Prestressed Concrete For Buildings Lin T Joist
Prestressed Concrete For Buildings Lin T Joist
President
Alfred A. Yee & Associates, Inc.
Honolulu, Hawaii
hen the first major prestressed terial was at a premium and the price
W concrete structure in Ameri-
ca, the Walnut Lane Bridge, was built
cf labor at a minimum.
The act of prestressing the con-
in Philadelphia in 1949 one could crete connoted the requirement for
hardly anticipate the proliferation of extra labor and effort over and above
prestressed concrete buildings that that required for conventionally rein-
was soon to follow. forced concrete where steel bars
The idea of deliberately introduc- were merely placed in forms and cast
ing a predetermined stress in the together without incurring the added
concrete to counteract the resulting labor of stressing.
forces and internal stress develop- Many engineers were then of the
ment from anticipated loads was still opinion that prestressed concrete
quite novel in the minds of engineers. would develop slowly in America in
Nevertheless, most engineers agreed view of its economic situation where
that the concept of prestressing con- the ratio of labor costs relative to ma-
crete would result in considerable terial costs was more significant in
savings in material for structures of comparison to that found in other
long span. countries of the world.
It was generally believed that its It was also thought that, if at all,
principal advantage would be felt prestressed concrete would be used
mainly in areas where the cost of ma- mostly for bridge structures where
112
Synopsis
During the past two decades the use of
prestressed concrete has gained considerable
volume in the building construction industry.
Various types of prestressed concrete structural
units and their applications are discussed in
this paper.
Economic factors leading to the superiority of
prestressed concrete in certain construction
applications are analyzed.
Special design considerations and concepts
relating to design for shear, full and partial
continuity, external preloading, deflection
considerations, expansion joints, connection
details and erection are presented.
The physical capabilities of prestressed concrete,
particularly in developing long spans and
unique framing systems, minimum structural
framing depth, speed in construction, material
and cost savings, are also discussed.
There are distinct advantages in reducing
building structural weight and developing
longer clear spans.
An analysis is made of these factors as they
relate to real building costs and functional
aspects._
Finally, the financial aspects of buildings with
respect to speed of construction are analyzed
in detail to develop insight into the merits of
developing more rapid building systems.
Diamond Head
Apartments
Honolulu, Hawaii.
long spans and heavy loads required This structure is 14 stories high
substantially greater proportion of and is framed with composite pre-
materials for conventionally con- tensioned I-joist sections and cast-
structed reinforced concrete systems in-place slabs. The building was
in contrast to prestressed concrete topped off in 1957. Figs. 1 through 3
systems. show various construction phases of
In 1949 designers of bridge struc- the Diamond Head Apartments.
tures in America had relatively little Subsequently, many other high rise
practical information on which to re- buildings in prestressed concrete be-
ly. The Walnut Lane Bridge design gan to appear on the construction
was based mainly on -classical bend- scene throughout the United States
ing theory with principal stresses cal- and in other countries worldwide.
culated and the structure reinforced The use of prestressed concrete in
accordingly. building construction has now be-
Shortly after this period several come quite common for both low rise
small precast concrete plants in the and high rise structures with both
United States began experimenting short and long spans.
with and producing pretensioned pre- The development of efficient low
stressed concrete components for cost mechanical devices for pre-
building structures. These structures stressing, refinement of mass produc-
involved one and two-story buildings tion techniques, and the use of high
with pretensioned flat slabs, channel capacity climbing cranes have con-
slabs, double-tee slabs, and rectan- tributed to reduce greatly the labor
gular beams. requirements for the production and
Gradually, as more information and erection of prestressed and precast
newer design concepts developed in concrete components.
the field of building construction with There is, today, a large body of
pretensioned components, more and design reference material which al-
larger precasting prestressing plants lows engineers to design prestressed
were initiated throughout the United concrete structures with as much
States. confidence as for other building ma-
Then in 1956, the construction of terials. The PCI Design Handbook,'
what is believed to be the first pre- the Connections Manual, 2 and the
stressed concrete high rise building Special Publication on Design Con-
in the world, namely, the Diamond siderations for a Precast Prestressed
Head Apartments, was begun in Ho- Apartment Building 3 are only three
nolulu, Hawaii. such references.
114
Fig. 2. Vertical transport of pre- Fig. 3. Diamond Head Apartments,
stressed precast joists to upper Honolulu, Hawaii (completed in
floors by jib hoist from tubular tower 1957). First prestressed concrete
shaft during construction. high rise building.
__ ___ Core_
Wire
Spiral'
1
' }
f
t
^'
f
Diameter i '
I^
^I
y `^ f^
^l
Prestressing _ ^^ y ` ^_^ 1 ^,
Strandt
Square Square Octagonal
Solid Hollow Solid or Hollow Round
L'
6" p itch
stress in the piles should be in- hard coral foundations, and the ac-
creased to 800 or 900 psi. tion of the prestress in preventing
In our experience we have found tension failures in the piles is most
that a blunt end pile, such as shown effective even under severe driving
in Table 1, would be capable of pene- conditions.
trating very dense sandstone and For instance, 16-in, octagonal piles
116
IL REINF
4"X6"X5/16"
SPLICE CAN
1cy" QIAMETER
STEEL PIPE JI8 WALLS
CONCRETE FILLED 200 TONS $60.00/L.F.
PRESTRESSED
CONCRETE 1&H" OCTAGONAL 200 TONS $16.00/L.F.
118
r, n (g>
C D E G
0
"0-270 ksi S RAND A II' N
I i
I I Q i I
w
c
H 8" CMU
WALLS
"o-270 ksi ' STF AND AT I3-" a (TYP)
t ^
w
{2" 6 °f _ 12 -6 12'-6"
421"
TEMPERATURE
STRANDS
AT 24"
`i0 270 ksi STRAND
120
Fig. 13. Profile of draped tendons for post- tensioning slab.
SPIRAL TIES
-PRESTRESSED
CONCRETE SLAB
SOFFIT
Fig. 14. Composite precast Fig. 15. Storage of flat slab soffits
prestressed slab construction. at precasting yard.
122
I/2" TOTAL
HICKNESS
ENT
Fig. 19. Utility details used with solid prestressed planks and selected
jointing concrete casting strips.
Fig. 20. Prestressed hollow-core slab manufacturing facility showing cast-
ing of a production line, handling and storage of finished products.
124
14" X 4'-0" DOUBLE TEE
NOMINAL 5'-0"
I2L
epic
I
` 3I/4--^III-
15° .1. 30" J. 15'
126
28"
2I/2
CHANNEL WITHOUT TOPPING
28" 28"
s 24" 24" _
CHANNEL WITH TOPPING
OPENINGS FOR
UTILITY
HAFT
L EQUIPMENT OR
DUCTWORK SPACE
Fig. 25B. Channel with openings for equipment, ductwork, or utility shafts.
I-Joists
Prestressed concrete I-joists for
building structures were developed in
1956. In general, they are manufac-
tured in four different sizes to accom-
modate floor framing spans ranging
from 24 to 70 ft.
Sectional views of various I-joists
are seen in Figs. 28 through Fig. 31.
Construction sequences of storage
and installation are shown in Figs.
32, 33, and 34.
The I-joists represent a unique
combination of advantages. Note that
the top flange of the joist is made
smaller than the lower flange, thus
the centroid of the section is closer
to the bottom of the section where
straight prestressing tendons are
placed.
As the joist is being manufactured
Fig. 27. Installation of tri slab. and remains in this isolated state the
128
SPACI
Fig. 28. 14-in. prestressed I-joists Fig. 29. 18-in. prestressed I-joists
for spans ranging from 24 to 34 ft. for spans ranging from 35 to 47 ft.
Fig. 30. 24-in. prestressed I-joists Fig. 31. 30-in. prestressed I-joists
for spans ranging from 48 to 62 ft for spans ranging from 63 to 70 ft.
130
SPAN: 46'
JOIST SPACING FOR REGULAR LOADING SPACING: 10'
CONCENTRATED
LOAD
SPAN: 56'
SPACING: 10'
r' rzi
TOPPING
C'
SPAN: 62'
SPACING: l0"
JOIST SPACING FOR SPECIAL OPENINGS
Fig. 37.
132
8' - 4"
CAST-IN-PLACE
COMPOSITE SLAB
24"
a ^
INTERMITTENT CIRCULAR
OPENINGS FOR A/C
OR ELECTRICAL
M
—51/2"
14"
Fig. 40. Precast prestressed flanged joists for clear span of 84 ft.
134
NO. 10 GA. SPIRAL
2-3/8" 0 PRESTRESSING
STRANDS
RT BEAM FROM
OF DOUBLE TEE
4 "X6" PRECAST-J
PRESTRESSED
TRELLIS BEAMS
Fig. 44. Precast fin section and Fig. 45. Gridwork of decorative
roof trellis framing. precast concrete members.
AJ
PRESTRESSED CAST-IN-PLACE
JOIST BEAMS & SLAB
CONTINUITY REINFORCEMENT FOR
PRESTRESSED JOISTS
Bi
B_J
!iii_J
PRECAST
SLAB SOFFIT CAST-IN-PLACE
BEAMS d SLAB
CONTINUITY REINFORCEMENT FOR
PRESTRESSED SLAB SOFFIT
138
tations of floor-to-floor heights in ISOLATED JOIST
buildings, minimum structural fram-
ing depth becomes imperative. Post-
tensioned cast-in-place concrete
slabs or pretensioned precast slabs, DEAD LOAD DEFLECTION
both composite and non-composite,
can provide the most satisfactory so-
lution to this problem provided de- ADDED TOP REINFORCEMENT
IN CAST-IN-PLACE SLAB
flection can be kept within to!erable
limits.
T _ T
In our experience we have found
ISHORE UP iSHOREUP
that if lightweight concrete is used
for pretensioned composite slabs the EXTERNAL PRELOADING
modulus of elasticity for the com-
bined slab action appears to be high-
er than slabs made of conventional
regular weight aggregate concrete.
In some instances we have found
that the use of lightweight concrete
FINAL COMPOSITE CONDITION
in these framing systems could re-
duce the deflections by 25-50 percent
of that resulting from conventional Fig. 50. Construction sequence
regular weight aggregate concrete. utilizing external preloading.
140
Fig. 52. Erection process of prestressed precast concrete girders by spe-
cially designed davits. Concrete girder is being readied for delivery to
pneumatic-tired dollies.
142
A high capacity truck crane lifted for several floors downward to pro-
the prestressed joists to the intended vide sufficient support by multiple
floor level where a sliding rail car- floor resistance.
riage was designed to transfer one When the crane has been posi-
end of the girder to a position within tioned in the structure, it may be dis-
sufficient reach capacity of the climb- covered that after a few floors of
ing crane. erection, the horizontal position of
With the truck crane holding up the crane may not be ideal due to
one end of the girder and the climb- change in framing in the upper floors,
ing crane at the other end, the girder error in original positioning, or other
was gently lifted and positioned in its reasons.
final location. Fig. 54 shows the rail In these instances it is possible to
transport and climbing crane position shift the position of the climbing
prior to lifting. crane horizontally. This has been
In most buildings the capacity of done on two occasions of which we
the climbing crane is selected on the know of and special equipment, brac-
basis of being able to lift all elements ing and procedure must be devised
into position. Determining the loca- to accomplish this.
tion of the crane with relationship to
the building structural elements re-
quires considerable thought and an- Physical Capabilities of
alysis. Prestressed Concrete
In general, the crane is positioned
as close as possible to the center of Long Spans and Unique
the building but within reach of the Framing Systems
extreme corners. If the building is Prestressed concrete will provide
longer than a reach-capacity point the means of achieving long spans
from the near center position of the and unique framing requirements at
building, then two cranes may have reasonably economical cost.
to be used, or a crane of a larger ca- Architectural requirements for the
pacity and reach may be necessary. new Honolulu Municipal Office Build-
The position of the crane should ing dictated that the interior floor
be such that it will not interfere with framing be completely column free.
elevator and stair shafts where ac- This building was constructed by a
cess to workmen is critical. Elevator combination of long span precast
shafts must be left free to allow the pretensioned concrete flanged joists,
elevator installation crews to work as and heavy long span hollow box gird-
the building is being topped off. ers which were cast-in-place and
Temporary structural framing sup- post-tensioned.
ports will have to be designed for the The hollow box girders spanning a
crane at its position within the struc- distance of 122 ft 8 in. also acted as
ture. These supports are usually in a housing for air conditioning supply
the form of steel beam grillages and return air ducts thus requiring
spanning between "hard" elements the tensioning elements of the box
of the structure such as shear walls, girders to be laid out in a fashion to
columns or girders. accommodate the positioning of the
If span requirements dictate that supply air and return air vents.
these grillages rest on suspended The building floor area increases
floor beams or girders, these struc- with each floor in height and the pre-
tural elements may have to be shored tensioned precast flanged joist clear
I ____ I
22-8 C.C.
Fig. 56. Profile layout of post-tensioning tendons and air conditioning duct
openings for prestressed concrete girder. Honolulu Municipal Office
Building.
144
spans range from 64 ft 4 in. at the
second floor to 84 ft at the 15th floor,
with the building sides flaring out-
ward progressively from lower to up- PRES1
per floors. Details of this engineering JOIST
system may - be seen in Figs. 55
through 58.
Minimum Structural
Framing Depth
Where minimum structural framing A/C
depth is required due to building or- OPE
dinance height limitations, utility
space requirements, or other rea-
sons, prestressed concrete may be
used to advantage.
The main tower of the Financial
POST-TENSIONED HOLLOW GIRDER
Plaza of the Pacific in Honolulu was
constructed in an area where build-
Fig. 57. Section of post-tensioned
ing height limitations were severe. To
construct the necessary number of girder. Honolulu Municipal
floors required for economic viability Office Building.
of the project the designer was com-
pelled to minimize the floor to floor
height.
This required the structural fram-
ing depth to be held at a minimum
and in this case precast pretensioned
conrcete slabs were used to accom-
plish the objective. Details of the
framing system are shown on Fig. 59.
The savings achieved in reducing
structural framing depth and floor to
floor height in the buildings are as
follows:
(1) Reduction in stair risers and
stairwell walls;
(2) Reduction in elevator shaft
walls and exterior perimeter walls;
(3) Reduction in the length of ver-
tical utility risers and shafts;
(4) Reduction in earthquake and
wind forces due to overall reduction
in height of building;
(5) Reduction in total volume of
building and consequent reduction in
heating and airconditioning require-
ments.
Fig. 58. Honolulu Municipal
Speed in Construction Office Building
With the use of prestressed con- (completed in 1975).
"N PRESTRESSED
J
U.
N
R 4'- 0"
PRESTRESSED
CEILIN G BEAM
U.
PRESTRESSED I I I Ir'A
BEAM ^_ L _^ ---L-^-^^--L---
s ip
-- i-- I ------i-- IL
I I I I I I
4' PRESTRESSED-- 1-^
PLANKS
I I I I
I I I
Fig. 59. Structural framing details for the Financial Plaza project.
Crete, particularly in the form of pre- prestressed flat slab sections were
cast structural components, consid- installed in framing this multistory
erable speed in construction can be structure. Column-beam frames were
achieved. spliced at mid-floor heights with a
In the case of the Ala Moana Hotel special splice sleeve device which
in Honolulu, a 39-story high rise 1260- permitted quick joinery.
room hotel structure with approxi- An assembly of the splice sleeve
mately 18,200 sq ft per floor, the pre- units used in the precast columns is
casting technique utilizing both pre- seen in Fig. 60. Precast column-beam
stressed concrete and reinforced frames for the Ala Moana Hotel are
units enabled the structure to prog- seen in Figs. 61 and 62.
ress at a rate of one floor every 21 An overall view showing general
days. construction and erection operations
One thousand two hundred ninety- is shown in Figs. 63 and 64. Full
nine (1299) precast column-beam thickness prestressed slabs were in-
frames combined .with 2868 precast stalled as shown in Fig. 65.
146
COLUMN
IRCING BARS
LOWER COLU
SPLICE SLEE'
Fig. 60. Assembly of splice sleeve units for precast column connection.
Savings in Material
Table 3 shows a comparison of
material requirements between com-
posite prestressed I-joists and non-
prestressed conventionally rein-
forced construction.
From the comparisons of the table
one can observe the considerable
material savings by using prestressed
concrete construction for buildings.
It should be noted that materials of
construction are manufactured items
requiring energy operated processes.
The manufacture of steel and ce-
ment requires considerable amounts
of energy as well as utilization of na-
tural resources. Engineers should
concern themselves with designs that
minimize the use of materials in or-
der to conserve the supply of energy
required to produce these materials
and accomplish efficient use of na-
tural resources.
Savings in Cost
The impact of prestressed con-
crete on the economics of building
construction can be described by the
charts of Tables 4A through 4C show-
ing a cost comparison between pre-
stressed joists versus structural steel
wide flange sections versus cast-in-
place conventionally reinforced con-
crete construction.
The pricing is based on Hawaiian
area construction costs. It should be
noted that the impact of cost savings
by prestressed concrete increases
with larger spans.
Fig. 64
Overview of Ala Moana Hotel
during construction of 34th floor.
Fig. 65. Installation of precast prestressed slabs.
REINFORCING PRESTRESSING
TYPE CONCRETE STEEL STEEL
SPACING :9'-0"
SPAN :64' 4.61 cy 367 LB 746 LB
9.60 cv 2,990 LB
CAST-IN-PLACE-BEAK
SPACING : 9'-0"
cli
SPAN: 40' 1.47 cy 119 LB 224 LB
18 PRESTRESSED I-JOIST
CAST-IN-PLACE BEAM
SPACING :7'-0"
SPAN :30 0.88 CY 59 LB 132 LB
14" PRESTRESSED I- JOIST
_____......
I.l
1.40 Cv 356 LB -
CAST-IN-PLACE BEAM
Table 4A. Cost comparison of prestressed I-joists, steel beams and cast-
in-place concrete beams. (See Appendix for basic unit cost data.)
FABRICATION TOTALCOST
TYPE MATERIALS & ERECTION FIREPROOF IN-PLACE
1r_
!r-,- T
W 14X30 BEAM
AW
SPz
P I0.72/LF $7.15/LF $ 525/LF $23.12/LF
jPACING70
$ 8.20/LF $12.30/LF $20.50/LF
CAST-IN-PLACE BEAM
FOR LL a 80 PSF
Table 4B. Cost comparison of prestressed 1-joists, steel beams and cast-
in-place concrete beams. (See Appendix for basic unit cost data.)
FABRICATION TOTALCOST
TYPE MATERIALS 8 ERECTION FIREPROOF IN-PLACE'
X
j1 S
SPAN: 40' $10 00/15 $10.75/LF $20.75/LF
ir
–I UI SPACING: 9-0
SPAN: 40' $17.15/LF $11.43/LF 6.85/LF $35.43/LF
j
W 18X55 BEAM
1' l:
, SCING:9'-0
SPAN 40' $12.54/LF $18.81/LF
CAST CE BEAM
FOR LL a 80 PSF
Table 4C. Cost comparison of prestressed I-joists, steel beams and cast-
in-place concrete beams. (See Appendix for basic unit cost data.)
FABRICATION TOTAL COST
TYPE MATERIALS 9 ERECTION FIREPROOF IN-PLACE
JM a
LS1SPAClNG:94
SPAN; 64'
$13.50/LF $21 50/LF $35 00/LF
04
SPACING: 9'-0°
M V SPAN: 64 $ II.70/LF $59.70/LF
$ 28.80/LF $19.20/LF
W 33X118 BEAM
9O"
"'I a .:. SPAN: 64'
$23.40/LF $35. 13/LF $58.53/LF
16°
CAST-IN-PLACE BEAM
Location Item Quantity Unit Price Cost Quantity Unit Price Cost
Total
Costs $2,545,500 $2,340,400
Total Savings $205,100
152
Table 6. In-place cost for various spans and different deck framing systems.
P1-PLACE COST PER SQUARE FOOT FOR VARIOUS SPANS
DECK FRAMING SYSTEMS FOR 80 PSF LL EXCLUSIVE OF SUPPORTING STRUCTURE (IN DOLLARS)
15 20' 25' 30 35 40 45' 50'
REINFORCED CONCRETE FLAT SLAB
VARIES 5" TO 9°
A - 3.52 4.32 5.27
I-W REINF.
DL: 63 TO 112 PSF
POST-TENSIONED FLAT PLATE
VARIES S TO 8-.
3.77 4.00 4.25 4.60
OL: 69 TO 94 PSF
COMPOSITE HOLLOW CORE SLAB
DL: 70 TO 96 PSF
REINFORCED CONCRETE PAN JOISTS
d ^ p 5.70 6.41
20°"
DU 67 PSF
COMPOSITE PRESTRESSED DOUBLE TEES
VARIES 41010 I
DL: 65 TO 79 PSF
PRESTRESSED RECTANGULAR JOISTS
j
VARIES 5 TO 10'
DL: 68 TO 80 PSF
Fig. 66. Framing with intermediate columns and framing with clear spans.
(See Appendix for basic unit cost data.)
154
tion of the building, there are some termediate columns.
instances where long spans will in- If the columns were 2 ft thick due
herently make the building more eco- to heavy upper multistory loads, the
nomical. efficiency of the structure will in-
For instance, in the case of parking crease by 11 percent with longer
garages, by utilizing clear spans of spans. Illustration of this garage park-
63 ft or more, double row perpendic- ing concept is shown in Fig. 66.
ular parking can be achieved without In the case of office buildings, in-
any interference by structural col- termediate columns located between
umns. In this manner, a parking ga- the central core and perimeter walls
rage can be more efficient so as to would mean less efficiency in floor
accommodate more cars per square utilization.
foot due to the absence of interme- An intermediate column would re-
diate columns of shorter span con- quire floor layouts that must circum-
struction. vent the column obstruction and thus
Assuming that 1-ft-wide columns result in less efficient floor area use.
are required at intervals of two car Shorter spans could also mean a
spaces, a clear span of 63 ft would considerable reduction in the flexi-
allow about 6 percent more cars in a bility of tenant area spacing in view
given area than if the spans were re- of limitations to required partitioning
duced to less than 63 ft to require in- and dividing locations.
200,000 200,000
*Construction Insurance
1,500,000 1,500,000
*Architect's Services
200,000 200,000
*Initial Leasing Expenses
3,000,000 3,000,000
*Value of Land
1,000,000 1,000,000
*Miscellaneous and Contingencies
$ 30,600,000 $ 30,600,000
Subtotal
$ 34,360,300 $ 898,200
Total Project Cash Cost (TPCC) $ 35,258,500
$ 36,092,600 $ 1,428,300
Total Project Cost $ 37,520.900
Assuming the building initial con- sume that land and construction
struction cost and maintenance costs costs were the same but construction
remain constant, the speed of con- by one method would be faster than
struction attainable by the use of pre- another method, the tabulated exam-
stressed and precast concrete repre- ple of Table 7 shows total cost differ-
sents a substantial impact on the ences realized by construction
economics of a building project. speed.
Considering the factors of land
acquisition costs, payments for legal, In addition to the above financing
architectural and engineering ser- cost differences, it should be noted
vices, construction financing, per- that with increased speed, benefits
manent financing, and the interest on toward savings in contractor's over-
monies required for various financing head, equipment rental time, man-
premiums, it can be determined that agement, etc., can become signifi-
the total cost of a building project is cant. From another viewpoint the
considerably influenced by the speed owner will realize more income from
of construction. his building during his lifetime if the
For instance, if one were to as- project is completed sooner.
Conclusion
156
References
APPENDIX
BASIC UNIT PRICES OF MATERIALS AND LABOR
USED FOR DEVELOPING COST FIGURES
(Hawaiian area, June 1976)
Materials
Ccncrete
3000 psi regular weight .......................... $ 39.40 per cu yd
4000 psi regular weight .......................... 42.85 per cu yd
5000 psi regular weight .......................... 46.85 per cu yd
6000 psi regular weight .......................... 52.65 per cu yd
4000 psi lightweight ............................. 47.80 per cu yd
5000 psi lightweight ............................. 57.75 per cu yd
6000 psi lightweight ............................. 59.10 per cu yd
Reinforcing steel (material only) ..................... 300 per ton
Reinforcing steel (material and installation)............ 600 per ton
1/2-in. diameter 270 prestressing steel (material only)... 0.105 per ft
1/2-in. diameter 270 prestressing steel (material and
installation) .................................. 0.13 per ft
Plywoodforms ................................... 0.385 per board ft
Formlumber ..................................... 0.285 per board ft
16-in, octagonal piles (material and installation)....... 16.00 per ft
Steel H-Pile HP 14x 117 (material and installation) ..... 40.00 per ft
Steel pipe pile 16 in. diameter (filled with concrete
material and installation) ....................... 60.00 per ft
Structural steel (material) ...................... 0.24 to 0.33 per lb
Structural steel (installation) .................... 0.16 to 0.22 per lb
Fireproofing (material and installation) ............... 1.25 per sq ft
Labor*
Commonlaborer ..................................$ 8.70 per hour
Carpenter(formwork) .............................. 9.76 per hour
Concreteworker .................................. 9.20 per hour
Ironworker(rebar) ................................ 11.10 per hour
Craneoperator ...................................12.29 per hour
* Includes fringe benefits.