BRC Price List
BRC Price List
CONCRETE
Kamen Steel STANDARD PRICE COMPANY X foomas Asia Wire Kamen Steel COMPANY A COMPANY A
BRC SIZE rate per m2 RATE 68.00% 43.00% 45.00% 55.00% 60.00% 60.00%
A13 35.19 78.20 25.02 44.57 43.01 35.19 31.28 31.28
A12 29.97 66.60 21.31 37.96 36.63 29.97 26.64 26.64
A11 22.68 50.40 16.13 28.73 27.72 22.68 20.16 20.16
A10 18.72 41.60 13.31 23.71 22.88 18.72 16.64 16.64
A9 15.17 33.70 10.78 19.21 18.54 15.17 13.48 13.48
A8 12.01 26.70 8.54 15.22 14.69 12.01 10.68 10.68
A7 9.18 20.40 6.53 11.63 11.22 9.18 8.16 8.16
A6 6.75 15.00 4.80 8.55 8.25 6.75 6.00 6.00
A5 5.22 11.60 3.71 6.61 6.38 5.22 4.64 4.64
A4 3.37 7.50 2.40 4.28 4.13 3.37 3.00 3.00
B13 41.85 93.00 29.76 53.01 51.15 41.85 37.20 37.20
B12 36.63 81.40 26.05 46.40 44.77 36.63 32.56 32.56
B10 24.71 54.90 17.57 31.29 30.20 24.71 21.96 21.96
B9 21.20 47.10 15.07 26.85 25.91 21.20 18.84 18.84
B8 18.04 40.10 12.83 22.86 22.06 18.04 16.04 16.04
B7 13.77 30.60 9.79 17.44 16.83 13.77 12.24 12.24
B6 11.34 25.20 8.06 14.36 13.86 11.34 10.08 10.08
B5 10.30 22.90 7.33 13.05 12.60 10.30 9.16 9.16
C10 22.68 50.40 16.13 28.73 27.72 22.68 20.16 20.16
C9 18.72 41.60 13.31 23.71 22.88 18.72 16.64 16.64
C8 14.62 32.50 10.40 18.53 17.88 14.62 13.00 13.00
C7 11.52 25.60 8.19 14.59 14.08 11.52 10.24 10.24
C6 8.82 19.60 6.27 11.17 10.78 8.82 7.84 7.84
C5 6.52 14.50 4.64 8.27 7.98 6.52 5.80 5.80
DA12 59.94 133.20 42.62 75.92 73.26 59.94 53.28 53.28
DA10 37.44 83.20 26.62 47.42 45.76 37.44 33.28 33.28
DA9 30.33 67.40 21.57 38.42 37.07 30.33 26.96 26.96
DA8 24.03 53.40 17.09 30.44 29.37 24.03 21.36 21.36
DA7 18.36 40.80 13.06 23.26 22.44 18.36 16.32 16.32
DA6 13.50 30.00 9.60 17.10 16.50 13.50 12.00 12.00
DA5 10.44 23.20 7.42 13.22 12.76 10.44 9.28 9.28
DA4 6.75 15.00 4.80 8.55 8.25 6.75 6.00 6.00
REINFORMENT BAR
FORMWORK / TIMBER
Mesmenang Went Seng Taikong
Plywood 12mm 45.00 pcs 50.00 47.50 45.00
timber per tonne 950.00 tonne 950.00
SKIM COAT
EXCAVATION
SAND BEDDING
ITEM cost per M3 25MM 30MM 50MM 100MM 150MM 250MM 300MM
Supply 70.20 1.76 2.11 3.51 7.02 10.53 17.55 21.06
Compaction 10.0% 5.00 0.13 0.15 0.25 0.50 0.75 1.25 1.50
Labour 5.00 0.13 0.15 0.25 0.50 0.75 1.25 1.50
Machine to lay 5.00 0.13 0.15 0.25 0.50 0.75 1.25 1.50
Unit rate/m2 85.20 2.13 2.56 4.26 8.52 12.78 21.30 25.56 PER M2
HARDCORE
ITEM Cost Per M3 100MM 150MM 200MM 250MM 300MM 400MM 450MM
Supply 2" crusher run 63.80 6.38 9.57 12.76 15.95 19.14 25.52 28.71
Compaction 10.0% 6.38 0.64 0.96 1.28 1.60 1.91 2.55 2.87
Labour 5.00 0.50 0.75 1.00 1.25 1.50 2.00 2.25
Machine 5.00 0.50 0.75 1.00 1.25 1.50 2.00 2.25
TOTAL 80.18 8.02 12.03 16.04 20.05 24.05 32.07 36.08 PER M2
Subcon prelims 0% - - - - - - - -
Unit rate/m2 80.18 8.02 12.03 16.04 20.05 24.05 32.07 36.08 PER M2
LEAN CONCRETE
SUB-STRUCTURE G15 15MM 50MM 75MM 100MM 115MM 150MM 200MM
Supply concrete 200.00 3.00 10.00 15.00 20.00 23.00 30.00 40.00
Wastage 30.0% 60.00 0.90 3.00 4.50 6.00 6.90 9.00 12.00
Labour 16.00 0.24 0.80 1.20 1.60 1.84 2.40 3.20
Plant 15.00 0.23 0.75 1.13 1.50 1.73 2.25 3.00
COST PER M3 291.00 4.37 14.55 21.83 29.10 33.47 43.65 58.20 PER M2
Subcon prelims 0% - - - - - - - -
Unit rate/m2 291.00 4.37 14.55 21.83 29.10 33.47 43.65 58.20 PER M2
SUB-STRUCTURE G10 G15 G20 G20-P G25 G25-P G30 G30-P G35 G35-P
Supply 195.00 200.00 206.00 215.00 226.00 238.00
Wastage 3.0% 5.85 6.00 6.18 - 6.45 - 6.78 - 7.14 -
Conc Pump/crane 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00
Construction joint & water stop 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00
Mortar - - - - - - - - - - -
Bonding agent - - - - - - - - - -
Labour 18.00 18.00 18.00 18.00 18.00 18.00 18.00 18.00 18.00 18.00 18.00
Unit rate/m3 243.85 249.00 255.18 43.00 264.45 43.00 275.78 43.00 288.14 43.00
0% - - - - - - - - - -
Unit rate/m3 243.85 249.00 255.18 43.00 264.45 43.00 275.78 43.00 288.14 43.00
SUPER-STRUCTURE G15 G15 G20 G20-P G25 G25-P G30 G30-P G35 G35-P
Supply 200.00 200.00 206.00 215.00 226.00 238.00
Wastage 3.0% 6.00 6.00 6.18 - 6.45 - 6.78 - 7.14 -
Conc Pump/crane 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00
Construction joint & water stop 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00
Mortar - Mortar - - - - - - - - -
Bonding agent Bonding agent - - - - - - - - -
Labour 18.00 18.00 18.00 18.00 18.00 18.00 18.00 18.00 18.00 18.00 18.00
259.00 259.00 265.18 53.00 274.45 53.00 285.78 53.00 298.14 53.00
- - - - - - - - - -
Unit rate/m3 0% 259.00 259.00 265.18 53.00 274.45 53.00 285.78 53.00 298.14 53.00
BRC MESH
REINFORCEMENT BAR
UNIT R6 - R8 R10 - R12 R16 - R32 T10 T12 T16 T20 T25 T32 T40
Material Price per tonne 3,200.00 3,200.00 3,200.00 3,200.00 3,200.00 3,000.00 3,000.00 3,000.00 3,000.00 3,000.00
Cut & bend to size - - - - - - - - - - -
Cost price 3,200.00 3,200.00 3,200.00 3,200.00 3,200.00 3,000.00 3,000.00 3,000.00 3,000.00 3,000.00
Wastage 5.0% 160.00 160.00 160.00 160.00 160.00 150.00 150.00 150.00 150.00 150.00
Crane PRICE UNDER PRELIM
Labour 800.00 800.00 800.00 800.00 800.00 800.00 800.00 800.00 800.00 800.00 800.00
Cost/tonne 4,160.00 4,160.00 4,160.00 4,160.00 4,160.00 3,950.00 3,950.00 3,950.00 3,950.00 3,950.00
Cost/kg 4.16 4.16 4.16 4.16 4.16 3.95 3.95 3.95 3.95 3.95
Subcon prelims 0% - - - - - - - - - -
4.16 4.16 4.16 4.16 4.16 3.95 3.95 3.95 3.95 3.95
FORMWORKS
1 : 3 MIX 1 : 4 MIX
Cement 28.0 BAGS = 1 M3 18.50 518.00 Cement 28.0 BAGS = 1 M3 18.50 518.00
Sand 3.0 M3 48.00 144.00 Sand 4.0 M3 48.00 192.00
662.00 710.00
Shrinkage 33.00% 218.46 Shrinkage 33.00% 234.30
880.46 944.30
Wastage 5.00% 44.02 Wastage 5.00% 47.22
4 m3 of cement mortar : 924.48 5 m3 of cement mortar : 991.52
COST PER M3 231.12 COST PER M3 198.30
1 : 6 MIX 1 : 2 MIX
Cement 28.0 BAGS = 1 M3 18.50 518.00 Cement 28.0 BAGS = 1 M3 18.50 518.00
Sand 6.0 M3 48.00 288.00 Sand 2.0 M3 48.00 96.00
806.00 614.00
Shrinkage 33.00% 265.98 Shrinkage 33.00% 202.62
1,071.98 816.62
Wastage 5.00% 53.60 Wastage 5.00% 40.83
7 m3 of cement mortar : 1,125.58 4 m3 of cement mortar : 857.45
COST PER M3 160.80 COST PER M3 285.82
Granolithic screed
1 : 3 : 4.5 MIX 1 : 3 : 2 MIX (for Conc Masonry Infill)
Cement 28.00 BAGS = 1 M3 18.50 518.00 Cement 28.0 BAGS = 1 M3 18.50 518.00
Sand 3.00 M3 48.00 144.00 Sand 3.0 M3 48.00 144.00
Granite chipping 1.00 M3 49.00 49.00 Aggregate 2.0 M3 78.40 156.80
Bonding agent 7.00 M3 4.00 28.00 818.80
739.00 Shrinkage 33.00% 270.20
Shrinkage 33.00% 243.87 1,089.00
982.87 Wastage 5.00% 54.45
Wastage 5.00% 49.14 1,143.45
4 m3 of cement mortar : 1,032.01 4 m3 of cement mortar : COST PER M3 285.86
COST PER M3 258.00
BLOCKWALL
INTERNAL EXTERNAL
BLOCK WALL BLOCK WALL
ht 5m high ht 5m high
BLOCK WALL 115 BLOCK WALL 225 BLOCK WALL 115 BLOCK WALL 225
COST/UNIT QTY/M2 M2 QTY/M2 M2 COST/UNIT QTY/M2 M2 QTY/M2
Common bricks 3.400 8.50 28.90 17.00 57.80 3.400 8.50 28.90 17.00
Wastages 5.0% 1.45 2.89 5.0% 1.45
Cement mortar (1:6) incl. wastage 168.84 0.02 3.38 0.05 8.44 168.84 0.02 3.38 0.05
Exmet 0.50 0.50 1.00 0.50 0.50
Stiffener Allowance 5% 1.45 - 2.89 2% 0.58 -
DPC & BONDING TIE Allow - - 0.80 - -
Labour normal 0.40 58.00 23.20 116.00 46.40 0.60 58.00 34.80 116.00
Total/m2 58.87 120.22 69.60
INTERNAL EXTERNAL
CEMENT SAND BRICK CEMENT SAND BRICK
ht 5m high ht 5m high
CEMENT SAND 115 CEMENT SAND 225 CEMENT SAND 115 CEMENT SAND 225
COST/UNIT QTY/M2 M2 QTY/M2 M2 COST/UNIT QTY/M2 M2 QTY/M2
Cement sand brick 0.190 58.00 11.02 116.00 22.04 0.190 58.00 11.02 116.00
Wastages 5.0% 0.55 1.10 5.0% 0.55
Cement mortar (1:6) incl. wastage 168.84 0.02 3.38 0.05 8.44 168.84 0.02 3.38 0.05
Exmet 0.50 0.50 1.00 1.00 1.00
Labour 0.35 58.00 20.30 116.00 40.60 0.45 58.00 26.10 116.00
Total/m2 35.75 73.18 42.05
INTERNAL EXTERNAL
COMMON CLAY BRICK COMMON CLAY BRICK
ht 5m high ht 5m high
CLAY BRICK 115 CLAY BRICK 225 CLAY BRICK 115 CLAY BRICK 225
COST/UNIT QTY/M2 M2 QTY/M2 M2 COST/UNIT QTY/M2 M2 QTY/M2
Common bricks 0.340 58.00 19.72 116.00 39.44 0.340 58.00 19.72 116.00
Wastages 5.0% 0.99 1.97 5.0% 0.99
Cement mortar (1:6) incl. wastage - 0.02 3.38 0.05 8.44 - 0.02 3.38 0.05
Exmet 0.50 0.50 1.00 0.50 0.50
Stiffener Allowance 5% 0.99 - 1.97 2% 0.39 -
DPC & BONDING TIE Allow - - 0.80 - -
Labour normal 0.30 58.00 17.40 116.00 34.80 0.40 58.00 34.80 116.00
Total/m2 42.97 88.43 59.78
PLASTERING
PLASTERING CEMENT MORTAR 1:3
INTERNAL EXTERNAL
COST/UNIT 12MM 13MM 19MM 20MM 25MM 12MM 19MM 20MM
Cement mortar (1:6) 160.80 1.93 2.09 3.06 3.22 4.02 160.80 1.93 3.06 3.22
Wastages 5.0% 0.10 0.10 0.15 0.16 0.20 5.0% 0.10 0.15 0.16
Eix mix 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77
Groove line - - - - - - - -
Corner Bead / metal lath 2.80 2.80 2.80 2.80 2.80 2.80 2.80 2.80 2.80 2.80
MATERIAL COST 5.60 5.77 6.78 6.95 7.79 5.60 6.78 6.95
Labour 20.00 20.00 20.00 20.00 20.00 20.00 11.00 11.00 11.00 11.00
Cost/m2 for ht <3.50m 25.60 25.77 26.78 26.95 27.79 16.60 17.78 17.95
RENDERING (PAVING)
BACKING SCREED
SCREEDING C&S 1:3
COST/UNIT 20MM 25MM 30MM 38MM 42MM 50MM 60MM 15MM 80MM 13MM
Cement mortar (1:3) 231.12 4.62 5.78 6.93 8.78 9.71 11.56 13.87 3.47 18.49 3.00
Wastages 10% 0.46 0.58 0.69 0.88 0.97 1.16 1.39 0.35 1.85 0.30
add for pump 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50
fibre mesh 12 0.59 0.78 0.94 0.94 0.94
MATERIAL COST 5.58 6.86 8.12 10.75 11.18 14.00 16.70 4.32 21.78 4.74
Labour 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00
Total/m2 13.58 14.86 16.12 18.75 19.18 22.00 24.70 12.32 29.78 12.74
SKIM COATING
G40 G40-P G45 G45-P G50 G50-P G35A G55-P G60 G60-P
252.00 268.00 -
7.56 - 8.04 - - - - - - -
30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00
5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00
- - - - - - - - - -
- - - - - - - - - -
18.00 18.00 18.00 18.00 18.00 18.00 18.00 18.00 18.00 18.00
312.56 53.00 329.04 53.00 53.00 53.00 53.00 53.00 53.00 53.00
- - - - - - - - - -
312.56 53.00 329.04 53.00 53.00 53.00 53.00 53.00 53.00 53.00
CK WALL 225 BLOCK WALL 450
M2 QTY/M2 M2
57.80 34.00 115.60
2.89 5.78
8.44 0.08 13.51
1.00 1.00
1.16 - 2.31
1.20 1.20
69.60 34.00 20.40
142.09 159.80
XTERNAL
25MM 35.00
4.02 5.63
0.20 0.28
0.77 0.77
- -
2.80 2.80
7.79 9.48
11.00 11.00
18.79 20.48
Skim coat - Render
1.60kg/m2/mm
25.0 m2/mm Render (40kg) - External
0.025 m3 Base (40kg) - Internal base
1m3 Finish (25kg) - Internal Finish