Module 3 Part 2
Module 3 Part 2
Highway Engineering
3
References
4
Problem – 3
Determine the number of potential conflict points on cross roads where the lane widths of
road A and road B are 7 m and 14 m respectively. Assume the following scenarios
a) Both roads are two-way
b) Road A is one-way and Road B is two-way
c) Both roads are one way
Solution
Both roads are two-way
- Crossing = 24
- Merging = 8
- Diverging = 8
Solution
Road A = One-way
Road B = Two-way
- Crossing = 13
- Merging = 4
- Diverging = 4
Solution
Both roads are one-way
- Crossing = 8
- Merging = 2
- Diverging = 2
Some Terminologies …
Signal cycle
Period of time required for one complete sequence of signal indications
Signal phase
Part of signal cycle time that is allocated to stop or allow the traffic movement
Red = STOP phase
Amber = CLEARANCE time
Green = GO phase
Interval
Any of the division of signal cycle during which signal indications do not change
9
Types of Traffic Signals
Types of
Pedestrian Signal
Traffic Signals
10
Traffic Control Signals
Different types
• Manually operated signals
Operated remotely by traffic police constable
• Fixed time automatic signals
Signal phase and signal cycle time constant
No significant variation in traffic flow
• Automatic traffic-actuated signals
Signal phase and signal cycle time change with traffic flow
Use of detectors and computer
11
Design of Isolated Fixed Time Signals
Objectives
• Sufficient intersection capacity for traffic volume entering from all roads
• Minimize overall delay
12
Two-Phase Signal Design Principles
Red Amber Green 𝑅1 = 𝐺2 + 𝐴2
Road – 1 𝑅1 𝐴1 𝐺1 No turning movement ⇒ Incorporate
Road – 2 𝑅2 𝐴2 𝐺2 pedestrian crossing time
14
Signal Design Methods
• Trial cycle method
• Approximate method based on pedestrian crossing time
• Webster’s method
• Design as per IRC guidelines
15
Trial Cycle Method
• 15-minute traffic count during design peak hour flow
𝑛1 for Road – 1 & 𝑛2 for Road – 2
• Assumption
Average time headway = 2.5 sec
Trial cycle length = 𝐶1
16
Trial Cycle Method
• Green periods
2.5 × 𝑛1 2.5 × 𝑛2
or
900/𝐶1 900/𝐶1
• Amber period – Assume (3 to 4 sec)
𝐴1 for Road – 1 & 𝐴2 for Road – 2
17
Trial Cycle Method – Example
The 15-minute traffic counts on cross roads 1 and 2 during peak hour are observed as
178 and 142 vehicles per lane respectively approaching the intersection in the direction
of heavier traffic flow. If the amber times required are 3 and 2 seconds respectively for
the two loads based on approach speeds, design the signal timings by trial cycle
method. Assume average time headway as 2.5 seconds during green phase.
18
Trial Cycle Method – Example
Given, 𝑛1 = 178 ; 𝑛2 = 142 ; 𝐴1 = 3 sec ; 𝐴2 = 2 sec ; 𝑡𝐻 = 2.5 sec
Assume trial cycle length, 𝑪𝟏 = 50 sec
Green period for Road – 1 and Road – 2
2.5 × 𝑛1 2.5 × 𝑛2
𝐺1 = ; 𝐺2 =
900/𝐶1 900/𝐶1
2.5 × 𝑛1 2.5 × 𝑛2
𝐺1 = ; 𝐺2 =
900/𝐶1 900/𝐶1
21
Webster’s Method – Example
The average normal flow of traffic on cross roads A and B during design period are
400 and 250 PCU per hour; the saturation flow values on these roads are estimated as
1250 and 1000 PCU per hour respectively. The all-red time required for pedestrian
crossing is 12 sec. Design two-phase traffic signal with pedestrian crossing by Webster's
method.
22
Webster’s Method – Example
𝑞1 = 400 PCU/hr ; 𝑞2 = 250 PCU/hr
𝑆1 = 1250 PCU/hr ; 𝑆2 = 1000 PCU/hr
𝑅 = 12 sec ; 𝑛=2
Determine 𝒀 and 𝑳
𝑞1 𝑞2 400 250
𝑦1 = ; 𝑦2 = ⇒ 𝑦1 = = 0.32 ; 𝑦2 = = 0.25
𝑆1 𝑆2 1250 1000
𝒀 = 𝑦1 + 𝑦2 = 𝟎. 𝟓𝟕
𝑳=𝟐𝒏+𝑹 ⇒ 𝐿 = 2 × 2 + 12 = 16 sec
23
Webster’s Method – Example
Optimum signal cycle time
1.5 𝐿 + 5 1.5 × 16 + 5
𝐶0 = ⇒ 𝐶0 = = 67.4 sec ≈ 67.5 sec
1−𝑌 1 − 0.57
Green time
𝑦1 𝑦2
𝐺1 = 𝐶0 − 𝐿 ; 𝐺2 = 𝐶0 − 𝐿
𝑌 𝑌
0.32 0.25
𝑮𝟏 = 67.5 − 16 = 𝟐𝟗 𝐬𝐞𝐜 ; 𝑮𝟐 = 67.5 − 16 = 𝟐𝟐. 𝟓 𝐬𝐞𝐜
0.57 0.57
24
Webster’s Method – Example
Amber time
𝐴1 + 𝐴2 = 𝐶0 − 𝐺1 + 𝐺2 + 𝑅
𝑨𝟏 = 𝑨𝟐 = 𝟐 𝐬𝐞𝐜
25
IRC Guidelines
Step 1 – Pedestrian crossing time
• Walking speed = 1.2 m/sec
• Initial walk time = 7 sec
Width of road to cross
Pedestrian green time = +7
1.2
Step 2 – Minimum green time for traffic
Minimum green time for minor road = Pedestrian green time for crossing major road
Total cycle time = (Green time + inter-green time + clearance time) for each phase
27
IRC Guidelines
Step 4 – Check for clearing the vehicles arrived during green phase
• Clearing of first vehicle = 6 sec
• Clearing of subsequent vehicle = 2 sec
28
IRC Guidelines
Step 5 – Check for optimum signal cycle by Webster's equation
Lost time per cycle
= (Amber time + inter-green time + time lost for initial delay of 1st vehicle) for 2 phases
= (2 + 2 + 4) × 2 = 16 sec
Approach roadway width (m) 3.0 3.5 4.0 4.5 5.0 5.5
Saturation flow (PCU/hr) 1850 1890 1950 2250 2550 2990
Approach roadway width > 5.5 m ⇒ Saturation flow = (525 × Width) PCU/hr
1.5 𝐿 + 5
𝐶0 = ⇒ If Optimum signal cycle < Cycle time calculated = Design is acceptable
1−𝑌
29
IRC Guidelines – Example
At a right-angled intersection of two roads, Road 1 has four lanes with a total width of
12.0 m and Road 2 has two lanes with a total width of 6.6 m. The volume of traffic
approaching the intersection during design hour are 900 and 743 PCU/hour on the
two approaches of Road 1 and 278 and 180 PCU/hour on the two approaches of
Road 2. Design the signal timings as per IRC guidelines.
30
IRC Guidelines – Example
Given data
• Road – 1
Width, 𝑊1 = 12 m
Approach volumes = 900 & 743 PCU/hr
Design traffic = max. (900, 743) = 900/2 = 450 PCU/hr (volume per lane)
• Road – 2
Width, 𝑊2 = 6.6 m
Approach volumes = 278 & 180 PCU/hr
Design traffic = max. (278, 180) = 278 PCU/hr (volume per lane)
31
IRC Guidelines – Example
Step 1 – Pedestrian crossing time
12
Pedestrian green time for Road – 1 = + 7.0 = 17 sec
1.2
6.6
Pedestrian green time for Road – 2 = + 7.0 = 12.5 sec
1.2
450
Minimum green time for vehicles on Road – 1, 𝐺1 = 17 × = 27.5 sec
278
32
IRC Guidelines – Example
Step 3 – Revised green time for traffic signals
Total cycle time = (Green time + inter-green time + clearance time) for each phase
Total cycle time = (17 + 2 + 2) + (27.5 + 2 + 2) = 52.5 sec
34
IRC Guidelines – Example
Step 5 – Check for optimum signal cycle by Webster's equation
Lost time per cycle
= (Amber time + inter-green time + time lost for initial delay of 1st vehicle) for 2 phases
= (2 + 2 + 4) × 2 = 16 sec
Saturation flow
Road – 1 (width = 6 m) = 525 × 6 = 3150 PCU/hr
Road – 2 (width = 3.3 m) = From Table = 1874 PCU/hr
35
IRC Guidelines – Example
Step 5 – Check for optimum signal cycle by Webster's equation
𝑞1 𝑞2 900 278
𝑦1 = ; 𝑦2 = ⇒ 𝑦1 = = 0.286 ; 𝑦2 = = 0.148
𝑆1 𝑆2 3150 1874
𝒀 = 𝑦1 + 𝑦2 = 𝟎. 𝟒𝟑𝟒
𝑳=𝟐𝒏+𝑹 ⇒ 𝐿 = 2 × 2 + 12 = 16 sec
1.5 𝐿 + 5 1.5 × 16 + 5
𝐶0 = ⇒ 𝐶0 = = 51.2 sec
1−𝑌 1 − 0.434
Road Green phase, sec Amber time, sec Red phase, sec Cycle time, sec
Road – 1 29 2 22 + 2 55
Road – 2 18 2 33 + 2 55
37
Road Markings
• Intended to regulate, control, warn or guide road
users
• Material (Clause 803 – MoRT&H)
Hot Applied Thermoplastic Compound
Solvent borne and Waterborne Road Marking Paints
Cold Applied Plastics
Preformed Adhesive Tapes
38
Road Markings
Classification
• Longitudinal Marking (LM)
• Transverse Marking (TM)
• Hazard Marking (HM)
• Block Marking (BM)
• Arrow Marking (AM)
• Directional Marking (DM)
• Facility Marking (FM)
39
Traffic Islands
Raised areas constructed within the roadway to establish physical channels through
which the vehicular traffic may be guided
Classification
• Divisional island
• Channelizing island
• Pedestrian loading island
• Rotary
40
Divisional Islands
• Divide highway into two
ONE-WAY roadways
41
Channelizing Islands
Guide traffic into proper channel
through intersection area
Uses
• Reduce potential conflict points
• Control merging and crossing
angles and direction of flow
• Refuge islands for pedestrian
42
Pedestrian Loading and Refuge Islands
• Provide at or near a cross walk
to aid and protect pedestrian
crossing carriageway
43
Rotary Islands
• Large central island
• Crossing converted to weaving
maneuver
44
Road Intersections
Intersections at Grade Grade Separated Intersections
Un-channelized Intersections Over-pass
Channelized Intersections Under-pass
Rotary Intersection
Signalized Intersections
45
Intersections at Grade
All roads meet at almost same level
46
Intersections at Grade
7 basic forms
• T; Y; Scissor; Cross; Staggered;
Staggered and skewed; Multiway.
47
Unchannelized Intersections
NO restriction to the vehicles to use any part of intersection area
48
Channelized Intersections
Channelize traffic flow into appropriate streams by introducing islands into
intersection areas
Functions
• Channelize turning traffic into appropriate paths
• Control angle of approach of vehicles
• Reduce relative speed
• Decrease conflict area at intersection
49
Rotary Intersections
Converging vehicles forced to move round a large central island in one direction
before they weave out into their respective directions radiating from central island
Design factors
• Design speed • Radius of entry and exit curves
• Shape of central island • Capacity
• Radius of rotary roadway • Channelizing islands
• Weaving angle and weaving distance • Camber and superelevation
• Width of entry and exit carriageway • Sight distance and grade
• Width of rotary roadway • Lighting and traffic signs
50
Rotary Intersections
Design speed
• One or more of converging roads is
important highway = 40 km/h
• All other cases = 30 km/h
51
Rotary Intersections
Radius of central island
• Different radii at different points
• Radius of entry curve
40 km/h = 20 to 35 m
30 km/h = 15 to 25 m
• Min. radius of central island =
1.33 times of radius of entry curve
52
Rotary Intersections
Weaving angle
Angle between path of vehicle entering
rotary and another vehicle leaving
rotary at adjacent roads
• Angle ≥ 15°
• Smaller angle ⇒ Larger diameter of
central island
53
Rotary Intersections
Weaving length
Length of rotary roadway between two
channelizing islands of adjacent
intersecting legs
• 40 km/h = 45 to 90 m
• 30 km/h = 30 to 60 m
54
Rotary Intersections
Width of rotary roadway, 𝑾
Mean width of entry and non-weaving
section + One traffic lane
55
Rotary Intersections
Entrance and exit curves
• Radius of entrance curve = Min.
recommended radius of central island
• Radius of entry curve
40 km/h = 20 to 35 m
30 km/h = 15 to 25 m
• Radius of exit curve
1.5 to 2.0 times radius of entry
curve
56
Rotary Intersections
Weaving section
Channelizing
Capacity of rotary island
𝒆 𝑷 Central
𝟐𝟖𝟎 𝑾 𝟏 + 𝟏− Island
𝑾 𝟑
𝑸𝒑 =
𝑾
𝟏+
𝑳
𝑸𝒑 = Practical capacity of weaving section, PCU/hr
𝑾 = Width of weaving section, m (Range = 6 to 18 m)
𝒆 = Average width of entry, 𝒆𝟏 and width of non-
weaving section, 𝒆𝟐 , m
𝒆𝟏 + 𝒆𝟐
𝒆= ; 𝒆Τ𝑾 = 𝟎. 𝟒 𝐭𝐨 𝟏. 𝟎
𝟐
57
Rotary Intersections
Weaving section
Channelizing
Capacity of rotary island
𝒆 𝑷 Central
𝟐𝟖𝟎 𝑾 𝟏 + 𝟏− Island
𝑾 𝟑
𝑸𝒑 =
𝑾
𝟏+
𝑳
𝒍 = Length of weaving section between ends of
channelizing island (𝒘Τ𝒍 = 0.12 to 0.40)
𝑷 = Proportion of weaving traffic (Range = 0.4 to 1.0)
𝒃+𝒄
𝑷= 𝒂 = Left turning traffic moving along left extreme lane
𝒂+𝒃+𝒄+𝒅
𝒃 = Crossing/weaving traffic turning right while entering rotary
𝒄 = Crossing/weaving traffic turning left while leaving rotary
𝒅 = Right turning traffic moving along right extreme lane
58
Rotary Intersections
Sight distance
• Minimum sight distance
40 km/h = 45 m
30 km/h = 30 m
Gradient
• Level ground preferable
• Max. slope with horizontal = 1 in 50
59
Signalized Intersections
• Prevent traffic conflicts
• Reduce accidents
• Minimize overall delay
• Economize on time spent by police personnel
60
Grade Separated Intersections
Intersecting roads provided vertical level separation by means of a bridge to
eliminate crossing conflicts at intersection
Types of Interchanges
61
Interchanges
Diamond Interchange Rotary Interchange
62
Interchanges
63
Capacity of Intersections
• Uncontrolled intersection
Two-lane two-way traffic = 1200 to 1400 veh/hr
Four-lane two-way traffic = 1400 to 1500 veh/hr
64
Accident Analysis
• Main objective of traffic engineering
SAFE traffic movements
Minimize accident rate
o Systematic accident studies
o Preventive measures – Design and control
65
Causes of Accidents
• Road users – Drivers, pedestrians, passengers
• Vehicle – Vehicle defects
• Road features – Road design and condition
• Traffic – Traffic condition
• Environmental factors – Weather, animals, road furniture
66
Accident Studies and Records
• Collection of accident data
• Preparation of accident reports
• Preparation of location file
• Preparation of diagrams showing type of collision
• Suggestion to prevent similar accidents at same location
67
Collection of Accident Data
Standard forms in IRC
68
Collection of Accident Data
69
Collection of Accident Data
70
Accident Report
• Report accidents to police authority
• Police authority
Collect further details
Take legal action
• Use of accident report
Accident analysis
Claims for compensation
Evaluation of accident cost
71
Accident Records
• Location files
Record of accident location
Identify locations of high accidents
Maintained by police station
• Spot maps
Accident location by spots or
symbols in road map
Suitable scale
72
Accident Records
• Collision diagram
Details of accident location & path
of vehicles and pedestrian involved
Compare accident pattern before
and after remedial measures taken
• Condition diagram
Accident location showing cross-
section and geometric details, road
environment.
73
Accident Investigations & Analysis
• Accident investigations
• Analysis of individual accidents
• Statistical analysis of accidents
74
Accident Investigations
• Determine primary and contributing cause of accident
Influence of alcohol
Overspeeding
Vehicle defect
Skidding – Poor pavement condition
75
Analysis of Individual Accidents
Some simple types of accidents
• Moving vehicle collides with stationary object/parked vehicle
• Two vehicles approaching from different directions collide at intersection
• Head-on collision of two vehicle approaching from opposite direction
• Rear-end collision of two moving vehicles
76
Analysis of Individual Accidents
Assumptions
• Skid marks
Present ⇒ Assume 100% skid. Use skid distance to find braking distance
Not present Free collision (NO application of brakes)
• Direct or oblique at a known angle
• Uniform coefficient of friction through skid distance
77
Analysis of Individual Accidents
Newton Law of Collision
Velocity of separation
Coefficient of restitution =
Velocity of approach
Elastic collision, 𝑒 = 1
𝑉𝐵′ − 𝑉𝐴′ Velocity of separation = Velocity of approach
𝑒=
𝑉𝐴 − 𝑉𝐵 𝑉𝐵′ − 𝑉𝐴′ = 𝑉𝐴 − 𝑉𝐵
Plastic collision, 𝑒 = 0
Velocity of separation = 0 ⇒ 𝑉𝐵′ − 𝑉𝐴′ = 0
Both vehicles will stick after collision and move together
78
Analysis of Individual Accidents
Analysis of initial speed from skid resistance
Braking or skid distance, 𝑆 for a vehicle of weight, 𝑊 to slow down from 𝑣1 to 𝑣2
79
Analysis of Individual Accidents
Accident Type 1 = Collision of moving vehicle with a parked car
Vehicle A Vehicle B
(Moving vehicle) (Parked car)
Initial speed 𝑣1 0
Speed just before collision 𝑣2 0
Speed just after collision 𝑣3 𝑣3
Skid distance before collision 𝑆1 0
Skid distance after collision 𝑆2 𝑆2
Mass of vehicle 𝑊𝑎 𝑊𝑏
Coefficient of friction 𝑓 𝑓
80
Analysis of Individual Accidents
Accident Type 1 = Collision of moving vehicle with a parked car
Step (a) – Before collision
𝑣1 2 = 𝑣2 2 + 2 𝑔 𝑓 𝑆1
81
Analysis of Individual Accidents
Accident Type 1 = Collision of moving vehicle with a parked car
Step (b) – At collision
• Assuming plastic collision
Total momentum before impact = Momentum after impact
𝑊𝐴 𝑊𝐴 + 𝑊𝐵
𝑣2 = 𝑣3
𝑔 𝑔
𝑊𝐴 + 𝑊𝐵
𝑣2 = 𝑣3
𝑊𝐴
2
2
𝑊𝐴 + 𝑊𝐵
𝑣1 = 𝑣3 2 + 2 𝑔 𝑓 𝑆1
𝑊𝐴
82
Analysis of Individual Accidents
Accident Type 1 = Collision of moving vehicle with a parked car
Step (c) – After collision
𝑣3 2 = 𝑣4 2 + 2 𝑔 𝑓 𝑆2 = 2 𝑔 𝑓 𝑆2
2
𝑊𝐴 + 𝑊𝐵
𝑣1 2 = 2 𝑔 𝑓 𝑆2 + 2 𝑔 𝑓 𝑆1
𝑊𝐴
𝟐
𝑾𝑨 + 𝑾𝑩
𝒗𝟏 = 𝟐 𝒈 𝒇 𝑺𝟐 + 𝟐 𝒈 𝒇 𝑺𝟏
𝑾𝑨
83
Analysis of Individual Accidents
A vehicle of weight 2.0 tonne skids through a distance equal to 40 m before
colliding with another parked vehicle of weight 1.0 tonne. After collision both the
vehicles skid through a distance equal to 12 m before stopping. Compute the initial
speed of the moving vehicle. Assume average coefficient of friction as 0.5.
𝟐
𝑾𝑨 + 𝑾𝑩
𝒗𝟏 = 𝟐 𝒈 𝒇 𝑺𝟐 + 𝟐 𝒈 𝒇 𝑺𝟏
𝑾𝑨
84
Analysis of Individual Accidents
Accident Type 2 = Two vehicles approaching from right angles collide
85
Analysis of Individual Accidents
Accident Type 2 = Two vehicles approaching from right angles collide
86
Analysis of Individual Accidents
Accident Type 2 = Two vehicles approaching from right angles collide
At collision
Momentum before collision = Momentum after collision
𝑊𝐴 𝑊𝐵 𝑊𝐴
𝑣𝐴2 = 𝑣𝐵3 sin 𝐵 − 𝑣𝐴3 c𝑜𝑠 𝐴
𝑔 𝑔 𝑔
𝑾𝑩
𝒗𝑨𝟐 = 𝒗𝑩𝟑 𝐬𝐢𝐧 𝑩 − 𝒗𝑨𝟑 𝐜𝐨𝐬 𝑨
𝑾𝑨
𝑾𝑨
𝒗𝑩𝟐 = 𝒗𝑨𝟑 𝐬𝐢𝐧 𝑨 + 𝒗𝑩𝟑 𝐜𝐨𝐬 𝑩
𝑾𝑩
87
Analysis of Individual Accidents
Accident Type 2 = Two vehicles approaching from right angles collide
88
Analysis of Individual Accidents
Accident Type 2 = Two vehicles approaching from right angles collide
Two vehicles A and B approaching at right angles, A from West and B from South,
collide with each other. After collision, vehicle A skids in a direction 50° North of
West and vehicle B, 60° East of North. The initial skid distances of vehicle A and
B are 38 m and 20 m respectively before collision. The skid distance after collision
are 15 m and 36 m respectively. If the weights of vehicle A and B are 4.0 and 6.0
tonnes, calculate the original speeds of the vehicles. Assume average coefficient of
friction as 0.55.
𝒗𝑨𝟏 = 96 km/h ; 𝒗𝑩𝟏 = 79 km/h
89
Statistical Analysis of Accidents
• Estimate relative safety of identified road stretches
• Predict probability of accident occurrence per day
90
Measure for Reduction in Accidents
• Road design
• Vehicle maintenance
Engineering • Before and after studies
• Road lighting
• Speed control
Measures • Traffic control devices
Enforcement • Training and supervision
• Medical check
• Observance of law & regulation
92
On-Street or Kerb Parking
Parallel parking
• Less roadway width required
• No. of vehicles parked per unit length = Least
• Parking and un-parking operations difficult
𝐿
5.9 m 5.9 m
Number of vehicles that can be
parked per unit length of road
5m 2.5 m
𝐿
𝑁=
0.9 m 5.9
93
On-Street or Kerb Parking
Angle parking
• Angles 30°, 45°, 60° or 90°
• Angle increases
Roadway width required increases
More vehicles accommodated per unit length of road
• Convenient to park and un-park
• More accidents
Best angle = 45°
94
On-Street or Kerb Parking
𝑳 = 𝑨𝑩 + 𝑵 − 𝟏 𝑩𝑪 + 𝑫𝑬
30° Angle Parking
𝐶𝑃
𝐿 𝐿 = 𝑂𝐵 sin 30° + 𝑁 − 1 + 𝐷𝑄 cos 30°
sin 30°
A B C D E
30° 30°
𝐿 = 1.25 + 𝑁 − 1 × 5 + 4.33 = 5 𝑁 + 0.58
O P Q 𝑊 𝑁 = 𝐿 − 0.58 Τ5
S R
𝑾 = 𝑬𝑸 + 𝑸𝑹
𝑊 = 𝐷𝑄 sin 30° + 𝑄𝑆 cos 30°
𝑊 = 2.5 + 2.16
𝑊 = 4.66 m
95
Off-Street Parking
Basic traffic operations
• Entrance
• Acceptance
Reservoir area
• Storage Space required in front of parking lot for
• Delivery entrance acceptance and exit operations
• Exit
96
Off-Street Parking
Surface parking lots Multi-storeyed parking garages
• High space requirement • Less space requirement
• Comparatively low cost • Very costly
• Types • Inter-floor travel facility
Self parking system Elevators
Attendant parking system Ramps
97
Traffic Planning and Management
• Traffic forecast
• Access control on highways
• Road Safety Audit
98
Traffic Forecast
Establishing past trends and Econometric models
extrapolation Traffic and gross national product
Growth of traffic as guide (GNP) as guide
𝑛
𝑃𝑛 = 𝑃0 1 + 𝑟 ln 𝑃 = 𝐴0 + 𝐴1 ln 𝐺𝑁𝑃
𝑃0 = Traffic flow in base year 𝑃 = Traffic volume
𝑃𝑛 = Traffic in nth year 𝐺𝑁𝑃 = Gross National Product
𝑛 = Number of years 𝐴0 , 𝐴1 = Regression constants
𝑟 = Annual rate of growth of traffic
99
Control of Access
Need Degree of access control
• Ribbon development • Full or partial
• Increase in interference from the • Dependent on
residential and commercial Level of service
establishments ⇒ Congestion Accident frequency
101
Road Safety Audit
Stages
1. Feasibility Stage/Preliminary Design Stage
2. Detailed Design Stage
3. Construction Stage
4. Pre-Opening Stage
5. Safety Audit of Existing Roads
102