Lesson 7 - Engineering Contract
Lesson 7 - Engineering Contract
ENGINEERING CONTRACTS
OBLIGATIONS RIGHTS
Employer Contractor
Project Manager
6
STRUCTURING CONTRACTS
➢Change and Variation in Engineering Contract are very common concepts.
➢Nevertheless, there are Changes that are beyond the allowance given in the
condition of Contract thus they require an addendum by consent of both parties.
❖Caution has however been given to the contracts that permit changes/variations
Variation Limit
➢To avoid extreme changes that may have either positive or negative impact to both
the Client and Contractor
➢In addition to setting limit, there is a need to define clearly what is to be termed
as variation and how it should be treated.
➢Most variations/changes are only binding when they have been supported by
appropriate instructions and given approval by authorized personnel.
STRUCTURING CONTRACTS
• The basic idea is for the Employer to have some kind of security for
performance towards the contractor.
• The employer 'retains' some of the price money until a stated date or
period after delivery or completion has elapsed.
• The amount might be 5%-10% of the actual price quoted.
• One way of creating a retention fund is simply by providing for the stage
payments.
• The last stage payment will be retained by the employer until a specific
period of time has elapsed.
PERFORMANCE BONDS OR GUARANTEES
FRUSTRATION
• This occurs due to radical changes in circumstances, beyond the control of either parties in which the
implementation of the contract is impossible or illegal e.g. death of one of the parties, outbreak of war or
destruction of the subject matter of the contract.
BREACH OF CONTRACT
• Occurs when one party makes it impossible to perform the contract by missing a crucial deadline. This
would be self-induced hence the party responsible would be liable to pay for damages.
SUSPENSION AND TERMINATION OF ENGINEERING CONTRACTS
SUSPENSION
Engineering Contracts allow for termination by one party thus depriving the other party the right
to terminate the contract, leaving the party to rely on breach of contract putting the party at a
disadvantage. GROUNDS FOR TERMINATION
CONTRACTOR Employer
1.Insolvency of the Contractor Insolvency of the Employer
2.Failure to work as stipulated by the contract Failure to make payments as specified in the contract
3.Negligence of the contract Interfering with the issue of any certificate by the
Engineer
4.Assigning the contract and Suspending the Execution Replacing the Engineer against reasonable objections
of work by the Contractor.
Quality & Fitness for Purpose
• The main objective of engineering contract is to have defect free equipment, plant or works which are
specified, fit and free from abnormalities and performed the required standards.
• The specifications of the equipment or works required should be up to a certain standard that is
acknowledged by the engineer in a specific field. It is not just simply a matter of legal content,
documentation and information in the relevant contract.
• Nor is it a matter of commercial, tactical and experienced expertise. Therefore, it is a collection of all
the things a legal and commercial scene in which several ideas intersect and interrelate.
• Note the main aim of this is to show where the responsibilities lie and to explain and clarify the issues if
a problem should occur, who is responsible and what is to be done.
SETTING THE COMMERCIAL SCENE
• The matter of quality and fitness should be any legal action. Making sound decisions, where both
parties set the commercial scene, the following issues should be reflected in contract:
a) The feasibility of the project in terms of technicality
b) The viability of the project in terms of it being commercial.
c) Choice of competent, adequate and reliable contractor
d) Clear directions and specifications
e) Clarity of the responsible parties and the responsibility of parties
f) Early identification of defects and deficiencies and a system for eradication of risks
g) Commercial and Financial leverage through the system of payment and/or security
Quality and fitness for purpose, is simplified in the method of kaleidoscope
Intellectual Property is the asset value involved in a commercial transaction. Terms of a contract
should be concerned with the creation of and protection of intellectual property.
For a purchaser it helps keep the developments a secret from competitors whilst for a Contractor
it helps keep details of contract e.g. price, secret so that contractor’s bargaining power over
different purchasers is not reduced.
Intellectual Property rights
Intellectual Property rights NOT created by Contract
This is found in the security(indemnity) clause of an engineering contract.
It occurs when one party provides documents to the other of which are to be
made. If these documents infringe the intellectual property right of a third party,
the third party might take action against either or both the contractor or
purchaser. The indemnity clause would place the costs and legal liability on the
party responsible for causing the situation. (class reading and discussion)
MULTIPARTITE ARRANGEMENTS
These are agreements in which multiple parties are involved. This is
allocation and level at which obligations should be carried out by the
parties involved, communications, chain of instructions and how to
handle liabilities in these types of contracts. Multipartite involve
AGENCY, SUBCONTACTING AND FREE ISSUE
AGENT
An agent as perceived by law, is just a channel between the seller and the
buyer, or between an employer and whole-seller. An agent has no contractual
obligations in the issues of warranty and liabilities involved with the products/
items being delivered.
An agent is just the means facilitating the contract between the seller and
the buyer. If there happens to be any issues with warranty and liabilities of
the items supplied, the seller or manufacturer will be directly responsible,
the agent will not be liable.
The form of tender usually indicate commissions or gratuities of fees to be paid to
agents (Read form of Tender)
• SUBCONTRACTOR
The relationship is such that, the employer is in a contractual
relationship with the main contractor, and the later is again in a
contractual relationship with the subcontractor.
In such contracts the employer is in no means supposed to give
instructions to the subcontractor, and if it happens the employer will be
liable for any damages that may occur as result, more in some cases the
employer might even be obligated to pay the main contractor
compensatory damages if any.
NOMINATED SUB-CONTRACTORS
An employer may direct or instruct the main contractor to pick a
certain sub-contractor. This sub-contractor is therefore referred to as
the nominated subcontractor.
In this case scenario, if there happens to be a collateral contract
between the sub-contractor and the employer then the main
contractor is revealed of any liabilities that may happen, on the other
hand, if there is no collateral contract the main contractor remains
responsible.
Under normal circumstances the warranty of items purchased is always
granted to the main contractor of the works and not the end user
(employer). (Discussion on performance security and engaging domestic sub-contractors)
• FREE ISSUE
The free issue creates a direct relationship between the seller/manufacture
and the employer. In this case, the employer obtains good straight from the
seller / manufacturer and issues them to the contractor, either to be used
for the works or during the course of work under contract.
ADVANTAGES OF FREE ISSUE
• With free issue, the employer has a commercial advantage of obtaining
the goods at a lower price considering a higher purchasing power he has.
• Moreover, with free issue the employer has an advantage of obtaining
goods at the exact standard that they require
• Warranty issues become less complicated.
CONSEQUENCES OF FREE ISSUE
• This chain of commands and responsibilities creates the order work and
thus the chain of liability in the same manner.
CONTRACTS
DOCUMENTS
4. CONDITIONS OF CONTRACT
5
5. SPECIFICATIONS
6. PAYMENT DOCUMENTS
7. MISCELLANEOUS DOCUMENTS
GENERAL PRINCIPLES
In engineering contracts, the contract document is a combination of four (4) major
key documents, that is Conditions of Contract (General and Specific), Specifications,
Drawings and Bills of Quantities or Schedule of rates.
Documents however may vary depending on the type of contract. In this regard,
drafting an Engineering Contract requires skills in the engineering field to describe
the engineering requirement and the other is legal for the purpose of incorporating
the appropriate information that carry legal weight and thus legal relationship.
Drafting contract has not been an easy task even for engineers with high
understanding of the legal field. The key is to have understanding of construction
law. The draftsman needs to take extra care in intention of parties to contract.
Expressed intention in the contract carry weight than what parties think or desire
from contract. Thus, expressed intentions should be put in avoiding use of wording
that may result to alternative interpretations.
GENERAL PRINCIPLES
Neutral
Mediation
Evaluation
Amicable
Conciliation Arbitration
Sattlement Adjudication Litigation
· Materials.
· Workmanship.
· Administrative requirements.
Types of Contracts
• Contracts for works can be classified into two main types:
• 1)Lump sum contracts
• 2)Measure and value contracts
Lump sum contracts
• These are contracts which the contractor is paid by the employer in lump sum for the whole of
the work which was initially described in the contract.
• In accordance with the terms and conditions of the contract, this lump sum is subjected to
adjustments in respect to the variations of the work. These are most common in building work,
mechanical and electrical engineering work and can be used where quantities of various types
of work cannot be fixed or initially accurately defined in some civil engineering work.
• For civil and building engineering works a tender lump sum is usually attached with detailed
bills of quantities which represent all the individual items for work such as material and
equipment supply and of general preliminary work.
Measure and value contracts
• This is the type of contract where the contractor is paid by the employer for the quantity
of work carried out, as weighed and valued in the respected manner, subject to
deduction of contra charges as stated and defined in the contract.
• This type of contract is mostly used by civil engineers and includes bills of quantities in
the documentation.
• The bills are used to weigh, measure and value the work carried out in order to arrive at
the final contract sum.
• This can also be used for interim payments, in this type of contract, authorised variations
in the works are valued and measured in accordance with the tender bill items in course
BILLS OF QUANTITIES
❑A contract for which bidders submit rates for the estimated quantities as
set out in a BoQs which forms part of the tendering documents and from
which the lump sum price is derived from the aggregation of sums
tendered based on these quantities and rates.
❑ Payment under a schedule of rates contract is determined by
measurement of the actual quantities completed and at the rates as
tendered.
Cost Reimbursement Contracts
Three forms:
I. Cost plus a fixed sum,
II. Cost plus a percentage of the costs or
III. Cost plus a fluctuating fee
Where cost reimbursement contracts are used, they
are to be arranged whenever possible on the basis of
“cost plus fixed fee” rather than “cost plus
percentage”.
Turnkey Contracts
It involve the engagement of a single contractor to carry out construction
works, supply and install plants and/or equipment.
suitable when there is a great need of integrating the design, engineering,
construction works and the supply of goods or equipment/plants for the
facility
Fixed and Fluctuating Contracts - 1
• Is used where it is appropriate to relate the fee paid directly to the estimated or
actual cost of the contract
• The contract shall clearly define the total cost from which the percentage is to be
calculated and the consultant or service provider shall be required to indicate his cost
as a percentage of the total cost of the assignment.
• The use of such a contract is recommended only if it is based on a fixed target cost
and covers precisely defined services.
5. Indefinite delivery contracts 85
Scope
Time
Resources Quality
Cost Communication
Risks Disputes
Project Delivery Methodologies
Design-Bid/Tender-Build (Traditional)
Nominated
Subcontractor
Employer –
Tendering Process Contractor - Build
Domestic
Subcontractor
Project Manager/
Consultant – Design
& Supervision
Project Delivery Methodologies
Design & Build
Project Manager/
Consultant –
Supervision
91
Employer Supplier
Roles of Consultant/Project Manager
1. Responsible for the correspondence on contractual issues exchanged
between PE and the Contractor;
2. Responsible for keeping the documents during the execution of the
contract;
3. Oversees the execution of the contract;
4. Manages the resolution of problems and up to a point of any disputes/
disagreements
5.Monitors the Contractor‘s performance
6. Responsible to establish a good spirit of project for achievement of
the desired results;
7. Responsible for the closure of the contract.
Roles of Client in Project
• Indemnify the contractor as appropriate;
• Responsible for special risks and any work done by his workmen and
1. omissions of the Project Manager;
2. • To give prompt notice to the Project Manager of any error, omission, or other defect
which can be discovered during execution of the project;
➢Engineering contracts are based upon or referred to, even when the
terms of the contract have been negotiated between the employer
and a single contractor is what is known as formal tender.
a. Cost control
b. Time control
• Payment Certificates
COST CONTROL 101
• Deductions of Retention.
• Application of Liquidated Damages
• Advance payment
• Performance securities
6/21/2022
102
TIME CONTROL
6/21/2022
QUALITY CONTROL 103
• Quality control and assurance plan is the base for time control during
execution of construction project.
• Identifying Defects.
• Tests.
• Correction of Defects
• Extension of Defect Liability Period
• Uncorrected Defects 6/21/2022
104
FINISHING THE CONTRACT
• Completion Certificate.
• As Built Drawings
• Final Account.
END OF COURSE
6/21/2022
A 106
H N
T K
YOU