EVM - Advanced Formula
EVM - Advanced Formula
CPI = EV / AC
= $225,000 / $200,000
= 1.125
TCPI = (BAC – EV) / (BAC – AC) = ($4,000-$1,200) / ($4,000-2,000) = $2,800 / $2,000 = 1.4
For your project, find the To-complete performance index (TCPI) based on the given data:
Budget at completion of the project = $700,000
Cost variance of the project = $25,000
Earned value of the project = $200,000
Estimate to Complete (ETC) has now been revised to $425,000
A. 0.9
B. 1.176
C. 1.5
D. -1.5
Answer:
Justification:
CV = EV - AC
AC = EV - CV = $200,000 - $25,000 = $175,000