Proposed Level-2 Schedule

The document provides a revised milestone schedule for the construction of the FDC Misamis 3x135MW CFB coal-fired power plant. It lists activities from A to J with estimated start and finish dates for each sub-activity ranging from August 2024 to September 2026.

Uploaded by

Danilo Magisa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
16 views

Proposed Level-2 Schedule

The document provides a revised milestone schedule for the construction of the FDC Misamis 3x135MW CFB coal-fired power plant. It lists activities from A to J with estimated start and finish dates for each sub-activity ranging from August 2024 to September 2026.

Uploaded by

Danilo Magisa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 2

FDC Misamis 3x135MW CFB coal-fired power plant

Revised Milestone Schedule as of Oct. 5, 2013


Activity Original
Activity Name start finish
ID duration
Unit 1 Milestone
A NOTIFICATION TO COMMENCE 1 01 Jul 24
B TEMPORARY FACILITIES
B.1 Site Office 90 01 Aug 24 31 Oct 24
B.2 Accommodation 150 01 Aug 24 31 Dec 24
C. BOILER STRUCTURE 01 Sep 24 31 May 26
C-1 Modification of Existing Ash Yard Portion 01 Aug 24 31 Aug 24
C-2 Pile Driving 90 01 Sep 24 30 Nov 24
C-3 Foundation 120 01 Dec 24 31 Mar 25
C-4 Steel Structure 01 Apr 25 30 Apr 26
C-5 Temporary Beaching Ramp for Steam Drum 01 Jan 25 31 Mar 25
C-6 Temporary Access Road for Steam Drum 01 Oct 24 31 Dec 24
C-7 Lifting of Steam Drum 30 Jun 25
C-8 Mechanical 01 May 25 31 Mar 26
C-9 Piping 01 Jun 25 31 Mar 26
C-10 Electrical & instrumentation 01 May 25 31 May 26
C-11 Architectural 01 Dec 25 30 Apr 26
C-12 Chemical Cleaning 01 Apr 26 30 Apr 26
C-13 Ignition & Steam Blowing 31 May 26
D. TURBINE & COAL BUNKER BAY 01 Sep 24 30 Jun 26
D-1 Pile Driving 01 Sep 24 30 Nov 24
D-2 Turbine & Generator Foundation 01 Dec 24 30 Apr 25
D-3 Turbine Hall Foundation 01 Feb 25 31 May 25
D-4 Steel Structure 01 Jun 25 31 Oct 25
D-5 Mechanical 01 Jun 25 31 May 26
D-6 Turbine Bedplate In-Place 30 Nov 25
D-7 Turbine Cylinder Cover 01 Mar 26
D-8 Piping 01 Nov 25 31 May 26
D-9 Electrical & Instrumentation 01 Nov 25 30 Apr 26
D-10 Architectural 01 Aug 25 28 Feb 26
D-11 Turbine Run-Up 30 Jun 26
E. SWITCHYARD 01 Mar 25 30 Sep 25
E-1 Site Development 01 Mar 25 31 Mar 25
E-2 Foundation 01 Apr 25 15 May 25
E-3 Steel structure 15 May 25 31 Jul 25
E-4 Electrical 01 Jul 25 30 Sep 25
F. CW INTAKE 01 Jan 25 31 Dec 25
F-1 Fabrication of Pipe 01 Jan 25 31 May 25
F-2 Underwater Installation 01 Jun 25 31 Dec 25
F-3 Intake Head 01 Oct 25 31 Dec 25
G. CW PIPE 01 Mar 25 31 Dec 25
G-1 Fabrication of Pipe 01 Mar 25 30 Jun 25
Activity Original
Activity Name start finish
ID duration
G-2 Demolition of Existing Fence 01 May 25 30 Jun 25
G-3 Excavation 01 Jul 25 30 Nov 25
G-4 Installation 01 Aug 25 30 Nov 25
G-5 Backfill 01 Nov 25 31 Dec 25
H. CW PUMPHOUSE 01 Jun 25 31 Jan 25
H-1 Sheet Piling & Bracing 01 Jun 25 15 Jul 25
H-2 Excavation 16 Jul 25 31 Aug 25
H-3 Formworks & Concreting 01 Sep 25 30 Nov 25
H-4 Mechanical 15 Nov 25 31 Jan 25
H-5 Piping 15 Nov 25 31 Jan 25
H-6 Electrical & Instrumentation 01 Oct 25 31 Jan 25
H-7 Architectural 01 Nov 25 31 Dec 25
I. TRANSFORMER YARD 01 Oct 25 31 Jan 26
I-1 Civil Structure 01 Oct 25 30 Nov 25
I-2 Installation 01 Dec 25 31 Dec 25
I-3 Electrical 15 Oct 25 31 Jan 26
I-4 Architectural 01 Dec 25 31 Jan 26
J. NEW FENCE

Pre-Commissioning 29 Jun 26
Initial Synchronization to Grid 30 Jun 26
Reliability Test Run 30 Sep 26
PAC 30 Sep 26