IOM Workbook (Contents)
IOM Workbook (Contents)
Prepared by:
Engr. Amina Israr
___________________________
Course teacher
INDEX
Ability to
No ability to Marginal ability properly Perfect
Problem Data properly to properly articulate data articulation of
Articulation & articulate data articulate data from problem data from the
Formulation from problem from problem statement with problem
30% statement statement minor statement
shortcomings
Exact solution
methodology
Solution
Problem No proper Understandable followed with
methodology
Solution solution solution proper
apparent to a
Methodology methodology methodology statement and
certain extent
30% validation of
assumptions
A generic result
without the Unique and
Final Result No result Incorrect Result
setup of valid applicable result
20%
assumptions
Total (%)
PRACTICAL 1
OBJECT:
To study the classic and EOQ inventory management models; also, determine the Economic Order
Quality for the given data.
INVENTORY:
Inventory is a list of movable items required for manufacturing the product and to maintain plant
facility in working condition. It is investment in the form of raw material, tools, gages, supplies etc.
Raw material
Work in process
Maintenance ,Repair and Operating Materials
Finished goods
INVENTORY CONTROL:
Inventory control means making the desired items, required quality and in scientifically determine
quantity to meet the production demands, available to various departments when needed.
√𝟐∗𝑨∗𝑪𝑷
Q* =
𝑪𝒉
A company that markets painless hypodermic needles to hospitals would like to reduce its
inventory cost by determining the optimal number of needles to obtain per order. The annual
demand is 1000 units; commodity cost per unit is $10; the setup or ordering cost is $10 per
order and the holding cost per unit per year is $0.50. Using these data, calculate:
Ability to
No ability to Marginal ability properly Perfect
Problem Data properly to properly articulate data articulation of
Articulation & articulate data articulate data from problem data from the
Formulation from problem from problem statement with problem
30% statement statement minor statement
shortcomings
Exact solution
methodology
Solution
Problem No proper Understandable followed with
methodology
Solution solution solution proper
apparent to a
Methodology methodology methodology statement and
certain extent
30% validation of
assumptions
A generic result
without the Unique and
Final Result No result Incorrect Result
setup of valid applicable result
20%
assumptions
Total (%)
PRACTICAL 2
OBJECTIVE
To calculate the reorder point for an EOQ model and otherwise (using safety stock).
REORDER POINT:
The two most important inventory questions are: How much to order and When to order. Simple
inventory models assume that receipt of inventory is instantaneous; i.e. the assumption is:
(1) That a firm will place an order when the inventory level reaches zero, and
(2) That it will receive the ordered items immediately.
However, the time between placement of order and receipt of order, called lead time can be short as
hours or as long as months. Therefore, the When-to-order decision is usually expressed in terms of a
reorder point (ROP) ---the inventory level at which an order should be placed that the order will
arrive just as the firm’s stock is depleted.
SAFETY STOCK
An important assumption for an EOQ model is that the demand rate and lead time are both known
and constant.
However, there may be situations wherein any of the two values may vary; i.e. Variances are caused
by changes in demand rates and lead times. To meet the average demand during lead time,
additional inventory is needed, in order to protect against uncertainties in demand or lead time. The
additional inventory is referred to as safety shock. When holding safety stock (SS), the average
inventory level is:
QUESTION 2
Calculate the reorder point for the above given data considering that the firm policy is to maintain
inventory levels (safety stock) at 10 units. Compare the cost results, and draw reorder point graph for
each of the two questions.
PERFORMANCE EVALUATION RUBRIC – EXERCISE # __
Ability to
No ability to Marginal ability properly Perfect
Problem Data properly to properly articulate data articulation of
Articulation & articulate data articulate data from problem data from the
Formulation from problem from problem statement with problem
30% statement statement minor statement
shortcomings
Exact solution
methodology
Solution
Problem No proper Understandable followed with
methodology
Solution solution solution proper
apparent to a
Methodology methodology methodology statement and
certain extent
30% validation of
assumptions
A generic result
without the Unique and
Final Result No result Incorrect Result
setup of valid applicable result
20%
assumptions
Total (%)
PRACTICAL 3
OBJECTIVE
To study the quantity discount model.
QUANTITY DISCOUNT:
A quantity discount is simple a reduced price for an item when it is purchased in large quantity.
The overall objective of any inventory model is to minimize the total cost. However, for a quantity
discount model, even with the greatest discount price, the large order quantity might not minimize
the cost. All discount quantity goes up, the product cost goes down. On the other hand holding cost
increases with the increase in order quantity. Therefore, the major trade-off when considering
quantity discount is between reduced product cost and increased holding cost.
2 × 𝐴 × 𝐶𝑝
𝑄 ∗= √
𝐼𝑃
Where
2-For any discount, if the order quantity is low to qualify for the discount, adjust the order
quantity upwards to the lowest quantity that will qualify for the discount.
3-Using the total cost equation, compute the total cost for each of the computed order quantity
4-Select the Q* that has the lowest cost value as computed in step 3 . this will be the quantity that
will minimize the total inventory costs, determining whether the quantity discount should be
availed or not.
QUESTION # 1
Wohl discount store stock toy race cars. Recently the store has been given a quantity discount
schedule for these cars. The normal cost for toy race cars is $ 5.00, for order between 1000-1999
units the cost drop to $ 4.8, for order of 2000 units or above the unit cost is only $4.75 . Furthermore
ordering cost is $49.0 per order. Annual demand is 5000 race cars and inventory charges as a
percentage of cost is I= 20
QUESTION # 2
Haier computer purchases integrated chips at cost $350 per chip. The ordering cost is $120 per order
and the demand is 400 per month. The computer supplier decided an offer price concession in order
to attract large orders the price structure is shown below. Haier computer wishes to use a 10 %
holding cost, what is the optimal order quantity and what is the optimal cost
PERFORMANCE EVALUATION RUBRIC – EXERCISE # __
Ability to
No ability to Marginal ability properly Perfect
Problem Data properly to properly articulate data articulation of
Articulation & articulate data articulate data from problem data from the
Formulation from problem from problem statement with problem
30% statement statement minor statement
shortcomings
Exact solution
methodology
Solution
Problem No proper Understandable followed with
methodology
Solution solution solution proper
apparent to a
Methodology methodology methodology statement and
certain extent
30% validation of
assumptions
A generic result
without the Unique and
Final Result No result Incorrect Result
setup of valid applicable result
20%
assumptions
Total (%)
PRACTICAL 4
OBJECTIVE:
To study the project management techniques using POM for windows.
PROJECT MANAGEMENT
Project management involves planning and controlling a project, its goal is to ensure that the
project’s objective are achieved on time and within budget
PERT = Program Evaluation and Review Technique and
CPM = Critical Path Method
are technique used by managers to plan, schedule and control the execution of large and complex
engineering project
Important Terminology:
Activity: A task or subproject in CPM or PERT network that occurs between two
events.
Event: An instant that marks the start or completion of task or activity in a network.
Networking approaches:
Activity on Node (AON):- Network diagram in which nodes designated activities.
Activity on Arrow (AOW):- Network diagram in which arrows designate
activities.
Path: An unbroken chain of activity arrows connecting initial event to sum other event.
Critical Path: The computed longest time path(s) through the network.
Slack Time: The amount of time by which an individual activity in a network can be delayed
without
delaying the entire project.
Dummy: Activities having no time, inserted into the network to show dependency i.e.
maintain
the logic of the network
Critical Path Method:
Critical path method, commonly known as CPM is a network technique based on assumptions that
activity times are known with certainty and hence, uses only one time factor activity. This
conveniently enables managers to schedule, monitor and control large and complex projects.
Critical Path Analysis:
The objective of critical path analysis is to determine the following quantities for each activity.
ES: Earliest activity starts time. In forward pass, predecessor activities must be completed before an
activity can be started. The ending time of the predecessor activity is the earliest time an activity can
be started.
LS: Latest activities start time. In backward pass, all following activity must be completed without
delaying the project; that is the latest time at which an activity can be started without delaying the
entire project.
Once these quantities are known for each activity, the overall project can be analyzed. Typically, this
analysis includes examination of the following:
The Critical Path------ the group of activities in the project that have a zero slack time. This path is
critical, because a delay in any activity along it would delay the entire project.
Project time----the total project completion time, calculated by adding the expected time values of
those activities on the critical path.
Question #1:
Given the following information, develop the precedence diagram/Network diagram to determine
critical path; also find ES, EF, LS, LF and slack for each activity.
Ability to
No ability to Marginal ability properly Perfect
Problem Data properly to properly articulate data articulation of
Articulation & articulate data articulate data from problem data from the
Formulation from problem from problem statement with problem
30% statement statement minor statement
shortcomings
Exact solution
methodology
Solution
Problem No proper Understandable followed with
methodology
Solution solution solution proper
apparent to a
Methodology methodology methodology statement and
certain extent
30% validation of
assumptions
A generic result
without the Unique and
Final Result No result Incorrect Result
setup of valid applicable result
20%
assumptions
Total (%)
PRACTICAL 5
OBJECTIVE:
To study the PERT model using POM for windows software
PERT:
Program Evaluation and Review Technique (PERT) is a technique to enable managers to schedule,
monitor and control large and complex engineering projects by employing 3 time estimate for each
activity. It allows randomness in activity completion times as the activities are subjected to
considerable degree of uncertainty ,the activity time estimate for PERT are probabilistic
Optimistic Time (a)-- The best activity completion time that could be obtained in PERT. It
is generally the shortest time in which an activity can be completed.
Most Probable Time (m)—the most likely time to complete an activity in PERT. It is the
completion time having the highest probability
Pessimistic Time (b)—The worst activity time that could be expected PERT network. It is the
longest time that an activity may require
PERT assumes a beta Probability distribution for the time estimates. For a beta distribution, the
expected time for each activity can be approximated using the following weighted average
To calculate the variance for each activity completion time, if three standard deviation times were
selected for the optimistic and pessimistic times, then there are six standard deviations between them,
so the variance is given by :
Develop the precedence diagram, and compute the result for the following data using PERT
networking model.
Activity time
A 01 01 01 -
B 5 6 7 A
C 2 5 8 A
D 6 7 14 B
E 1 2 3 C
F 3 3 3 D,E
G 6 8 10 C
H 1 4 7 F
I 4 5 6 G,H
PERFORMANCE EVALUATION RUBRIC – EXERCISE # __
Ability to
No ability to Marginal ability properly Perfect
Problem Data properly to properly articulate data articulation of
Articulation & articulate data articulate data from problem data from the
Formulation from problem from problem statement with problem
30% statement statement minor statement
shortcomings
Exact solution
methodology
Solution
Problem No proper Understandable followed with
methodology
Solution solution solution proper
apparent to a
Methodology methodology methodology statement and
certain extent
30% validation of
assumptions
A generic result
without the Unique and
Final Result No result Incorrect Result
setup of valid applicable result
20%
assumptions
Total (%)
PRACTICAL 6
OBJECTIVE:
To study the concept of project crashing and using POM software, determine solution to the given
problem.
Crashing:
Additional resource allocation to shorten critical activity times in a network to reduce the total
project completion time is referred to as Crashing. These resources might be additional labor, more
equipment, etc.
Significance of Crashing:
Crashing or reducing activity times can be expensive. However, doing so might be worthwhile, in the
following cases.
• If a company faces costly penalties for being late with a project, using additional resources to
complete the project on time might be economical.
• Also, there may be fixed costs every day the project is in process. Therefore, it might be profitable-
to allocate extra resources to shorten the overall project time and save some of the daily fixed costs
• Crashing is especially important when contracts for projects include bonuses or penalties nor early
or late finishes.
For simplicity, it is assumed that costs increase linearly as the activity time is reduced from its
expected to its crash value.
With the above given formula, the least cost for least expensive method) of reducing the project
completion time can easily be determined.
Two or more critical paths may exist after performing project crashing. Thus, for two critical
paths, critical activities on both should be crashed to reduce the project completion time
QUESTION #1
Development of a new deluxe version of a particular software product is being considered by a
software house. The activities necessary for the completion of this are listed as follows:
QUESTION # 2
Cole Builder manufactures steel storage sheds for the commercial us. The activities necessary to build an
experimental model are related data are given in the accompanying table.
Activities Normal time Crash time Normal cost Crash cost Immediate
predecessor
A 0 0 0 0 -
B 3 2 1000 1600 A
C 2 1 2000 2700 A
D 1 1 300 300 A
E 7 3 1300 1600 B
F 6 3 850 1000 C
G 2 1 4000 5000 D
H 4 2 1500 2000 E,F,G
Ability to
No ability to Marginal ability properly Perfect
Problem Data properly to properly articulate data articulation of
Articulation & articulate data articulate data from problem data from the
Formulation from problem from problem statement with problem
30% statement statement minor statement
shortcomings
Exact solution
methodology
Solution
Problem No proper Understandable followed with
methodology
Solution solution solution proper
apparent to a
Methodology methodology methodology statement and
certain extent
30% validation of
assumptions
A generic result
without the Unique and
Final Result No result Incorrect Result
setup of valid applicable result
20%
assumptions
Total (%)
PRACTICAL 7
OBJECTIVE
To study the assembly line balancing models and to solve the problem by largest Candidate Rule and
Ranked positional Weight method, using POM for windows.
Assembly Line:
A manual assembly line is a production line that consists of a sequence of workstations where
assembly tasks are performed by human workers. Products are assembled as they move along. At
each station, a portion of the total work is performed on each unit. The production rate of an
assembly line is determined by its slowest station.
Terminology:
Assembly Workstation:-
A workstation on a manual assembly line is designated location along the work flow path at which
one or more work elements represent small portions of the total work that must be accomplished to
assemble the product.
Movement of work units along manual assembly line may be accomplished in two ways:
Manually
By a mechanized system
1. Continuous---comprises of a continuously moving conveyor that operates at a constant
velocity.
2. Synchronous—also known as intermittent transfer, all work units are moved simultaneously
between stations with a quick discontinuous motion and then positioned at their respective
stations.
3. Asynchronous---a work unit leaves a given station when the assigned task has been
completed and the worker releases the unit.
Line pacing:
A manual assembly line operates at a certain cycle time which is established to achieve the required
production rate of the line. Each worker must complete the assigned task at his station within this
cycle time or else the required production rate will not be achieved.Assembly lines can be designed
to deal with differences in assembled products. The three assembly line types are:-
Single model
Batch model
Mixed model
RC=1/TC
TS=TC+TR
RC=Production Rate (parts/minutes)
TC=Cycle Time (minute/part)
Ts=Allowalble Services Time Per station(minutes)
Tr=Respositioning Time (minutes)
1. The work elements are arranged in descending order according to their Tek valus.
2. Assign elemetns to the worker at the first workstation by starting at the top pf the list
and selecting the first element that satisfies the precedence requirements and does not
cause the total sum of Tek at the station to exceed the allowable Ts.
3. When no more elements can be assigned without exceeding Ts, then proceed to the
next station.
4. Repeat steps 2 ans 3 until all element have been assigned.
The ranked positional weight method (RPW) takes into account both the Tek value and its position in
the precedence diagram.
1) RPWk is calculated by summing Tek and all other times for elements that follow Tek in thye
arrow chain of precedence diagram.
2) Elements are compiled into a list according to their descending order of RPW values.
3) Assign elements to the worker at the first workstation by starting at the top of the list and
selecting the first element that satisfies the precedence requirements and does not cause the
total sum of Tek at the station to exceed the allowable Ts.
4) When no more elements can be assigned without exceeding Ts , then proceed to the next
station.
5) Repeat steps 3 and 4 until all elements have been assigned.
PERFORMANCE EVALUATION RUBRIC – EXERCISE # __
Ability to
No ability to Marginal ability properly Perfect
Problem Data properly to properly articulate data articulation of
Articulation & articulate data articulate data from problem data from the
Formulation from problem from problem statement with problem
30% statement statement minor statement
shortcomings
Exact solution
methodology
Solution
Problem No proper Understandable followed with
methodology
Solution solution solution proper
apparent to a
Methodology methodology methodology statement and
certain extent
30% validation of
assumptions
A generic result
without the Unique and
Final Result No result Incorrect Result
setup of valid applicable result
20%
assumptions
Total (%)
PRACTICAL 8
OBJECTIVE:
To evaluate the most feasible facility / plant location using the location strategic
models available in POM Software. (Location breakeven analysis)
Location Strategies:
Selection of the plant location is an important and complex strategic decision, as plant
location greatly affects both, the fixed and variable costs. Location is a significant cost
driver that requires location decisions to be made only after careful considerations; as
once setup, an industry cannot be shifted to another location unless it is inevitable to
do so.
Location decisions depend upon the type of business. For industrial location decisions,
the strategy is usually minimizing costs. Whereas, for retail and professional service
organizations, the strategy focus is on maximizing revenue. In general, the objective of
location strategy is to maximize the benefit of location to the firm.
Factors affecting location decisions come under the general jurisdiction of the
following titles:-
Selection of country.
Selection of region / community
Selection of site.
Location Decision Models:
Steps:
Determine the fixed and variable costs for each location.
Plot the costs for each location, with costs on the vertical axis and annual
volume on the horizontal axis of the graph.
Select the location that has the lowest total cost for the expected production
volume.
Question:
The fixed and variable cost for four potential plant sites for ski equipment
manufacturer are shown below:
Site Fixed cost per year ($) Variable cost per unit
($)
Karachi 125,000 4
Lahore 75,000 7
Islamabad 100,000 5
Peshawar 50,000 12
Ability to
No ability to Marginal ability properly Perfect
Problem Data properly to properly articulate data articulation of
Articulation & articulate data articulate data from problem data from the
Formulation from problem from problem statement with problem
30% statement statement minor statement
shortcomings
Exact solution
methodology
Solution
Problem No proper Understandable followed with
methodology
Solution solution solution proper
apparent to a
Methodology methodology methodology statement and
certain extent
30% validation of
assumptions
A generic result
without the Unique and
Final Result No result Incorrect Result
setup of valid applicable result
20%
assumptions
Total (%)
PRACTICAL 9
OBJECTIVE:
To evaluate the most feasible facility/plant location using the location strategy model available in POM
software (Factor Rating Method)
Steps:
Spencer has rated each location for factor on a 100 point basis. These rating are given
below:
Location
Factors Present Location Newbury hyderPark
1 40 60 50
2 20 20 80
3 30 60 50
4 80 80 50
PERFORMANCE EVALUATION RUBRIC – EXERCISE # __
Ability to
No ability to Marginal ability properly Perfect
Problem Data properly to properly articulate data articulation of
Articulation & articulate data articulate data from problem data from the
Formulation from problem from problem statement with problem
30% statement statement minor statement
shortcomings
Exact solution
methodology
Solution
Problem No proper Understandable followed with
methodology
Solution solution solution proper
apparent to a
Methodology methodology methodology statement and
certain extent
30% validation of
assumptions
A generic result
without the Unique and
Final Result No result Incorrect Result
setup of valid applicable result
20%
assumptions
Total (%)
PRACTICAL 10
Objective:
To evaluate the most feasible facility/ Plant Location using the location strategic
models available in POM software (Center of gravity method)
Step:
Centre of gravity method works of location placed on arbitrary coordinates system wherein the
relative distance are to be represented correctly. The centre of gravity is given by:
Since the number of containers shipped each month affects cost, distance alone should not be the principal
criterion. The center of gravity method assumes that cost is directly proportional to both distance and volume
shipped. The ideal location is that which minimizes the weighted distance between the warehouse and its retail
outlets , whrere the distance is weighted by the number of container shipped.
Question 1
The following table gives the map coordinates and the shipping load for the set of
cities that are to be connected through a central hub. Using the center of gravity
method, identify near which location coordinates should the hub be collected?