0279stx-N-Wm-Pw01-Qa-Itp-0001-B01 Tank
0279stx-N-Wm-Pw01-Qa-Itp-0001-B01 Tank
Document
Tag No’s
(if applicable)
Contractor
H19201-PW01-QA-ITP-0001 Rev 01
Document No:
Seon 디지털 서명
자Seongjae Jo
DN: cn=Seongjae Jo,
o=Sae-A STX Entech,
Jo
ae-a.com, c=<없
날짜: 2022.07.25
09:51:48 +03'00'
Rev.
Para. Reason for Revision
No.
A01 All Issued for Review
Hold
Para. Description of Hold
No.
NR PWRI PHASE 1 – CONSTRUCTION INSPECTION
& TEST PLAN
Rev A01
BP Iraq NV
COMPANY
Points beyond which work shall not Proceed without formal approval
"H" – HOLD: by the appropriate Inspectorate .Achievement “H” point shall be
notified to the COMPANY by STX.
Remarks:
Page 1 of 17
0279STX-N-WM-PW01-QA-ITP-0001 .
NR PWRI PHASE 1 – CONSTRUCTION INSPECTION & TEST PLAN
Page 2 of 17
0279STX-N-WM-PW01-QA-ITP-0001 .B01
Rev. A02
NR PWRI PHASE 1 – CONSTRUCTION INSPECTION & TEST PLAN
0000BF-C-G0-G000-ME-SPC-0007
• Ensure all welded lugs and brackets for
Approved Drawing
erection purpose has been removed. API650
API 650
Ensure PT applied after Temporary 0000BF-C-G0-G000-
Internal Mechanical PT/MT Procedure (0279STX-N- Check List
attachment Removal ME-SPC-0007 H H S
18.0 Completion WM-PW01-QA-PRO-0007) PT/MT Report
• Ensure all the internal work has been ASME Sec VIII
completed as per approved drawings ,Appendix 6 &8
Page 4 of 17
0279STX-N-WM-PW01-QA-ITP-0001 .B01
Rev. A02
NR PWRI PHASE 1 – CONSTRUCTION INSPECTION & TEST PLAN
Page 5 of 17
0279STX-N-WM-PW01-QA-ITP-0001 .B01
Rev. A02
INSPECTION TEST PLAN FOR FABRICATION AND ERECTION OF TANKS
Name: Name:
Signature: Signature:
Date: Date:
Page 6 of 17
0279STX-N-WM-PW01-QA-ITP-0001 .B01
Rev
INSPECTION TEST PLAN FOR FABRICATION AND ERECTION OF TANKS
Drawing Joint NDE WPS No Welder Visual Inspection UT MPI/DPI RAD PWHT Comments
No Report No
No ACC REJ ACC REJ ACC REJ ACC REJ ACC REJ
Weld Categories P-Shop Weld F- Fillet Weld R1- First Repair R2- 2nd Repair RW-Re weld
STX REPRESENTATIVE: ROO/GCMC REPRESENTATIVE:
Name: Name:
Signature: Signature:
Date: Date:
Page 7 of 17
0279STX-N-WM-PW01-QA-ITP-0001 .B01
Rev
INSPECTION TEST PLAN FOR FABRICATION AND ERECTION OF TANKS
Description:
Plate No: Peaking & Banding Tolerance Actual Deviation Plate No: Peaking & Banding Tolerance Actual Deviation
Name: Name:
Signature: Signature:
Date: Date:
Page 8 of 17
0279STX-N-WM-PW01-QA-ITP-0001 .B01
Rev
INSPECTION TEST PLAN FOR FABRICATION AND ERECTION OF TANKS
No Check Tank height Not Exceed Tank Plumb ness Tank Tank Roundness Remarks
Points Course Up Point Down Deviation Radius Radius Actual Value
Point Tolerance Actual Radius Deviation
Observation/Comments:
Name: Name:
Signature: Signature:
Date: Date:
Page 9 of 17
0279STX-N-WM-PW01-QA-ITP-0001 .B01
Rev
INSPECTION TEST PLAN FOR FABRICATION AND ERECTION OF TANKS
Observation/Comments:
Name: Name:
Signature: Signature:
Date: Date:
Page 10 of 17
0279STX-N-WM-PW01-QA-ITP-0001 .B01
Rev
INSPECTION TEST PLAN FOR FABRICATION AND ERECTION OF TANKS
Test Medium
Inspection:
The Following Weld joints are inspected by injecting air and applying soap solution on weld
Observation/Comments
Name: Name:
Signature: Signature:
Date: Date:
Page 11 of 17
0279STX-N-WM-PW01-QA-ITP-0001 .B01
Rev
INSPECTION TEST PLAN FOR FABRICATION AND ERECTION OF TANKS
Test Medium
Inspection:
Observation/Comments:
Name: Name:
Signature: Signature:
Date: Date:
Page 12 of 17
0279STX-N-WM-PW01-QA-ITP-0001 .B01
Rev
INSPECTION TEST PLAN FOR FABRICATION AND ERECTION OF TANKS
Inspection:
No Water Leve Observed Settlement Value for Each position (mm)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
1 0% Height
2 25% Height
3 50% Height
4 75% Height
5 100% Height
6 Full of water
after 24 Hour
7 Empty of Test
water
Observation/Comments:
Name: Name:
Signature: Signature:
Date: Date:
Page 13 of 17
0279STX-N-WM-PW01-QA-ITP-0001 .B01
Rev
INSPECTION TEST PLAN FOR FABRICATION AND ERECTION OF TANKS
Name: Name:
Signature: Signature:
Date: Date:
Page 14 of 17
0279STX-N-WM-PW01-QA-ITP-0001 .B01
Rev
INSPECTION TEST PLAN FOR FABRICATION AND ERECTION OF TANKS
Drawing Number
Remarks:
Name: Name:
Signature: Signature:
Date: Date:
Page 15 of 17
0279STX-N-WM-PW01-QA-ITP-0001 .B01
Rev
INSPECTIONTEST PLAN FOR FABRICATION AND ERECTION OF TANKS
06 Leak Test (oil Test) have been completed inside root welding
of first course fillet joints
07 PT for finished welding 1st Course fillet joints
Page 16 of 17
0279STX-N-WM-PW01-QA-ITP-0001
.A01 Rev
INSPECTIONTEST PLAN FOR FABRICATION AND ERECTION OF TANKS
17 Base plate of Flare Line Supports have been Done and ACC
21 Base Plates of foam piping and fire water piping have been
welding with shell plates
Name: Name:
Signature: Signature:
Date: Date:
Page 17 of 17
0279STX-N-WM-PW01-QA-ITP-0001
.A01 Rev