Tutorial Chapter 9 (Week 4) A
Tutorial Chapter 9 (Week 4) A
Answer
To calculate the payback period, we need to find the time that the project requires to recover
its initial investment. After three years, the project has created:
Payback = 3 + ($500/$1,700)
Payback = 3.29 years
Answer
To calculate the payback period, we need to find the time that the project requires to recover
its initial investment. The cash flows in this problem are an annuity, so the calculation is
simpler. If the initial cost is $1,900, the payback period is:
Payback = 2 + ($230/$835)
Payback = 2.28 years
There is a shortcut to calculate payback period when the project cash flows are an annuity.
Just divide the initial cost by the annual cash flow. For the $3,600 cost, the payback period is:
Payback = $3,600/$835
Payback = 4.31 years
The payback period for an initial cost of $7,400 is a little trickier. Notice that the total cash
inflows after eight years will be:
Total cash inflows = 8($835)
Total cash inflows = $6,680
If the initial cost is $7,400, the project never pays back. Notice that if you use the shortcut for
annuity cash flows, you get:
Payback = $7,400/$835
Payback = 8.86 years
This answer does not make sense since the cash flows stop after eight years, so again, we
must conclude the payback period is never.
Answer
When we use discounted payback, we need to find the value of all cash flows today. The
value today of the project cash flows for the first four years is:
Value today of Year 1 cash flow = $2,800/1.09 = $2,568.81
Value today of Year 2 cash flow = $3,700/1.092 = $3,114.22
Value today of Year 3 cash flow = $5,100/1.093 = $3,938.14
Value today of Year 4 cash flow = $4,300/1.094 = $3,046.23
To find the discounted payback, we use these values to find the payback period. The
discounted first year cash flow is $2,568.81, so the discounted payback for a $5,200 initial
cost is:
Discounted payback = 1 + ($5,200 – 2,568.81)/$3,114.22
Discounted payback = 1.84 years
The equation for the NPV of the project at a 24 percent required return is:
NPV = –$41,000 + $20,000/1.24 + $23,000/1.242 + $14,000/1.243
NPV = –$2,569.77
At a required return of 24 percent, the NPV is negative, so we would reject the project.
Answer
The NPV of a project is the PV of the inflows minus the PV of the outflows. At a zero
discount rate (and only at a zero discount rate), the cash flows can be added together across
time. So, the NPV of the project at a zero percent required return is:
NPV = –$18,700 + 9,400 + 10,400 + 6,500
NPV = $7,600
Notice that as the required return increases, the NPV of the project decreases. This will
always be true for projects with conventional cash flows. Conventional cash flows are
negative at the beginning of the project and positive throughout the rest of the project.
Answer
a. The payback period for each project is:
A: 3 + ($144,000/$366,000) = 3.39 years
B: 2 + ($4,000/$17,200) = 2.23 years
The payback criterion implies accepting Project B, because it pays back sooner than
Project A.