Operating Manual
Operating Manual
3. Maintenance 25
3.1 Installation & Inspection Check List
3.2 Flange-Type Sleeve Bearing (for ring lubrication system)
3.3 Flange-Type Sleeve Bearing (forced lubrication system)
3.4 Rolling-Contact Bearings (series 02 and 03)
3.5 Coupling A-Type (single-bearing generators with flanged shaft and one-part fan wheel)
3.6 Coupling B-Type (single-bearing generators with flanged shaft)
3.7 Coupling (double bearing generator)
3.8 Air Filters
3.9 Terminal Box
3.10 Disassembly of A.C. Generator (Fig. 39 and 40)
3.11 Cooler
3.12 Cooling-Water Failure Emergency Operation
4. Trouble Shooting 46
4.1 Excitation Part for SPRESY 15
4.2 Excitation Part for 6 GA 2491
4.3 Main Machines and Exciters (HF. 5 and 6)
4.4 Bearing Part
4.5 Operating Procedure & Check Sheet for Trouble Shooting
DANGER
This warning is used when an operation, procedure, or 1.1 Component
use may cause personal injury or loss of life.
The brushless A.C. generators, as shown in Figs. 8. 9. 10
and 11, (drip-proof type, totally-enclosed internal-cooling
WARNING
type) are composed of
This Warning is used when an operation, procedure, or a synchronous generator
use may cause a latently dangerous state of personal
an A.C. exciter
injury or loss of life.
a Rotary rectifier
static excitation devices.
CAUTION
Fig. 1 Single line diagram for brushless generator Unless otherwise stated, the rated output for continuous
operation applies to a frequency of 50 Hz, a cooling-air
temperature of 40 and a site altitude of up to 1000 m
above sea level.
3) Degree of protection
The DIN 40050 or IEC 34-5 degree of protection of basic
design machines is IP 23. Such machines are suitable for
operation indoors and may be provided with a built-in
filter box or with pipe connections.
Closed-circuit cooled machines comply with degree of
1.2 General protection IP 54.
The degree of protection of the machine supplied is
1) Type definition shown in the dimension drawing.
The supply scope of the machine designs a vailable is
determined entirely by the data given in the catalogs or
offers. The machines of basic design are open-circuit 4) Type of construction
cooled, brushless, low-voltage, synchronous machines The machines are normally provided with two bearings
with top-mounted excitation control unit. (DIN 42950 types of construction B3 or B20) or with one
bearing (DIN 42950 types of construction B2 or B16).
The machines have a shaft-mounted exciter on the The type of construction of the machine supplied is
inboard side of the non-drive endshield. shown in the dimension drawing.
The three-phase AC they generate is rectified and fed to
the rotor winding of the main machine.
5) Cooling and ventilation
The excitation current required for the shaft-mounted The basic design machines use self-ventilation by a shaft-
exciter is provided by the main machine via an excitation mounted internal fan at the AS-end.
control unit placed in the top mounted housing, and via a Cooling air enters the top housing (at the BS-end) and
thyristor voltage regulator. cools the excitation control unit and, subsequently, the
windings and core packs of the exciter and of the main
For further information, see the supplementary machine before leaving the top housing at the BS-end.
instructions entitled THYRIPART excitation system on
pages 15-24. On machines provided with air filters at the air inlet,
Depending on the application, the machines may also be the loading condition of the filter should be monitored.
designed in accordance with the type variant defined in
the table below. In machines having closed-circuit cooling, the air-to-water
cooler is placed transversely in the top-mounted box in
Table 1-1. Type definition
transverse arrangement, in front of the excitation control
Type Type of construction
unit.
Machines with closed-circuit cooling and air-to- The primary cooling air circulated by the internal fan is re-
HFJ 5, 6 water cooler with provisions for emergency cooled in the cooler and passed through the excitation
operation in case of cooling water failure control unit, the exciter, and the main machine.
HFC 5, 6 Machines with open circuit cooling and air-to-air
High voltage machines with open or closed circuit Given the necessary provisions, the machine can be
HSR
cooling adapted for emergency operation with open-circuit
cooling in case of cooling water failure. See pages 44-45.
>>
Instruction Manual 3
01 Construction of Brushless A.C Generator
Connect the machines in accordance with the diagram in Dry new windings have insulation resistance values
the working drawing. between 100 and 2000 or higher.
If the insulation resistance value is in the region of the
Before closing the terminal box, check to see that minimum value, dampress and or dirt could be the cause.
If the insulation resistance value falls below this minimum
Its interior is clean and free from any cable chippings figure, the cause must be established and the winding
All terminal screws or bolts are tight dried.
The minimum clearances in air are maintained
(>10 mm for 500 V, >14 mm for 1 kV and >60 mm In case of drying by warm air oven.
for 6 kV; check for any projecting wire ends) Remove bearing housings
Entry openings not in use are closed off by firmly Remove rotor
screwed-in plugs Remove diode varistor is excitation equipment part
For maintaining the particular degree of protection all
sealing surfaces of the terminal box are in order. Bake in oven at temperatures per below table.
The surfaces of metal-to-metal sealing joints must be The heat should be applied slowly so the desired
cleaned and thinly regreased. temperature will not be obtained in less than six hours.
Insulation resistance should be measured before the heat
Before starting a machine and during operation make is applied, and every six to eight hours thereafter.
sure that all relevant safety regulations are complied with.
Table 1-3. Insulation Drying Temperatures*
Class “B” Class “F” Class “H”
7) Insulation testing
200 F 245 F* 275 F*
94 C 118 C 135 C
DANGER
* Class “F” and “H” insulated units should be baked at 70% specified
Hazardous voltage temperature (to avoid steam inside winding) for about six hours,
before temperature is raised to drying temperature.
Will cause death, serious injury, electrocution or property
damage.
Disconnect all power before working on this equipment.
The insulation resistance for clean windings is largely
dependent on temperature: for each 10K rise in
Before commissioning and after long periods of storage or temperature it falls by half, i.e. with a temperature rise of
standstill the insulation resistance of the windings to the 50K (e.g. from 25 to 75 ) it falls to about 1/30 of the
frame must be measured with D.C. voltage. initial value.
Do not discontinue measurement before the final
resistance value is indicated(with high-voltage machines, During operation the insulation resistance of the windings
this process may take up to 1minute). may decrease as result of environmental and operating
The limit values for minimum insulation resistance and conditions.
critical insulation resistance (for measurement at a The critical value of the insulation resistance at a winding
winding temperature of 25 ) and for measuring voltage temperature of 25 can be calculated depending on the
can be derived from the following table depending on the rated voltage by multiplying the latter (kV) by the specific
rated voltage for the machine. critical resistance value in the table ( /kV).
Minimum insulation
resistance with new machine. 10 100 When the measured value reaches or falls below this
Cleaned of repaired windings critical insulation resistance figure, however, the windings
must either be dried, or the rotor must be removed and
Critical specific insulation
the windings thoroughly cleaned and dried.
resistance after long 0.5 /kV 5 /kV
period of operation
If the measured value approaches the critical value, the 11) Storage
resistance should subsequently be checked at
appropriate short intervals. WARNING
8) Noise emission The location for storage should be dry and clean.
There should be no fever min that could attack the
The noise level of the generator will not exceed that
winding.
specified in Part 9. VDE 0530 (1981).
The machined surfaces (coupling part, foots part, etc).
are coated with rust-resistant grease.
If the coating is broken, immediately remover the rust or
9) Vibration stability
moisture and recoat with grease for rust prevention.
Reciprocating engines used as prime mover impress
vibrations on the alternator because of the pulsating
If the machine is to be stored for some time, apply all
torque output.
openings with waterproof paper, wooden, or metallic
Permissible vibration stress measured at the bearing is:
covers.
It is necessary, to protect from the machine wind and rain
during trans-portation and storage and to select less
< 10 Hz vibration amplitue S < 0.40 mm-peak
humid place for storage.
10-100 Hz vibration velocity Veff < 18 mm/s-rms
For storage for a long-term or in the rainy season, it is
> 100 Hz acceleration b < 1.6 g
best to insert heaters to remove moisture or prevent its
condensation.
Please inquire if a higher vibration stress level is expected.
Improper handling can cause severs injury or property For long time storage, a space heater is placed inside the
damage.
generator. Its specification is described in the generator
When lifting generator.
final specification and on the nameplate attached to the
1. Lift only at designated locations.
2. Use spreader for lifting. generator.
3. Apply tension gradually to slings.
4. Do not jerk or attempt to move unit suddenly.
5. Do not use cover lugs when lifting. 12) Installation
>>
Instruction Manual 5
01 Construction of Brushless A.C Generator
Install the machines so that the cooling air has free 14) Maintenance
access and can escape unobstructed. Before starting any work on a machine, make sure that it
Warm exhaust air must not be drawn in again. has been disconnected from the power supply and that
unintentional starting is safely prevented.
Louver openings must face downwards to maintain the
particular degree protection. Clean the cooling air passages at regular intervals,
Remove the shaft block (where applicable). matching the degree of pollution and using oil-free
Follow the instructions attached to the shaft extension or compressed air, for example.
shown in the terminal box.
The inside of totally-enclosed fan-cooled machines need
The rotors are normally balanced dynamically by means only be cleaned during normal overhauls.
of a half feather key placed in the shaft extension.
Align the machines carefully and accurately balance the If dust or moisture has penetrated into the terminal
elements to be fitted on the shaft to ensure smooth and compartment, it should be carefully cleaned and dried,
vibration-free running. in particular the surfaces of the insulating parts.
Check the seals and eliminate the leak.
Place shims under the feet of the machines if necessary
to prevent them from being stressed mechanically. Before forcing off a part, replace two upper fixing screws
Transmission elements may be fitted and removed only with longer screws or threaded bolts to support the part
by means of a suitable tool. after forcing it out of its central facility.
The feather keys in the shaft extensions are only secured
to prevent them from falling out during shipment.
A machine must not be commissioned without its 15) Inspection
transmission element having been fitted.
The first inspection should be carried out after
approximately 500 hours.
The rate of fouling should be assessed and appropriate
13) Operation
periods for cleaning the cooling air ducts decided upon.
WARNING
The following checks should also be carried out:
Do not operate equipment beyond design limitations.
Running smoothness of machine satisfactory
Can cause personal injury or damage to equipment.
Operate in accordance with instructions in the manual Rotor alignment within tolerances
and nameplate ratings. No subsidence or cracks in the foundation
All fixing bolts of mechanical and electrical joints tight
Insulation resistance of windings satisfactory
NOTICE
(compare with previous reading and record)
In case of cooling system of IP44 (air to water), check the No bridging of any bearing insulation
flow of cooling water for sure before starting.
Any excessive deviations or changes ascertained during
Internal temprature rise may cause fatal damage to the
generator. the checks must be corrected immediately.
Damaged or used locked elements from released bolted
joints must be renewed.
NOTICE
Before starting, check if the bearing oil is filled with or, not The basic intervals between inspections are approximat-
to the sufficient oil level. ely 4000 hours, 1000 switching operations or 1 year for
intermittent operation and approximately 16,000 hours
Covers fitted to prevent access to rotating and current or 2 years for continuous operation, depanding on which
carrying parts or to correct the air flow for better cooling occurs first.
must not be open in operation. The cleaning of all parts becoming fouled by the flow of
If machine application is abnorma (high temperature, cooling air depends on the intervals decided after the first
extreme vibration, etc.) consult HHi for special inspection according to the rate of fouling which occurs
instructions. locally.
Cleaning should be carried out with dry compressed air. 2) Rotor and windings
Information on oil changes, regreasing, etc. is given on The shaft for machines construction type B3 and B20
the lubrication instruction plate on the machine or in the is designed with a normal cylindrical shaft extension for
supplementary instructions for bearings. two bearings. In the case of types B2 and B16 the shaft
The checks stated for the first inspection after 500 hours is fitted with a flange.
should be performed during these inspections also. The rotor core of the main machine is mounted on the
When a machine is dismantled the following checks shaft, tensioned axially, and supports the field and damper
should be made: windings. The damper winding bars lie in the slots of the
Slot wedges in stator and rotor cores tight rotor core and are welded to the rings.
Windings, connection leads, and insulating parts in The rotor core of the exciter is mounted on the shaft and
satisfactory condition with no discoloration supports the three-phase field winding.
The rectifier supporting wheel is mounted on the shaft
After reassembly, again follow the instructions given for between the two laminated cores.
installation. The rotor is balanced dynamically.
1.3 Composition
4) Rotating rectifier
1) Stator frame and winding
The rotating rectifier is a silicon rectifier which is
The stator frame is of welded design. connected so as to compose a three-phase full-wave
The stator core is centred in the frame and locked against rectification circuit as shown in Fig. 3 and is mounted on
rotation and shifting. the rotor shaft of generator in Fig. 8-1.
The stator winding is of a two-layer coil design with
insulation class F. The mounting screws are between 4.5 Nm and 5.5 Nm
This insulation is made in a special way and is comprised The contact screws are between 2.5 Nm and 3.5 Nm
of integrated-mica & enamel coated insulating material
impregnated with cast resin. CAUTION
It is characterized by high dielectric strength, resistance
The rotating diode fastening screws must be tightened to
to moisture, aggressive gases and vapours, as well as the recommended torque.
rigidity and long life.
>>
Instruction Manual 7
01 Construction of Brushless A.C Generator
Fig. 3 Single line diagram for rotating rectifier It is a one-way ventilating system which takes in air from
the opposite side of the prime mover and lets out exhaust
air at the prime mover's side.
We have taken into consideration that the engine's oil
vapor should not be sucked into the machine.
The exciter yoke ring in which the exciter poles are bolted
in regular distribution, is welded to the BS-end shield.
The regulator variably reduces the field current as Fig. 4 Rotor locking device
6) Shaft
Concerning the generator shaft, the ship's classification
certified forged steel should be applied and designed with
ample strength for coupling with the prime mover.
End shield AS Flanged shaft
Retaining ring half Fixing screw for 1
Shaft supporting ring Fixing screw for 3
7) Bearing
Depending on the design and the operating conditions
specified in the order, the machines are fitted with
grease-lubricated rolling-contact bearings or with sleeve 11) Insulation for the prevention of shaft current
bearings with or without forced-oil lubrication. (high voltage and large machines)
For a full description and special instructions, reference
NOTE
should be made to the supplementary instructions.
Insulated Bearing
Any connection to this bearing must be insulated from it
8) Cooling fan to prevent bearing current.
When a shaft current flows, by this voltage the shaft and 13) Space heater
journal part are tarnished. In the worst condition, sparking
results in minute black spots. DANGER
Hazardous voltage
There is a possibility that the oil film is broken locally, Will cause death, serious injury, electrocution or property
developing burn-out trouble. damage.
When disassembling or assembling, be sure to measure Disconnect all power before working on this equipment.
the insulation resistance.
The cooler can be used for fresh water or sea water and
can be of the double-tube type.
12) Thermometer
The electrical version of the alternator remains unchanged.
For checking the bearing temperature, a mercury
The alternators HFJ can easily be converted for emergency
thermometer is provided.
operation as an open-circuit aircooled machine if the
U-shaped as shown in Fig. 6.
coolant system or the cooling element fails.
>>
Instruction Manual 9
01 Construction of Brushless A.C Generator
In this case the degree of protection is IP 23 with the rated 15) Terminal box
output as shown on pages 44-45.
DANGER
Please provide the following information with any inquiry:
Hazardous voltage
Will cause death, serious injury, electrocution or property
Alternate rated output damage.
Classification society Disconnect all power before working on this equipment.
Coolant temperature (air)
Cooling water inlet temperature
Cable entry to the 3 main connections, (U.V.W.) and to the
Fresh water or sea water
2 field terminals +F1, -F2 can be from the left or right, as
required.
The cable entry plates are supplied undrilled or drilled
with cable gland as required.
See Fig. 7.
Fig. 8 Sectional drawing for HF. 5 type generator (single sleeve bearing)
>>
Instruction Manual 11
01 Construction of Brushless A.C Generator
Fig. 9 Sectional drawing for HF. 5 type generator (double sleeve bearing)
Fig. 10 Sectional drawing for HF. 6 type generator (single sleeve bearing)
>>
Instruction Manual 13
01 Construction of Brushless A.C Generator
Fig. 11 Sectional drawing for HF. 6 type generator (double sleeve bearing)
2.1 Mode of Operation (SPRESY 15) Depending on the reference potential of terminal 16,
terminal 12 of the comparator point of the control
1) Description amplifier can be given an additional D.C. pulse, e.g for
Brushless synchronous generators consist of the main reactive power control in parallel operation.
machine and of exciter.
The main machine field winding is powered from the For tuning to the signal level, a rheostat must be soldered
exciter rotor winding via a rotating, three-phase bridge- onto the available soldering pins.
connected rectifier set. The power supply for the gate control module(s) is
The exciter is THYRIPART-excited. available from terminal 11.
>>
Instruction Manual 15
02 Excitation System (operation)
>>
Instruction Manual 17
02 Excitation System (operation)
Fig. 16 Voltage regulator "6 GA 2491" Fig. 17 Voltage regulator "6 GA 2491"
(for generator top mounting) (for panel mounting)
>>
Instruction Manual 19
02 Excitation System (operation)
Fig. 19 Connection diagram of generator (for generator top mounted AVR): 35 Fr~40 Fr
Fig. 19-1 Connection diagram of generator (for generator top mounted AVR): 45 Fr~56 Fr
Fig. 20-1 Connection diagram of generator (for panel mounted AVR): 45 Fr~56 Fr
>>
Instruction Manual 21
02 Excitation System (operation)
In the case of identical plants, the THYRIPART excitation Parallel connection on the exciter side or droop
system or the individual components can be interchanged compensation equipment ensures uniform distribution
if the need arises. of the reactive power and reduces the generator output
The transformer tapings, however must be used which voltage in linear proportion to the increasing reactive
are shown in the circuit diagram of the generator and current.
which correspond to those of the original transformer.
Regarding generators with current transformer for droop
compensaton, potentiometer S in the regulator is
3) Regulator gain, setpoint voltage integral action adjusted so that there is no reduction in the generator
The control module comprises potentiometers U, K, T, voltage at unity p.f. but a 6% reduction at zero p.f.
R47 and S. The corresponding voltage reduction at 0.8 p.f. is 3.6%.
The rated generator voltage has been adjusted in the In isolated operation and at any loading condition of the
works on potentiometer U, and the dynamic behaviour generator, the droop compensation provided for the
of the regulator on potentiometers K, T and R47. generator voltage can be checked with the following
The settings are shown in the test certificate. relationship:
Potentiometer K is used to adjust the controller gain and Ust = 6% 1-cos2 IB/IN (%)
potentiomter T is used to adjust the integral action time,
whereas potentiomter R47 is used to inject a disturbance e. g. at 0.8 pf, IB/IN = 1,
variable into the comparator point of the control amplifier
in order to adjust dynamic behaviour. Ust = 6% 1-0.82 1 = 3.6 (%)
Turning the knob of K and R47 in the direction of
descending numerals and that of T in the direction of
ascending numerals normally stabilizes the control circuit If the generator is to operate by it self, droop
and reduces the control rate. compensation equipment is not required.
The stability of the control circuit can also be improved by It can be deactivated by short-circuiting the associated
increasing the bucking resistance, but the voltage setting current transformer on the secondary side or setting
range of the regulator then is reduced at the lower end. potentiometer S on the regulator to the left-hand stop.
If the neutral points of several generators are
The setpoint of the generator voltage can be shifted via interconnected or connected direct with the neutral
potentiometer U or an additional external setpoint points of transformers and loads, currents at 300%
selector (R = 4.7 , P greater than 1 W) can be connected frequency may occur.
to terminals A1 and A3.
Potentiometer U should be set to the centre position, and Their magnitude should be checked by measurements in
microswitch S 1/3 on the printed-circuit board should be the neutral conductors of the generators under all load
opened. conditions occurring.
>>
Instruction Manual 23
02 Excitation System (operation)
3.1 Installation & Inspection Check List The purpose of this checklist is to ensure that all
installation and inspection work is fully carried out.
DANGER
It is therefore essential for the list to be filled in carefully.
Hazardous voltage
Will cause death, serious injury, electrocution or property The number of relevant questions will depend on the
damage. scope of the work to be carried out,
Disconnect all power before working on this equipment.
In the "Answer" column, "yes" or "no" or "n/a" (for "not
applicable") should therefore be checked off in each case.
NOTICE
In some lines, additional data or information must be
Before the initial starting for in-sevice, check the items on entered or irrelevant items deleted.
table 3-1 for sure. If any further explanations are necessary they should be
If not, may cause fatal damage in generator.
placed in the report or final spec of the generator.
>>
Instruction Manual 25
03 Maintenance
1) Inspection schedule
Daily Monthly
Check bearing. Check insulation resistance.
L.O. condition. Caution: Before checking insulation resistance,
Oil ring. disconnect and earthed the leads from A.V.R.
Noise. Bolts and nuts.
Vibration.
Temperature. Tighten all bolts and nuts.
Check electric circuit. Check ventilation openings.
Earth fault by earth lamp. Check air intake opening and its air filter, clean or
Check loading condition. replace the filter if necessary.
Voltage, output kW, current.
Corresponding to the operating conditions the sleeve The lubrication oil indicated on the data plate is used for
bearings of new machines have a favorable bearing starting up the machines at an ambient temperature of
clearance which should not be changed. above +5 .
Scraping (spot-grinding) is not allowed not to make worse
the antifrictional qualities. At lower temperatures (to about -20 ) it is sufficient to
preheat the oil.
It is recommended that the contour of the transmission If the ambient temperature is below -20 another type of
element remain within the hatched range (see Fig. 24) oil according to the special conditions is used.
to remove the upper part of the bearing housing for Do not mix oils of different grades.
maintenance without removing the transmission element.
>>
Instruction Manual 27
03 Maintenance
If only slight damage has occurred to the bearing The replacement bearing shells are delivered by the
surface, it may be re-conditioned by scraping, as long as works with a finished inner diameter.
the cylindrical shape of the bore is maintained, so that a Oil rings which have become bent through careless
good oil film can form. handling will not turn evenly.
The lining must be renewed if more serious damage is
found. Straighten or replace such rings.
The oil pockets and grooves of the new lining or scraped Replace any damaged sealing rings.
shell should be cleaned and finished with
particular care (Fig. 23).
Fig. 24 Ring-lubricated flange-type sleeve bearings (examples, delivered design may deviate in details)
a 2 14
45
25 1
26 3
4
d1
18
d2
6
19
27
32
15
Limiting range for
transmission element 8
1. Screw plug 20
(thermometer mounting and oil filling point)
1 2. Inspection glass
2 3. Sealing ring for 2
3 4. Sealing ring for 1 21
4 14 5. Bearing housing, upper part, drive end
6. Cylindrical pin
5 7. Sealing ring, upper half, drive end
8. Guide pin to prevent twisting
6 9. Upper bearing shell, drive end 22
7 10. Oil ring, drive end
11. Lower bearing shell, drive end
8
12. Bearing ring, lower half, drive end
15 23
9 13. Sealing ring, lower half, drive end
14. Taper pin
15. Guide pin to fix bolted parts 24
16. Sealing ring for 17 3
17. Drain plug 2
10 18. Bearing housing, upper part, non-drive end 16
19. Sealing ring, upper half, non-drive end 17
20. Upper bearing shell, non-drive end
21. Oil ring, non-drive end
22. Lower bearing shell, non-drive end
23. Bearing housing, lower part, non-drive end 28
11 24. Sealing ring, lower half, non-drive end 29 31
25. Upper adjusting shim, drive end
26. Sealing cover, drive end
12 27. Lower adjusting shim, drive end
28. Upper adjusting shim, non-drive end
29. Sealing cover, non-drive end
13 30. Lower adjusting shim, non-drive end
3 30
2 31. Protective cap
32
32. Pressure compensation opening
16
17 d1 (mm) 80 100 120 150 180 215
d2 (mm) 140 160 170 190 210 245
a (mm) 8 8 10 15 18 22
>>
Instruction Manual 29
03 Maintenance
Connect the bearings to the oil pump, oil tank and cooler
before commissioning the machines. 2) Operating description
No reducers must be fitted in the piping.
NOTE
Install a regulating orifice on the oil supply line to protect
the bearing from flooding. Before starting, check if the bearing is filled with oil or not
If the oil pump fails, the lubrication maintained by the oil to the sufficient oil level.
CAUTION
Fill the oil tank with the lubricating oil indicated on the
data plate. Prolonged operation at extremely slow rotation speeds
This oil is used for starting up the machine at an ambient (several rpm) without lubrication could seriously damage
temperature of above +5 . the service life of the bearing.
>>
Instruction Manual 31
03 Maintenance
Fig. 26 Flange-type sleeve bearing for forced-oil lubrication (examples, delivered design may deviate in details)
1. Screw plug
(thermometer mounting and oil filling point)
2. Inspection glass
3. Sealing ring for 2
4. Sealing ring for 1
2 14
5. Bearing housing, upper part, drive end 1
1 6. Cylindrical pin 3
2 4
7. Sealing ring, upper half, drive end
3
4 8. Guide pin to prevent twisting
14 18
9. Upper bearing shell, drive end
10. Oil ring, drive end 6
5
11. Lower bearing shell, drive end 19
12. Bearing housing, lower part, drive end
6
13. Sealing ring, lower half, drive end 15
7
14. Taper pin
8
15. Guide pin to fix bolted parts
8 15 20
16. Sealing ring for 17
9
17. Drain plug
18. Bearing housing, upper part, non-drive end
19. Sealing ring, upper half, non-drive end 21
20. Upper bearing shell, non-drive end
10 21. Oil ring, non-drive end
22. Lower bearing shell, non-drive end
23. Bearing housing, lower part, non-drive end
24. Sealing ring, lower half, non-drive end 22
25. Upper adjusting shim, drive end
26. Sealing cover, drive end
11
27. Lower adjusting shim, drive end 23
28. Upper adjusting shim, non-drive end
29. Sealing cover, non-drive end
12 24
30. Lower adjusting shim, non-drive end 3
31. Protactive cap 2
13 32. Pressure compensation opening
3 16
33. Oil supply tube with orifice
2 17
34. Oil discharge tube with sight glass
16
17 28
29 31
a 25
45
26
100mm
d1
d2
30
33
32
34
27
32
Limiting range for
transmission element
3.4 Rolling-Contact Bearing (series 02 and 03) Initial lubrication of the bearings is normally carried out in
the works with an Alvania #2 grease satisfying the
1) Mounting conditions of the running test at a test temperature of
Electrical machines fitted with rolling-contact bearings 120 to DIN 51 806.
mentioned above are subject to the following If a different type of grease is required, this is indicated on
instructions supplementing and modifying the operating the data plate, provided that the particular operating
instructions of the machine: conditions were given in the order.
CAUTION
The locating bearings are deep-groove ball bearings for
horizontally mounted machines. Do not mix grease of different soapbases.
These bearings may also be in pairs with cylindrical roller When changing the type of grease, clean the bearing
beforehand using a brush with solvent.
bearings in the case of bearings is not guide radially and
is prevented from rotating by compression springs.
NOTE
The locating bearings for vertically mounted machines are The most widely-used solvent is gasoline: white spirit is
angular-contact ball bearings of type range 72 or 73 acceptable.
(angular-contact ball bearings with increased axial fixation
see suplementary operating instructions).
DANGER
The floating bearings are deep-groove ball bearings or
The prohibited solvents are:
cylindrical roller bearings.
Chlorinated solvent (trichlorethylene, trichloroethane)
In the case of deep-groove ball bearings as floating which becomes acid.
bearings, the axial play is compensated by means of Fuel-oil (evaporates too slowly).
compression springs. Gasoline containing lead.
Benzine (toxic)
>>
Instruction Manual 33
03 Maintenance
The shaft should rotate during regreasing, hence the 4) Dismantling, assembling
machines need not be stopped. For working on the locating bearing in the vertical
After regreasing, the bearing temperature will rise by a position of the machine, support or discharge the rotor.
few degrees and will drop to the normal value when the
grease has reached its normal service viscosity and the It is recommended that new rolling bearings be installed
excess grease has been forced out of the bearing. as follows: Heat the ball bearings or the inner ring of the
roller bearings in oil or air to a temperature of approx 80
It is recommended that the lubricating instructions be and slip them onto the shaft.
strictly followed. Heavy blows may damage the bearings and must be
Special cases may require lubrication according to special avoided.
instructions, e.g. where there is an extreme coolant
temperature oraggressive vapours. When installing single angular-contact ball bearings, make
sure that the broad shoulder of the inner ring (and the
The old grease from several regreasing operations gathers narrow shoulder of the outer ring) in operating
in the space inside the outer bearings caps. position points upwards, i.e. in a direction opposite to
Remove the old grease when overhauling the machines. that of the axial thrust.
The model of bearing is favorably chosen for direction and When assembling the machines, avoid damage to the
size of load (type of construction, forces acting on the sealing rings.
shaft) and therefore it should not be hung. Rubber sealing rings (V-rings) should be carefully fitted
The permissible values of axial and radial forces may be over the shaft as shown the illustration.
taken from the list of machine or may be inquired about.
New felt sealing rings should be so dimensioned that the
The machines should operate in only one type of shaft can run easily while proper sealing is still effected.
construction as shown on the rating plate, because Before fitting new rings, soak them thoroughly in highly
another type of construction requires perhaps further viscous oil (normal lubricating oil N68 to DIN 51 501)
measures in addition to a modification of the model of having a temperature of approx 80 .
bearing.
In this case an inquiry is always necessary.
5) Locating faults
The trouble shooting table 4-6 helps to trace and remove
3) Lubrication
the causes of faults as shown on page 49.
Regrease the bearings if the machines have been Sometimes it is difficult to assess damage to the bearings.
unused/stored for longer than 2 years. In this case, renew the bearings.
>>
Instruction Manual 35
03 Maintenance
Lubricating nipple
Inner bearing cap with felt sealing rings 2) Fig. 30 Fitting instructions for V-ring and oil seal for shaft
Angular-contact ball bearing
Bearing slinger 2)
Grease slinger 2)
Circlip 2)
Outer bearing cap 2)
V-ring 2)
Deep-groove ball bearing (locating bearing)
or angular-contact ball bearing
Compression spring 2)
Cylindrical roller bearing 2)
Cylindrical roller bearing 2)
Oil seal for shaft 1) 2) 3)
1)
floating bearing side
2)
locating bearing side
3)
special operating conditions only Single bearing, shaft does not pass through the outer bearing cap
3.5 Coupling A-type (single-bearing generators Insert shims underneath the mounting feet until the
with flanged shaft and one-part fan wheel) centering faces of the generator flange and engine
(flywheel) or gear flange are in line with the flanges being
1) Transport, storage parallel to each other.
The following instructions supplementing and modifying
the basic. Experience shows that less shims are required at the non-
Operating Instructions apply to single-bearing drive end than at the drive end, since the engine coupling
generators of type of construction B2 or B16 which are flange is inclined by the weight of the flywheel.
coupled with diesel engines or turbines: Bolt the coupling flanges together while re-pressing the
generator axially, lightly tighten the foot bolts, and undo
For transport and assembly, the generator rotor is the retaining-ring halves.
centered radially and fixed axially by means of bolted
retaining-ring halves fitted between the end shield AS
3) Checking the air gap (Fig. 33)
(unsplit) and the shaft supporting ring (Fig. 31).
The ring halves should therefore not be detached before Check the air gap between the shaft supporting ring and
the generator is assembled with the diesel engine or the end shield AS.
turbine. The gap should be uniform all around.
If the maximum difference between the measured
Fig. 31 Rotor locking device (example, delivered values "a max-a min" exceeds 0.3 mm, correct the gap
design may deviate in details)
by inserting or removing shims underneath the
mounting feet.
>>
Instruction Manual 37
03 Maintenance
Fig. 34 Fixing of the retaining-ring halves after Fig. 35 Rotor locking device (example, delivered
assembling with prime mover design may deviate in details)
Experience indicates that the number of shims to be 3) With axial end play at bearing
inserted or removed at the non-drive end is only 50% of In this case, the axial position of the rotor assembly was
the number at the drive end. Tighten the foot bolts and adjusted during the initial test at the factory.
the web clearance of the diesel engine.
It may be necessary to correct the air gap and the web The generators are delivered with a magnetic center
clearance several times. gauge an the drive bearing side with a groove on the
shaft and must be kept in the rotor position during the
Fig. 36 Aligning the coupling fanges
alignment with the prime mover.
>>
Instruction Manual 39
03 Maintenance
When the filter is clean, rinse it with clear water. The supply leads should be matched to the rated current
Drain the filter properly (there must be no more formation in line with VDE0100 and their cross section must not be
of droplets). excessive.
The main circuit is normally connected at both sides of
Refit the filter on the machine. the circuit bars with conductor cross sections of max.
300 and may be made by cable lugs or when
CAUTION connecting parts used in hazardous locations which are
Do not use water with a temperature higher than 50 , present without any lugs.
do not use solvents.
The ends of the conductors should be stripped in such a
Do not clean the filter using compressed air. way that the remaining insulation almost reaches up to
This procedure would reduce filter efficiency. the lug or terminal ( 5 mm).
In the case of cable lugs with long sleeves, it may be
necessary to insulate the latter to maintain the proper
clearances in air.
3.9 Terminal Box If using cable lugs, see that the dimension of the cable
lugs and its fastening elements (normally M12) agree with
DANGER the holes in the copper bus bar.
High voltage Use hexagon-head screws with a min. breaking point of
Power source must be disconnected before working on 500 N/ , hexagon nuts and spring elements which are
equipment.
protected against corrosion according to DIN 43673.
Failure to disconnect power source could result in injury
or death.
Terminal box only to be opened by skilled personnel. The connection of accessories is achieved by terminal
strips.
Use a 5 mm maximum screwdriver to work on the
1) Description
blocking screws.
Use the attached terminal box drawing in the final
See the terminal connection diagram in the final
specification.
specification.
The main terminal box of the machine is located on the
top of the machine.
The supply leads particularly the protective conductor
The neutral and phase wires are connected to the copper
should be laid loosely in the terminal box with an extra
bus bar-one copper bus bar per phase and one copper
length for protecting the cable insulation against splitting
bus bar per neutral line (option).
and to prevent the terminals and circuit bars from the
See terminal box diagram in the final specification.
tension load of the leads.
The openings provide access to the terminals.
The gland plates are made of non-magnetic materials in
They should be introduced into the terminal box through
order to avoid circulating currents if needed.
cable entry fittings and sealed.
Protected fittings with strain relief cleats should be used
Compare the supply voltage with the data on the rating
for loose leads to prevent them from becoming twisted.
plate. Connect the supply leads and the links in
Close off any unused cable-entry openings.
accordance with the circuit diagram on the inside of the
terminals box.
Pay attention to the right direction of rotation (phase
sequence in the case of three phase and polarity in the
case of direct current).
{ }
{ }
{ }
{ }
{ }
>>
Instruction Manual 41
03 Maintenance
{ }
{ }
{ }
{ }
{ }
2) Cleaning
The frequency of cleaning operations depends essentially
on the purity of the water used.
We recommend a minimum of one inspection per year. 5) Cooler removal
The life of zinc block for anti-corrosion is about a year. The cooler unit is slid into its housing.
Therefore replace it with a new one every year. It is possible to remove the cooler from the housing
Cut off the water supply by isolating the inlet and outlet without removing the water boxes as shown in Fig. 42.
lines, and drain the water. The cooler is fastened to the housing via a series of
screws on the housing.
Disconnect the leak sensor (option with double-tube Remove the supply and return pipes.
cooler), and make sure that there are no leaks. Provide two eye-bolts to hold the cooler when it comes
Remove the water boxes on each side of the machine. out of its housing.
Rinse and brush each water box. Remove the cooler using slings that can be attached to
the connecting flanges.
NOTE
>>
Instruction Manual 43
03 Maintenance
3.12 Cooling-Water Failure Emergency Operation The following supplements the machine description and
the module for the closed-circuit cooling.
1) HFJ 5. Type Should the cooling water supply for the electrical machine
(1) Changing over to oepn-circuit cooling fail, the machine can be changed over to an open cooling
The electrical machine has a facility for emergency circuit (Fig. 44), as follows:
operation if the cooling water supply fails. The electrical version of the alternator remains
unchanged.
Fig. 42 Cooler removal
Open the air vents at the BS-end for the air inlet and
at the AS-end for the air outlet (Figs. 43 and 44 - No.
3 & 5),
Remove enclosure or cover 2 (Fig. 43)
Insert air cut-off plate 6 (Fig. 44) into the slot in the
raised section on the housing on the hot air side of
the cooler and secure.
Fig. 43 Normal operation with air-to-water Fig. 44 Emergency operation with open cooling circuit
closed-circuit cooling following failure of the cooling water supply
Air vent with cover AS-end, closed. Air vent with cover AS-end, open.
Enclosure or cover. Air cut-off plate before insertion.
Air vent with cover BS-end, closed. Air cut-off plate, inserted and screwed tight.
Air-to-water cooler. Air vent with cover BS-end, open.
2) HFJ 6, Type Detach the cover (part 2) from the side opposite the
(1) Changing over to open-circuit cooling cooling water connections, insert the air-stop plate
On failure of the cooling-water flow the following (part 3) which was supplied loose, and secure with the
operations are required to convert the generator for screws provided.
emergency operation with internal cooling.
The electrical version of the alternator remains (2) Changing over to closed-circuit cooling
unchanged. Air-to-water colling element
Detach louvered covers (parts 4) together with the Cover for No. 1
closure plates (parts 5) at the drive and nondrive ends, Air-stop plate (emergency operation)
remove closure plates and attach louvered covers in Louvered cover (emergency operation)
their original positions. Closure plate
Cover for No 1.
Louvered cover (emergency operation).
Closure plate.
Fig. 46 Emergency operation with open cooling circuit following failure of the cooling water supply
>>
Instruction Manual 45
04 Trouble Shooting
4.1 Excitation Part for SPRESY 15 If the voltage does not be induced, either the excitation
equipment or the main machine or the exciter can be
In the case of faults it is advisable to check the voltage defective. Troubleshoot according to Table 4-4.
controller, excitation equipment, and main machine with Information concerning voltage values for the thyristor
an exciter separately. regulator module is given overleaf and assists in the
For troubleshooting in the thyristor voltage controller all location of faults.
the leads connecting excitation equipment and thyristor
voltage controller must be disconnected and if present, Table 4-1. Excitation part
the intermediate transformers of the droop-compensating Terminal 20-14 < 30 V > 30 V
equipment secondaries short-circuited. Terminal 15-14 about 1 V about 10 V about 1 V about 10 V
In this case the generator voltage must rise above the Fault Regulator Firing Firing Regulator
location
maximum reference value as given under "Description". module module module module
(Fig.13)
In this case the thyristor voltage controller is defective.
Troubleshooting should be continued according to If the remnant should not be adequate for exciting the
Table 4-2. generator, a D.C. voltage (6 to 24 V) must be connected
to terminals F1 and F2 (+ to F1, - to F2) for a short time.
DANGER
Please note that the terminals F1 and F2 start carrying a
Hazardous voltage voltage as soon as self-excitation sets in.
Will cause death, serious injury, electrocution or property When ordering spare parts please state the type and
damage.
serial number of the generator, as they are shown on the
Disconnect all power before working on this equipment.
rating plate.
Controller module
Genetator voltage
Genetator voltage
Reactive current
Reactive current
Reactive power
Power thyristor
Active power
defective
defective
too high
too high
hunting
hunting
hunting
too low
too low
Cause
fails
No wiring links
Wiring links in wrong position
Controller Connected improperly
module Wrong setting of potentiometer Usoll
Wrong setting of potentiometer VR or TN
Internal defect
Discontinuity
Power thyristor Blocking failure
Gate electrode failure
Discontinuity
Measuring-circuit
Inter-turn fault
transformer
Connected improperly
Reference-value Discontinuity
selector Short-circuit in leads
Discontinuity
Series resistor Resistance too high
Resistance too low
Discontinuity
Intermediate
Short-circuit
transformer
Connected improperly
Discontinuity
Tandem Resistance too high
potentiometer Resistance too low
Connected improperly
DANGER
Hazardous voltage
Will cause death, serious injury, electrocution or property
damage.
Disconnect all power before working on this equipment.
Fault Fault
UN, not adjustable via
not adjustable via set
Genetator voltage
parallel operation
External set point
set point selector
without function
not proportional
Load sharing in
point selector
current swing
Voltage and
selector
<0.1 UN
Too high
Drive speed
Too low Check speed control of prime mover.
Speed oscillation
Unsolder diode connections, check diodes in
Rotating rectifier defective
forward and reverse direction, replace diodes.
>>
Instruction Manual 47
04 Trouble Shooting
DANGER
Hazardous voltage
Will cause death, serious injury, electrocution or property
damage.
Disconnect all power before working on this equipment.
Table 4-4. Fault diagnosis chart for excitation equipments, main machines and exciters
Voltage Too warm
Electric fault symptoms deviates
from rated Main
Defective rectifier
value Exciter
machine
excitation fails
Transformer
No load follo-
conditions
Genetator
On-load
winding
winding
winding
winding
Reactor
Stator
Stator
Rotor
Rotor
Cause
Incorrect Overload
service
conditions or Speed deviating from set point
duty under
conditions
deviating from Excessive deviation from rated power factor
order Incorrect operation, e.g.paralleling with
specifications 2nd generator in phase opposition
Stator
Main machine
Rotor
Inter-turn fault
Stator
Exciter
Rotor
Stator
Main machine
Rotor
Winding
discontinuity
Stator
Exciter
Rotor
No remanence
Inter-turn fault
Transformer
Winding discontinuity
Inter-turn fault
Single-phase
current transformer
Faults on Winding discontinuity
excitation
equipment Inter-turn fault
Reactor
Winding discontinuity
Defective rectifier
DANGER
Hazardous voltage
Will cause death, serious injury, electrocution or property
damage.
Disconnect all power before working on this equipment.
Felt sealing rings pressing on shaft Fit rings better into grooves or replace them
Strain applied from coupling Improve alignment of machine
Excessive belt tension Reduce belt tension
Bearing contaminated Clean or renew bearing, inspect seals
Ambient temperature higher than 40 Use special high-temperature grease
Lubrication insufficient Lubricate according to instructions
Bearing canted Check mounting conditions, install outer ring with lighter fit
Too little bearing play Fit bearing with larger play
Bearing corroded Renew bearing, inspect seals
Scratches on raceways Renew bearing
Scoring Renew bearing, avoid vibration while at a standstill
Excessive bearing play Install bearing with smaller play
>>
Instruction Manual 49
04 Trouble Shooting
EACH
GEN.
(No. 1, 2...)
, , , , , , , , ,
No.1,
, , , , , , , , ,
No.2,
, , , , , , , , ,
No.3 & No.4,
, , , , , , , , ,
Memo
>>
Instruction Manual 51
HHIS-WZ-RE-005-01 ’02.07 Designed by SKYdesign
www.hhi.co.kr
ELECTRO ELECTRIC SYSTEMS