Timber Formwork
Timber Formwork
TIMBER FORMWORK
Patil Sneha Mahesh Bidavi Riddhi Rajendra Frade Supriya Chandrakant Wable Vaishali Vishwanath
Department of Civil Department of Civil Department of Civil Department of Civil
Engineering Engineering Engineering Engineering
ARMIET, ARMIET, ARMIET, ARMIET,
Shahapur, India Shahapur, India Shahapur, India Shahapur, India
[email protected] [email protected] [email protected] [email protected]
010414 www.ijiird.com 60
INTERNATIONAL JOURNAL OF INTERDISCIPLINARY INNOVATIVE RESEARCH AND DEVELOPMENT (IJIIRD)
III. SCOPE AND STUDY AREA better coordinated. Room sizes can vary a few inches to
accommodate the structural design ;
The scope of this Project is limited to the structural The engineer/architect should consider architectural
elements of building projects such as column, beam, slab, features, depressions, and openings for mechanical or
shear wall and stair that are casted in the construction site. In electrical work when detailing the structural system, with
addition this research will be based on the comparison of two the aim of achieving economy. Variations in the structural
type of formwork for concrete elements. It will not be focused system caused by such items should be shown on the
on the rivalry between two specific opposing systems, nor that structural plans. Wherever possible, depressions in the
between two different manufacturers. The purpose is not to tops of slabs should be made without a corresponding
prove that one product is superior to another, but rather to break in elevations of soffits of slabs, beams or joists;
determine which systems, steel panel or timber panel, are Embedment for attachment to or penetration through the
superior. concrete structure should be design to minimize random
The research was conducted for different category of building penetration of formed surface;
type such as apartment, office, multipurpose, condominium Avoid locating columns or walls, even for few floors,
and hospital buildings. The study compromise different where they would interfere with the use of large
category of contractors, starting from grade 6 up to grade 1 formwork shoring units in otherwise clear bays.
contractor, involved in the construction of building projects.
VI. LITERATURE REVIEW
IV. OBJECTIVES OF RESEARCH WORK The type of formwork systems used is among the key
factors determining the success of a construction project in
To study the present condition of timber formwork and its terms of speed, quality, cost and safety of works. Therefore,
material. selecting the formwork system, that is, making structural
To do various types of timber formwork to obtain the frames faster, simpler, and less costly to build, must begin in
good design. the earliest phase of the design efforts(Basher Alamin,
To design the best and effective formwork. 1999).Generally there are two board category of formwork
To design and analysis the timber formwork in different system as horizontal and vertical formwork system; these are
types. described in detail below.
As we research the topic of timber formwork for
concrete it is anticipated that this review will continue to grow
as we find more work previously done, more opinions and are
V. ECONOMICAL CONSIDERATION OF FORMWORK able to search more specifically following our own findings in
preliminary tests. It is also to be expected that the literature
review will begin to become more specific as we become
To simplify and permit maximum reuse of formwork, the experts on the subject and follow detailed areas of research
dimensions of footings, columns and beams should be of within the field.
standard material multiples, and the number of sizes At this time, much of the literature reviewed is broad
should be minimized; overviews as we familiarize ourselves with the timber
When interior columns are the same width as or smaller formwork process and what has been done in the field as a
than the girders they support, the column form becomes whole rather than looking too specifically at the formwork for
a simple rectangular or square box without box outs, and non-prismatic columns.
the slab form does not have to be cut out at each corner of Among the first pieces of literature looked at
the column ; was Formwork for Concrete Structures, 1965 by A.E.
When all beams are made one depth (beams framing into Wynn & G.P. Manning. This was to gain a better
beams as well as beams framing into columns), the understanding of traditional formwork solutions, primarily the
supporting structures for the beam form can be carried on application of timber formwork. The book stresses the need
level platform supported on shores; for skilled and experienced craftsmanship highlighting the
Considering available sizes of dressed lumber, plywood, potentially huge costs in time, money and materials should the
formwork be constructed incorrectly. Just some of the
and other ready-made formwork components and
problems that can arise include; material waste due to
keeping beam and joist sizes constant will reduce labor
excessive timber used, failure due to inadequate timber used,
time;
lengthy construction due to inexperience, lengthy dismantling
The design of the structure should be based on the use of
due to inexperience, high transport costs… etc. The book also
one standard depth wherever possible when states that these issues are particularly important when casting
commercially available forming systems, such as one or
concrete columns as strength is extremely important and any
two-way joist systems, are used;
finish defects will be more obvious than on other elements.
The structural design should be prepared simultaneously
with the architectural design so that dimensions can be
010414 www.ijiird.com 61
INTERNATIONAL JOURNAL OF INTERDISCIPLINARY INNOVATIVE RESEARCH AND DEVELOPMENT (IJIIRD)
Pedreschi also highlights three perceptions of concrete Based on rental cost of the formwork system all
construction that fabric formwork directly challenges. These respondents prefer steel formwork system than timber
are; formwork system. As remark all respondents pointed out
that finding rental timber formwork is difficult and there
• It is a harsh and unforgiving material is no company that involved in renting timber formwork.
• Accuracy requires great skill and detail specification Modern timber formwork system such as MDF and ply
• Complexity in form is expensive wood improve productivity of labour force. Factors such
as less required time of maintenance, large panel size and
smooth formwork face for modern formwork system with
RESULTS AND ANALYSIS compared to steel formwork system helps in improving
productivity of MDF and ply wood formworks.
The average per meter square cost of steel formwork is
Table (1). Average cost of formwork per square meter higher than timber formwork system. Cost of steel beam
Respondents(R) Steel
Structural
Timber formwork is 17.05% higher than timber beam formwork,
R1 R2 R3 R4 R5 R6 R7 R8 R9
Average Average
column steel formwork costs 22.88% higher than timber
element Cost
Cost column formwork and steel slab formwork costs 23.16%
Beam 35* 65 70* 250* 150 132* 108* 90 119 101.67
than timber slab formwork. Taking average the difference
is steel formwork costs 16.96% higher than timber
Column 35* 65 70* 250* 150 94* 108* 90 72 115.75 94.2
formwork.
Slab 35* 40* 55 250* 150 132* 108* 90 72 113 91.75 The main justifications for this statement is steel
formwork can be reused for so many time than timber
Stair 35* 55* 75* 250* 150 132* 108 90 72 109.4 105
formwork system, it required less number of props for
Shear wall 35* 90 70* 250* 150 94 108 90 72 118.33 100.67 beams and slabs, it easily available for rental and it is
possible to maintain.
For best quality of finished concrete, it is better to use
modern timber formwork system such as MDF and ply
Table (2). Average cost difference for steel & timber formwork per square
meter. wood. Modern timber formwork system have smooth
Structural Steel Timber Difference in surface that helps in the time of removing the formwork
elements formwork formwork both from concrete surface.
average cost average cost The type of formwork used in building projects affects
per meter per meter the productivity of labour force.
square. square.
Beam 119 101.67 17.4 RECOMMENDATIONS
Columns 115.75 94.2 21.55
Slabs 113 91.75 21.25 Based on my findings the following two
recommendations are given on cost and time of construction
Stairs 109.4 105 4.4 of the formwork.
Shear wall 118.33 100.7 17.66 1. Cost of formwork system:-
Unlike our perception the cost of steel formwork
system does not have much difference with compared to cost
of timber formwork system. Even in same projects the cost of
imported modern timber formwork system is greater than
CONCLUSION conventional steel formwork system. Thus proper life cycle
costing should be performed by contractors to accurately
The main objective of this research is to compare steel determine whether the steel formwork system used in building
and timber formwork for building projects and to come up projects will justify the higher initial cost when looked at over
which system advantageous in regarding with cost, quality and the lifespan of the forms.
completion time of the of building projects. Considering these
three parameters analysis has been done in chapter four and 2. Completion time of formwork:-
based the results of the analysis the following conclusion has Steel formwork can have faster rate of erection
been made:- during construction when we compared with timber formwork
Initial cost analysis of the formwork shows that timber system but this is not always true when comes to modern
formwork is cheaper than steel formwork but most of the timber formwork system they improve the productivity of the
respondents prefer to buy steel formwork over timber crew. Thus future research should focus on better defining
formwork system. and quantifying the influence of type of formwork on
productivity of crew. Factors such as formwork maintenance,
010414 www.ijiird.com 62
INTERNATIONAL JOURNAL OF INTERDISCIPLINARY INNOVATIVE RESEARCH AND DEVELOPMENT (IJIIRD)
panel size and formwork face were touched upon in this 10. Abebe Dinku. (2007). A Text book of Building
thesis, but require further research to determine their precise construction. (1 st ed.). Addis Ababa: Addis Ababa University
impact on productivity. Printing press. P224-238
Future Study:-
The following three suggestions are put forward for 11. American Concrete Institute (ACI), Committee 347R-94.
future research to further improve the understanding of (1994). Recommended practice for concrete formwork (ACI
formwork construction for building projects: 347R 94). Detroit, Michigan: American Concrete Institute
The effect of type of formwork on the productivity of 12. Alamin, B. (1999). Analysis of construction loads on
the crew concrete formwork. Unpublished master‟s thesis, Concorde
The impact of formwork maintenance, panel size and University. USA
formwork face on the productivity
Life cycle costing of the formwork in the projects 13. American Society of Concrete Contractors ASCC (2008),
The Contractor‟s Guide to Quality Concrete Construction,
USA
REFERENCES
14. Argaw Tarekegn. (2010). Application of modern
1. Orr, J. J., Darby, A. P., Ibell, T. J., Evernden, M. C. formwork system in Ethiopia. Unpublished master‟s thesis,
and Otlet, M., 2011. Concrete structures using fabric Addis Ababa University. Addis Ababa, Ethiopia.
formwork. The Structural Engineer, 89 (8), pp. 20-26.
15. British Standards BS8110-1997 part 1, Structural Use
2. WRI (2005) Carbon Dioxide Emissions by Source 2005. Concrete
Earth trends Data Tables: Climate and Atmosphere, Available
online 16. Doka framed formwork. Frami 300 product catalogue.
2005. Doka formwork international.)
3. Orr JJ, Darby AP, Ibell TJ, et al (2011) Concrete structures
using fabric formwork. The Structural Engineer 89(8): 17. Edward, G. (2008). Concrete Construction Engineering
2026. http://opus.bath.ac.uk/23588/ Hand Book. (2 nded.). New Brunswick, New Jersey
4. Kostova K, Ibell T, Darby AP and Evernden M (2012) 18. Ethiopian Building Codes Standard, EBCS2 (1995).
Advanced composite reinforcement for fabric formed strutural Structural Use of Concrete. Addis Ababa
elements. In Second International Conference on Flexible
Formwork (Orr JJ, Darby AP, Evernden M and Ibell T. (eds)). 19. Fetene Nega. (2008). Causes and Effects of Cost overrun
University of Bath, Bath, UK. www.icff2012.co.uk on Public building construction projects in Ethiopia.
Unpublished master‟s thesis, Addis Ababa University. Addis
5. Garbett J, Darby AP and Ibell TJ (2010) Optimised beam Ababa, Ethiopia.
design using innovative fabric-formed concrete. Advances in
Structural Engineering 13(5): 849-860. 20. Hanna, A.S. (1999). Concrete formwork system. (1st ed.).
New York: Marcel Dekker, Inc.,
6.Orr JJ, Darby AP, Ibell TJ and Evernden M (2012a)
Optimisation and durability in fabric cast 'Double T' beams. In 21. Hurd, M.K. (1995). Formwork for concrete AC1 SP-4.
The Second International Conference on Flexible Formwork (6th ed.). Detroit, Michigan: American Concrete Institute.
(Orr JJ, Darby AP, Evernden M and Ibell
T. (eds)). University of Bath, Bath, UK. 22. Jensen, D.A. (1986). Choosing a forming system for
http://opus.bath.ac.uk/30078/ concrete floors and roofs. Concrete Construction, 8 1(1), 5-12
7.Lee, DSH (2010) Study of construction methodology and 23. Niekerk, A.J. (2009). Concrete elements: Timber faced
structural behaviour of fabric formed form-efficient reinforced formwork versus steel faced formwork systems, and which is
concrete beam. PhD Thesis, University of Edinburgh, truly better for the contractor?. Unpublished master‟s thesis,
Edinburgh. University of Pretoria. Pretoria, South Africa
8.[Section 90-7] from the Caltrans Standard Specifications, 24. Peurifoy , R.L. and Oberlender, G.D. (2011). Formwork
2006 for concrete structures. (4 th ed.). New York: McGraw-Hill
Inc.
9.[Section 6-02.3(11)] from the WSDOT Standard
Specifications, 2006 25. Ratay, R.T. (1996), Handbook of temporary structures in
construction. (2 nded.). New York: McGraw-Hill, Inc.
010414 www.ijiird.com 63