Formulas
Formulas
TABLE OF CONTENTS
The following equation can be used to make a rough approximation of the volume of cement that will be necessary to
squeeze off an interval of open perforations. The volume of cement calculated using this equation should then be
compared with the casing through the perforated interval to be certain the volume of cement used is at least as great as the
casing capacity.
Where the injection rate is in barrels per minute and the surface pressure is in pounds per square inch.
Example:
It is desired to squeeze off an interval of perforations in 9-5/8" casing. An injection rate into the formation is established at
1.5 bpm with a corresponding surface pressure of 2000 psi. What volume of cement is required?
The actual volume of cement pumped should be rounded up from this figure. In this example, the required volume of
cement should be rounded up to 100 cuft.
The compressibility of water can be estimated using the following equation. It should be noted that this equation is only an
approximation and should be used by field personnel in estimating the volume of fluid necessary to achieve a specific
pressure or vica versa (e.g., volume of water to pump in order to pressure test a pack-off).
Vw = 2.8 x 10-6 x P x Vc
Where:
Example:
Assume that a casing hanger pack-off is to be pressure tested on a semi-submersible rig and that the volume of the kill line
from the cementing unit to the pack-off is 3.0 bbls. If a test pressure of 6500 psi is required, what volume of water must be
pumped to achieve this test pressure?
Therefore, only a fraction of a barrel of fluid would be required to pressure up against the pack-off, which is what is
actually experienced in practice.
USEFUL FORMULAS
In a manner similar to that used above for oil base muds, an estimate of the volume of water base mud that must be
pumped to achieve a given pressure can be determined using the following equation (taken from Occidental's Well Control
Manual, Section 12.3).
Where:
Example:
Assume that 9000' of 47 ppf, 9-5/8" casing will be pressure tested to 6000 psi using a water base mud. What volume of
mud must be pumped to achieve the test pressure?
Vm = 10.5 bbls
Therefore, it would require approximately 10.5 bbls of mud to pressure up the casing to 6000 psi.
The equation presented in this section is to be used to calculate the height of a balanced column of cement that will be
spotted using a cementing string. The general equation for cement height (with the cementing string on bottom) is given as
follows.
Vcmt
Hc = ____________
Vp + Va
Where:
It should be noted that the volumetric capacity of the cementing string and the cementing string annulus ARE NOT to be
calculated using the nominal inside and outside diameters of the cementing string and casing. For example, in the case of
5", 19.5 ppf drill pipe, do not use a nominal I.D. of 4,276" to calculate the volumetric capacity of the cementing string, V p.
This procedure will result in over-estimation of the volumetric capacity, since the restricted I.D. through the tool joints will
not have been taken into account. This will subsequently result in calculation of a lower cement height and, therefore, a
greater displacement volume. the correct volumetric capacities can be calculated using the equations given in Section IV,
Part 1.10, VOLUMETRIC CAPACITIES of PIPE and CASING.
Example:
It is desired to place a 110 cuft balanced cement plug in the bottom of an 8000' string of 7", 26 ppf casing using
2.875" tubing. The cement column is to be exactly balanced. The well bore fluid and displacement fluid will be
drill water. Assume that Vp = 0.0325 cuft/ft and that Va - 0.1697 cuft/ft. Therefore:
Vcmt 110
Hc = ____________ = _______________ = 544 feet
Vp + V a 0.0325 + 0.1697
Therefore the height of the cement column (with the cementing string in the well) would be approximately 544 feet. The
volume of water to pump behind the cement can now be determined by taking the difference between the depth of the
cementing string and the height of cement and multiplying by the volumetric capacity of the cementing string. This would
be (8000' -544') 0.0325 = 242.32 cuft or 43.19 bbls.
If it is necessary to pump a cementing space ahead of and behind the cement plug, then the necessary volumes of spacer
can be determined by using the ratio of the annulus volumetric capacity to the volumetric capacity of the pipe. This can be
expressed as follows:
Va bbl
Spacer Ratio = ____ , ___
Vp bbl
Using this example in this section, the spacer ratio would be:
0.1697 bbl
Spacer Ratio = ______ = 5.22 ____
0.0325 bbl
Therefore, for every 5.22 bbls of spacer pumped ahead of the cement plug 1.0 bbls of spacer must be pumped behind the
cement plug.
USEFUL FORMULAS
The buoyancy factor for steel immersed in a fluid of known density can be determined using the following equation.
Using the buoyancy factor, the buoyed weight of steel drilling tools can be determined by multiplying air weight by the
appropriate buoyancy factor.
Example:
If a drilling assembly is calculated to weigh 84,000 lbf in air, what will it weigh in an 11.7 ppg drilling fluid?
11.7
BF = 1.0 - ______ = 0.821
65.5
Therefore the buoyed weight would be 0.821 x 84,000 lbf = 68,964 lbf.
The equations used in the following sub-sections for the calculation of Power Law drilling fluid hydraulics are detailed in
Section III, Part 5.4.2, Circulating Pressure Losses & Critical Velocities. This section provides a worked example
using these equations.
Well Data
Assume that the drill pipe has been run in the hole with nothing more than a bit on the end and that it is planned to
circulate the hole. Also assume that the average hole size is 12-1/4" from surface to total depth.
USEFUL FORMULAS
For flow down the drill string, the Fann viscometer readings at 300 and 600 rpm are to be used for calculation of n and K.
0600 75
n = 3.32 log ____ = 3.32 log ___ = 0.643
0300 48
0300 48
K= _____ = _______ = 0.870
511n 5110.643
For annular flow, the Fann viscometer readings at 6 and 100 rpm are to be used for the calculation of n and K assuming, of
course, that the velocity profile is laminar. If the velocity profile is turbulent, the equations given in Part 1.5.1 above
would have to be used.
0100 23
n = 0.82 log ____ = 0.82 log ___ = 0.334
06 9
0100 23
K= _____ = _______ = 4.14
170n 1700.334
The average fluid velocity down the drill pipe is calculated as follows:
24.5 Q (24.5)(775)
V = ______ = _________ = 1038, ft/min
D2 (4.276)2
The average fluid velocity in the drill string annulus is calculated as follows:
24.5 Q (24.5)(775)
V = _______ = ____________ = 151.8, ft/min
Dh2 - Dp2 (12.25)2 - (5)2
USEFUL FORMULAS
Using the calculated values of n and K for pipe flow determined in Part 1.5.1 above, and the well data given previously,
the critical velocity pumping down the drill string can be calculated as follows.
1 n
MW D 4n
0.643
4.276 4(0.643)
= 1.969(171.17)(0.667)
Vc = 224.8 ft/min.
Therefore, since the critical velocity is less than the average fluid velocity down the drill pipe (calculated in Part 1.5.3), the
fluid velocity profile is turbulant.
USEFUL FORMULAS
Using the calculated values of n and K for annular flow determined in Part 1.5.2 above, and the well data given previously,
the critical velocity pumping up the drill pipe annulus can be calculated as follows.
1 n
MW 0.64(Dh - Dp)n
10.5
0.334
2(0.334) + 1) _______
X _________________ 2 - 0.334
0.64(12.25 - 5)0.334
Since the average fluid velocity in the annulus of 151.8 ft/min (calculated previously in Part 1.5.4) is less than the critical
velocity, the annular flow profile is laminar.
USEFUL FORMULAS
The interval pressure loss inside the drill string is to be calculated using either the laminar or turbulent flow equations.
Following on with the example presented in this section, flow down the drill pipe is turbulent based on the critical velocity
calculations performed previously. Therefore, the turbulent flow pressure loss down the drill pipe is determined as
follows:
1.4 - log n
0.4V 3n + 1 n _________
19.36 K __________ 7
(log n + 2.5)MW V2 L D n
PT = __________________ __________________
4645029 D MW V2
.4 - log 0.643
0.4(1.038) 3(0.643) + 1 0.643 _____________
19.36(0.87) ___________________ 7
X 4.276 0.643
___________________________________
(10.5)(1038)2
lbf
PT = (12490)(7.48 x 10-5)0.2274 = 1439.75, ____
sqin
If the fluid velocity profile down the drill pipe were laminar, the equation for laminar pipe flow given in Section III, Part
5.4.2 (A)(4) would have to be used, with calculations performed in a similar manner to those presented here.
USEFUL FORMULAS
Since the annular velocity profile was previously determined to be laminar, the following equation for laminar flow
interval pressure loss is to be used. If the flow profile was determined to be turbulent, the equation given in Section III,
Part 5.4.2(B)(3) would be used, with calculations performed in a similar manner to those presented here.
0.8V 2n + 1 n KL
PL = ____________ ___________
Dh - Dp n 300(Dh - Dp)
lbf
PL = (4.386)(18.08) = 79.3, ____
sqin
Using the data given previously, the pressure drop across the jet nozzles is calculated as follows. In this example the
nozzle coefficient, Cn, has been taken as 0.95.
MW Q2 (10.5)(775)2 lbf
PB = __________ = __________________ = 1694, ____
11884 Cn A2 (11884)(.95)2(.5891)2 sqin
Using the previously calculated pressure drop across the bit, the bit hydraulic horsepower can be calculated as follows.
Q PB (775)(1694)
HHPB = ______ = __________ = 766, hp
1714 1714
The jet impact force generated through all of the nozzles in the bit is calculated as follows.
MW Q2 (10.5(775)2
IFJ = _________ = _____________ = 1778.6, lbf
6019 An (3.125)(.5891)
USEFUL FORMULAS
The average jet velocity through the bit nozzles is calculated as follows.
Q (775) ft
VJ = _________ = ____________ = 421, ____
3.125 An (3.125)(.5891) sec
The equivalent circulating density in the drill string annulus is to be taken as the sum of the mud weight, annular
circulating pressure loss and density increase due to formation cuttings in the drilling fluid. The general equation for
performing this calculation is as follows.
Where:
Example:
Detailed procedures and an example calculation for determining the free point of stuck drilling assemblies are given in
Section III, Part 10.12, TOOL JOINT BACK-OFF PROCEDURES.
Detailed procedures for determining the reduction in density of brine formulations based on an increase in the average fluid
temperature are given in Section III, Part 14.5.3, Completion/Kill Fluid Requirements.
Detailed procedures for determining the percent solids in drilling fluids are contained in Section III, Part 5.3.2, Water
Base Drilling Fluids: Field Testing Requirements.
The operating pressure requirements of hydrocyclones will generally be expressed in feet of head. For example, the
specification for a desilter fitted with 4" hydrocyclones may state that the unit is to be operated at a feed head of 75 feet,
regardless of mud density. If it was desired to determine the correct operating pressure of the unit when using a 10.5 ppg
mud, the following calculation can be performed.
P = 0.052 x HEAD x MW
Where:
Therefore:
lbf
P = 0.052 x 75 x 10.5 = 40.95 , ____
sqin
USEFUL FORMULAS
In a similar manner, the operating head can be calculated knowing the operating pressure by using the following equation.
P lbf
HEAD = _________ , _____
0.052 MW sqin
Using the data from the example above, if the operating pressure were 60 psi, the equivalent feet of head would be:
60 lbf
HEAD = __________ = 109.9, _____
(0.052)(10.5) sqin
The volumetric capacity per linear foot inside pipe and in the annulus between the casing I.D. and pipe O.D. can be
estimated using the following equations. It should be noted that these equations are only a close approximation based on
the nominal dimensions of the pipe and casing. If more accurate figures are available from pipe manufacturers, their
figures should be used.
Note: DO NOT use the volumetric capacities given in the Halliburton "Red Book", BJ Decimal Book or Dowell Field
Data Handbook, as the figures presented do not take account of tool joint dimensions. This could result in significant
errors in spotting cement plugs, particularly on deep wells.
Pipe Capacity
Where:
Example:
Calculate the volumetric capacity of 5", 19.5 ppf drill pipe with the following dimensions:
IDTJ = 2.875"
IDPB = 4.276"
LTJ = 3.0' (box + pin)
LPB = 28.0'
Annulus Capacity
The capacity of the annulus between the pipe and open hole or pipe and casing can be calculated as follows:
Where:
Example:
Calculate the annulus capacity per foot of 5" drill pipe inside 9-5/8", 47.0 ppf casing.
IDCSG = 8.681"
ODTJ = 6.500"
ODPB = 5"
LTJ = 3.0'
LPB = 28.0'
bbls
= 0.0473 _____
ft
CONVERSION FACTORS
TABLE OF CONTENTS
1 sq inch = 6.4516 sq cm
CONVERSION FACTORS
2.4 UNITS OF MASS (WEIGHT)
2.7 TEMPERATURE