Estimation
Estimation
estimation
Purpose
Find material required
Find cost of material, labour, machine, petty items
Need of estimate
It gives an idea of cost of the work
It gives an idea of time required for completion of the work
It helps to invite tenders.
It helps to monitor the contractor payment record.
It helps to foresee the minor and major components of the project.
Estimate will serve as the basis for developing job costing system.
It will help to build construction schedule before execution.
Sanction
Administrative sanction is given based on approximate estimate
Technical sanction is given based on detailed estimate
Material statement
It shows total quantity of all the item of material required for the completion of
the construction
Revised estimate
Detailed estimate is revised in following condition
- When sanctioned estimate exceeds more than 5%
- When expenditure of any particular item exceeds more than 10%
- When rate or quantity of material changes
Supplementary estimation
Supplementary cost estimate is a detailed estimate
It is prepared when there is an additional requirement of works during the
construction work
Extended estimate
It is prepared when there is an additional requirement of works after
completion of the construction work
Solution
Estimated cost = plinth area x rate
Estimated cost = 500 (m2) x 3000 (rupee/m2) = 15 lakh
Method
Crossing method
Centre line method
Long wall - Short wall method
- PWD MTD
- Out to out and in to in method
- Individual / separate wall method
Note
Excavation for foundation is the first sub head of the estimate
CENTRE LINE METHOD
Suitable for big building having more rooms.
Suitable for any shape of building like circular, hexagonal …
Suitable for walls having same width
Takes less time
The centre line act as length for the complete calculation of the estimate.
Deduction for repeated measurement must be done at junction.
Cement bag
- Weight = 50 kg
- Dimension = 0.3 m2 x 0.18 m
- Volume = 35 liter
𝑐𝑒𝑚𝑒𝑛𝑡 𝑟𝑎𝑡𝑖𝑜
𝐶𝑒𝑚𝑒𝑛𝑡 𝑐𝑜𝑛𝑡𝑒𝑛𝑡 = × 𝑞𝑢𝑎𝑛𝑖𝑡𝑦 𝑜𝑓 𝑤𝑜𝑟𝑘 × 𝑓𝑎𝑐𝑡𝑜𝑟
𝑡𝑜𝑡𝑎𝑙 𝑟𝑎𝑡𝑖𝑜
Grade Proportion
M5 1 : 5 : 10
M 7.5 1:4:8
M 10 1:3:6
M 15 1:2:4
M 20 1 : 1.5 : 3
Procedure
𝑊𝑒𝑡 𝑐𝑜𝑛𝑐𝑟𝑒𝑡𝑒 = 𝑣𝑜𝑙. 𝑜𝑓 𝑤𝑜𝑟𝑘
𝐷𝑟𝑦 𝑐𝑜𝑛𝑐𝑟𝑒𝑡𝑒 = 𝑤𝑒𝑡 𝑐𝑜𝑛𝑐𝑟𝑒𝑡𝑒 × (1.52 − 1.54)
𝑐𝑒𝑚𝑒𝑛𝑡 𝑟𝑎𝑡𝑖𝑜
𝐶𝑒𝑚𝑒𝑛𝑡 𝑐𝑜𝑛𝑡𝑒𝑛𝑡 = × 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑑𝑟𝑦 𝑐𝑜𝑛𝑐𝑟𝑒𝑡𝑒
𝑡𝑜𝑡𝑎𝑙 𝑟𝑎𝑡𝑖𝑜
Solution
Total quantity of work = 0.4 x 0.8 x 1 m3 = 1.6 m3
1 0.448 𝑚3
𝑐𝑒𝑚𝑒𝑛𝑡 = × 2.464 𝑚3 = 0.448 𝑚3 → = 13 𝑏𝑎𝑔
5.5 0.035 𝑚3
1.5
𝑠𝑎𝑛𝑑 = × 2.464 𝑚3 = 0.672 𝑚3
5.5
3
𝑎𝑔𝑔𝑟𝑒𝑔𝑎𝑡𝑒 = × 2.464 𝑚3 = 1.32 𝑚3
5.5
Question
Concrete = 1:3:6
Buking of sand = 15%
Actual quantity of sand = ?
Quantity of sand per unit volume of cement = ?
Solution
1
𝑐𝑒𝑚𝑒𝑛𝑡 = = 0.1 𝑚3
10
3
𝑠𝑎𝑛𝑑 = = 0.3 𝑚3
10
0.345
𝑆𝑎𝑛𝑑 𝑎𝑠 𝑝𝑒𝑟 𝑣𝑜𝑙 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡 = = 3.45 𝑚3
0.1
Question
Determine the quantity of cement, sand and aggregate and water
- Concrete volume = 1 m3
- Concrete mix = 1 : 2 : 4 {by weight}
- Water – cement ration= 0.60 (by weight)
- Density of concrete =2400 kg/m3
Solution
Cement + sand + agg. + water = concrete
x + 2x + 4x + 0.6x = 2400 x 1
x = 315.79 kg
Cement = 315.79 kg
Sand (2x) = 631.59 kg
Aggregate (4x) = 1263.16 kg
Water (0.60 x) = 189 liter
OR
1 528 𝑘𝑔
𝑐𝑒𝑚𝑒𝑛𝑡 = × 3696 𝑘𝑔 = 528 𝑘𝑔 → = 10.56 𝑏𝑎𝑔 = 𝟏𝟏 𝒃𝒂𝒈
7 50 𝑘𝑔
2
𝑠𝑎𝑛𝑑 = × 3696 𝑘𝑔 = 𝟏𝟎𝟓𝟔 𝒌𝒈
7
4
𝑎𝑔𝑔𝑟𝑒𝑔𝑎𝑡𝑒 = × 3696 𝑘𝑔 = 𝟐𝟏𝟏𝟐 𝒌𝒈
7
Thickness of plaster
Internal wall – 12 mm (assume it 12mm if thickness not given)
External wall – 20 mm
Procedure
𝑊𝑒𝑡 𝑚𝑜𝑟𝑡𝑎𝑟 = 𝑣𝑜𝑙. 𝑜𝑓 𝑝𝑙𝑎𝑠𝑡𝑒𝑟 𝑤𝑜𝑟𝑘
𝑐𝑒𝑚𝑒𝑛𝑡 𝑟𝑎𝑡𝑖𝑜
𝐶𝑒𝑚𝑒𝑛𝑡 𝑐𝑜𝑛𝑡𝑒𝑛𝑡 = × 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑑𝑟𝑦 𝑚𝑜𝑟𝑡𝑎𝑟
𝑡𝑜𝑡𝑎𝑙 𝑟𝑎𝑡𝑖𝑜
Question
Find the quantity of cement and sand
- Mortar mix = 1:6 {by volume}
- Wall dimension = 6m x 4m x 12 mm
Solution
Total quantity of work = 6 x 4 x 0.012 x (2) = 0.576 m3
1 0.1337 𝑚3
𝑐𝑒𝑚𝑒𝑛𝑡 = × 0.936 = 0.1337 𝑚3 → = 𝟒 𝒃𝒂𝒈
7 0.035 𝑚3
6
𝑠𝑎𝑛𝑑 = × 0.936 = 0.8022 𝑚3 → 𝟐𝟖. 𝟑𝟐𝟔 𝒇𝒕𝟑
7
Question
Estimate the quantity of plaster (both face)
Length = 3m, height = 3m, thickness = 30cm
Solution
𝑃𝑙𝑎𝑠𝑡𝑒𝑟 = 3 × 3 × 0.30 × 2 = 5.4 𝑚3 → 𝑤𝑟𝑜𝑛𝑔
𝑃𝑙𝑎𝑠𝑡𝑒𝑟 = 3 × 3 × 2 = 18 𝑚2
Question
Find the quantity of cement and sand and water
- Mortar mix = 1:4 {by weight}
- Quantity of work = 3.6 m3
- w/c ratio = 0.38 {always by weight}
- density of mortar = 1450 kg/m3
Solution
calculation will be based on weight
cement + sand + water = mortar
x + 4x + 0.38x = 1450 x 3.6
x = 970.26 kg
Size of brick
Standard or modular brick
- Actual size (w/o mortar) - 19 cm x 9 cm x 9 cm
- Nominal size (with mortar) - 20 cm x 10 cm x 10 cm
No. of brick
𝑣𝑜𝑙. 𝑜𝑓 𝑡𝑜𝑡𝑎𝑙 𝑏𝑟𝑖𝑐𝑘 𝑤𝑜𝑟𝑘 𝑣𝑜𝑙. 𝑜𝑓 𝑎𝑙𝑙 𝑏𝑟𝑖𝑐𝑘 𝑖𝑛 𝑏𝑟𝑖𝑐𝑘 𝑤𝑜𝑟𝑘
𝑁 = =
𝑉𝑜𝑙. 𝑜𝑓 𝑛𝑜𝑚𝑖𝑛𝑎𝑙 𝑏𝑟𝑖𝑐𝑘 𝑉𝑜𝑙. 𝑜𝑓 𝑠𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑏𝑟𝑖𝑐𝑘
1 𝑚3
𝑁= = 500 𝑛𝑜𝑚𝑖𝑛𝑎𝑙 𝑏𝑟𝑖𝑐𝑘𝑠
0.2 × 0.1 × 0.1 𝑚3
ANALYSIS OF 1 M3 BRICK WORK
Brickwork (1 m3)
𝑐𝑒𝑚𝑒𝑛𝑡 𝑟𝑎𝑡𝑖𝑜
𝑐𝑒𝑚𝑒𝑛𝑡 𝑐𝑜𝑛𝑡𝑒𝑛𝑡 = × 𝑣𝑜𝑙. 𝑜𝑓 𝑏𝑟𝑖𝑐𝑘𝑤𝑜𝑟𝑘 × 0.3 𝑜𝑟 0.33
𝑡𝑜𝑡𝑎𝑙 𝑟𝑎𝑡𝑖𝑜
Question
Calculate no. of traditional bricks required for 1 m3 masonry work
a) 5050 b) 4950 c) 4500 d) 5075
Solution
< 10 𝑚3
N= = < 5018
0.23 𝑚 × 0.114 𝑚 × 0.076 𝑚
Closest option B
Question
Calculate quantity of cement, sand and brick for a wall
- Dimension of wall = 10m x 2m x 30cm
- Mortar mix = 1:4
Solution
Volume of brickwork = 10 x 2 x 0.3 m3 = 6 m3
1 0.4 𝑚3
𝑐𝑒𝑚𝑒𝑛𝑡 = × 2 𝑚3 = 0.4 𝑚3 → = 12 𝑏𝑎𝑔
5 0.035 𝑚3
4
𝑠𝑎𝑛𝑑 = × 2 𝑚3 = 1.6 𝑚3 → 56.15 𝑓𝑡3
5
SOILING WORK
brick soiling
N = 32 𝑏𝑟𝑖𝑐𝑘𝑠 N = 54 𝑏𝑟𝑖𝑐𝑘𝑠
Question
For flat brick soling, what is no. of brick required of nominal size 20 x 10 x 10
cm3 with 1.2 cm cement mortar and with allowing the wastage of 1 % of brick
for 10 m2 area.
Solution
10 𝑚2
𝑁= × 1.01
0.212 𝑚 × 0.112 𝑚
𝑁 = 425 𝑏𝑟𝑖𝑐𝑘𝑠
STONE WORK
Column
- Minimum – 0.8 %
- Maximum – 6 %
𝑡𝑜𝑡𝑎𝑙 𝑙𝑒𝑛𝑔ℎ𝑡
𝑁𝑜. 𝑜𝑓 𝑏𝑎𝑟𝑠 =
𝑐⁄𝑐 𝑠𝑝𝑎𝑐𝑖𝑛𝑔 𝑜𝑓 𝑏𝑎𝑟𝑠
ROAD ESTIMATE
Lead
It is the average horizontal distance between
- the source of availability of material (borrow pit) and
- the construction site (site of disposal / spreading)
Lift
It is the Average vertical distance between
- the source of availability of material (borrow pit) and
- the construction site (site of disposal / spreading)
Note
Nominal lead = 30 meter
Nominal lift = 1.5 meter
Note
The Intial lead for earthwork = 50 m
The lead is generally measured in terms of 50m distances.
The unit of lift is 2.00m for first lift and one extra lift for every 1.0m.
The costing is done on the basis of lead for metal road hence lift should be
converted to lead
Lift Lead
< 3.6 m Lift x 10
3.6 m to 6 m (lift)2 x 8.3
>6m Lift x 20
Type of surface MF
Metal tracks 1 Concrete road or bitumen road
Cart 1.1 Gravel road
Sandy 1.4 Earthen road
Area of cross section
𝐴 = 𝐵𝑑 + 𝑠𝑑 2 𝑠𝑏 2 + 𝑟 2 (2𝑏𝑑 + 𝑠𝑑 2 )
𝐴=
B = width of formation 𝑟2 − 𝑠2
= crest width
1 (𝑏 − 𝑟𝑑)2
𝐴𝑐𝑢𝑡𝑡𝑖𝑛𝑔 = ×
2 𝑟−𝑝
1 (𝑏 + 𝑟𝑑)2
𝐴𝑓𝑖𝑙𝑙𝑖𝑛𝑔 = ×
2 𝑟−𝑠
Planimeter
Used to measure area of irregular shapes
EARTH WORK
When cross section area is same When cross section area varies
along entire length along length
⇓ ⇓
𝑉 = 𝑐⁄𝑠 𝑎𝑟𝑒𝑎 × 𝑙𝑒𝑛𝑔ℎ𝑡 Mid-section method
𝑉 = 𝐵𝑑 + 𝑠𝑑 2 × 𝐿
Trapezoidal method
(Mean section area mtd.)
(End area mtd.)
Prismoidal method
(simpson’s 1/3 rule)
Mid section method
𝑑1 + 𝑑2
𝑑𝑚 =
2
2
𝐴𝑚 = 𝐵𝑑𝑚 + 𝑠𝑑𝑚
𝑉 = 𝐴𝑚 𝐿
Trapezoidal method