0% found this document useful (0 votes)
847 views

BRC Price List

Uploaded by

Alyaa Anisah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
847 views

BRC Price List

Uploaded by

Alyaa Anisah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 22

LEMBAGA GETAH MALAYSIA

MATERIAL PRICE LAGEND


Need to direct key-in price / rate
LIST OF LABOUR RATE / WASTAGE / SHRINKAGE need to link to choose rate
can change size / thickness
labour machine wastage / usage joint replenishment shrinkage Price / rate link from table
Sand Bedding 5.00 5.00 10% 0
Hardcore 5.00 5.00 10%
Lean con 16.00 15.00 30%
concrete - sub 18.00 20.00 5% 5.00
concrete - super struc 18.00 30.00 5% 5.00
BRC 1.80 25%
reinforcement 500.00 5%
formwork 17.00 5.00 25%
cement mortar 5% 33%
brickwall - internal 0.20 5% 33%
brickwall - external 0.40 5% 33%
plastering 10.00 5%
paving / rendering / screed 8.00 10%

CONCRETE

LATEST YTL LATEST COMPANY A COMPANY A COMPANY X COMPANY A


Grade Rate/m3 Rate/m3 (JKR) Rate/m3 Rate/m3 Rate/m3 Rate/m3 (JKR) Rate/m3 Rate/m3 (JKR)
G10 195.00 - 240.00 148.00 168.00 140.00 158.00
G15 200.00 210.00 240.00 153.00 173.00 145.00 163.00
G15-P 245.00 - 155.00
G20 206.00 215.00 245.00 158.00 178.00 165.00 169.00
G20-P 250.00 170.00
G25 215.00 223.00 255.00 167.00 187.00 174.00 178.00
G25-P 260.00 173.00 193.00 166.00 193.00
G30 226.00 232.00 267.00 177.00 197.00 184.00 188.00
G30-P 272.00 183.00 203.00 176.00 203.00
G35 238.00 242.00 272.00 188.00 208.00 195.00 199.00
G35-P 277.00 194.00 214.00 187.00 214.00
G40 252.00 254.00 284.00 201.00 221.00 193.00 211.00
G40-P 289.00 207.00 227.00 199.00 226.00
G45 268.00 268.00 298.00 216.00 236.00 206.00 224.00
G45-P 303.00 222.00 242.00 212.00 239.00
G50 - - 233.00 253.00 227.00
G50-P - 239.00 259.00 289.00
G35A - 203.00 250.00
G55 - 284.00
G55-P - 290.00
G60 - 305.00
G60-P - 311.00

SAND & CRUSHER RUN

Washed Coarse sand Supply 39.00 per ton


factor 1.80
Per m3 70.20

2" crusher run Supply 29.00 ton HANSON


Per Tonne 29.00
Factor 2.20
Per M3 63.80
BRC WORKS

Kamen Steel STANDARD PRICE COMPANY X foomas Asia Wire Kamen Steel COMPANY A COMPANY A
BRC SIZE rate per m2 RATE 68.00% 43.00% 45.00% 55.00% 60.00% 60.00%
A13 35.19 78.20 25.02 44.57 43.01 35.19 31.28 31.28
A12 29.97 66.60 21.31 37.96 36.63 29.97 26.64 26.64
A11 22.68 50.40 16.13 28.73 27.72 22.68 20.16 20.16
A10 18.72 41.60 13.31 23.71 22.88 18.72 16.64 16.64
A9 15.17 33.70 10.78 19.21 18.54 15.17 13.48 13.48
A8 12.01 26.70 8.54 15.22 14.69 12.01 10.68 10.68
A7 9.18 20.40 6.53 11.63 11.22 9.18 8.16 8.16
A6 6.75 15.00 4.80 8.55 8.25 6.75 6.00 6.00
A5 5.22 11.60 3.71 6.61 6.38 5.22 4.64 4.64
A4 3.37 7.50 2.40 4.28 4.13 3.37 3.00 3.00
B13 41.85 93.00 29.76 53.01 51.15 41.85 37.20 37.20
B12 36.63 81.40 26.05 46.40 44.77 36.63 32.56 32.56
B10 24.71 54.90 17.57 31.29 30.20 24.71 21.96 21.96
B9 21.20 47.10 15.07 26.85 25.91 21.20 18.84 18.84
B8 18.04 40.10 12.83 22.86 22.06 18.04 16.04 16.04
B7 13.77 30.60 9.79 17.44 16.83 13.77 12.24 12.24
B6 11.34 25.20 8.06 14.36 13.86 11.34 10.08 10.08
B5 10.30 22.90 7.33 13.05 12.60 10.30 9.16 9.16
C10 22.68 50.40 16.13 28.73 27.72 22.68 20.16 20.16
C9 18.72 41.60 13.31 23.71 22.88 18.72 16.64 16.64
C8 14.62 32.50 10.40 18.53 17.88 14.62 13.00 13.00
C7 11.52 25.60 8.19 14.59 14.08 11.52 10.24 10.24
C6 8.82 19.60 6.27 11.17 10.78 8.82 7.84 7.84
C5 6.52 14.50 4.64 8.27 7.98 6.52 5.80 5.80
DA12 59.94 133.20 42.62 75.92 73.26 59.94 53.28 53.28
DA10 37.44 83.20 26.62 47.42 45.76 37.44 33.28 33.28
DA9 30.33 67.40 21.57 38.42 37.07 30.33 26.96 26.96
DA8 24.03 53.40 17.09 30.44 29.37 24.03 21.36 21.36
DA7 18.36 40.80 13.06 23.26 22.44 18.36 16.32 16.32
DA6 13.50 30.00 9.60 17.10 16.50 13.50 12.00 12.00
DA5 10.44 23.20 7.42 13.22 12.76 10.44 9.28 9.28
DA4 6.75 15.00 4.80 8.55 8.25 6.75 6.00 6.00

REINFORMENT BAR

HAP SENG COMPANY X HAP SENG Foomas Southen COMPANY A COMPANY A


REINFORMENT BAR SIZE rate / tonne Rate/m3 (JKR) rate / tonne rate / tonne rate / tonne rate / tonne rate / tonne rate / tonne
Y 10MM X 12M 3,200.00 2,800.00 3,020.00 3,450.00 3,530.00 3,000.00 3,000.00
Y 12MM X 12M 3,200.00 2,800.00 3,020.00 3,350.00 3,530.00 3,000.00 3,000.00
Y 16MM - 32MM X 12M 3,000.00 2,800.00 2,870.00 3,300.00 3,330.00 3,000.00 3,000.00
Y 40MM X 12M 3,000.00 2,800.00 2,920.00 3,200.00 3,430.00 3,000.00 3,000.00
R6 - R8 3,200.00 2,800.00 3,020.00 3,450.00 3,530.00 3,000.00 3,000.00
R 10MM & 12MM X 12M 3,100.00 2,800.00 3,020.00 3,350.00 3,530.00 3,000.00 3,000.00
R 16MM - 32MM X 12M 3,000.00 2,800.00 2,920.00 3,350.00 3,530.00 3,000.00 3,000.00
R 5MM - 8MM X 12M 3,200.00 2,800.00 3,020.00 3,450.00 3,530.00 3,000.00 3,000.00
Labour 800.00 380.00 800.00 500.00 500.00 420.00 420.00

FORMWORK / TIMBER
Mesmenang Went Seng Taikong
Plywood 12mm 45.00 pcs 50.00 47.50 45.00
timber per tonne 950.00 tonne 950.00

CEMENT / SAND / CRUSHER RUN / BRICK


convertion factor PER M3 x Hextar Hansons YTL
Walcrete/ normal cement supply, BAG 18.50
Fine Sand supply , M3 48.00 1.8 86.40
Washed coarse sand, M3 46.00
2" crusher run, ton 30.00 29.00 34.00
3/4" Aggregate, ton 49.00 1.6 78.40
Granite Chipping , M3 49.00 1.6 78.40
unwash coarse sand 52.20 1.6 83.52
3/4" Aggregate, ton 49.00 1.6 78.40
Bonding agent, m3 4.00
Clay brick 0.34 pcs 0.34
cement sand brick 0.19 pcs
Exmet 0.50
corner bead 2.80
0.25mm thk DPM 4.00
Imported soil 30.00 1.6 48.00 RM/m3

SKIM COAT

COMPANY X COMPANY X COMPANY A COMPANY A wastage 8%


SKIM COAT - RENDER rate / tonne Rate/m3 (JKR) per pack per pack per pack labour 1.50
Render (40kg) - External 15.40 15.40 15.80 15.80
Base (40kg) - Internal base 18.85 18.85 17.80 17.80
Finish (25kg) - Internal Finish 19.05 19.05 17.00 17.00

STANDARD COSTING FOR BUILDING WORKS

EXCAVATION

ITEM UNIT oversite <1.50m dp 1.50-3.00m dp 3.00-4.50m dp 4.50-6.00m dp


Structural Excavation per m3 10.00 13.00 13.00 15.00 60.00
backfilling (excavated material) per m3 3.50
removing ( working dumping site) per m3 10.00
import filling to retaining wall per m3 35.00
excavation in rock per m3 60.00
oversite 325mm per m2 3.25

SAND BEDDING

ITEM cost per M3 25MM 30MM 50MM 100MM 150MM 250MM 300MM
Supply 70.20 1.76 2.11 3.51 7.02 10.53 17.55 21.06
Compaction 10.0% 5.00 0.13 0.15 0.25 0.50 0.75 1.25 1.50
Labour 5.00 0.13 0.15 0.25 0.50 0.75 1.25 1.50
Machine to lay 5.00 0.13 0.15 0.25 0.50 0.75 1.25 1.50
Unit rate/m2 85.20 2.13 2.56 4.26 8.52 12.78 21.30 25.56 PER M2
HARDCORE

ITEM Cost Per M3 100MM 150MM 200MM 250MM 300MM 400MM 450MM
Supply 2" crusher run 63.80 6.38 9.57 12.76 15.95 19.14 25.52 28.71
Compaction 10.0% 6.38 0.64 0.96 1.28 1.60 1.91 2.55 2.87
Labour 5.00 0.50 0.75 1.00 1.25 1.50 2.00 2.25
Machine 5.00 0.50 0.75 1.00 1.25 1.50 2.00 2.25
TOTAL 80.18 8.02 12.03 16.04 20.05 24.05 32.07 36.08 PER M2
Subcon prelims 0% - - - - - - - -
Unit rate/m2 80.18 8.02 12.03 16.04 20.05 24.05 32.07 36.08 PER M2

LEAN CONCRETE
SUB-STRUCTURE G15 15MM 50MM 75MM 100MM 115MM 150MM 200MM
Supply concrete 200.00 3.00 10.00 15.00 20.00 23.00 30.00 40.00
Wastage 30.0% 60.00 0.90 3.00 4.50 6.00 6.90 9.00 12.00
Labour 16.00 0.24 0.80 1.20 1.60 1.84 2.40 3.20
Plant 15.00 0.23 0.75 1.13 1.50 1.73 2.25 3.00
COST PER M3 291.00 4.37 14.55 21.83 29.10 33.47 43.65 58.20 PER M2
Subcon prelims 0% - - - - - - - -
Unit rate/m2 291.00 4.37 14.55 21.83 29.10 33.47 43.65 58.20 PER M2

SUPER-STRUCTURE G20 15MM 50MM 75MM 100MM 115MM 150MM 200MM


Supply concrete 206.00 3.09 10.30 15.45 20.60 23.69 30.90 41.20
Wastage 30.0% 61.80 0.93 3.09 4.64 6.18 7.11 9.27 12.36
Labour 16.00 0.24 0.80 1.20 1.60 1.84 2.40 3.20
Plant 15.00 0.23 0.75 1.13 1.50 1.73 2.25 3.00
COST PER M3 298.80 4.48 14.94 22.41 29.88 34.36 44.82 59.76 PER M2
Subcon prelims 0% - - - - - - - -
Unit rate/m2 298.80 4.48 14.94 22.41 29.88 34.36 44.82 59.76
CONCRETE

SUB-STRUCTURE G10 G15 G20 G20-P G25 G25-P G30 G30-P G35 G35-P
Supply 195.00 200.00 206.00 215.00 226.00 238.00
Wastage 3.0% 5.85 6.00 6.18 - 6.45 - 6.78 - 7.14 -
Conc Pump/crane 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00
Construction joint & water stop 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00
Mortar - - - - - - - - - - -
Bonding agent - - - - - - - - - -
Labour 18.00 18.00 18.00 18.00 18.00 18.00 18.00 18.00 18.00 18.00 18.00
Unit rate/m3 243.85 249.00 255.18 43.00 264.45 43.00 275.78 43.00 288.14 43.00
0% - - - - - - - - - -
Unit rate/m3 243.85 249.00 255.18 43.00 264.45 43.00 275.78 43.00 288.14 43.00

SUPER-STRUCTURE G15 G15 G20 G20-P G25 G25-P G30 G30-P G35 G35-P
Supply 200.00 200.00 206.00 215.00 226.00 238.00
Wastage 3.0% 6.00 6.00 6.18 - 6.45 - 6.78 - 7.14 -
Conc Pump/crane 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00
Construction joint & water stop 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00
Mortar - Mortar - - - - - - - - -
Bonding agent Bonding agent - - - - - - - - -
Labour 18.00 18.00 18.00 18.00 18.00 18.00 18.00 18.00 18.00 18.00 18.00
259.00 259.00 265.18 53.00 274.45 53.00 285.78 53.00 298.14 53.00
- - - - - - - - - -
Unit rate/m3 0% 259.00 259.00 265.18 53.00 274.45 53.00 285.78 53.00 298.14 53.00

BRC MESH

ITEM A4 A5 A6 A7 A8 A9 A10 A11 A12 A13


A63 A98 A142 A193 A252 A318 A393 A475 A566 A664
Supply BRC rate pe m2 3.37 5.22 6.75 9.18 12.01 15.17 18.72 22.68 29.97 35.19
Wastage+Lapping 25.0% 0.84 1.31 1.69 2.29 3.00 3.79 4.68 5.67 7.49 8.80
Labour 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80
COST PER M2 6.02 8.33 10.24 13.28 16.82 20.76 25.20 30.15 39.26 45.79

ITEM B5 B6 B7 B8 B9 B10 B12 B13


B196 B283 B385 B503 B636 B785 B1131 B1328
Supply BRC rate pe m2 10.30 11.34 13.77 18.04 21.20 24.71 36.63 41.85
Wastage+Lapping 25.0% 2.58 2.83 3.44 4.51 5.30 6.18 9.16 10.46
Labour 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80
COST PER M2 14.68 15.98 19.01 24.36 28.29 32.68 47.59 54.11

ITEM DA7 DA8 DA9 DA10 DA12


B1328 B1328 B1328 B1328 B1328
Supply BRC rate pe m2 18.36 24.03 30.33 37.44 59.94
Wastage+Lapping 25.0% 4.59 6.01 7.58 9.36 14.98
Labour 1.80 1.80 1.80 1.80 1.80 1.80
COST PER M2 24.75 31.84 39.71 48.60 76.73
Subcon prelims 0% - - - - -
24.75 31.84 39.71 48.60 76.73
convertion factor KG/M2 6.04 7.90 9.98 12.32 17.75
COST PER KG 4.10 4.03 3.98 3.94 4.32

REINFORCEMENT BAR
UNIT R6 - R8 R10 - R12 R16 - R32 T10 T12 T16 T20 T25 T32 T40
Material Price per tonne 3,200.00 3,200.00 3,200.00 3,200.00 3,200.00 3,000.00 3,000.00 3,000.00 3,000.00 3,000.00
Cut & bend to size - - - - - - - - - - -
Cost price 3,200.00 3,200.00 3,200.00 3,200.00 3,200.00 3,000.00 3,000.00 3,000.00 3,000.00 3,000.00
Wastage 5.0% 160.00 160.00 160.00 160.00 160.00 150.00 150.00 150.00 150.00 150.00
Crane PRICE UNDER PRELIM
Labour 800.00 800.00 800.00 800.00 800.00 800.00 800.00 800.00 800.00 800.00 800.00
Cost/tonne 4,160.00 4,160.00 4,160.00 4,160.00 4,160.00 3,950.00 3,950.00 3,950.00 3,950.00 3,950.00
Cost/kg 4.16 4.16 4.16 4.16 4.16 3.95 3.95 3.95 3.95 3.95
Subcon prelims 0% - - - - - - - - - -
4.16 4.16 4.16 4.16 4.16 3.95 3.95 3.95 3.95 3.95

FORMWORKS

SAWN FORMWORK conversion USAGE PER F2 PER M2


Plywood 32 3.00 0.47 5.05
Strutting 0.0025 3.00 0.79 8.52
1.26 13.57

ITEM n.e 3.50m 3.50-5.00m 5.00-6.50m 6.50-8.00m F2 F3


Supply 13.57 13.57 13.57 13.57 13.57
additional supply cost - 4.00 8.00 12.00
Replenishment 25% 3.39 3.39 3.39 3.39
Labour 25.00 25.00 25.00 25.00 25.00
41.96 45.96 49.96 53.96
Subcon prelims 0% -
41.96 45.96 49.96 53.96 46.96 51.96
CEMENT MORTAR

1 : 3 MIX 1 : 4 MIX
Cement 28.0 BAGS = 1 M3 18.50 518.00 Cement 28.0 BAGS = 1 M3 18.50 518.00
Sand 3.0 M3 48.00 144.00 Sand 4.0 M3 48.00 192.00
662.00 710.00
Shrinkage 33.00% 218.46 Shrinkage 33.00% 234.30
880.46 944.30
Wastage 5.00% 44.02 Wastage 5.00% 47.22
4 m3 of cement mortar : 924.48 5 m3 of cement mortar : 991.52
COST PER M3 231.12 COST PER M3 198.30

1 : 6 MIX 1 : 2 MIX
Cement 28.0 BAGS = 1 M3 18.50 518.00 Cement 28.0 BAGS = 1 M3 18.50 518.00
Sand 6.0 M3 48.00 288.00 Sand 2.0 M3 48.00 96.00
806.00 614.00
Shrinkage 33.00% 265.98 Shrinkage 33.00% 202.62
1,071.98 816.62
Wastage 5.00% 53.60 Wastage 5.00% 40.83
7 m3 of cement mortar : 1,125.58 4 m3 of cement mortar : 857.45
COST PER M3 160.80 COST PER M3 285.82
Granolithic screed
1 : 3 : 4.5 MIX 1 : 3 : 2 MIX (for Conc Masonry Infill)
Cement 28.00 BAGS = 1 M3 18.50 518.00 Cement 28.0 BAGS = 1 M3 18.50 518.00
Sand 3.00 M3 48.00 144.00 Sand 3.0 M3 48.00 144.00
Granite chipping 1.00 M3 49.00 49.00 Aggregate 2.0 M3 78.40 156.80
Bonding agent 7.00 M3 4.00 28.00 818.80
739.00 Shrinkage 33.00% 270.20
Shrinkage 33.00% 243.87 1,089.00
982.87 Wastage 5.00% 54.45
Wastage 5.00% 49.14 1,143.45
4 m3 of cement mortar : 1,032.01 4 m3 of cement mortar : COST PER M3 285.86
COST PER M3 258.00

BLOCKWALL

INTERNAL EXTERNAL
BLOCK WALL BLOCK WALL
ht 5m high ht 5m high
BLOCK WALL 115 BLOCK WALL 225 BLOCK WALL 115 BLOCK WALL 225
COST/UNIT QTY/M2 M2 QTY/M2 M2 COST/UNIT QTY/M2 M2 QTY/M2
Common bricks 3.400 8.50 28.90 17.00 57.80 3.400 8.50 28.90 17.00
Wastages 5.0% 1.45 2.89 5.0% 1.45
Cement mortar (1:6) incl. wastage 168.84 0.02 3.38 0.05 8.44 168.84 0.02 3.38 0.05
Exmet 0.50 0.50 1.00 0.50 0.50
Stiffener Allowance 5% 1.45 - 2.89 2% 0.58 -
DPC & BONDING TIE Allow - - 0.80 - -
Labour normal 0.40 58.00 23.20 116.00 46.40 0.60 58.00 34.80 116.00
Total/m2 58.87 120.22 69.60

BRICKWORKS (CEMENT SAND)

INTERNAL EXTERNAL
CEMENT SAND BRICK CEMENT SAND BRICK
ht 5m high ht 5m high
CEMENT SAND 115 CEMENT SAND 225 CEMENT SAND 115 CEMENT SAND 225
COST/UNIT QTY/M2 M2 QTY/M2 M2 COST/UNIT QTY/M2 M2 QTY/M2
Cement sand brick 0.190 58.00 11.02 116.00 22.04 0.190 58.00 11.02 116.00
Wastages 5.0% 0.55 1.10 5.0% 0.55
Cement mortar (1:6) incl. wastage 168.84 0.02 3.38 0.05 8.44 168.84 0.02 3.38 0.05
Exmet 0.50 0.50 1.00 1.00 1.00
Labour 0.35 58.00 20.30 116.00 40.60 0.45 58.00 26.10 116.00
Total/m2 35.75 73.18 42.05

BRICKWORKS (CLAY BRICK)

INTERNAL EXTERNAL
COMMON CLAY BRICK COMMON CLAY BRICK
ht 5m high ht 5m high
CLAY BRICK 115 CLAY BRICK 225 CLAY BRICK 115 CLAY BRICK 225
COST/UNIT QTY/M2 M2 QTY/M2 M2 COST/UNIT QTY/M2 M2 QTY/M2
Common bricks 0.340 58.00 19.72 116.00 39.44 0.340 58.00 19.72 116.00
Wastages 5.0% 0.99 1.97 5.0% 0.99
Cement mortar (1:6) incl. wastage - 0.02 3.38 0.05 8.44 - 0.02 3.38 0.05
Exmet 0.50 0.50 1.00 0.50 0.50
Stiffener Allowance 5% 0.99 - 1.97 2% 0.39 -
DPC & BONDING TIE Allow - - 0.80 - -
Labour normal 0.30 58.00 17.40 116.00 34.80 0.40 58.00 34.80 116.00
Total/m2 42.97 88.43 59.78

PLASTERING
PLASTERING CEMENT MORTAR 1:3
INTERNAL EXTERNAL
COST/UNIT 12MM 13MM 19MM 20MM 25MM 12MM 19MM 20MM
Cement mortar (1:6) 160.80 1.93 2.09 3.06 3.22 4.02 160.80 1.93 3.06 3.22
Wastages 5.0% 0.10 0.10 0.15 0.16 0.20 5.0% 0.10 0.15 0.16
Eix mix 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77
Groove line - - - - - - - -
Corner Bead / metal lath 2.80 2.80 2.80 2.80 2.80 2.80 2.80 2.80 2.80 2.80
MATERIAL COST 5.60 5.77 6.78 6.95 7.79 5.60 6.78 6.95
Labour 20.00 20.00 20.00 20.00 20.00 20.00 11.00 11.00 11.00 11.00
Cost/m2 for ht <3.50m 25.60 25.77 26.78 26.95 27.79 16.60 17.78 17.95

RENDERING (PAVING)

PAVINGS CEMENT MORTAR 1:3


COST/UNIT 20MM 25MM 30MM 48MM 50MM 75MM 12MM
Cement mortar (1:3) 231.12 4.62 5.78 6.93 11.09 11.56 17.33 2.77
Wastages 10% 0.46 0.58 0.69 1.11 1.16 1.73 0.28
waterproof - 0.46 0.58 0.69 1.11 1.16 1.73 0.28
MATERIAL COST 5.55 6.93 8.32 13.31 13.87 20.80 3.33
Labour 12.00 12.00 12.00 12.00 12.00 12.00 12.00 12.00
Total/m2 17.55 18.93 20.32 25.31 25.87 32.80 15.33

Labour to render to treat/ riser


treat/ riser 12.00 RM/M
nosing tile to staircase 18.00 RM/M
scupper drain 200x50 20.00 RM/M
350x150 27.00 RM/M
400x150 28.00 RM/M
500x150 30.00 RM/M
250x50 21.00 RM/M
300x50 22.00 RM/M
380x50 24.00 RM/M
grooove line 40x20mm 20.00 RM/M

BACKING SCREED
SCREEDING C&S 1:3
COST/UNIT 20MM 25MM 30MM 38MM 42MM 50MM 60MM 15MM 80MM 13MM
Cement mortar (1:3) 231.12 4.62 5.78 6.93 8.78 9.71 11.56 13.87 3.47 18.49 3.00
Wastages 10% 0.46 0.58 0.69 0.88 0.97 1.16 1.39 0.35 1.85 0.30
add for pump 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50
fibre mesh 12 0.59 0.78 0.94 0.94 0.94
MATERIAL COST 5.58 6.86 8.12 10.75 11.18 14.00 16.70 4.32 21.78 4.74
Labour 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00
Total/m2 13.58 14.86 16.12 18.75 19.18 22.00 24.70 12.32 29.78 12.74

screed to riser/ tread 9.00 per m


Skirting 15.50 per m
nosing 5.50 per m
drop 25mm 4.50 per m
drop 50mm 5.50 per m
drop 75mm 6.50 per m
drop 100mm 7.00 per m

SKIM COATING

RENDER Cost/unit 1MM 2MM 3MM 4MM 5MM


Skim coat 15.40 0.62 1.23 1.85 2.46 3.08 coverage =
Wastage 8.00% 0.05 0.10 0.15 0.20 0.25 1 bag (40kg) =
MATERIAL COST 0.67 1.33 2.00 2.66 3.33 1 bag (40kg) =
Labour 1.50 1.50 1.50 1.50 1.50 1.50 40bag =
Total/m2 2.17 2.83 3.50 4.16 4.83

BASE Cost/unit 1MM 2MM 3MM 4MM 5MM


Skim coat 18.85 0.66 1.32 1.98 2.64 3.30 coverage =
Wastage 8.00% 0.05 0.11 0.16 0.21 0.26 1 bag (40kg) =
MATERIAL COST 0.71 1.43 2.14 2.85 3.56 1 bag (40kg) =
Labour 1.50 1.50 1.50 1.50 1.50 1.50 35bag =
Total/m2 2.21 2.93 3.64 4.35 5.06

FINISH Cost/unit 1MM 2MM 3MM 4MM 5MM


Skim coat 19.05 0.91 1.83 2.74 3.66 4.57 coverage =
Wastage 8.00% 0.07 0.15 0.22 0.29 0.37 1 bag (25kg) =
MATERIAL COST 0.99 1.98 2.96 3.95 4.94 1 bag (25kg) =
Labour 1.50 1.50 1.50 1.50 1.50 1.50 48bag =
Total/m2 2.49 3.48 4.46 5.45 6.44
to direct key-in price / rate
to link to choose rate
hange size / thickness
/ rate link from table
G40 G40-P G45 G45-P G50 G50-P G35A G55-P G60 G60-P
252.00 268.00 -
7.56 - 8.04 - - - - - - -
20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00
5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00
- - - - - - - - - -
- - - - - - - - - -
18.00 18.00 18.00 18.00 18.00 18.00 18.00 18.00 18.00 18.00
302.56 43.00 319.04 43.00 43.00 43.00 43.00 43.00 43.00 43.00
- - - - - - - - - -
302.56 43.00 319.04 43.00 43.00 43.00 43.00 43.00 43.00 43.00

G40 G40-P G45 G45-P G50 G50-P G35A G55-P G60 G60-P
252.00 268.00 -
7.56 - 8.04 - - - - - - -
30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00
5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00
- - - - - - - - - -
- - - - - - - - - -
18.00 18.00 18.00 18.00 18.00 18.00 18.00 18.00 18.00 18.00
312.56 53.00 329.04 53.00 53.00 53.00 53.00 53.00 53.00 53.00
- - - - - - - - - -
312.56 53.00 329.04 53.00 53.00 53.00 53.00 53.00 53.00 53.00
CK WALL 225 BLOCK WALL 450
M2 QTY/M2 M2
57.80 34.00 115.60
2.89 5.78
8.44 0.08 13.51
1.00 1.00
1.16 - 2.31
1.20 1.20
69.60 34.00 20.40
142.09 159.80

MENT SAND 225 CEMENT SAND 345


M2 QTY/M2 M2
22.04 174.00 33.06
1.10 1.65
8.44 0.06 10.13
2.00 4.00
52.20 174.00 78.30
85.78 127.14

Y BRICK 225 CLAY BRICK 450


M2 QTY/M2 M2
39.44 232.00 78.88
1.97 3.94
8.44 0.08 13.51
1.00 1.00
0.79 - 1.58
1.20 1.20
69.60 232.00 139.20
122.44 239.31

XTERNAL
25MM 35.00
4.02 5.63
0.20 0.28
0.77 0.77
- -
2.80 2.80
7.79 9.48
11.00 11.00
18.79 20.48
Skim coat - Render
1.60kg/m2/mm
25.0 m2/mm Render (40kg) - External
0.025 m3 Base (40kg) - Internal base
1m3 Finish (25kg) - Internal Finish

Skim coat - Base


1.40kg/m2/mm
28.6 m2/mm
0.029 m3
1m3

Skim coat - Finish


1.20kg/m2/mm
20.8 m2/mm
0.021 m3
1m3
48% less
price/m2 supply wages

26.70 13.88 1.80


20.40 10.61 1.80
wastage la crane cost
35%

4.86 0.50 21.04


3.71 0.50 16.62

You might also like