Module 2
Module 2
• Embrace diversity
• Helps to stay on top of extra tasks that might be added during the
course of the project
• Defines and outlines all of the work that is included within a project,
• Objectives
• Tasks
• Outputs
• Deadlines
• Budgets
Steps of project scope management
• 1. Resource planning
• 2. Cost estimation
• 3. Cost budget.
• 4. Cost control.
• 1. Resource planning: plan, allocate, and schedule the resources needed for
each stage of a project
• 2. Cost estimation: process of approximating the costs associated with each of
the resources required for all scheduled activities
• Analogous estimating – Past projects should inform the cost estimate, here.
Analogous estimations use previous, similar projects as a reference point for
costing up the new one.
• Parametric modelling – Mathematical formulas, based on Regression Analysis
or Learning Curve models, informed potential project cost estimations.
• Bottom-up estimating – Costs are based on known quantities, such as
individual work or item cost and duration or time spent on individual tasks.
Learning curves
Problems with Cost Estimation
• Low initial estimates
• Unexpected technical difficulties
• Lack of definition
• Specification changes
• External factors
3. Cost budget.
• Process of mitigating the potential negative impact unforeseen events can have
on a project's cost, time table, or other resources
Risk management occurs in 5 steps:
1.Risk planning
2.Risk identification
3.Risk analysis
4.Risk response plan
5.Risk monitoring
RISK PLANNING This includes how risks will be identified and scored, along
with how contingencies and their owners will be determined
and assigned.
Risk response plan viable risk response for each threat and opportunity should
be identified as falling within the range of risk tolerance
threshold
Threats: Avoid: Mitigate: Transfer: Accept:
Opportunities: Exploit, enhance, share, accept
Risk monitoring The project manager monitors the risk register, executing on
response plans, as well as documenting subsequent threats
and opportunities as they become known throughout the
project life cycle.
9. Project procurement management