EMC Testing - Part 2 - Conducted Emissions
EMC Testing - Part 2 - Conducted Emissions
2 Conducted emissions
Part 0 of this series [1] described the various types of EMC test that might be carried out, including:
A different type of current probe is the Rogowski coil, basically a single-turn loop around the conductor whose
current is to be measured. Their frequency response is not the highest, but they can be used to measure currents
of thousands of Amps up to 1MHz, so can be very useful in power generation and heavy power applications
where other transducers can’t cope. Figure 2 shows a commercially available product based on this technology.
A LISN couples the interference from the EUT connection to the measuring equipment and at the same time
presents a stable and well-defined impedance to the EUT across the desired frequency range. The actual
measured voltage depends on the ratio of the EUT’s source impedance and the LISN’s load impedance, so if the
impedance were not stabilised, there would be no repeatability between different test locations. CISPR defines
the LISN and its impedance for some different classes of network: the most common one is shown in Figure 6
and is known as the “50ȍ/50μH+5ȍ” network, since the impedance curve is determined by these values.
Figure 7 shows that its frequency response is defined down to 9kHz and a fully compliant LISN will stay within
the specified tolerance of ±20% of this curve whatever the termination at the mains side of the unit. This is
easily achieved across most of the frequency range, but poorly designed units can exceed the specification
below 50kHz or above 25MHz. Figure 7 also shows the impedance curve for a different type of LISN, a
“50ȍ/5μH+1ȍ” network that is sometimes specified where currents are very high.
x For the 50μH inductor, follow the construction shown in Figure 9 (taken from [4]) an example of which is
given in Figure 10.
x Use a number of large-value safety-rated capacitors (preferably Y1 rated) in parallel for the 8μF parts, and
low-inductance resistors (not wire-wound types) for the 5ȍ. Keep all lead lengths very short and use the
chassis of the unit as the earth connection for the schematic, rather than any earth wires. Any unavoidable
wired earth connections (e.g. from the earth pin of the EUT mains socket to the chassis must be no longer
than 50mm and should use braid straps or metal plates at least 10mm wide.
x For the general assembly of the LISN follow the sketch of Figure 11 (taken from [3]).
2.1.10 ISNs
Impedance Stabilising Networks (ISNs) are often broadly similar in design and construction to LISNs and are
used to make conducted emissions measurements on signal and data cables. Like LISNs, they are invasive
transducers which must be connected in series with the conductors to be measured to standardise their CM and
DM impedances. ISNs differ from LISNs in that they are designed to measure CM conducted emissions. Also,
whereas LISNs create an impedance of 50ȍ, ISNs create an impedance of 150ȍ because this is thought to more
closely match the real impedances of signal and data cables.
Figure 13 shows an example of an ISN taken from the 1998 issue of EN 55022. This ISN design is very similar
to the coupling-decoupling networks (CDNs) specified by the conducted immunity test IEC 61000-4-6, and in
fact it may be possible to use these CDNs as ISNs in some cases. Several other types of ISNs are specified in
this standard, not all of which use a similar circuit.
The full testing method is described below and should be followed as far as is needed for the accuracy required
when pre-compliance testing. More detailed advice on pre-compliance conducted measurements using a
spectrum analyser can be found in [8].
x Take an ambient scan with the EUT switched off. Create a list of ambients.
x With the EUT switched on and operating, take a peak detector sweep with a reasonably fast scan speed,
taking into account the EUT’s cycle time, to create a list of significant emission frequencies. Subtract
known ambients from this list, leaving a list of ‘suspects’.
x Test the suspect frequencies individually using the quasi-peak and average detectors as required to make the
comparison with the limits in the relevant standard, modifying the EUT’s operation to maximise the
emissions if this is relevant.
x It is a good idea to recheck the ambients from time-to-time during a test to make sure that new ambient
sources (such as someone using an electric drill nearby) aren’t being mistaken for EUT emissions.
This procedure is repeated for all the mains phases at each location to be measured.
The factors outside the EUT that control the coupling, and hence the measured value, are:
x Bandwidth
x Detectors
x Overload performance and pulse accuracy
x Input VSWR and sensitivity
– and they are equally applicable to the radiated measurements described in Part 1 of this series [1] as they are
to the conducted tests being described in this part.
If an interference signal spectrum is wider than the bandwidth of the instrument which measures it, then the
indicated value will depend on that bandwidth. If it is narrower, then the indicated value is independent of
bandwidth. This is the basis of the distinction between “narrowband” and “broadband” interference. If you are
measuring known radio signals then you can tailor the measurement bandwidth to the characteristics of the
signal, but this is not possible for EMC measurements, since the characteristic of the interference is almost by
definition not known in advance. Therefore the measuring receiver specification must include a defined value
not only for the bandwidth, but for the shape of the filter that determines this bandwidth. This specification is
given in Figure 19.
The quasi-peak detector weights the indicated value in terms of its perceived “annoyance factor”: low pulse
repetition frequencies (PRF) are less annoying when experienced on broadcast radio and TV channels than high
PRFs. The detector is specified in terms of its attack and decay time constants, and these are fairly
straightforward to implement. The average detector simply returns the average value rather than the peak value
of the interference with which it is presented. This can in principle be achieved with a simple low-pass filter
whose time constant is slower than the slowest pulse repetition frequency of the input.
The difficulty which faces designers of measuring receivers is that to give an accurate measure of the actual
quasi-peak or average level of low PRF interference, the linear dynamic range of the RF circuits before the
detector, and of the detector itself, must be at least equal to the dynamic range of the desired pulse weighting if
2.8 References
[1] “EMC Testing Part 1 – Radiated Emissions” Keith Armstrong and Tim Williams, EMC + Compliance
Journal February 2001, pages 27-39, can be read and downloaded from the Publications & Downloads
pages at www.cherryclough.com.
[2] “The measurement of emissions (methods and instrumentation)” R. W. Gubisch, Compliance
Engineering European Edition, January/February 1998, Pages 46-55, (part 2 of a series of 7 articles on
EMC testing).
[3] “Calibration and use of artificial mains networks and absorbing clamps (Application of transducers for
CISPR-based emissions measurements)” Tim Williams and Geoff Orford, DTI-NMSPU Project FF2.6
report, April 1999. May be available from the EMCTLA – see [10] below.
[4] “Proposed new CSA standard C108.1.5, Line Impedance Stabilising Network (LISN)” Canadian
Standards Authority (CSA), C108.1.5, 4th draft, June 1984.
[5] “Design techniques for EMC – Part 3: Filters and surge protection devices” Keith Armstrong, the UK
EMC Journal, June 1999, pages 9-15, can be read and downloaded from the Publications & Downloads
pages at www.cherryclough.com..
[6] “EMC for systems and installations” Tim Williams and Keith Armstrong, Newnes, January 2000, ISBN
0-7506-4167-3 (available from RS and Farnell).
[7] “An alternate, complementary method for characterising EMI filters” Michel Mardiguian and Joel
Raimbourg, IEEE EMC Symposium, Seattle 1999, Volume 2, pages 882-886.
[8] “Cookbook for EMC pre-compliance measurements” Application Note 1290-1, Agilent Technologies
(previously Hewlett Packard).
[9] “Making radiated and conducted compliance measurements with EMI receivers” Application Note
1302, Agilent Technologies (previously Hewlett Packard).
[10] “EMCTLA Technical Guidance Note #42 – Emissions tests on telecom ports as per CIPSR22 (EN
55022)” plus it’s “Addendum 1”, Tim Williams, EMC Test Labs Association, P.O. Box 129, Romsey,
SO51 6ZT, UK. www.emctla.co.uk