5 - MIU-SWE 321-Spring 2024-Students
5 - MIU-SWE 321-Spring 2024-Students
Computer
Science
Software Project
Management
(SWE 321)
=
‘Crashing’
Reducing task
durations by
increased costs
5 (1)
2 6(3)
3
1
5(0)
4(0) 3(0)
5 (1)
2 6(3)
3
1
5(0)
If we used all 4 days, then path 1-2-3 has
(5-1) + (6-3) = 7 completion weeks
Now, we need to check if the completion time for path 1-3 has
lesser than 7 weeks (why?)
Now, path 1-3 has (5-0) = 5 weeks
Since path 1-3 still shorter than 7 weeks, we used up all 4 crashed
weeks
Example – crashing (1)
5 (1)
2 6(3)
3
1
8(0)
Such as
5 (1)
2 6(3)
3
1
8(0)
Now, we cannot use all 4 days (Why?)
Because path 1-2-3 will not be critical path anymore as
path 1-3 would now has longest hour to finish
Example – crashing (1)
Such as
5 (1)
2 6(3)
3
1
8(0)
Now, we cannot use all 4 days (Why?)
Because path 1-2-3 will not be critical path anymore as
path 1-3 would now has longest hour to finish
Rule: When a path is a critical path, it will not stay as a
critical path.
So, we can only reduce the path 1-2-3 completion time to the
same time as path 1-3. (HOW?)
Example – crashing (1)
Solution:
5 (1)
2 6(3)
3
1
8(0)
We can only reduce total time for path 1-2-3 = path 1-3, that is 8
weeks
If the cost for path 1-2 and path 2-3 is the same then.
Example – crashing (1)
Solution:
5 (1)
2 6(3)
3
1
8(0)
We can only reduce total time for path 1-2-3 = path 1-3, that is 8
weeks
If the cost for path 1-2 and path 2-3 is the same then.
OR 3(0)
5 (1) 6(3)
2
1
3
8(0)
Now, paths 1-2-3 and 1-3 are both critical paths
Procedure for crashing
1. Crash one time unit at a time
2. Only crashing critical path activities has any effect
on Total Project Time
3. Crash first the activity that is the cheapest to
reduce in time
4. Be aware of multiple critical paths
5. Stop crashing when:
• the crash-time is reached at every activity,
• benefits of possible crashing are lower than crashing
costs.
Example – crashing (2) Crashing
table
Activity Duration Crash Cost-slope
(label) (day) time (€/day)
a 4 2 100
b 2 1 150
c 2 1 110
d 5 3 200
e 2 1 160
f 3 2 500
a b f
6 11
a b f
6 11
300 €/day
Example – crashing (2) Crashing
Solution method table
Activity Duration Float Crash Cost-slope
(label) (day) (day) time (€/day)
a 4 0 2 100
b 2 0 1 150
c 2 1 1 110
d 5 0 3 200
e 2 1 1 160
f 3 0 2 500
Benefit of reducing TPT by one day: 400 €/day
250 €/day
Example – crashing (2) Crashing
Solution method table
Activity Duration Float Crash Cost-slope
(label) (day) (day) time (€/day)
a 4 0 2 100
b 2 0 1 150
c 2 1 1 110
d 5 0 3 200
e 2 1 1 160
f 3 0 2 500
Benefit of reducing TPT by one day: 400 €/day
200 €/day
Example – crashing (2) Crashing
Solution method table
Activity Duration Float Crash Cost-slope
(label) (day) (day) time (€/day)
a 4 0 2 100
b 2 0 1 150
c 2 1 1 110
d 5 0 3 200
X
e 2 1 1 160
f 3 0 2 500
Benefit of reducing TPT by one day: 400 €/day
-100 €/day
Example – crashing (2) Crashing
Solution method table
Activity Duration Float Crash Cost-slope
(label) (day) (day) time (€/day)
a 4 0 2 100
b 2 0 1 150
c 2 1 1 110
d 5 0 3 200
e 2 1 1 160
f 3 0 2 500
Benefit of reducing TPT by one day: 400 €/day
300 €/day
Solution method
Step 1: identify the critical activities
Step 2: find the critical activity with cheapest crash
cost, and if its cost slope is lower than the
daily benefit from crashing, reduce its
duration with one day. If there is no activity
to crash, or it is too costly, stop crashing
and go to step 4.
Step 3: reidentify the critical path, and go back to
step two.
Step 4: identify the newest critical path, TPT and
the total net benefit of crashing.
Example – crashing (2) 6 8 8 10
e
c
11 14
0 4 4 6
a b f
6 11
d
Example – crashing (2) 6 8 8 10
e
c
7 9
5 7 11 14
0 4 4 6
a b f
6 11
0 3 10 13
3 5
d
5 10
a-b-d-f 14 13
Solution
Pathdurations
Path durations
Path / normal
normal step 11 step
step step 22 step 33
step step 44
step step 55
step
Path / activity
activity
crached
crashed – a
a-b-c-e-f 13 12
a-b-d-f 14 13
Cost: Cost: 100
–
300
Cumulated net
Cumulated
benefit: – 300
net benefit:
After crashing:
– there is one critical path and TPT is 13 days
– total benefit of crashing is €300
Example – crashing (2) 6 8 8 10
e
c
6 8
4 6 11 14
0 4 4 6
a b f
6 11
0 2 9 12
2 4
d
4 9
a-b-d-f 14 13 12
Solution
Pathdurations
Path durations
Path / normal
normal step 11 step
step step 22 step 33
step step 44
step step 55
step
Path / activity
activity
crached
crashed – a a
a-b-c-e-f 13 12 11
a-b-d-f 14 13 12
Cost: Cost: 100 100
–
300 300
Cumulated net
Cumulated
benefit: – 300 600
net benefit:
After crashing:
– there is one critical path and TPT is 12 days
– total benefit of crashing is €600
Example – crashing (2) 6 8 8 10
e
c
5 7
3 5 11 14
0 4 4 6
a b f
6 11
0 2 8 11
2 3
d
3 8
a-b-d-f 14 13 12 11
Solution
Pathdurations
Path durations
Path / normal
normal step 11 step
step step 22 step 33
step step 44
step step 55
step
Path / activity
activity
crached
crashed – a a b
a-b-c-e-f 13 12 11 10
a-b-d-f 14 13 12 11
Cost: Cost: 100 100 150
–
300 300 250
Cumulated net
Cumulated
benefit: – 300 600 850
net benefit:
After crashing:
– there is one critical path and TPT is 11 days
– total benefit of crashing is €850
Example – crashing (2) 6 8 8 10
e
c
5 7
3 5 11 14
0 4 4 6
a b f
6 11
0 2 7 10
2 3
d
3 7
a-b-d-f 14 13 12 11 10
Solution
Pathdurations
Path durations
Path / normal
normal step 11 step
step step 22 step 33
step step 44
step step 55
step
Path / activity
activity
crached
crashed – a a b d
a-b-c-e-f 13 12 11 10 10
a-b-d-f 14 13 12 11 10
Cost: Cost: 100 100 150 200
–
300 300 250 200
Cumulated net
Cumulated
benefit: – 300 600 850 1050
net benefit:
After crashing:
– there are two critical paths and TPT is 10 days
– total benefit of crashing is €1050
Example – crashing (2) Solution method
Step 1: identify the critical activities
Step 2: find the critical activity with cheapest crash
cost, and if its cost slope is lower than the
daily benefit from crashing, reduce its
duration with one day. If there is no activity
to crash, or it is too costly, stop crashing
and go to step 4.
Step 3: reidentify the critical path, and go back to
step two.
Step 4: identify the newest critical path, TPT and
the total net benefit of crashing.
Example – crashing (2) 6 8 8 10
e
c
5 7
3 5 11 14
0 4 4 6
a b f
6 11
0 2 7 10
2 3
d
3 7
a b f
6 11
0 2 7 10
2 3
d
3 7
a b f
6 11
0 2 7 10
2 3
d
3 7
a b f
6 11
0 2 6 9
2 3
d
3 6
a-b-d-f 14 13 12 11 10 9
Solution
Pathdurations
Path durations
Path / normal
N. Stepstep 1
Step step
Step2 Step
step 3StepstepStep
4 step 5
Step
Path / activity
activity 1 2 3 4 5 6 7
crached
crashed – a a b d d,c
a-b-c-e-f 13 12 11 10 10 9
a-b-d-f 14 13 12 11 10 9
Cost:
Cost: 100 100 150 200 310
–
Cumulated net 300 300 250 200 90
benefit:
Cumulated
– 300 600 800 1050 1140
net benefit:
After crashing:
– there are two critical paths and TPT is 9 days
– total benefit of crashing is €1140
Example – crashing (2) 6 8 8 10
e
c
4 5
3 4 11 14
0 4 4 6
a b f
6 11
0 2 5 8
2 3
d
3 5
Path / normal
N. Stepstep 1
Step step
Step2 Step
step 3StepstepStep
4 step 5
Step
Path / activity
activity 1 2 3 4 5 6 7
crached
crashed – a a b d d,c d,e
a-b-c-e-f 13 12 11 10 10 9 8
a-b-d-f 14 13 12 11 10 9 8
Cost:
Cost: 100 100 150 200 310 360
–
Cumulated net 300 300 250 200 90 40
benefit:
Cumulated
– 300 600 800 1050 1140 1180
net benefit:
After crashing:
– there are two critical paths and TPT is 8 days
– total benefit of crashing is €1180
Example – crashing (2) 6 8 8 10
e
c
4 5
3 4 11 14
0 4 4 6
a b f
6 11
0 2 5 7
2 3
d
3 5
Path / normal
N. Stepstep 1
Step step
Step2 Step
step 3StepstepStep
4 step
Step5
Path / activity
activity 1 2 3 4 5 6 7
crached
crashed – a a b d d,c d,e f
a-b-c-e-f 13 12 11 10 10 9 8 7
a-b-d-f 14 13 12 11 10 9 8 7
Cost:
Cost: 100 100 150 200 310 350 500
–
300 300 250 200 90 50 -100
X
Cumulated net
benefit:
Cumulated
– 300 600 800 1050 1140 1180 1080
net benefit:
After crashing:
– there are two critical paths and TPT is 7 days
– total benefit of crashing is €1080
Solution
Pathdurations
Path durations
Path / normal
N. Stepstep 1
Step step
Step2 Step
step 3StepstepStep
4 step 5
Path / activity Stop
activity 1 2 3 4 5 6
crached
crashed – a a b d d,c d,e
a-b-c-e-f 13 12 11 10 10 9 8
a-b-d-f 14 13 12 11 10 9 8
Stop
Cost:
Cost: 100 100 150 200 310 360
–
Cumulated net 300 300 250 200 90 40
benefit:
Cumulated
– 300 600 800 1050 1140 1180
net benefit:
After crashing:
– there are two critical paths and TPT is 8 days
– total benefit of crashing is €1180
Example – crashing (3) Reducing the Time of a
Project (crashing)
Immediate Durat
Activity Description
Predecessor (week
A Develop product specifications None 4
B Design manufacturing process A 6
C Source & purchase materials A 3
D Source & purchase tooling & equipment B 6
E Receive & install tooling & equipment D 14
F Receive materials C 5
G Pilot production run E&F 2
H Evaluate product design G 2
I Evaluate process performance G 3
J Write documentation report H&I 4
K Transition to manufacturing J 2
Example – crashing (3) Reducing the Time of a
Project (crashing)
Example – crashing (3) Reducing the Time of a
Project (crashing)
Example – crashing (3) Reducing the Time of a
Project (crashing)
Normal Time Normal Cost Crash Cost
Activity Crash Time
(wk) ($) ($)
A 4 8,000 3 11,000
B 6 30,000 5 35,000
C 3 6,000 3 6,000
D 4 24,000 2 28,000
E 14 60,000 12 72,000
F 5 5,000 4 6,500
G 2 6,000 2 6,000
H 2 4,000 2 4,000
I 3 4,000 2 5,000
J 4 4,000 2 6,400
K 2 5,000 2 5,000
Example – crashing (3) Reducing the Time of a
Project (crashing)
Normal
Normal Crash Crash Max. weeks Reduce cost
Activity Time
Cost ($) Time Cost ($) of reduction per week
(wk)
A 4 8,000 3 11,000 1
B 6 30,000 5 35,000
C 3 6,000 3 6,000
D 4 24,000 2 28,000
E 14 60,000 12 72,000
F 5 5,000 4 6,500
G 2 6,000 2 6,000
H 2 4,000 2 4,000
I 3 4,000 2 5,000
J 4 4,000 2 6,400
K 2 5,000 2 5,000
Example – crashing (3) Reducing the Time of a
Project (crashing)
Normal
Normal Crash Crash Max. weeks Reduce cost
Activity Time
Cost ($) Time Cost ($) of reduction per week
(wk)
A 4 8,000 3 11,000 1
B 6 30,000 5 35,000 1
C 3 6,000 3 6,000 0
D 4 24,000 2 28,000 2
E 14 60,000 12 72,000 2
F 5 5,000 4 6,500 1
G 2 6,000 2 6,000 0
H 2 4,000 2 4,000 0
I 3 4,000 2 5,000 1
J 4 4,000 2 6,400 2
K 2 5,000 2 5,000 0
Example – crashing (3) Reducing the Time of a
Project (crashing)
Normal Time Normal Cost Crash Cost
Activity Crash Time
(wk) ($) ($)
A 4 8,000 3 11,000
B 6 30,000 5 35,000
C 3 6,000 3 6,000
D 4 24,000 2 28,000
E 14 60,000 12 72,000
F 5 5,000 4 6,500
G 2 6,000 2 6,000
H 2 4,000 2 4,000
I 3 4,000 2 5,000
J 4 4,000 2 6,400
K 2 5,000 2 5,000
Example – crashing (3) Reducing the Time of a
Project (crashing)
Normal
Normal Crash Crash Max. weeks Reduce cost
Activity Time
Cost ($) Time Cost ($) of reduction per week
(wk)
A 4 8,000 3 11,000 1 3,000
B 6 30,000 5 35,000 1
C 3 6,000 3 6,000 0
D 4 24,000 2 28,000 2
E 14 60,000 12 72,000 2
F 5 5,000 4 6,500 1
G 2 6,000 2 6,000 0
H 2 4,000 2 4,000 0
I 3 4,000 2 5,000 1
J 4 4,000 2 6,400 2
K 2 5,000 2 5,000 0
Example – crashing (3) Reducing the Time of a
Project (crashing)
Normal
Normal Crash Crash Max. weeks Reduce cost
Activity Time
Cost ($) Time Cost ($) of reduction per week
(wk)
A 4 8,000 3 11,000 1 3,000
B 6 30,000 5 35,000 1 5,000
C 3 6,000 3 6,000 0 0
D 4 24,000 2 28,000 2 2,000
E 14 60,000 12 72,000 2 6,000
F 5 5,000 4 6,500 1 1500
G 2 6,000 2 6,000 0 0
H 2 4,000 2 4,000 0 0
I 3 4,000 2 5,000 1 1,000
J 4 4,000 2 6,400 2 1,200
K 2 5,000 2 5,000 0 0
Example – crashing (3) Reducing the Time of a
Project (crashing)
Normal
Normal Crash Crash Max. weeks Reduce cost
Activity Time
Cost ($) Time Cost ($) of reduction per week
(wk)
A 4 8,000 3 11,000 1 3,000
B 6 30,000 5 35,000 1 5,000
C 3 6,000 3 6,000 0 0
D 4 24,000 2 28,000 2 2,000
E 14 60,000 12 72,000 2 6,000
F 5 5,000 4 6,500 1 1500
G 2 6,000 2 6,000 0 0
H 2 4,000 2 4,000 0 0
I 3 4,000 2 5,000 1 1,000
J 4 4,000 2 6,400 2 1,200
K 2 5,000 2 5,000 0 0
Example – crashing (3) Reducing the Time of a
Project (crashing)
Max. Reduce
Activity weeks of cost per
reduction week
A 1 3,000
B 1 5,000
C 0 0
D 2 2,000
E 2 6,000
F 1 1500
G 0 0
H 0 0
I 1 1,000
J 2 1,200
K 0 0
Example – crashing (3) Reducing the Time of a
Project (crashing)
Max. Reduce
Activity weeks of cost per
reduction week
A 1 3,000
B 1 5,000
C 0 0
D 2 2,000
E 2 6,000
F 1 1500
G 0 0
H 0 0
I 1 1,000
J 2 1,200
K 0 0
Example – crashing (3) Reducing the Time of a
Project (crashing)
Max. Reduce
Activity
A
weeks of
reduction
1
cost per
week
3,000
X
B 1 5,000
C 0 0
D 2 2,000
E 2 6,000
F 1 1500
G 0 0
H 0 0
I 1 1,000
J 2 1,200
K 0 0
Example – crashing (3) Reducing the Time of a
Project (crashing)
Max. Reduce
Activity
A
weeks of
reduction
1
cost per
week
3,000
X
B 1 5,000
C 0 0
D 2 2,000
E 2 6,000
F 1 1500
G 0 0
H 0 0
I 1 1,000
J 2 1,200
K 0 0
Example – crashing (3) Reducing the Time of a
Project (crashing)
Max. Reduce
Activity weeks of cost per
reduction week
A 1 3,000
B 1 5,000
C 0 0
D 2 2,000
E 2 6,000
F 1 1500
G 0 0
H 0 0
I 1 1,000
J 2 1,200 2
K 0 0 2400
Example – crashing (3) Reducing the Time of a
Project (crashing)
Max. Reduce
Activity weeks of cost per
reduction week
A 1 3,000
B 1 5,000
C 0 0
D 2 2,000
E 2 6,000
F 1 1500
G 0 0
H 0 0
I 1 1,000
J 2 1,200
K 0 0
Example – crashing (3) Reducing the Time of a
Project (crashing)
Max. Reduce
Activity weeks of cost per 4 + 6 + 4 + 14 = 28
reduction week
A 1 3,000
B 1 5,000
C 0 0
D 2 2,000
E 2 6,000
F 1 1500
G 0 0
H 0 0
I 1 1,000
J 2 1,200
K 0 0
Example – crashing (3) Reducing the Time of a
Project (crashing)
Max. Reduce
Activity weeks of cost per 4 + 6 + 4 + 14 = 28
reduction week
A 1 3,000
B 1 5,000
C 0 0
D 2 2,000
E 2 6,000
F 1 1500
G 0 0
H 0 0 4 + 3 + 5 = 12
I 1 1,000
J 2 1,200
K 0 0
Example – crashing (3) Reducing the Time of a
Project (crashing)
Max. Reduce
Activity weeks of cost per 4 + 6 + 4 + 14 = 28 16
reduction week
A 1 3,000
B 1 5,000
C 0 0
D 2 2,000
E 2 6,000
F 1 1500
G 0 0
H 0 0 4 + 3 + 5 = 12
I 1 1,000
J 2 1,200
K 0 0
Example – crashing (3) Reducing the Time of a
Project (crashing)
Max. Reduce
Activity weeks of cost per 4 + 6 + 4 + 14 = 28 16
reduction week
A 1 3,000
B 1 5,000
C 0 0
D 2 2,000
E 2 6,000
F 1 1500
G 0 0
H 0 0 4 + 3 + 5 = 12
I 1 1,000
J 2 1,200
K 0 0
Example – crashing (3) Reducing the Time of a
Project (crashing)
Max. Reduce
Activity weeks of cost per 4 + 6 + 4 + 14 = 28 16
reduction week
A 1 3,000
B 1 5,000
C 0 0
D 2 2,000
E 2 6,000
F 1 1500
G 0 0
H 0 0 4 + 3 + 5 = 12
I 1 1,000
J 2 1,200
K 0 0
Example – crashing (3) Reducing the Time of a
Project (crashing)
Max. Reduce
Activity weeks of cost per 4 + 6 + 4 + 14 = 28 16
reduction week
A 1 3,000
B 1 5,000
C 0 0
D 2 2,000
E 2 6,000
F 1 1500
G 0 0
H 0 0 4 + 3 + 5 = 12
I 1 1,000
J 2 1,200
K 0 0
Example – crashing (3) Reducing the Time of a
Project (crashing)
Max. Reduce
Activity weeks of cost per 4 + 6 + 4 + 14 = 28 16
reduction week
A 1 3,000
B 1 5,000
C 0 0
D 2 2,000
E 2 6,000
F 1 1500
G 0 0
H 0 0 4 + 3 + 5 = 12
I 1 1,000 5
J 2 1,200 21000
K 0 0
2400
23400
Example – crashing (3) Reducing the Time of a
Project (crashing)
Max. Reduce
Activity weeks of cost per
reduction week
A 1 3,000
B 1 5,000
C 0 0
D 2 2,000
E 2 6,000
F 1 1500
G 0 0
H 0 0
I 1 1,000 1
J 2 1,200 3000
K 0 0
23400
26400
Example – crashing (3) Reducing the Time of a
Project (crashing)
1 2 2
1 2
36 – 8 = 28 weeks
Example – crashing (3) Reducing the Time of a
Project (crashing)
1 2 2
1 2
1 2
1 2
1 2
X X
X 1 2
• TPT = 36 – 4 = 32 weeks
• Total crashing cost = 2400 + 4000 = 6400 ($)
Example – crashing (3) Reducing the Time of a
Project (crashing)
1 2 2
X X
X 1 2
10000-6400
X X
1 2
• TPT = 36 – 5 = 31 weeks
• Total crashing cost = 6400 + 3000 = 9400 ($)
Example – crashing (3) Reducing the Time of a
Project (crashing)
1 2 2
X X
1 2
12500-9400
X
1 2
• TPT = 36 – 6 = 30 weeks
• Total crashing cost = 9400 + 5000 = 13400 ($)
Example – crashing (3) Reducing the Time of a
Project (crashing)
1 2 2
X
1 2
15000-13400
1 2
• TPT = 36 – 7 = 29 weeks
• Total crashing cost = 13400 + 6000 = 19400 ($)
Example – crashing (3) Reducing the Time of a
Project (crashing)
1 2 1
1 2
17500-19400
• TPT = 36 – 6 = 30 weeks
A, B, D and F.
Example – crashing (4) Reducing the Time of a
Project (crashing)
A, B, D and F.
A, C, E, G and H.
Example – crashing (4) Reducing the Time of a
Project (crashing)
A, B, D and F.
A, C, E, G and H.
A, B, D and F.
A, C, E, G and H.
• Given that the normal time of activity A is 4 weeks while its crash
time is 3 weeks.
• The normal cost of this activity is LE. 8,000 whereas the crash cost
is LE. 9,000.
• From this, we see that crashing of activity A by one week will cost
the management an extra amount of LE. 1,000.
• In a similar way, we can work out the crash cost per unit time for
the other activities also.
Example – crashing (4) Reducing the Time of a
Project (crashing)
Example – crashing (4) Reducing the Time of a
Project (crashing)
Example – crashing (4) Reducing the Time of a
Project (crashing)
X
3 3
Result
• Reduce the time of A, C and E by one week each.
• Project time after crashing is 22 weeks.
• Extra amount required = 1,000 + 1,000 + 1,000 =
= 3,000 LE
Example – crashing (5) Reducing the Time of a
Project (crashing)
The network and table given below summarize the time-cost
information for the activities. The owner wants to finish the project
in 110 days. Find the minimum possible cost for the project if you
want to finish it on 110 days.
Example – crashing (5) Reducing the Time of a
Project (crashing)
The network and table given below summarize the time-cost
information for the activities. The owner wants to finish the project
in 110 days. Find the minimum possible cost for the project if you
want to finish it on 110 days.
Example – crashing (5) Reducing the Time of a
Project (crashing)
The network and table given below summarize the time-cost
information for the activities. The owner wants to finish the project
in 110 days. Find the minimum possible cost for the project if you
want to finish it on 110 days.
20 days $100/day
5 days $200/day
10 days $600/day
10 days $60/day
10 days $120/day
15 days $300/day
Example – crashing (5) Reducing the Time of a
Project (crashing)
• A = 120 days
• B-C-D-E = 140 days
• B-F-E = 130 days
• The normal cost for the project = $48300
• The normal duration = 140 days.
• Critical path = B-C-D-E
Example – crashing (5) Reducing the Time of a
Project (crashing)
140 days
130 days
Example – crashing (5) Reducing the Time of a
Project (crashing)
130 days
120 days
Example – crashing (5) Reducing the Time of a
Project (crashing)
120 days
• Crashing the activity E by 10 days (120 * 10 = $1200).
• The project duration is now 120 days
• The total project cost is $50100 (48300+600+1200).
• There are now three critical paths (A, B-C-D-E, and B-F-E).
Example – crashing (5) Reducing the Time of a
Project (crashing)
120 days
115 days
120 days
120 days
Example – crashing (5) Reducing the Time of a
Project (crashing)
115 days
• Activity A is paired with each of the other activities to determine
which has the least overall cost slope for those activities which
have remaining days to be crashed.
115 days
• Activity A is paired with each of the other activities to determine
which has the least overall cost slope for those activities which
have remaining days to be crashed.
• Activity A ($100) + activity C ($600) + activity F ($300)
• = 1000
Example – crashing (5) Reducing the Time of a
Project (crashing)
115 days
• The total project cost for the crashed schedule to 110 days of
duration would be $56600.
• $48300 + $600 + $1200 + $1500 + $5000
2-5 2 225
1-2 3 50
4-6 2 125
2 X 50
2 x 125
Example – crashing (6)
Critical Paths:
1-2-5-7 : Project completion 16 weeks
1-4-6-7 : Project completion 16 weeks
Example – crashing (6)
= 10,100
– (2 x 200)
$ 50 + (2 x 50) + (2 x125)
= $ 10,050
Critical Paths:
Example – crashing (6) 1-2-5-7 : Project completion 16 weeks
1-4-6-7 : Project completion 16 weeks
Parallel Crashing
2-5 2 225
1-2 1 50
4-6
X 2 125
Critical Paths:
Example – crashing (6) 1-2-5-7 : Project completion 16 weeks
1-4-6-7 : Project completion 16 weeks
Parallel Crashing
1 x 50
1 x 200
Example – crashing (6)
= 10,050
– (1 x 200)
+ (1 x 50) + (1 x 200)
= $ 10,100
Example – crashing (6)