0% found this document useful (0 votes)
40 views4 pages

Maçonnerie

This document outlines the procedures and requirements for concrete masonry unit assemblies including mortar and reinforcement. It specifies material acceptance criteria, installation procedures, quality control processes, and tolerances for masonry walls.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
40 views4 pages

Maçonnerie

This document outlines the procedures and requirements for concrete masonry unit assemblies including mortar and reinforcement. It specifies material acceptance criteria, installation procedures, quality control processes, and tolerances for masonry walls.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

METHOD STATEMENT

FOR CONCRETE MASONRY UNIT


1. Scope:
This procedure relates the concrete masonry unit assemblies and these required properties
including mortar and reinforcement accessories.

2. REFERENCE DOCUMENTS
2.1. Documents establish by the contractor
A. Execution documents (SBG/SENLABO BTP)
 Dar specifications 04810
 Material test report
 Design mix
B. Documents du Plan Quality (SBG/SENLABO BTP)
 ITP
 NCR
2.2. Acceptance criteria’s of blocks
 Compressive strength 13.1 MPa for net area or 7.5 MPa for gross area
 Size +/- 10mm on nominal size
 No crack, no chips, and no deformed shape
 Fire rate if require
 Density 2002 kg/cu.m

2.3. Acceptance criteria’s of wall


Tolerance:
 Cross section dimension 12mm to 6mm
 Location of wall +/- 12mm
 Location in elevation +/- 6mm in the story heath or +/- 12mm in the total
 For bed joint and top surface do not varied 6mm in 3m or 12mm maximum
 For vertical line and surface do not varied from plumb by more than 6mm in 3 m; 9mm
in 6m an 12mm au maximum
 For vertical line such as corner door and expansion joint and control joint do not vary
from plumb by 3 mm in 3m ; 6mm in 6m or 12 mm maximum
 For line surface do not varied from do not varied from straight by more than 6mm in 3
m; 9mm in 6m an 12mm au maximum
 For joint bed +/- 3mm in indicated joint stickiness and 12mm maximum
3. PREVIOUS OPERATIONS
 Cleaning the surfaces of slab or ground beams where the wall will be build
 scarified if it is smooth
 The surveyor give the alignment and the exact location of the wall
4. MANPOWER
 Site engineer
 Surveyor
 Foreman
 Masons
 Helpers/ labors
5. MASONRY EQUIPMENT
 scaffoldings with complete accessories and approved by the engineer
 Tooling of masonry (trowel, plumb line, and hammer. Ruler, niveau….)
 Mortar contains, Brush, sponge
 Sawing block machine
 Mortar mixer
Material
 Approved blocks
 Approved and tested sand
 Cement
 Admixture
 Reinforcement and accessories
6. PROCEDURE FOR MASONRY LAYING AND REINFORCEMENT
6.1 Laying masonry walls

 Lay unit after cleaning all faces and use only block of correct size
 Bricks shall be laid on a full bed of mortar and all cross joints and collar joints should be
filled.
 Immediately after the brick is laid, excess mortar should be struck off the external face of
the work and off the internal face of leaves of cavity walls.
 Solid and cellular blocks shall normally be laid on a full bed of mortar and cross joints and
collar joints should be filled.
 All beds of mortar shall be level and straight and vertical joints formed so as to present a
uniform pattern of bond.
 Units shall be adjusted in position only while the mortar is still soft and plastic.
 Any unit disturbed after mortar has begun to set shall be removed, cleaned and re-laid
with fresh mortar.
 Damaged units shall not be re-used.
 No portion of masonry shall be built up more than 7 blocks high at a time.
 Work which is stopped and later resumed shall not be toothed and bonded together, but
the work shall be racked back in preparation for re-commencement.
 All masonry to receive plaster, stucco or any other such applied finish shall have
sufficiently rough-keyed surfaces and/or joints.
 Exposed masonry shall be of uniform texture and color or a uniform blend within the
ranges accepted for these characteristics and shall be obtained from one source or
manufacturer.
 No section of the work shall be constructed with a mixture of units from differing
sources. Batches from the same manufacturer or source shall be mixed to ensure that no
patchiness results from allowable natural manufacturing variations in color.
 The absorption rates of masonry units shall be adjusted by previously wetting to ensure a
good solid bond with the mortar.
 The external surface of buried CUM shall be coated with approved bituminous paint to
prevent capillary water climbing

6.2- Composite masonry

Provides ties as shown installed in horizontal joint min 0.25m and max 610 mm

Provides masonry joint reinforcement installed in horizontal mortar joints

Provides masonry header bonding

Provides interlocking masonry unit in corner

Provides individual or rigid metal in intersection and abutting walls

6.3- Masonry joint reinforcement

Extending 305mm beyond opening in additional to continuous reinforcement;

Interrupt joint reinforcement at control and expansion joints unless otherwise indicate

Provides continuity at wall by using prefabricated T-shaped units

Provides continuity at comers by using prefabricated L-shaped units

Cut and bend reinforcement unit as directly by manufacturers for continuity at returns,
offsets columns fireproofing, pipe enclosures and other special conditions.
6.4-Anchors masonry to structural steel and concrete

Provides an open spaces not less than 25mm wide between masonry and structural steel

Anchor masonry with anchor embedded in masonry joint and attaché to structure

Spaces anchors as indicated, but not more than 610 mm vertically and 915mm horizontally

6.5- Control and expansion joints

Install control expansion joint material in unit masonry as masonry progresses. Do not allow
material to span control and expansion joints without provision to allow for in-place
concrete wall or partition movement

6.6-Lintels

Will be install where shown and where the opening of more than 305mm for brick-size units
and 610mm for block-size units are shown without structural steel or other supporting lintels

6.7- Flashing, weep holes, cavity drainage and vents

Install embedded flashing and weep holes in masonry at shelf angles lintels and ledges other
obstruction to downward flow of water in wall and where indicated ,install vents at self
angles ,ledges ,and other obstructions to flow of air in cavities and where indicated.

6.8-Repairing and cleaning pointing

All unconfirmed units will be removed and replace

Point up joint, including corners, opening, and adjacent construction to provides a neat,
uniform appearances

Clean unit masonry as work progresses by dry brushing to remove mortar fins and smears
before tooling joints

Cure masonry wall with water up to 3 days