent.
Rebar will be placed according to the project specifications and IFC drawings.
Rebar will be assembled either inside or outside the concrete member, outside
assembly steel will be placed by a crane to avoid any disturbance to the water
proofing materials / or polyethylene plastic sheet. Additionally, when leveling
concrete is provided, rebar mats can be assembled in the place.
Reinforcement support shall be properly assembled at site: non metallic or plastic
concrete spacer shall be used to maintain the cover as required by the
specifications.
All embedded materials items for civil. Mechanical or electrical activities shall be placed
/ inspected by QC inspectors ensuring materials comply with specifications.
All embedded items shall be unpainted unless noted otherwise, and free of
deleterious materials, such as dirt, grease, and heavy scale.
Anchor bolts and other embedded items shall be positioned and secured within the
tolerances shown on the drawings, in accordance with ENV 13670 and as required by
this specification.
All embedded elements to comply with the project specification and fabricated in
accordance with IFC drawings.
The embedded metals and anchor bolts will be installed in accordance with IFC
drawings.
The QC inspector shall check formwork, rebar steel, embedded metal and anchor bolts
prior to concrete placement.
Section / Site Engineer will submit Request for inspection to QC inspector prior to start
site delivery of concrete.
After the concrete has hardened sufficiently, the exposed portion of anchor bolt shall be
cleaned of all concrete and the threads chased. Threads shall then be carefully coated
with grease and the washers and nuts installed.
Stage 1:
Embedded elements, inserts, box outs chases, chamfers, water bars etc. as per
approved drawings.
Surveyor marks the concrete top level on the shutter as per approved drawings.
Formworks is clean from inside using compressor and magnetic bars used to remove
pieces of binding wires.
Sub- Contractors QC (civil) and company / contractor QCI ( civil) shall inspect each
member prior to pouring of concrete.
Stage 2:
Concrete shall be placed at each individual pour location dependent on access and
pour configuration either by;
o Direct discharge
o Crane and skip
o Concrete pump
o Chute
The exact method / procedure for placing concrete shall be decided depending
accessibility of structural member on site.
All necessary laboratory tools for fresh concrete quality testing shall be available on
site prior to pouring of concrete ( cube moulds / cylinder mould, slump cone, thermometer
etc.) And third party laboratory technician is available at site or Concrete site station
( checking temperature, slump air content and fresh concrete density and samples taken as
per specifications ). Then transit mixer Mixer released to specified Concrete location.
Place the approved mix concrete into layers 450 mm per layer maximum using one of the
above methods.
Preparation forms, reinforcement, joints and mixing conveying. Concrete shall not be
dropped from a height exceeding 1.8 meters. Expansion / Contraction joints shall be
provided as per IFC drawings.
8. Concrete Compaction:
Stage 3:
Full compaction of the concrete shall be achieved throughout the entire depth of the layer
using mechanical vibrator
Vibration of concrete shall be thoroughly worked against the formwork and around the
reinforcement: successive layers shall be thoroughly bonded together during vibration.
Compaction of concrete shall be carried out by mechanical or electrical vibrators to expel all
air bubbles formed during the mixing and casting.
Care shall be taken to avoid over vibration which could cause segregation, surface laitance
or leakage through formwork.