Document IEQ 2
Document IEQ 2
For example: When number of observations are plotted in the form of frequency polygon For any
variable characteristic, such as, diameter of shafts produced, then frequency Polygon shows a smooth
curve obtained by joining various points (observations) on the Graph (Normal distribution curve).
D) Consideration in Display Design –
Following consideration should be taken in the design of display
1. Environmental Conditions. 2. Worker’s Capacity. 3. Safety. 4. Nature of work
6. Biological factors
1) Flow Process Chart is defined as the process Travel Chart is defined as the record of the
chart which sets out the sequence of the amount of travel by the worker or material
flow of a product through the various while going from machine to machine or
departments by recording the event using from one department to another.
the appropriate process chart symbols.
2) Generally flow chart records a Travel chart records complex movements.
simple and main movements.
3 Flow process chart uses symbols for It uses a tabular format for the
representation of movements representation of movements.
4) It is used to identify the flow of man, It is used to identify the frequency of
machine and material movements.
b. Prepare a two handed process chart for a task of cutting glass tubes using appropriate
Process chart symbol.
C. Explain Heuristic approach of line balancing.
1. Line Balancing means balancing the production or assembly line.
2. Line balancing is the arrangement of the individual processing and assembly tasks at the
Workstation so that the total time required at each workstation is same and the flow of
Production will be smooth.
3. The main objective of line balancing is to distribute task evenly over the workstations so That
idle time of man and machine is minimized..
4. Heuristic method involves two stages for line balancing
i. Drawing the precedence diagram which determines the priority order of
element.
ii. Assignments of elements to the stations.
5. Task can be assigned in two ways:
i. Permutability of task: It means that any number of tasks or steps of the column
can be Combined to make their total time closer to cycle time.
ii. Transferability of task: For making the total time equal to the cycle time tasks
or steps May be shifted laterally.
6. Consider an example: Suppose there are three machines (workstations) A, B and C Which can
process 5, 10 and 15 pieces per unit time respectively and the pieces flow From A to B to C
(precedence constraint).
7. Since A has minimum capacity i.e. of processing only 5 pieces per unit time naturally Work
station (machine) B will remain idle for 50% of its time and machine C for 66.66% Of its
time.
8. It shows that the line is unbalanced
9. Line can be balanced by addition of one or more machine A which has the capacity of 5
Pieces per unit.
D .Explain compatibility in the design of Toggle switch and Push button.
1. Compatibility is central concept in the study of displays and controls and gives Relationship
between signals, control responses and the expectations of the operator.
2. The most common two categories are as follows:
i. Spatial Compatibility: It refers to the physical arrangements of display and control
Components.
ii. Movement Compatibility: It refers to the relationship between the movement of
Control devices and display.
3. Compatibility in the design of toggle switch:
i. Toggle switch should be positioned on machine in such a way that it should be
easily Accessible to operator.
ii. Toggle switch should confirm with the anatomy of the operator’s hand.
iii. Toggle switch should provide desired movement on display when it is operated.
iv. E.g. if toggle switch is positioned upwards, display should indicate either open,
on,Start, increase.
v. Toggle switch should be painted in either red or black colour to grasp the attention
of An operator.
4. Compatibility in the design of Push button
i. Push button should have concave surface, so that the finger force may be
transmitted More effectively.
ii. Push button is used for emergency purpose so it should be positioned on machine
in Such a way that it should be easily accessible to the operator.
iii. Diameter of pushbutton should be able to accommodate the fingertip without
sliding.
iv. Push button should give desired movements on controls of machine when it is
Operated.
v. It should be made of such material which is easily distinguishable and preferably
can
vi. Shine even in the dark so that there should no problem in locating it
Q.4 Attempt any THREE of the following. (3x4=12)
A project consists of 8 activities. Precedence relation and activity times are given. Draw the
Network and compute the critical path.
Path 1 = P-Q-R-S-V-W
= 12+20+28+12+8+8
Path 1 = 88
Path 2 = P-T-U-W
= 12+28+12+8
Path 2 = 60
Path 3 = P-Q-T-U-W
= 12+20+28+12+8
Path 3 = 80
Path 4 = P-Q-R-S-U-W
= 12+20+28+12+12+8
Path 4 = 92
Critical Path is P-Q-R-S-U-W as project duration is 92 Days.
B .Apply ergonomics aspects for designing of Hand Wheel for driving a car.
1. Hand wheel is a device which provides controlling torque via both hands.
2. Hand wheel of car should be positioned in front of driver’s seat so that it can be easily
Accessible .
3. Diameter of hand wheel should be such that driver’s hand can be comfortably
Positioned.
4. Shape of hand wheel which comes in contact with the driver’s hand should confirm
With the anatomy of driver’s hand
5. Surface of the hand wheel should be smooth and shiny and it should not harm driver’s
Hand.
1. Α = 0.10
It is Producer’s RiskSometimes it happen that in spite of good quality, the sample
taken may show defective units As such the lot will be rejected. In spite of good
quality the lot is rejected, such a type of risk of Rejection is known as producer’s risk.
Thus, the risk of rejecting a lot of good items is known as Producer’s risk.
2. AQL = 0.01.
3. AQL stands for Acceptable Quality Level
It indicates that maximum number of defectives that customer accepts.
Also, probability of acceptance For AQL is higher.
4. Β = 0.05
It is Consumer’s Risk
Sometimes it may happen that the quality of the lot is not good but the sample results
show Good quality units as such the consumer has to accept a defective lot. Such a risk
is known as Consumer’s risk.
5. LTPD = 0.25
LTPD stands for Lot Tolerance Percent Defective
It indicates unsatisfactory quality level and customer not accepts it due to high number
of Defectives in the lot.
e. The record of number of defectives on daily samples of size 300, for 24 days is given
below. Prepare a control chart for number of defectives (np) and establish revised control
limits (Assume 3 σ Limits)
Day 1 2 3 4 5 6 7 8 9 10 11 12
No.of 10 5 10 12 11 9 22 4 12 24 21 15
defec
t
Day 13 14 15 16 17 18 19 20 21 22 23 24
No.of 8 14 4 10 11 11 26 13 10 9 13 12
defec
t
Answer:-
Lots=N=24. Sample Size=300
Histogram: The most commonly used graph for showing frequency distributions, or How
often each different value in a set of data occurs.
• Pareto chart :
- The pareto chart is one of the too in 7 basic tools of quality management
- Pareto chart is a chart that contains bar and line graph which is also known as
pareto Diagram or paraeto analysis.
- Bar graph shows number of defects in decending order and line graph shows
Cumulative persentage of defects.
The purpose of pareto giagram is to highlight the higest occurring type of defects.
• Scatter diagram: Graphs pairs of numerical data, one variable on each axis, to look for
a Relationship.
• It is a tool to get relationships between two variables. This is a graph where one
Variable is plotted on the x-axis whereas the other is plotted on y-axis. It can be cause
And effect relation also you put on the respective axis.
C The following tensile strength readings were taken from a line processing a heap of steel
After heat treatment :
Date 1 2 3 4 5 6 7 8 9
Reading 95.5 93.0 96.5 87.5 90.5 96.0 100.0 98.0 97.0
Date 10 11 12 13 14 15 16 17 18
Reading 96.0 93.5 98.0 90.0 94.0 89.5 96.5 92.0 98.5
Date 19 20 21 22 23
Reading 96.5 92.0 97.0 97.0 91.0
Construct a two days moving average and range chart for the data. Analysis the results.