0% found this document useful (0 votes)
18 views

MTH601 Solution

The document provides solutions to four questions. Question 1 involves network diagramming and calculating earliest start and finish times. Question 2 identifies the critical path and total project duration. Question 3 calculates economic order quantity. Question 4 calculates expected times, variances, and standard deviations for activities.

Uploaded by

Javeria Fayyaz
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
18 views

MTH601 Solution

The document provides solutions to four questions. Question 1 involves network diagramming and calculating earliest start and finish times. Question 2 identifies the critical path and total project duration. Question 3 calculates economic order quantity. Question 4 calculates expected times, variances, and standard deviations for activities.

Uploaded by

Javeria Fayyaz
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 5

MTH601

Assignment
Solution vu360
Question 1 Solution By Mudasar Qureshi:

(a) Network Diagram:

A --> B --> D --> G


/ --> C --> E --> H
| --> F -->
+

(b) Time Estimates:

Activity Duration Predecessor Earliest Start Time Earliest Finish Time

A 5 - 0 5

B 7 A 5 12

C 9 A 5 14

D 11 B 12 23

E 3 C 14 17

F 6 C 14 20

G 6 D, F 23 29

H 8 E 17 25

Vu360 Assignments Solutions: https://chat.whatsapp.com/HJYBCFqTTpX3QYAHhOLSa2

Share with your friends.


Here are the calculations for Earliest Start Time (EST) and Earliest Finish Time (EFT) for each
activity:
Earliest Start Time (EST)
 A: 0 (no predecessor)
 B: 5 (A's EFT)
 C: 5 (A's EFT)
 D: 12 (B's EFT)
 E: 14 (C's EFT)
 F: 14 (C's EFT)
 G: 23 (max of D's EFT and F's EFT)
 H: 17 (E's EFT)
Earliest Finish Time (EFT)
 A: 5 (EST + Duration)
 B: 12 (EST + Duration)
 C: 14 (EST + Duration)
 D: 23 (EST + Duration)
 E: 17 (EST + Duration)
 F: 20 (EST + Duration)
 G: 29 (EST + Duration)
 H: 25 (EST + Duration)

Vu360 Assignments Solutions: https://chat.whatsapp.com/HJYBCFqTTpX3QYAHhOLSa2

Share with your friends.


Question 2 Solution By Mudasar Qureshi:

To find the critical path and total project duration, we need to construct a network diagram and
calculate the Earliest Start Time (EST), Earliest Finish Time (EFT), Latest Start Time (LST), and Latest
Finish Time (LFT) for each activity.

Network Diagram:

A --> C --> E --> G --> I --> J

/ --> D --> I

| /--> E --> H --> J

|/--> F --> J

Calculations:

Activity Duration Predecessor EST EFT LST LFT

A 15 - 0 15 0 15

B 15 - 0 15 0 15

C 3 A 15 18 15 18

D 5 A 15 20 15 20

E 8 B, C 18 26 18 26

F 12 B, C 18 30 18 30

G 1 E 26 27 26 27

H 14 E 26 40 26 40

I 3 D, G 27 30 27 30

J 14 F, H, I 40 54 40 54

Vu360 Assignments Solutions: https://chat.whatsapp.com/HJYBCFqTTpX3QYAHhOLSa2

Share with your friends.


Critical Path:

The critical path is the longest path in the network diagram, which determines the total project
duration. The critical path is:

B -> E -> F -> H -> J

Total Project Duration:

The total project duration is the Earliest Finish Time (EFT) of the last activity, which is J.

Total Project Duration = 54 units

Question 3 Solution By Mudasar Qureshi:


𝐺𝑖𝑣𝑒𝑛 𝐷𝑎𝑡𝑎:
𝑌𝑒𝑎𝑟𝑙𝑦 𝑑𝑒𝑚𝑎𝑛𝑑 (𝐷) = 10,000 𝑢𝑛𝑖𝑡𝑠
𝑈𝑛𝑖𝑡 𝑐𝑜𝑠𝑡 (𝐶) = 𝑅𝑠 1
𝐻𝑜𝑙𝑑𝑖𝑛𝑔 𝑐𝑜𝑠𝑡 (𝐻) = 20% 𝑜𝑓 𝑢𝑛𝑖𝑡 𝑐𝑜𝑠𝑡 = 𝑅𝑠 0.20 𝑝𝑒𝑟 𝑢𝑛𝑖𝑡 𝑝𝑒𝑟 𝑦𝑒𝑎𝑟
𝑆𝑒𝑡𝑢𝑝 𝑐𝑜𝑠𝑡 (𝑆) = 𝑅𝑠 10
𝑆𝑡𝑜𝑐𝑘𝑜𝑢𝑡 𝑐𝑜𝑠𝑡 (𝑃) = 𝑅𝑠 5 𝑝𝑒𝑟 𝑢𝑛𝑖𝑡 𝑜𝑓 𝑠ℎ𝑜𝑟𝑡𝑎𝑔𝑒
𝐶𝑎𝑙𝑐𝑢𝑙𝑎𝑡𝑖𝑜𝑛𝑠:
𝐸𝑐𝑜𝑛𝑜𝑚𝑖𝑐 𝑂𝑟𝑑𝑒𝑟 𝑄𝑢𝑎𝑛𝑡𝑖𝑡𝑦 (𝐸𝑂𝑄):

2𝑆𝐷
𝐸𝑂𝑄 = √
𝐻

2 𝑥 10 𝑥 10,000
= √
0.20

1,000,000
= √
0.20

= √5,000,000
= 2,236.07 𝑢𝑛𝑖𝑡𝑠 (𝑎𝑝𝑝𝑟𝑜𝑥𝑖𝑚𝑎𝑡𝑒𝑙𝑦)
𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑜𝑟𝑑𝑒𝑟𝑠 𝑝𝑒𝑟 𝑦𝑒𝑎𝑟:
𝑌𝑒𝑎𝑟𝑙𝑦 𝑑𝑒𝑚𝑎𝑛𝑑
𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑜𝑟𝑑𝑒𝑟𝑠 𝑝𝑒𝑟 𝑦𝑒𝑎𝑟 =
𝐸𝑂𝑄

Vu360 Assignments Solutions: https://chat.whatsapp.com/HJYBCFqTTpX3QYAHhOLSa2

Share with your friends.


10,000 𝑢𝑛𝑖𝑡𝑠
= = 4.47 (𝑎𝑝𝑝𝑟𝑜𝑥𝑖𝑚𝑎𝑡𝑒𝑙𝑦)
2,236.07
𝑢𝑛𝑖𝑡𝑠
𝑆𝑖𝑛𝑐𝑒 𝑤𝑒 𝑐𝑎𝑛′𝑡 𝑝𝑙𝑎𝑐𝑒 𝑎 𝑓𝑟𝑎𝑐𝑡𝑖𝑜𝑛 𝑜𝑓 𝑎𝑛 𝑜𝑟𝑑𝑒𝑟,
𝑤𝑒′𝑙𝑙 𝑟𝑜𝑢𝑛𝑑 𝑢𝑝 𝑡𝑜 𝑡ℎ𝑒 𝑛𝑒𝑎𝑟𝑒𝑠𝑡 𝑤ℎ𝑜𝑙𝑒 𝑛𝑢𝑚𝑏𝑒𝑟 𝑡𝑜 𝑒𝑛𝑠𝑢𝑟𝑒 𝑚𝑒𝑒𝑡𝑖𝑛𝑔 𝑑𝑒𝑚𝑎𝑛𝑑.
𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑜𝑟𝑑𝑒𝑟𝑠 𝑝𝑒𝑟 𝑦𝑒𝑎𝑟 = 5

Question 4 Solution By Mudasar Qureshi:

Calculations:

Activity Expected Time (te) Variance (σ²) Standard Deviation (σ)

A (3+5+7)/3 = 5 ((7-5)^2 + (5-5)^2 + (3-5)^2)/18 = 2 √2 = 1.414

B (2+4+6)/3 = 4 ((6-4)^2 + (4-4)^2 + (2-4)^2)/18 = 1.33 √1.33 = 1.155

C (4+6+8)/3 = 6 ((8-6)^2 + (6-6)^2 + (4-6)^2)/18 = 2 √2 = 1.414

D (5+7+9)/3 = 7 ((9-7)^2 + (7-7)^2 + (5-7)^2)/18 = 2 √2 = 1.414

E (6+8+10)/3 = 8 ((10-8)^2 + (8-8)^2 + (6-8)^2)/18 = 2 √2 = 1.414

F (3+5+7)/3 = 5 ((7-5)^2 + (5-5)^2 + (3-5)^2)/18 = 2 √2 = 1.414

G (4+6+8)/3 = 6 ((8-6)^2 + (6-6)^2 + (4-6)^2)/18 = 2 √2 = 1.414

𝐹𝑜𝑟𝑚𝑢𝑙𝑎𝑠 𝑢𝑠𝑒𝑑:
(𝑡𝑚 + 𝑡𝑝 + 𝑡𝑚)
𝐸𝑥𝑝𝑒𝑐𝑡𝑒𝑑 𝑇𝑖𝑚𝑒 (𝑡𝑒) =
3
((𝑡𝑝 − 𝑡𝑚)2 + (𝑡𝑚 − 𝑡𝑒)2 + (𝑡𝑒 − 𝑡𝑚)2)
𝑉𝑎𝑟𝑖𝑎𝑛𝑐𝑒 (𝜎2) =
18

𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝐷𝑒𝑣𝑖𝑎𝑡𝑖𝑜𝑛 (𝜎) = √𝑉𝑎𝑟𝑖𝑎𝑛𝑐𝑒


𝑁𝑜𝑡𝑒: 𝑡𝑚, 𝑡𝑝, 𝑎𝑛𝑑 𝑡𝑒 𝑟𝑒𝑝𝑟𝑒𝑠𝑒𝑛𝑡 𝑡ℎ𝑒 𝑚𝑖𝑛𝑖𝑚𝑢𝑚, 𝑚𝑎𝑥𝑖𝑚𝑢𝑚, 𝑎𝑛𝑑 𝑒𝑥𝑝𝑒𝑐𝑡𝑒𝑑 𝑡𝑖𝑚𝑒𝑠, 𝑟𝑒𝑠𝑝𝑒𝑐𝑡𝑖𝑣𝑒𝑙𝑦
.

Vu360 Assignments Solutions: https://chat.whatsapp.com/HJYBCFqTTpX3QYAHhOLSa2

Share with your friends.

You might also like