PROJECT - STANDARD - AND - SPECIFICATIONS - Progress - Measurement - Procedure - Rev01 Web Copy-ALIU
PROJECT - STANDARD - AND - SPECIFICATIONS - Progress - Measurement - Procedure - Rev01 Web Copy-ALIU
TABLE OF CONTENTS
PURPOSE 2
PROGRESS PLANNING 2
ATTACHMENTS 12
Attachment 1 Engineering Weight Value List 12
Attachment 2 Procurement Weight Value List 13
Attachment 3 Construction Weight Value List 14
Attachment 4 Overall Progress Table 15
Attachment 5 Project Summary Progress Table 16
Attachment 6 Engineering progress Sheet (from EDMS) 17
Attachment 7 Procurement progress Sheet 18
Attachment 8 Weighted Factors for Work Step (for Construction 19
Progress)
Page 2 of 23
KLM Technology PROGRESS MEASUREMENT
Group Rev: 01
PROCEDURE
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2012
SPECIFICATIONS)
PURPOSE
The purpose of this procedure is to establish a method for the progress measurement
of engineering, procurement and construction for the PROJECT. This procedure
defines the physical progress measurement and progress calculation method for the
PROJECT.
PROGRESS PLANNING
In parallel with schedule planning, CONTRACTOR will carry out progress planning in
accordance with the project schedules. The following studies will be conducted.
Contractor will be prepared the progress reports based on the progress measurement
system described Work Breakdown Structure. Overall progress will be composed sum
of the value of each phase with following weighted percentage.
PHASE WEIGHTED %
Engineering 6.88%
Procurement 59.97%
Construction 33.15%
OVERALL TOTAL 100.00%
Page 4 of 23
KLM Technology PROGRESS MEASUREMENT
Group Rev: 01
PROCEDURE
Project Engineering Standard
(PROJECT STANDARDS AND Feb 2012
SPECIFICATIONS)
PORTION WEIGHTED %
The weight value for each discipline is apportioned by a ratio of the engineering
man-hours assigned to each discipline as follows:
DISCIPLINE WEIGHTED %
2. Engineering Deliverables
The basis of percentage for engineering design and weighted value of each
deliverable by discipline are shown in Attachment 1.
• For Approval/Review
Start 10%
Drafting 10%
Check 10%
Issue 80%
Approval 10%
Total 100%
• For information
Start 20%
Issue 80%
Total 100%
• P&ID
Start 10%
Drafting 10%
Check 10%
Issue for Review 30%
Issue for Design 30%
Issue for Construction 10%
Total 100%