This proposal seeks funding to replace Western Washington University's aging fiber optic network and upgrade campus security systems. The current fiber network is reaching the end of its life and constraints growth. The proposal would replace the fiber network, upgrade electronic door controls, install locks on classrooms that can be engaged from inside, and move the campus data center to improve reliability in response to safety needs.

Uploaded by

azimx77x
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
35 views71 pages

Critical Safety, Access Control, and FIber Optic Network Upgrades

This proposal seeks funding to replace Western Washington University's aging fiber optic network and upgrade campus security systems. The current fiber network is reaching the end of its life and constraints growth. The proposal would replace the fiber network, upgrade electronic door controls, install locks on classrooms that can be engaged from inside, and move the campus data center to improve reliability in response to safety needs.

Uploaded by

azimx77x
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 71

2022 PROJECT PROPOSAL CHECKLIST

2023-25 Biennium Four-year Higher Education Scoring Process

INSTITUTION CAMPUS LOCATION


380 - Western Washington University Bellingham
PROJECT TITLE OFM/CBS Project #
Critical Safety, Access Control, and Fiber Optic
30000604
Network Upgrades
PROJECT CATEGORY FPMT UNIQUE FACILITY ID # (OR NA)
Replacement - Standalone Click or tap here to enter text.
PROPOSAL IS
New or Updated Proposal (for scoring) Resubmitted Proposal (retain prior score)
☐ New proposal
☐ Resubmittal from 2018 (2019-21 biennium)
☐ Resubmittal to be scored (more than 2 biennia
☒ Resubmittal from 2020 (2021-23 biennium)
old or significantly changed)
CONTACT PHONE NUMBER
Brian A. Ross 360.650.6539

Proposal content
☒ Project Proposal Checklist: this form; one for each proposal
☒ Project Proposal Form: Specific to category/subcategory (10-page limit)
☒ Appendices: templates, forms, exhibits and supporting/supplemental documentation for scoring.

Institutional priority
☒ Institutional Priority Form. Sent separately (not in this packet).

Check the corresponding boxes below if the proposed project meets the minimum threshold or if the item
listed is provided in the proposal submittal.

Minimum thresholds
☒ Project is not an exclusive enterprise function such as a bookstore, dormitory, or contract food service.
☒ Project meets LEED Silver Standard requirements.
☒ Institution has a greenhouse gas emissions reduction policy in place in accordance with RCW
70A.45.050 and vehicle emissions reduction policy in place per RCW 47.01.440 or RCW 43.160.020 as
applicable.
☐ A complete predesign report was submitted to OFM by July 1, 2022 and approved.
☐ Growth proposals: Based on solid enrollment projections and is more cost-effectively providing
enrollment access than alternatives such as university centers and distance learning.
☐ Renovation proposals: Project should cost between 60 – 80% of current replacement value and extend
the useful life of the facility by at least 25 years.
☐ Acquisition proposals: Land acquisition is not related to a current facility funding request.
☒ Infrastructure proposals: Project is not a facility repair project.

Office of Financial Management


June 2022
2022 PROJECT PROPOSAL CHECKLIST
2023-25 Biennium Four-year Higher Education Scoring Process

☐ Stand-alone, infrastructure and acquisition proposals is a single project requesting funds for one
biennium.
Required appendices
☒ Project cost estimate: Excel C-100
☐ Degree Totals and Targets template to indicate the number of Bachelors, High Demand and Advanced
degrees expected to be awarded in 2023. (Required for Overarching Criteria scoring criteria for Major
Growth, Renovation, Replacement and Research proposals).
☐ Availability of Space/Campus Utilization template for the campus where the project is located.
(Required for all categories/subcategories except Infrastructure and Acquisition proposals).
☐ Assignable Square Feet template to indicate program-related space allocation. (Required for Growth,
Renovation and Replacement proposals, all categories/subcategories).

Optional appendices
Attach supplemental and supporting project documentation, limit to materials directly related to and needed for the
evaluation criteria, such as:
☐ Degree and enrollment growth projections
☒ Selected excerpts from institutional plans
☐ Data on instructional and/or research space utilization
☐ Additional documentation for selected cost comparables (acquisition)
☐ Selected materials on facility conditions
☐ Selected materials on code compliance
☐ Tables supporting calculation of program space allocations, weighted average facility age, etc.
☐ Evidence of consistency of proposed research projects with state, regional, or local economic
development plans
☐ Evidence of availability of non-state matching funds
☒ Selected documentation of prior facility failures, high-cost maintenance, and/or system unreliability
for infrastructure projects
☐ Documentation of professional assessment of costs for land acquisition, land cleanup, and
infrastructure projects
☒ Selected documentation of engineering studies, site survey and recommendations, or opinion letters
for infrastructure and land cleanup projects
☐ Other: Click or tap here to enter text.

I certify that the above checked items indicate either that the proposed project meets the minimum thresholds,
or the corresponding items have been included in this submittal.

Name: Brian A. Ross Title: Associate Director, Capital Budget

Signature: Electronic Signature Date: 8.8.2022

Office of Financial Management


June 2022
INFRASTRUCTURE 2023-25 Biennium Project
2022 Higher Education Project Proposal Form

INSTITUTION CAMPUS
Western Washington University Bellingham
PROJECT TITLE
Critical Safety, Access Control, and Fiber Optic Network Upgrades

SUMMARY NARRATIVE

• Problem statement

Western Washington University has two urgent and interrelated infrastructure needs that need to be solved
in a single, consolidated effort. Western must replace and expand the campus fiber optic network, which
has reached the end of its expected life and constrains growth in academic instruction; fire and life safety
systems; business operations; and building automated control systems.

Most significantly, the current fiber network constrains Western’s ability to make urgently needed changes
to the campus electronic access control system. Existing manual and electronic locks are no longer
adequate to meet campus efficiency, safety, and security obligations. In response to recent national active
shooter events, the campus emergency management committee recommended two key improvements to
campus security: expanding electronic access control capacity and installing manual classroom locks
operable from the inside. This project proposes implementation of both recommendations.

Finally, the importance of having a uniform access control system across campus has been underscored by
the demands of providing a safe workplace during the COVID pandemic, as handling physical keys
requires personal contact which could be avoided.

• Project description

The project would replace the existing damaged and undersized fiber optic communications system
between and within buildings and install electronic controls on exterior doors and designated high security
internal doors of all major academic buildings. The project will also install new hardware on classroom
doors to enable locking from the inside in the case of an active shooter emergency.

UPDATE: The project will also move the campus data center from Administrative Services Center
(approximately 1/2 mile from the southern campus border) to the Communications Facility (on campus) in
order to improve network reliability and make the access control more resilient.

Overall, these upgrades will enable Western to meet the continuing mission-critical communication and life
safety needs of students, faculty, and staff. A unified electronic access control system will simplify and
improve campus building access and security; provide improved integration with other security systems
such as video monitoring and intrusion detection; and simplify dispatch functions during emergency
responses. Manual classroom locks operable from the inside form a last line of defense should an active
shooter incident ever occur.

This project is proposed to accomplish the following:

• Replace the existing campus fiber optic network, including improving efficiency by combining stand-
alone switches and controllers to reduce space, power, and cooling needs.
• Upgrade power to network equipment closets to include emergency power and cooling.
• Bring affected data communication conduits and cable trays into electrical code compliance by
removing abandoned electrical cable and adding new trays where necessary.
• Reduce operating costs by reducing or eliminating the need for daily manual locking and opening of
academic buildings and by consolidating existing dedicated networks, such as Building Automation
Control, onto a common high-capacity backbone.
• Provide centralized lockdown functionality to facilitate more agile, appropriate, and effective response
capabilities in the event of a campus emergency.
• Provide classrooms with internally lockable doors so that students and faculty can effectively take
shelter under the “Run, Hide, Fight” response to an active shooter.

• History of project or facility

This project scope represents the convergence of several studies and plans completed over past biennia, as
well as the opportunity for construction efficiencies as similar work can be accomplished within buildings
in a single contract.

A 2017 Utilities Master Plan Update suggested that the existing fiber network supporting the Fire, Security
Alarm, Access Control, and Building Automated Control systems are at capacity and should be replaced to
maintain current service delivery and support future growth.

In the 2017-2019 biennium, Western received funding to separate its existing access control system from
the fire alarm system. During the design stage of that project, the designer confirmed the recommendation
in the Utilities Master Plan Update (in the Telecommunications Section), concluding that scattered damage
to the existing 20-year-old fiber loop, the ever-increasing reliance of academic and business operations on
web-based applications, and emerging technologies in building operating systems are stretching the fiber
loop to its capacity. The section addressing the fiber loop is included in Appendix E.

Concurrently, in response to recent national active shooter events, the campus emergency management
committee was charged with recommending strategies to improve campus safety and security. That
committee identified the risks and operational shortcomings of relying on manual keying systems that are
obsolete and failing or which do not provide the technical functionality required to safeguard buildings and
facilities quickly and effectively. Lessons learned from active shooter events around the country pointed at
two key improvements:

• Lockdown: The committee recommended expanding electronic access control capacity to improve
safety and security across campus. Electronic access controls would be installed on exterior doors,
sensitive areas, and selected high use labs. This would allow for immediate lockdown of campus, for
securing buildings automatically on a schedule for non-working hours, and for providing an electronic
record credentials used for access.
• Classroom Locks: The Final Report of the Sandy Hook Advisory Commission strongly recommended
“a standard requiring classroom and other safe-haven areas to have doors that can be locked from the
inside.” The Commission’s research indicated that “there has never been an event in which an active
shooter breached a locked classroom door.” Western’s emergency management committee urged the
adoption of that standard for campus classrooms.

More recently, the demands of the COVID pandemic have highlighted the mission-critical nature of data
communications for all university services. The institution’s resilience in the face of evolving and
increasingly unpredictable challenges hinges on a robust data network.

UPDATE: In the 2021-23 biennium, Western received partial funding ($2.15 million) that will implement
over 23,000 feet of fiber (of the approximately 155,000 total), 63 exterior access control locks (of the 290
total), and 100 classroom/lab lock upgrades. In 2023-25, Western is requesting the remainder of funding,
for a total of $15 million. The $15 million includes the inflationary adjustments to finish the scope of work
as well as moving the data center from Administrative Services Center (approximately 1/2 mile from the
southern campus border) to the Communications Facility (on campus). During project design efforts over
the past year, it was determined that moving the data center to the Communications Facility will reduce the
overall amount of fiber renewal/replacement associated with this project and improve network reliability
across campus. Overall, the data center re-location will make access control more resilient.

• University programs addressed or encompassed by the project

A robust fiber optic network is crucial for virtually all the university’s academic programs, administrative
activities, and student services, beginning with the foundation of safe, accessible spaces and continuing to
provide a technologically relevant, modern education, offering flexibility for changing conditions,
supporting communications and learning opportunities, and allowing efficient administration. Expansion of
electronic access controls, which is severely constrained without upgrading the fiber optic loop, will
improve the security of campus buildings and enhance the safety of those who study and work in them.

GENERAL CATEGORY SCORING CRITERIA

1. Significant health, safety, and code issues

A. While Western’s facilities comply with current life safety codes, the completion of this
project assures that conformance is not jeopardized by failing network equipment. Life
safety systems depend on efficient notification to the monitoring agency, which at Western is
the University Police Department. The campus fiber optic network is the spine that provides
this vital communication link.

B. This project would improve consistency with the following standards and codes:

Campus Safety and Security Guidelines: Western has determined that emergency lockdown
capability during an active shooter event is of paramount importance. Recommendations from
active shooter analyses across the country have concluded that locking, blocking, or otherwise
obstructing access to a classroom is a highly effective deterrent to an active shooter – thus an
important lifesaving functionality. This new lockdown functionality will complement Western’s
emergency preparedness and response plans, which include text, cell phone, and voice
notification.

Energy Code Compliance: Operation and management of RCW required high efficiency
building systems and system components requires a reliable fiber network for communications.
Western constantly monitors the performance of HVAC systems through a data analytics tool
directly connected to the Siemens operating system. The data is transmitted over the fiber optic
line to a central station in the physical plant, where trained technicians evaluate the performance
of all systems to reveal performance anomalies and identify areas of potential energy savings.
Over the past three years, this process of real time data analysis has saved Western over
$200,000 per year in energy.

Fire Code Compliance: All fire safety system monitoring, alarms, and notification rely on the
fiber optic loop to communicate with the central monitoring station in the University Police
Dispatch Center, as well as with the City of Bellingham first responders.

ADA Accessibility: Electronic and classroom locks will improve ADA compliance and
accessibility through modification of existing hardware. As electronic entries are installed,
existing traditional doorknobs will be replaced with ADA compliant openers. Newly installed
classroom locks will also be fully compliant with both Fire Code and ADA requirements.

2. Evidence of increased repairs and/or service interruption

Recent studies and subsequent evaluation of the condition of the fiber optic network as work has
been performed suggest the network is approaching the end of its useful service life. The
university has outgrown its network, which was primarily installed in 1999-2000, in several key places.
Physical cable degradation is evident in the campus utility tunnels, threatening the foundation of all
network services on campus. Replacement is required to avoid service interruption in the event of
network failure.

In addition, the existing fiber network has several bottlenecks in which the number of available fiber
strands has nearly run out, including:

• Direct fiber connections between the two network cores.


• Direct fiber connections between primary and secondary data centers.
• Direct fiber connections between the primary network core/data center and the emergency
operations center.

These constraints limit our ability to implement critical electronic access control systems on the
consolidated network. Without the fiber replacement and expansion access control need a separate
fiber network, which would add substantial cost to the project and to university operations overall.

Once fiber optic upgrades are complete, this project proposes to expand the use of electronic
credentialing across campus, reducing need for traditional brass keys. Four years ago, in response to a
lost ring of master keys, Western accelerated an internal project to rekey all of campus. The
monumental effort to issue new keys to thousands of students and staff highlighted the vulnerability
of access control dependent on traditional keys and the routine maintenance costs involved in tracking
and replacing keys.

3. Impact on institutional operations without the infrastructure project

The fiber optic data network is essential to the delivery of all aspects of the educational
mission. Nearly all academic and administrative functions depend on a reliable fiber optic
communications infrastructure. Emergency response capabilities will be enhanced by electronic
credentialing and lockdown functionality. A fully capable electronic access system is a risk mitigation
strategy. Access to a building or space can be immediately rescinded upon report of a lost credential,
reducing or eliminating concerns of unauthorized access.

Under the current operating model, Western’s academic buildings are locked and opened by a team of
University Police Department student employees according to established building schedules. This
process can be nearly eliminated through an automated electronic locking system, saving up to two
FTE salaries per year. In addition, the lower operating costs of using electronic credentials is well
established in the security industry.

4. Reasonable estimate

The post-escalation MACC ($10,451,316) and Equipment ($1,950,873) cost identified in the C100 is
based on unit and equipment cost associated with recent access control and fiber optic upgrade
projects. Those projects include the Access Control Project funded with State funds in the 2017-19
biennium and fiber optic and switchgear equipment associated with several recent major and minor capital
projects. Those calculations are included in Appendix B (Cost Breakdown) and match the MACC and
equipment costs in the C100 (Appendix A).

5. Engineering study

Western has commissioned several studies about safety and utility condition. The consensus
is overwhelming that data communications and robust access control are central to university
operations.

In 2017, Western completed a utilities master plan update which identified the need to replace the
existing fiber network to meet current and predicted requirements.

In 2013, Western contracted with TRUSYS, an operational security assessment company, to define a
roadmap for conversion of our existing access control system. This capital request reflects the
recommendations of that study, included in Appendix C.

6. Support by planning

A. As Western plans for enrollment and program growth, an expanded and modernized
fiber optic network will be essential for supporting an upgraded access control
system, along with virtually all other campus functions. Western’s Comprehensive
Campus Master Plan contains six guiding principles for future campus development. This
project is fully aligned with Principle #3: “Provide convenient and safe access to and through
the campus for the University’s guests, faculty, staff and students.”

B. Western’s 2018 Strategic Plan requires that the University “provide technological and
other academic infrastructure to support curricular innovation, research, scholarship,
and creative activity, civic engagement and social justice” and that it ensure the safety
and security of students and staff. The fiber optic infrastructure, on which nearly all
academic and business functions rely, is essential to campus operations. The maintenance and
improvement of Western’s security infrastructure is fully aligned with strategic intent.

The proposed project supports the standards and procedures of the campus Access Control
Policy, included in Appendix D.

7. Resource efficiency and sustainability

Western will be able to continue energy conservation and monitoring efforts through a fully
capable fiber optic infrastructure. The electronic access component will lower maintenance and
labor costs associated with physical key security and provide indirect energy conservation
opportunities with the enhanced ability to manage access control of buildings. By limiting
unauthorized access to academic buildings, conservation of resources can be managed more efficiently
and effectively. Building controls will be tied to building and room occupancy, enabling selective
heating and ventilation rather than whole building measures. Alarms on exterior doors will reduce the
potential or duration of propped open doors, conserving energy within the buildings.

8. Appendices: the following supporting documentation is included

A. Project Cost Summary/C100


B. MACC and Equipment Cost Breakdown
C. WWU Access Control Assessment Report prepared by TRUSYS
D. WWU Access Control Policy
E. WWU Utilities Master Plan Update, Telecommunications Section

Office of Financial Management


June 2022
Appendix A
STATE OF WASHINGTON
AGENCY / INSTITUTION PROJECT COST SUMMARY
Updated June 2022
Agency Western Washington University
Project Name Critical Safety, Access Control, and Fiber Optic Network Upgrades
OFM Project Number 30000604

Contact Information
Name Brian Ross
Phone Number 360.650.6539
Email [email protected]

Statistics
Gross Square Feet MACC per Gross Square Foot
Usable Square Feet Escalated MACC per Gross Square Foot
Alt Gross Unit of Measure
Space Efficiency A/E Fee Class B
Construction Type Other Sch. B Projects A/E Fee Percentage 10.98%
Remodel Yes Projected Life of Asset (Years) 50
Additional Project Details
Procurement Approach DBB Art Requirement Applies No
Inflation Rate 4.90% Higher Ed Institution No
Sales Tax Rate % 8.80% Location Used for Tax Rate
Contingency Rate 10%
Base Month (Estimate Date) July-22 OFM UFI# (from FPMT, if available)
Project Administered By Agency

Schedule
Predesign Start Predesign End
Design Start October-21 Design End October-23
Construction Start January-23 Construction End June-25
Construction Duration 29 Months

Green cells must be filled in by user

Project Cost Estimate


Total Project $15,761,983 Total Project Escalated $17,015,052
Rounded Escalated Total $17,015,000

Cost Estimate Summary


Acquisition
Acquisition Subtotal $0 Acquisition Subtotal Escalated $0

Consultant Services
Predesign Services $0
Design Phase Services $802,463
Extra Services $171,000
Other Services $360,527
Design Services Contingency $133,399
Consultant Services Subtotal $1,467,390 Consultant Services Subtotal Escalated $1,521,353

Construction
Maximum Allowable Construction Maximum Allowable Construction Cost
$9,628,999 $10,451,316
Cost (MACC) (MACC) Escalated
DBB Risk Contingencies $0
DBB Management $0
Owner Construction Contingency $962,900 $1,045,132
Non-Taxable Items $0 $0
Sales Tax $932,087 Sales Tax Escalated $1,011,687
Construction Subtotal $11,523,986 Construction Subtotal Escalated $12,508,135

Equipment
Equipment $1,652,000
Sales Tax $145,376
Non-Taxable Items $0
Equipment Subtotal $1,797,376 Equipment Subtotal Escalated $1,950,873

Artwork
Artwork Subtotal $0 Artwork Subtotal Escalated $0

Agency Project Administration


Agency Project Administration
$618,232
Subtotal
DES Additional Services Subtotal $0
Other Project Admin Costs $0

Project Administration Subtotal $618,232 Project Administration Subtotal Escalated $671,029

Other Costs
Other Costs Subtotal $355,000 Other Costs Subtotal Escalated $363,662

Project Cost Estimate


Total Project $15,761,983 Total Project Escalated $17,015,052
Rounded Escalated Total $17,015,000
Funding Summary

New Approp
Request
Project Cost Funded in Prior
2023-2025 2025-2027 Out Years
(Escalated) Biennia
Acquisition
Acquisition Subtotal $0 $0

Consultant Services
Consultant Services Subtotal $1,521,353 $393,528 $1,127,825 $0

Construction
Construction Subtotal $12,508,135 $1,490,872 $11,017,264 $0

Equipment
Equipment Subtotal $1,950,873 $1,950,873 $0

Artwork
Artwork Subtotal $0 $0

Agency Project Administration


Project Administration Subtotal $671,029 $80,600 $590,429 $0

Other Costs
Other Costs Subtotal $363,662 $50,000 $313,662 $0

Project Cost Estimate


Total Project $17,015,052 $2,015,000 $15,000,053 $0 -$1
$17,015,000 $2,015,000 $15,000,000 $0 $0

Percentage requested as a new appropriation 88%

What is planned for the requested new appropriation? (Ex. Acquisition and design, phase 1 construction, etc. )
See scope of work in MACC worksheet

Insert Row Here

What has been completed or is underway with a previous appropriation?


See scope of work in MACC worksheet (highlighted in blue)

Insert Row Here

What is planned with a future appropriation?

Insert Row Here


Cost Estimate Details

Acquisition Costs
Escalation
Item Base Amount Escalated Cost Notes
Factor
Purchase/Lease
Appraisal and Closing
Right of Way
Demolition
Pre-Site Development
Other
Insert Row Here
ACQUISITION TOTAL $0 NA $0

Green cells must be filled in by user


Cost Estimate Details

Consultant Services
Escalation
Item Base Amount Escalated Cost Notes
Factor
1) Pre-Schematic Design Services
Programming/Site Analysis
Environmental Analysis
Predesign Study
Other
Insert Row Here
Sub TOTAL $0 1.0000 $0 Escalated to Design Start

2) Construction Documents
A/E Basic Design Services $802,463 69% of A/E Basic Services
Other
Insert Row Here
Sub TOTAL $802,463 1.0121 $812,174 Escalated to Mid-Design

3) Extra Services
Civil Design (Above Basic Svcs)
Geotechnical Investigation
Commissioning
Site Survey
Testing
LEED Services
Voice/Data Consultant
Value Engineering
Constructability Review
Environmental Mitigation (EIS)
Landscape Consultant
Electrical Engineering $78,000
Travel & Per Diem $40,000
Advertising $3,000
Site Surveying and Testing $50,000

Sub TOTAL $171,000 1.0121 $173,070 Escalated to Mid-Design

4) Other Services
Bid/Construction/Closeout $360,527 31% of A/E Basic Services
HVAC Balancing
Staffing
Other
Insert Row Here
Sub TOTAL $360,527 1.0854 $391,317 Escalated to Mid-Const.

5) Design Services Contingency


Design Services Contingency $133,399
Other
Insert Row Here
Sub TOTAL $133,399 1.0854 $144,792 Escalated to Mid-Const.

CONSULTANT SERVICES TOTAL $1,467,390 $1,521,353

Green cells must be filled in by user


Cost Estimate Details

Construction Contracts
Escalation
Item Base Amount Escalated Cost Notes
Factor
1) Site Work
G10 - Site Preparation
G20 - Site Improvements
G30 - Site Mechanical Utilities
G40 - Site Electrical Utilities
G60 - Other Site Construction
Other
Insert Row Here
Sub TOTAL $0 1.0244 $0

2) Related Project Costs


Offsite Improvements
City Utilities Relocation
Parking Mitigation
Stormwater Retention/Detention
Other
Insert Row Here
Sub TOTAL $0 1.0244 $0

3) Facility Construction
A10 - Foundations
A20 - Basement Construction
B10 - Superstructure
B20 - Exterior Closure
B30 - Roofing
C10 - Interior Construction
C20 - Stairs
C30 - Interior Finishes
D10 - Conveying
D20 - Plumbing Systems
D30 - HVAC Systems
D40 - Fire Protection Systems
D50 - Electrical Systems
F10 - Special Construction
F20 - Selective Demolition
General Conditions
MACC per "MACC Breakdown" in
$9,628,999
Appendix of proposal
Insert Row Here
Sub TOTAL $9,628,999 1.0854 $10,451,316

4) Maximum Allowable Construction Cost


MACC Sub TOTAL $9,628,999 $10,451,316
NA NA per 0
$0
This Section is Intentionally Left Blank

$0

7) Owner Construction Contingency


Allowance for Change Orders $962,900
Other
Insert Row Here
Sub TOTAL $962,900 1.0854 $1,045,132

8) Non-Taxable Items
Other
Insert Row Here
Sub TOTAL $0 1.0854 $0

9) Sales Tax
Sub TOTAL $932,087 $1,011,687

CONSTRUCTION CONTRACTS TOTAL $11,523,986 $12,508,135

Green cells must be filled in by user


Cost Estimate Details

Equipment
Escalation
Item Base Amount Escalated Cost Notes
Factor
1) Equipment
E10 - Equipment $1,652,000
E20 - Furnishings
F10 - Special Construction
Other
Insert Row Here
Sub TOTAL $1,652,000 1.0854 $1,793,081

2) Non Taxable Items


Other
Insert Row Here
Sub TOTAL $0 1.0854 $0

3) Sales Tax
Sub TOTAL $145,376 $157,792

EQUIPMENT TOTAL $1,797,376 $1,950,873

Green cells must be filled in by user


Cost Estimate Details

Artwork
Escalation
Item Base Amount Escalated Cost Notes
Factor
1) Artwork
0.5% of total project cost for
Project Artwork $0
new construction
0.5% of total project cost for
Higher Ed Artwork $0 new and renewal
construction
Other
Insert Row Here
ARTWORK TOTAL $0 NA $0

Green cells must be filled in by user


Cost Estimate Details

Project Management
Escalation
Item Base Amount Escalated Cost Notes
Factor
1) Agency Project Management
Agency Project Management $618,232
Additional Services
Other
Insert Row Here
Subtotal of Other $0
PROJECT MANAGEMENT TOTAL $618,232 1.0854 $671,029

Green cells must be filled in by user


Cost Estimate Details

Other Costs
Escalation
Item Base Amount Escalated Cost Notes
Factor
Mitigation Costs
Hazardous Material
Remediation/Removal
Historic and Archeological Mitigation
Plan Review $55,000
In-Plant Services $300,000
OTHER COSTS TOTAL $355,000 1.0244 $363,662

Green cells must be filled in by user


Appendix B
MACC and Equipment Cost Breakdown
Summary Statistics (Represents July 2022 Costs):
Average access control cost per door leaf per PW728 $18,375
Average conversion cost per door per PW728 $10,500
Average cost per network Switch per PW733 & 746 $45,000
Average cost per linear feet of fiber (includes material, labor, testing, replacement of existing $9.17
infrastructure)

Scope Included in 2021-23 Appropriation

MACC Cost Equipment Cost

Exterior Access Control and Associated Fiber at Academic Buildings Associated Equipment in the Buildings
Bldg Name Access Door Associated MACC Bldg Name # of Cost
Count Linear Feet of network
Fiber switches
Communications Facility 23 5357 $ 471,749 Fine Arts 1 $ 45,000
Morse Hall 12 6876 $ 283,553 SMATE 2 $ 90,000
Biology Building 14 6555 $ 317,359 Ross Engineering 2 $ 90,000
Fine Arts 14 4403 $ 297,626 Performing Arts Center 2 $ 90,000
Ross Engineering 15 6800 $ 337,981 Arts Annex 1 $ 45,000
Performing Arts Center 40 5900 $ 789,103 Canada House 1 $ 45,000
Arts Annex 20 6300 $ 425,271 College Hall 1 $ 45,000
Canada House 7 5700 $ 180,894 Commissary 1 $ 45,000
College Hall 7 4900 $ 173,558 Environmental Studies 2 $ 90,000
Commissary 10 6600 $ 244,272 Fairhaven Academic 1 $ 45,000
Environmental Studies 22 6350 $ 462,480 Haggard Hall 2 $ 90,000
Fairhaven Academic 3 3500 $ 87,220 High Street Hall 2 $ 90,000
Haggard Hall 17 7550 $ 381,609 Humanities 2 $ 90,000
High Street Hall 13 6000 $ 293,895 Old Main 2 $ 90,000
Humanities 16 7050 $ 358,649 Steam Plant 1 $ 45,000
Old Main 26 9850 $ 568,075 Wilson Library 2 $ 90,000
Steam Plant 7 6800 $ 190,981 Bond Hall 4 $ 167,000
Wilson Library 17 8950 $ 394,447 Academic Instruction Center 2 $ 90,000
Fiber to prior converted buildings 7 44150 $ 533,481 Campus Services 2 $ 90,000
Total 290 159,591 $ 6,792,199 Fraser Hall 2 $ 90,000
Miller Hall 2 $ 90,000
Other Total Network Switches 37
Scope Cost/unit # of Units/feet MACC
Interior Doors under Access Control $10,000/door 30 doors $ 300,000 Total Equipment Cost $ 1,652,000
Classroom Locks $1056/door 300 doors $ 316,800
Lab wireless access locks $2200/unit 100 Labs $ 220,000
Data Center $ 2,000,000
Total $ 2,836,800

Pre-escalated MACC $ 9,628,999


Appendix C
WESTERN
WASHINGTON
UNIVERSITY
ACCESS CONTROL SYSTEM ROADMAP

Dave Miller, Principal, TRUSYS


March 15, 2013

UNITEDSTATES|CANADA|CARIBBEAN|INDIA|NETHERLANDS
CONTENTS
EXECUTIVE SUMMARY ........................................................................................................... 4
ISSUE .................................................................................................................................... 4
RECOMMENDATION........................................................................................................... 4
ROADMAP ............................................................................................................................. 5
EXISTING SYSTEM ................................................................................................................. 5
5-POINT ROADMAP ............................................................................................................ 5
DEFINE REQUIREMENTS ...................................................................................................... 5
ASSESS FEASIBILITY & COSTS .............................................................................................. 7
PLAN & DESIGN ................................................................................................................. 7
PROCUREMENT & INSTALLATION ...................................................................................... 7
OPERATION........................................................................................................................ 8
ALTERNATIVE ....................................................................................................................... 8
SUMMARY ........................................................................................................................... 8
BUDGETS ................................................................................................................................ 9
ACCESS CONTROL SYSTEM ................................................................................................ 9
INTRUSION DETECTION SYSTEM .........................................................................................10
VIDEO MANAGEMENT SYSTEM .........................................................................................11
OTHER SERVICES ................................................................................................................11
ROADMAP PONTS 1 & 2...................................................................................................11
MANUFACTURER SELECTION PROCESS ...........................................................................11
BUDGETARY TIMELINE ........................................................................................................12
PERSONNEL ........................................................................................................................12
DISPATCH ..........................................................................................................................12
SYSTEM OPERATIONS ........................................................................................................12
SUMMARY ..........................................................................................................................14
APPENDIX A - EXISTING SYSTEM: EST-3 SYNERGY.................................................................15
CONFIGURATION & SOFTWARE ........................................................................................15
EXISTING IDS .......................................................................................................................15
CREDENTIAL SYSTEMS ........................................................................................................16
INTEGRATION OF INTRUSION & VIDEO .............................................................................16
SECURITY TECHNOLOGY PLAN .........................................................................................17
PERSONNEL & BUDGETS ....................................................................................................17
APPENDIX B - SECURITY TECHNOLOGY IN THE MARKET TODAY .........................................19
VIDEO MANAGEMENT SYSTEM (VMS) ..............................................................................19
ACCESS CONTROL BEST PRACTICES.................................................................................19

WWU Access Control System Roadmap © 2013 Page 2 of 35


CONCEPT..........................................................................................................................19
BEST PRACTICES RECOMMENDATION .............................................................................21
INTERIM BEST PRACTICES ..................................................................................................21
SYSTEM INTEGRATION ........................................................................................................21
RECOMMENDATION ........................................................................................................22
TECHNOLOGY RECOMMENDATIONS ...............................................................................22
EDGE TECHNOLOGY ........................................................................................................23
CONTROL HARDWARE .....................................................................................................23
ACS SOFTWARE ................................................................................................................24
SUMMARY .........................................................................................................................25
INTEGRATED SYSTEMS VS. STAND-ALONE .........................................................................25
APPENDIX C - SECURITY PLAN COMMENTS ........................................................................27
BUILDING BLOCKS .............................................................................................................27
TEAMS ...............................................................................................................................28
TECHNIQUES .....................................................................................................................29
TECHNOLOGIES ................................................................................................................29
TRAINING ..........................................................................................................................29
ISSUES FOR CONSIDERATION IN A SECURITY PLAN ........................................................ 30
APPENDIX D - RESULTS OF REQUIRED VS. DESIRED ASSESSMENT ........................................31
SUMMARY ..........................................................................................................................33
BUDGETARY ESTIMATE FIGURE 1: TIMELINE (ENLARGED VIEW)...........................................35

WWU Access Control System Roadmap © 2013 Page 3 of 35


EXECUTIVE SUMMARY
Western Washington University (WWU) has contracted TRUSYS to provide a Roadmap
detailing how to move forward with the implementation of the replacement for the
Access Control System (ACS) at WWU.

ISSUE
The WWU process to date has created an impasse between two different approaches.
The first approach advocates an immediate upgrade of the system due to funds being
available in this biennium.
The other approach is to defer the replacement of the system as long as possible until it
is no longer supported by the manufacturer. This approach is advocated by some
within WWU so that badly needed capital dollars can be deferred for other projects as
long as possible.

The need for replacing the ACS has been brought on by the following:
1. The need for distributed administrative control of the access control due to the
inability to address it through staffing.
2. The pending “end of life" declaration that will be issued for the access control
portion of the integrated EST system, and the future roll-out of the EST-4 which will
make the access control portion of the system obsolete.

RECOMMENDATION
The key points to TRUSYS’ recommendation are:
• Defer Replacement of the ACS for two to three years.
• Cease investment in current ACS
• Implement a 5-Point Roadmap for replacement of the Access Control System.
The 5-Points of the Roadmap are:
1. Define Requirements
2. Assess Feasibility & Costs
3. Plan and Design System Replacement
4. Procurement and Implementation
5. Operation of System
By following this Roadmap, WWU can achieve an access control system that can meet
their growing needs and expectations, and that can be incorporated into their overall
Security Plan.

WWU Access Control System Roadmap © 2013 Page 4 of 35


ROADMAP
EXISTING SYSTEM
The existing ACS can continue to meet WWU’s basic needs for the next two to three
years. It is recommended that investment in customizing the EST ACS be stopped due
to the following considerations:
• Creating the ACDB into a custom software application that is only understood by
a limited number of people at WWU could be highly disruptive and expensive if
WWU can no longer support the ACDB internally.
• Outside vendors may, or may not, be able to support a customized system.
• The cost in customization of ACDB would only bring it to what most ACS
manufacturers offer today which makes the Return on Investment (ROI)
questionable.
TRUSYS recommends that a moratorium be placed on any additions or modifications to
the EST-3 Synergy access control system with the following exceptions:
1. New construction with exterior doors and audio/visual components that require
monitoring. Where interior access control doors and intrusion detection are
desired, a Risk Assessment should be provided to determine the risk associated,
and the Assessment determines an immediate need for Security Technology.
Infrastructure such as boxes, conduit stub-outs, conduit runs, and pull strings
should be provided for the future devices.
2. Remodeled space that meets the criteria in Item 1 of this list.
3. Other spaces where a Risk Assessment determines an immediate need for
Security Technology.
If more detailed information about the existing ACS is required, please refer to
Appendix A.

5- POINT ROADMAP
TRUSYS recommends a 5-Point Roadmap to obtain an upgraded and operational
access control system.

Assess
Define Procurement &
Feasibility & Plan & Design Operation
Requirements Implementation
Costs

Figure 1 - 5-Point Roadmap

DEFINE REQUIREMENTS
The definition of requirements should be based on two levels:

WWU Access Control System Roadmap © 2013 Page 5 of 35


1. The overall Security Plan and how the ACS will be integrated with other security
technologies.
2. The technical requirements of the Access Control System.

SECURTY PLAN
A Security Plan that encompasses all aspects of security at WWU will be defined. It
would assess key aspects such as:

OPERATIONS BUDGET
SECURITY PLAN
TECHNOLOGY PERSONNEL
Figure 2 - Security Plan
Commentary on a Security Plan can be found in Appendix C.

ACCESS CONTROL TECHNOLOGY


Technology issues that require definition for the new ACS are:

• Card Technology
• Reader/Lock Technology
Edge

• Retrofit
•New Installation
Hardware

• Operating System
• Platform
Software •Client Interface

• Intrusion Detection
• Video Management
Integration •Security Intercom

• Banner and Other Systems


• Active Directory / LDAP
Data •Data Card
Integration

Figure 3 - Defining ACS Requirements


Commentary on current Security Technology can be found in Appendix B.

WWU Access Control System Roadmap © 2013 Page 6 of 35


ASSESS FEASIBILITY & COSTS
Using the Requirements that are developed for the Security Plan and Access Control,
the various avenues that are available for implementation should be evaluated for their
feasibility and costs. Examples of these approaches include:

• A integrated system approach


where by individual buildings are
upgraded over a multi-year project
with all needed Security Technology
Integration

• Each Securty Technology system is


upgraded campus wide in a
phased deployment
Systems

Figure 4 - Example Approaches

Each approach should be evaluated based on costs and impact to existing systems
and operations.

PLAN & DESIGN


WWU should quantify the desired approach into a systematic plan that incorporates
the defined requirements.
This stage will have deliverables such as:

Tasks Tasks
Cards, Card Readers & Reader/Locks
Manufacturer Selection Control Hardware
Software
System Plans Detailed, Shop Drawing Level
Specifications Specific to Project, Integrated with Plans
Budget Estimates Detailed, Based on Specified System(s)
Figure 5 – Plan & Design

PROCUREMENT & INSTALLATION


Based upon the approach to be taken, the system(s) will be Procured and
Implemented. Using accepted project management practices, the implementation
process will be tightly controlled to ensure that the specified solution is installed.
System commissioning will be a major focus, which will lead to system acceptance by
WWU.

WWU Access Control System Roadmap © 2013 Page 7 of 35


OPERATION
Following system acceptance by WWU, the new technology will be used in a manner
that supports the overall Security Plan for WWU.

ALTERNATIVE
If it is determined that the budgeted funds from the current biennium for the
replacement of the Access Control System will be lost if no action is taken, then the
following should be done:
1. Engage a consultant to specify and design a new ACS system which would
include at a minimum:
a. Determination of the optimum solution for smart card technology, readers
and integrated reader/locks, or if the use of Proximity technologies be
maintained.
b. Determination of a hardware manufacturer that has the broadest range
of ACS hardware that can support the chosen technologies.
c. Qualify and select an ACS manufacturer who can provide the technology
solution determined in Items 1 and 2 above.
2. Design and specify the system upgrade.
3. Receive quotations from authorized resellers of the ACS manufacturer
selected in Item 1 above.
Development of a Security Plan including future Security Technology updates and
integration should be done, following the recommended 5-Point Roadmap.

SUMMARY
By deferring for 24 to 36 months, the replacement of the Access Control System,
Western Washington University can assure itself of enough time to implement the 5-Point
Roadmap so that a cohesive and well thought out Security Plan and Security
Technology Plan can be implemented.

WWU Access Control System Roadmap © 2013 Page 8 of 35


BUDGETS
Both low and high budgets have been prepared and the Tables below summarize the
differences and provide the assumptions that have been made.
The Consultant Design Fees quoted are based on a detailed design that would be
created, and would effectively eliminate the need for shop drawings to be submitted
by the contractor.

ACCESS CONTROL SYSTEM


Assumption Low High
Quantity of ACS Panels 32: Replaces only those 59: Replaces all SAC-3
panels that have existing cards in existing FACP with
ACS doors at this time. new ACS control panel.
ACS Panel Location Assumes that new ACS Assumes that new ACS
panel will be located in the panel will be located in the
same room as the existing same room as the existing
EST panel. EST panel.
Upgrades HID Prox to Smart 212 212
Card Reader (Dual Tech)
Wireless Access Points 13: Provides wireless access 13: Provides wireless access
points for conversion of 54 points for conversion of 54
stand-alone reader/lock stand-alone reader/lock
combinations. combinations.
Upgrade of older style 44 54
Stand-Alone reader/locks
to Wireless
Convert AD-200 to AD-400 10 0
New RS-485 wiring for door 150’ average per existing 300’ average per existing
modules door. door.
Software 1 Server License 1 Server License
320 Door Reader Licenses 320 Door Reader Licenses
2 Thick Client Stations 2 Thick Client Stations
10 Concurrent Thin Client 10 Concurrent Thin Client
Stations Stations
3 Data Base Integration 3 Data Base Integration
Licenses Licenses
System Budgetary Estimate: $832,000 $1,143,000
Software Support $6,000/year based on $6,667/year based on
parameters indicated. parameters indicated.
Consultant Design Fee $149,640 $205,632
Budgetary Estimate Table 1: ACS
Savings can be obtained if it is determined that the existing RS-485 wiring can be used
in lieu of providing new wiring.

WWU Access Control System Roadmap © 2013 Page 9 of 35


INTRUSION DETECTION SYSTEM
Instead of trying to determine how much new wiring would be required from a single
intrusion detection system (IDS) panel to the various devices and RCC-7s in each
building, the approach of installing a minimum of one (1) IDS panel per building or 1 per
RCC-7 where there are multiple locations in a building has been applied.

Assumption Low High


Quantity of IDS Panels 79: Assumes that where 88: When IDS devices are
only 1 IDS point is indicated indicated, provides a
on the inventory, that it minimum of one per
could be monitored by building, or one per RCC-7
ACS. location.
IDS Panel Location Typically RCC-7 location or Typically RCC-7 location or
central location such as central location such as
MDF/IDF. MDF/IDF.
New wiring for devices & 125’ average per existing 200’ average per existing
keypads device or keypad. device or keypad.
Software 1 Integration License per 1 Integration License per
IDS Panel. IDS Panel.
Existing Devices Assumes that all existing Assumes that all existing
devices can be re-used. devices can be re-used.
System Budgetary Estimate: $510,645 $568,220
Consultant Design Fee $91,916 $102,280
Budgetary Estimate Table 2: IDS
Savings can be obtained if it is determined that when a building has a small amount of
devices, i.e. 1 to 10, that they can be re-wired to the ACS system controller which will
have this capacity.

WWU Access Control System Roadmap © 2013 Page 10 of 35


VIDEO MANAGEMENT SYSTEM

Assumption Low High


Quantity of Servers 2 2
Storage Capacity 24 TB 24 TB
Cameras Use existing cameras with Install new IP cameras with
video encoders to convert new CAT 6 cabling to each
analog to IP signal. camera.
Software Licensing Assumes 1 license per Assumes 2 licenses per
camera for integration with camera (1 ACS/1 VMS) for
ACS. integration with ACS.
System Budgetary Estimate: $149,616 $321,660
Software Support $1,870/year based on $4,194/year based on
parameters indicated. parameters indicated.
Consultant Design Fee $26,931 $57,899
Budgetary Estimate Table 3: VMS

OTHER SERVICES
There are other recommended services that are not included with the Consultant
Design Fees noted above.

ROADMAP PONTS 1 & 2


The above Consultant Design Fees do not include the first two points on the 5-Point
Roadmap:
• Define Requirements
• Assess Feasibility & Costs
A budget range of $16,000 to $32,000 is suggested for this depending on the scope of
services to be provided by a consultant. This does not include travel expenses which
would likely run at 15% to 20% of the fee.

MANUFACTURER SELECTION PROCESS


The detailed selection process for determining card technology, reader/lock
technology, hardware, and system software is not included with the Consultant Design
Fees noted above.
A budget range of $13,000 to $19,000 is suggested for this depending on the scope of
services to be provided by a consultant. This does not include travel expenses which
would likely run at 15% to 20% of the fee.

WWU Access Control System Roadmap © 2013 Page 11 of 35


BUDGETARY TIMELINE
The following timeline is based upon the following assumptions:
1. That WWU will be able to find funding for Road Map Points 1 & 2, and
Manufacturer Selection in 2013.
2. Funding for system design can occur in the 2nd half of 2014.
3. Funding for system replacements can occur in 2015/2017 biennium.

Budgetary Estimate Figure 1: Timeline


A larger view of this timeline is added at the end of the report.

PERSONNEL
TRUSYS has been asked to provide manpower recommendations for two aspects of the
systems at WWU.

DISPATCH
Currently dispatch is operating with five (5) full time dispatchers for a 24/7 operation
with no supervisor currently in place. The following, based on a discussion with Chief
Randy Stegmeier, the following is considered the optimum personnel needed.
• 1 – Supervisor: The Supervisor will have the additional duties of covering sick or
unexpectedly absent dispatchers, and to be the Terminal Agency Coordinator.
• 6 – Dispatchers: This will allow normal eight (8) hour shift coverage and minimize
overtime. The Chief expressed a desire to have shifts maintained for a six (6)
month duration, and then rotation can occur.
• 2 – Part Time Dispatchers: These are envisioned to be on call dispatchers to cover
sickness and unexpected absences or short-term planned absences such as
vacations. They are envisioned to be eligible for up to 16-hours per person per
month, unless covering for a longer term duration such as a maternity leave.

SYSTEM OPERATIONS
Upon systems being installed, including fire alarm and mass notification, they become
tools for dispatchers to be notified of conditions that affect the health, safety and
welfare of the students, faculty and staff at WWU. Under this premise, it would make
sense that the same entity that has authority over the dispatchers would have the
ability to control the systems including their maintenance.

WWU Access Control System Roadmap © 2013 Page 12 of 35


The Organizational Chart shown below has been provided with this in mind. The
Systems Manager would have bilateral relationships with counterparts in IT, Facilities,
and Residence Halls.
The Systems Manager would be the stakeholder representative for systems during
capital project planning and implementation to ensure that collaboratively published
system design requirements are adhered to, and that these systems are not
compromised due to “value engineering”.

Deputy Chief of
Police

Security &
IT Life/Safety Facilities Residences
Systems Manager

Administrative
Assistant

Maintenance Lock Shop


Staff x3 - 4 x3

Budgetary Estimate Figure 2: Systems Team


There are not to TRUSYS’ knowledge, published standards or metrics for how many
personnel are required for the maintenance and ongoing support of security systems.

SYSTEMS MAINTENANCE
The current maintenance of two (2) seems to be low, and does not allow for coverage
of the campus should one of the two need to take an extended absence. WWU has
begun to address this by training more personnel. The team should be able to be more
efficient in maintaining the combined fire/life safety systems and security systems if one
or two full time employees are added to this segment of the systems team.

LOCK SHOP
With the administration of the system moved to the System Manager and the
Administrative Assistant, the Lock Shop should be able to fully focus on its purpose of
lock maintenance and repair, issuing of “brass keys” and rekeying of locks.
The existing staff of three (3) should be sufficient for this task.

WWU Access Control System Roadmap © 2013 Page 13 of 35


SUMMARY
The following are the budgetary estimates by system, and for the consultant cost by
Roadmap point. Where we have felt that clarification was needed in the parts of the
Roadmap Point, we have indicated the cost associated with the part.

System Low High


Access Control $ 832,000 $1,143,000
Intrusion Detection $ 510,645 $ 568,220
Video Management $ 149,616 $ 321,660
Systems Costs Total $1,492,261 $2,032,880
Budgetary Estimate Table 4: Systems Budget Summary

System Low High Timeline


Roadmap Points 1 & 2 $ 16,000 $ 32,000 April 2013 – Sept. 2013
Define Requirements & Feasibility/Costs
Roadmap Point 3 $201,365 $291,358 April 2014 – Dec. 2014
Select ACS Manufacturer $ 13,000 $ 19,000 April 2014 – June 2014
Design & Specification (All Systems) $201,365 $272,358 July 2014 – Dec. 2014
Roadmap Point 4 (All Systems) $ 67,122 $ 91,453 July 2015 – June 2017
Procurement & Implementation
Total Consultant Budget $284,487 $414,811
Budgetary Estimate Table 5: Systems Budget Summary
Note: Consultant fee does not include travel expenses which typically be estimated at
an average of 15% of the fee amount.

WWU Access Control System Roadmap © 2013 Page 14 of 35


APPENDIX A - EXISTING SYSTEM: EST-3 SYNERGY
CONFIGURATION & SOFTWARE
The existing access control system (ACS) is an integrated component of the EST-3 fire
alarm system. The security portion of the system, trade named as Synergy, has been in
the market place since the early 2000’s.
EST has gone through two (2) corporate buyouts, and since 2005 EST has been directed
by corporate not to upgrade and improve the system technology as it is considered to
be a competing product with several security product lines within GE and UTC.
• GE Security Purchases EST in 2005
• UTC Purchases GE Security in 2010
The ACDB while “state of the art” at the time of its release in the early 2000’s has seen
little development since its initial offering. The ACDB uses Delphi with JET engine as the
data base language which is not commonly used in the development of data base
applications today. Discussions have occurred between EST and WWU, where WWU
would be given the source code for the ACDB, and have the ability to modify the
ACDB for improvements that are deemed necessary. EST would be released from all
liability associated with the source code being provided, and would only be obligated
to support WWU should EST adopt any of the changes for their product offering. Based
on previous history, it appears unlikely that EST would adopt these modifications.
EST has clearly stated that while a defined end-of-life date has not yet been published,
that the ACS will in the near term of 2 to 3 years likely not be supported. The SAC-3
communications card and the CRC modules have been on the discontinued products
price list for several years, but these parts are available with up to a two (2) week lead
time.
The ACS is accessed and programmed via a separate ACDB server from the Fireworks
stations. The Lock Shop manages card holders and credentials on the ACDB via a
client station and communicates via modem to the respective panels.
The system panels are currently networked across a dedicated multi-mode fiber optic
network. This network allows the EST-3 Synergy (fire alarm, mass notification, and
security components) to be networked using TCP/IP. The “ring” topology of the fiber
optic network makes it highly resilient.
Where ACS is currently installed within a building on the campus, the security system
resides on the EST system using one of two formats:
• SAC-3 using RS-485: Keypads and Card Reader Controller (CRC)
• Addressable SLC: Security Devices; i.e. door contacts, motion sensors,
audio/visual (A/V) alarms, via input modules
The CRC modules currently support HID Corporate 1000 Proximity technology card
readers. With the exception of the CRC module all door devices and components
could be retrofitted into a new system.

EXISTING IDS
The existing IDS is an integral part of the EST-3 Synergy system. The system is comprised
of centrally located zone modules and distributed zone modules. In some cases, the

WWU Access Control System Roadmap © 2013 Page 15 of 35


same area of the building might be served by both centrally located zones and
distributed zones.
The centrally located zones located in RCC-7 enclosures in MDF and IDF rooms are
relatively easily upgraded.
The field located security devices are not as easily upgraded to a new system
infrastructure as they can reside on the same circuit as fire alarm devices.
Keypads will likely need to be rewired when the RS-485 circuit is taken over by the new
access control system.

CREDENTIAL SYSTEMS
For the purpose of this report, a credential is any method that allows an authorized user
access via a door into a building or space.
The vast majority of credentials issued at WWU are “brass keys”. Keys are issued either
via the Lock Shop which reports to the WWU Campus Police Chief or via the resident
hall management system using their in-house developed “Keys” database.
When resident dormitory room keys have been lost, and not recovered within a
predetermined time period, residence management notifies the Lock Shop of the need
to rekey the affected door(s) and issue new keys.
Access control “cards” in the form of actual cards or fobs are issued on an as needed
basis via the Lock Shop. WWU ID cards are not currently integrated with an access
control card.
The “cards” are used to access three (3) different access control systems on the
campus. The majority of card readers are on the EST-3 Synergy system with
approximately 165 readers currently in use.
The other two systems are “stand-alone” door readers which must be programmed into
a software program and then upload via a handheld device. The older stand-alone
system is being phased out in lieu of the Schlage AD-200 system. The AD-200 integrated
locksets have the capability to be upgraded from a stand-alone product to a 900 MHz
wireless network product or to a Wiegand product using an RS-485 protocol. There are
46 stand-alone readers at WWU today.

INTEGRATION OF INTRUSION & VIDEO


The integration of intrusion detection system (IDS) is well integrated with the ACS on the
EST-3 platform.
The integration of video is not well integrated with the EST-3 Synergy. Dispatch
personnel were only able to identify five (5) cameras that could be viewed on alarm
conditions from the EST-3 system.
The campus cameras are displayed on a single monitor in Dispatch. Dispatchers are
not able to view camera thumbnails in full displayed view. In Dispatch there is no
control of pan/tilt/zoom (PTZ) cameras on Campus.
Recorded video cannot be viewed from Dispatch.

WWU Access Control System Roadmap © 2013 Page 16 of 35


SECURITY TECHNOLOGY PLAN
TRUSYS found that Security Technologies at WWU have been implemented as budgets
and personnel have been available over the last 10-15 years and there has not been a
Security Plan guiding implementation.
For example, there are numerous and disparate systems in Police Dispatch where the
primary dispatcher’s location has nine (9) “systems” that can provide “alarm” data and
that requires observation or require interface by the dispatcher:
1. Emergency Phones
2. Web MSS (Runs license plates and driver licenses, but not the same system as in
the officers’ cars.)
3. ARMS – CAD and Incident Reporting
4. Voice Recording System
5. “Access Systems” for arming/disarming intrusion area when called on phone by
occupant.
6. Aiphone – Audio/video system for access to the Campus Police building.
7. Fireworks – Fire and Security Annunciation of alarms.
8. HVAC Alarms – Operated for two weeks during summer leave period.
9. Video (CCTV) Camera Monitor (see notes above on integration)
In addition to the systems noted above, the dispatchers are tasked with answering the
following audio systems or components:
1. Safe Phone (650-SAFE)
2. Primary Phone (3555 – non-emergency, 3911 – emergency)
3. Primary Phone (duplicate for when audio recording is required)
4. Emergency Call System Radio
5. Primary Police Radio desktop and portable
6. Parking Radio
7. Hard Line Phone (off campus)
8. TTY
9. Aiphone
Security Technology must work in a cohesive manner that allows the University’s first
responders to support those in need, and to create a document trail for incident
response and reporting.

PERSONNEL & BUDGETS


The existing ACS is maintained by the “fire alarm shop”. This two person team, David
Holmwood and Lane Weaver, are exceptionally talented. They have developed
capabilities on the EST-3 network that have been adopted by EST for the product line.
This team reports to Facilities Management - Operations.
The Lock Shop is supervised by Kevin Conforti, and the administration of the card
databases is performed by Ethan Van Diest. It reports directly to the WWU Chief of
Police.
TRUSYS found three (3) common constraints during interviews with all stakeholders.
1. Funding is insufficient to support the work required to maintain the existing ACS.

WWU Access Control System Roadmap © 2013 Page 17 of 35


2. There is uncertainty of the ability to obtain funding for a new and expanded
ACS.
3. There is not a single person accountable and responsible for the maintenance
and operation of the ACS; and who has the authority to make daily operational
decisions using a prescribed standard of operation.
These opinions are not specific only to those personnel noted above, but was a general
theme voiced by all that were interviewed.

WWU Access Control System Roadmap © 2013 Page 18 of 35


APPENDIX B - SECURITY TECHNOLOGY IN THE MARKET TODAY
This section will provide a brief update on Video Management Systems (VMS), ACS Best
Practices, and System Integration. These comments are based on TRUSYS’ experience.

VIDEO MANAGEMENT SYSTEM (VMS)


VMS, formerly called CCTV, is the fastest growing area in the security industry. The use
of megapixel IP-based cameras is driving this growth. Camera manufacturers are
focused on creating better resolution by pairing higher quality lenses with ever
increasing megapixel sensors.
To counter ever increasing resource demand on Network Video Recorder (NVR)
processor bandwidth and storage requirements, the following trends have been
identified:
• Movement to “Edge” processing of camera analytics. Cameras are now built
with sufficient processing power to determine if there is a rules based need to
have the video images recorded at the VMS and to alert monitoring personnel.
• Many cameras now have a built in ability to record video images to an SD card;
thus allowing onboard storage for later upload to the VMS during off-peak
transmission periods.
• Use of H.264 video format instead of MPEG and MPEG4.
There is a growing trend to use “purpose-built” servers and storage devices to run the
VMS software and to store video. These manufacturers have partnered with VMS
manufacturers to certify the manufacturers’ VMS software on their purpose-built
hardware solutions. TRUSYS recommends this approach as a best practice versus using
commercial, off the shelf (COTS) solutions such as Dell, IBM and HP.
Two key areas that continue to require development are:
1. The ability to provide “backup” power to cameras and recording systems so that
they can continue to operate during the loss of primary power.
2. The ability of high megapixel cameras to work in low and adverse light
conditions.

ACCESS CONTROL BEST PRACTICES


CONCEPT
The best “Best Practice” that a client can implement is to create a Security Technology
Plan (STP) that can be replicated. The STP should be part of the documented Security
Plan, and should be made available to the contracted design team each time a new
building or remodel is to be undertaken.
The use of an STP will minimize the cost of designing additions to the ACS, and provide
savings for the maintenance of the system by minimizing the spare parts that should be
maintained on site.
The SDS can minimize the impact of operating the system as well. A strong and
resolute STP can ensure that items such as IDS keypads are included for areas where
arming and disarming of the IDS is required, instead of allowing it to be “value
engineered” (VE) out of the design. This VE has occurred at WWU, and areas are now
armed & disarmed over the phone with the Campus Police Dispatch.

WWU Access Control System Roadmap © 2013 Page 19 of 35


The STP should take into consideration the following:
1. Cost of Installation
2. Cost of Maintenance
3. Capabilities of Internal Resources
4. Capabilities of External Resource
By developing and adhering to a Security Technology Plan, each client can develop
their own “best practices”, because what is best for one owner may not work for the
next owner.
Practical Application
TRUSYS has broken ACS Best Practices into two levels, Tactical and Strategic.
Tactical level best practices are those that can be ascribed to such issues as power
supply configurations and mounting configurations of various door components. These
are considerations that can be left to the design stage of the project.
Strategic level best practices are those that impact the overall operation of the system
or dictate how the infrastructure will be placed within a building. It is these Strategic
considerations that must be customized to each individual client’s needs.
The best consensus in the industry today, is that there is no consensus. This can best be
exemplified that for access control (and security in general) that unlike fire alarm
systems, there are not Codes and Standards which dictate when to install these
systems, and more importantly, how they shall be installed.
The following are examples of where accepted best practices are being challenged:
1. Centrally Located Control Hardware:
A common practice has been to locate ACS control hardware and power
supplies in a central location for an entire building, or for larger buildings in
multiple locations. These configurations typically consisted of a custom
enclosure for housing the ACS modules and power supplies for powering
electronics and door locks. Often times a 4’ x 8’ space would have to be
dedicated in the room where the equipment was to be located.
New technology such as IP-based door controllers and integrated wireless and
Wi-Fi reader/locks have begun to financially incentivize clients to move to a
“distributed” technology format, and also minimize the centrally located space
that is needed.
In the case the one TRUSYS client, they chose to remain with a central
configuration that required a very expensive two-door, 4’ x 5’ enclosure with
redundant levels of power supplies and that required cooling fans due to heat
generation. This was the best practice adopted by the client based on their risk
and cost assessment.
2. Wire Exterior Doors
It has been a commonly accepted practice since the inception of wireless
communication technologies to only have wired doors on the exterior of a
building. This was due to the long lag times for the wireless technology to
achieve lockdown from a central command input.
Advances in battery efficiency coupled with better technology now have
wireless technology that can achieve lockdown in 10 seconds. Is the 10 second

WWU Access Control System Roadmap © 2013 Page 20 of 35


window an acceptable risk to the client? Is the cost savings that can be
achieved using this technology worth the potential risk of doors being delayed
for locking on demand? The greater frequency of “handshake” between the
wireless device and the system will have an impact on the device’s battery life,
thus an impact to operating cost.
WWU will likely continue to be challenged with budgets for the foreseeable future, and
it is highly recommended that they review options like the above examples to
determine their own best practices that balance cost vs. risk.

BEST PRACTICES RECOMMENDATION


TRUSYS recommends that WWU create a Security Plan with an integral component
being the Security Technology Plan for the University. The process of creating an
encompassing Security Plan will create the best practices that will be prescribed by
WWU.

INTERIM BEST PRACTICES


What should WWU do with the wiring infrastructure where ACS and IDS have to be
added to the EST system in the interim period while the Security Plan is created and the
new ACS is selected and installed?

RECOMMENDATIONS
1. Wiring from the EST Panel to the door for the CRC module:
- Use the required unshielded, twisted – low capacitance cable required for
the SAC-3 RS-485 circuit.
- Future Wiring:
o Provide a shielded, twisted 4-conductor cable
o Consider the option of “home-running” one or two CAT-6 cables from
each CRC to the EST-3 panel or to an MDF/IDF as a “future or spare”.
2. Place keypads on a separate extension of the SAC-3 RS-485.
3. Do not mix security monitor modules on the same addressable loop as fire alarm
devices.
4. Home run all security field devices such as door contacts, motion sensors, glass
break sensors, etc… back to the RCC-7 locations. Do not use field located
monitor modules for security purposes.

SYSTEM INTEGRATION
In the market place today, Access Control System (ACS) is the system around which
security system integration is achieved. Many ACS manufacturers realize that they do
not have the ability to design, develop and manufacturer all the needed systems such
as intrusion detection (IDS), video management (VMS), and security intercom (SIS).
Instead they turn to manufacturers of these systems and create partnerships.
The primary method of integration between each of these systems and the ACS is via
TCP/IP network technology. To ensure interoperability between these systems, many
ACS manufacturers offer their partners certification programs; thereby ensuring that as
new versions of software are rolled out, the systems will continue to operate.

WWU Access Control System Roadmap © 2013 Page 21 of 35


When considering an integrated system, the selection of an ACS manufacturer who has
multiple partners is highly desired.

RECOMMENDATION
The following are the Milestones that TRUSYS recommends for achieving the desired
integration:

1 • Convert Existng Prox Readers to Multi-


Technology
• Create a Comprehensive Security Plan and
2 Upgrade ACS
• Begin to Issue Smart Cards Once Existing
3 Stocks of Prox Run Out for ID & Access
Purposes (Data Card Integration)
• Create Integration with Banner & Deploy
Client (Steward) SolutionIntegrated with -
4 - Other Data Base Systems Such as Event
and Conference
• Convert Existing Stand Alone Readers to
New ACS
5
• Implement Security Integration with Other
Systems (IDS, VMS, SIS)
6

Figure 2: Recommended Milestones


Integration of the ACS with Banner, Data Card and the Event and Conference
management systems can be accomplished using WWU’s in-house resources, unless
the ACS manufacturer has a “canned” integration that can be deployed effectively
and efficiently.

TECHNOLOGY RECOMMENDATIONS
The following 3-step process should be adhered to regardless of whether the 5-Point
Roadmap is used or the ACS is replaced immediately:
1. Determination of the optimum solution for smart card technology, readers and
integrated reader/locks.
2. Determination of a hardware manufacturer that has the broadest range of ACS
hardware that can support the chosen technologies.

WWU Access Control System Roadmap © 2013 Page 22 of 35


3. Qualify and select an ACS manufacturer who can provide the technology
solution determined in Items 1 and 2 above.

EDGE TECHNOLOGY
WWU should create a Request for Information to select the manufacturers who should
be interviewed for their Smart Card and reader and integrated reader/lock
technologies. Based on these interviews, a single source technology should be chosen
for the Control Hardware selection.

CARD TECHNOLOGY
TRUSYS recommends that “Smart Card” technology be adopted at WWU. This will allow
future upgrades of systems such as Dining, the Library, printing, etc… to leverage the
existing Smart Card technology when they are migrated away from bar codes scanners
and mag stripe readers. Most importantly, it will allow WWU to be proactive should WTA
convert in the next few years to an ISO 14443 Compliant Application.

INTEGRATED READER/LOCK TECHNOLOGY


WWU should use Integrated Reader/Lock technology for the following applications:
• Exterior Doors where an ADA Door Operator will not be installed. These should
be a wired, not a wireless or Wi-Fi configuration unless a delay in activation of a
lock down is acceptable.
• Interior Doors as follows:
o Doors behind which critical assets are maintained and managed or where
instantaneous Lock Down is required: These should be a wired, not a wireless
or Wi-Fi configuration unless a delay in activation of a lock down is
acceptable.
o All other interior doors: Wireless or Wi-Fi Configurations.
Note: A Wi-Fi solution will be able to leverage WWU’s existing Wi-Fi infrastructure
if a VLAN can be created on that infrastructure and the system can be
encrypted at 128-AES or higher to prevent hacking.
A wireless solution of either 900 MHz or 2.4 GHz will require an additional
infrastructure of wireless access points, but the technology is being directed to
respond to a lock down signal within 10 seconds of activation. Faster response
times are anticipated in the future.

CONTROL HARDWARE
WWU should select an ACS control hardware solution that works with the smart card
reader and integrated smart card reader/lock technology chosen above.
The two primary “open” platforms for access control controller hardware are Mercury
and HID VertX. Mercury appears, in the opinion of TRUSYS, to have a larger percentage
of ACS system manufacturers who have chosen this hardware solution, and both
primary manufacturers of integrated reader/locks have integrations with the Mercury
hardware solution.
Issues that need to be addressed prior to the new system’s installation are:
1. What is the ability of the new system to use the existing wiring infrastructure?

WWU Access Control System Roadmap © 2013 Page 23 of 35


Note: The existing system uses a non-shielded, twisted pair for the RS-485
communications to the CRCs. RS-485 is a robust serial communications protocol
that is often specified with a shielded, twisted pair cable. Per Mercury, the shield
“drain” which is connected to the RS-485 terminal block is more for the purpose
of creating a common ground reference than for electronic noise reduction.
The common reference can be achieved by bonding all of the negative sides of
the modules’ power circuits (not lock power circuits) together and referencing
them to ground.

The Mercury stated that they have run in house tests using unshielded CAT-5
cable, and using one of the conductors to create a ground reference at the
power supply.

This approach assumes that the wiring is installed per the National Electrical
Code (NEC) and that the cabling has not been simply laid along the top of
ceiling areas where it can come into direct contact with fluorescent light ballast
or other noise inducing components.

A two stage testing process to confirm this approach is recommended:


Stage 1: A lab test using the same cable that is currently installed
Stage 2: A single building installation that confirms operation prior to moving
forward with a system wide replacement

2. Can the existing multi-mode fiber optic network be used for the TCP/IP
communications for the new ACS?
Note: This fiber network is extremely robust, and by using this network where the
existing panels are located, it will help to minimize the installation cost of the new
system by not requiring wiring runs between an MDF and/or IDF in the building.

The decision can be made later whether or not to maintain the above practice
or shift to an MDF/IDF model for buildings that have not yet had ACS installed.

3. Can the existing power supplies be used?


Note: Should the power supplies provide any functions that are for the purpose
of life safety, then new power supplies should be required for installation. If they
are dedicated for the purposes of security, then it is highly likely that they could
be reused.

ACS SOFTWARE
Once the card technology and associated readers and integrated reader/lock
technology have been selected and the open control hardware platform selected,
then ACS software manufacturers should be selected via an RFP for interview that can
support the selected technologies.
Features that TRUSYS recommends focusing on during the RFP process are:

WWU Access Control System Roadmap © 2013 Page 24 of 35


How does the ACS integrate with Banner and Data Card?
• How does the ACS software integrate with other 3rd Party Applications
such as Event and Conference Management?

What Partners has the ACS manufacturer chosen for


System Integration?
• How many VMS Partners have they Certified with their solution?
• How many IDS Partners have they Certified with their solution?
• Have they developed an alternative IDS solution such as using Mercury's
keypad for IDS interface?

What is the software's ability to support "concurrent thin


clients" and administrative functions needed at WWU?

What is the cost of ongoing licensing and software


support agreements?
• Per individual or blocks of door reader licenses?
• Integration with 3rd Party data bases?
• Integration with Partner solutions such as IDS and VMS?
• Camera licensing, i.e. do they double charge?
Figure 3: ACS Software Issues

SUMMARY
WWU should select an ACS solution that meets their needs and expectations.
TRUSYS recommends that WWU develop a Security Plan before moving forward on any
ACS Solution. Simply using a consultant to tell WWU how and what should be used for
their ACS solution will lead to a short term, successful implementation, but will likely be a
long term failure if a comprehensive Security Plan is not created and implemented.

INTEGRATED SYSTEMS VS. STAND-ALONE


TRUSYS recommends that an integrated systems approach be taken at WWU. The
following path assumes that funds will be made available.
The following is Milestone 6 from Figure 2 above with more detail provided.

WWU Access Control System Roadmap © 2013 Page 25 of 35


• Remodel and Upgrade Dispatch to be able
6a to use the integrated systems as a daily
tool. This will include combining "audio
inputs".
• Convert EST-3 IDS components to new
6b selected IDS infrastructure building by
building.
• Convert Analog Video System to IP-Based
6c cameras and Upgrade to a Network VMS
that integrates with ACS
• Upgrade Security Intercom System (SIS) to
become integrated with ACS as alarm
6d points and with integrated audio in
Dispatch.
• Integrate an electronic key cabinet(s) for
automated distribution of keys to
contractors and temporary workers. This
6e
could also be used for WWU fleet vehicles

Figure 3: Recommended Milestones

WWU Access Control System Roadmap © 2013 Page 26 of 35


APPENDIX C - SECURITY PLAN COMMENTS
A primary question that must be answered to create a Security Plan is what is the
purpose or mission of security? Said in a different way, what is the role of security in
supporting the mission of Western Washington University?
If Security Technology such as access control, video, audio communications, and
intrusion detection cannot deter security events or be used as a tool to manage such
an event it is likely to atrophy after its initial deployment.

SECURITY Support Mission of WWU?

PLAN Benefit Students, Faculty &


Staff?

Educate Students, Faculty &


Staff?

Commitment from Exective


Level

Funding?

Figure 1: Critical Questions for Security Plan


The following are offered as key points for consideration in developing a Security Plan
for WWU.
1. How will a Security Plan support the mission of WWU?
2. How will a Security Plan benefit students, faculty and staff at WWU?
3. How will students, faculty and staff be educated about the Security Plan at
WWU; and how will that education process be appropriate for their status or
position at WWU?
4. What is the commitment from the Executive level of WWU to a long term Security
Plan?
5. What is the ability of WWU to fund a Security Plan?

BUILDING BLOCKS
The ability to build a resilient Security Plan will rest upon the ability of WWU to create key
Building Blocks. TRUSYS has found that when the following building blocks are
developed at functional, tactical and strategic levels that a resilient Security Plan can
occur.

WWU Access Control System Roadmap © 2013 Page 27 of 35


SECURITY
PLAN TEAMS

TECHNIQUES

TECHNOLOGY TRAINING

Figure 2: Building Blocks for Security Plan

1. Teams: People
2. Techniques: How to use Teams, Technology, and Training
3. Technology: Tools to assist and leverage the Security Plan
4. Training: The practical integration of Teams, Techniques, and Technology

TEAMS
Teams, Functional, Tactical, and Strategic, would be discerned during the planning and
preparation of the Security Plan. The ability for the Security Plan to remain resilient and
sustainable is based upon the collective strength of the employees, staff and
stakeholders who comprise the various Teams.
There are several Functional Teams that are suggested to be formed and given
operating parameters at WWU. They are:
1. Operations: This Team would be responsible for the daily operation and
programming of the security technologies, including ACS. Note: As previously
mentioned, it is highly desired to have a single management position that has
accountability and responsibility for the daily operation of the Security
Technology component, while still working within the Team environment. This
should be considered as an “Exempt” position versus a “Classified” position at
WWU.
2. Maintenance: This Team would likely be comprised of various trades from
Facilities, IT, and the Lock Shop, and would have representation from the
Operations Team.
3. Response: This would be primarily comprised of the Police Dispatch and
Uniformed Officers.
4. Administrative: This would be comprised of all users with access to the client
software, and who can assign privileges to card holders within their group and to

WWU Access Control System Roadmap © 2013 Page 28 of 35


areas within their building(s). At the highest level this would include all areas
including Residence Management, and could be comprised of smaller Teams
that are based upon specific use areas/buildings on the campus or satellite
areas.
Tactical Teams typically would be in response to a range of security events, with each
Team appropriate to the level of the event.
There are two (2) apparent Strategic Teams that should be developed at WWU, with
others that may be developed during the planning and preparation of the Security
Plan.
1. Strategic Security Vision: This Team, similar to the Access Control Committee to
whom this report is being submitted, would be responsible for the long range
Security Plan. It would monitor the progress of the Security Plan to reach
milestones and to audit its capabilities and effectiveness.

Another primary task would be to secure funding for maintaining and operating
the aspects of the Security Plan that are already in place, and to secure funding
for upcoming milestones that are planned as enhancements or modifications to
the Security Plan.

All key stakeholders should be represented on this Team including a


representative from the University President’s or Provost’s offices.

2. Strategic Response: This Team would function during security events where such
things as press releases, press interviews, and notification to families are required.

TECHNIQUES
Teams must have Techniques based upon the task at hand, as well as on the structure
of the organization, legislation, and stakeholder involvement. There can, of course, be
different Techniques employed for different security events; however, at a minimum
there are Assessment, Operational, and Compliance Techniques.

TECHNOLOGIES
In order to support the Teams and their Techniques, Technologies must be introduced
based on strategies, how those strategies are employed, and the tasks that need to be
accomplished. Technology must not drive the process; it must support the Teams and
the Techniques that are employed to accomplish their mission.

TRAINING
Training is critical for implementing a successful Security Plan. Training must be
continuous for all Teams, in all areas in which they are working. Without Training, the
Teams will not be current in the Techniques or the Technologies they are using, or as
new Techniques and Technologies emerge.

WWU Access Control System Roadmap © 2013 Page 29 of 35


ISSUES FOR CONSIDERATION IN A SECURITY PLAN
The following are offered for consideration with this Roadmap approach.
1. Is there a commitment by WWU to develop a long term, comprehensive Security
Plan?
2. Does WWU have the ability to provide the financial support for the following?
a. Planning Phase
b. Deployment of Initial Security Plan Technologies
c. Cost of licensing and software support agreements needed for Security
Technologies, and maintenance of said technology
d. Funding for development and final planning of the identified milestones or
those that will be identified as the Security Plan matures
3. Will satellite facilities such as Shannon Point Marine Center be included in the
Security Plan? If yes, how many satellite locations are there, and what is the
extent of their security needs?
4. Security Technology Considerations:
a. What is the role of each specific Security Technology at WWU?
b. What level of Security Technology integration is desired for WWU?
c. What is the role of ACS for integrating other Security Technologies such as
intrusion detection, video and audio emergency communications?
d. What card and reader technology will be used at WWU?
i. What are the policies and issues that need to be resolved for using this
technology including the placement of pictures and personal information
on the card?
ii. What are the driving factors to move from Proximity technology to Smart
Card technology such as WTA and other vendor type systems such as
cafeteria, printing, and library?
e. What are the specific needs for the transfer of data base information
between systems such as Banner, Data Card, etc…?
f. How will the integration of systems affect the ability of Campus Police
Dispatch to efficiently work with the systems?
g. Should advance training and remodel of Dispatch be considered as
milestones for the Security Plan?

WWU Access Control System Roadmap © 2013 Page 30 of 35


APPENDIX D - RESULTS OF REQUIRED VS. DESIRED ASSESSMENT
On January 28, 2013, TRUSYS facilitated an Access Control Stakeholder Meeting at
WWU. It was attended by the members of the Access Control Replacement
Committee and key stakeholders from WWU.
This meeting established that WWU does not have a clear and cohesive approach to
which options and features/benefits should be incorporated either into the existing ACS
or a new ACS.
The following are the results of a “Needs versus Wants” discussion regarding these new
features for the WWU ACS:
Issue Need Want
Work with Existing Prox Readers X
Work with WTA Now/Future X X
Logical Access Control X X
ISO 14443 Compliant Apps X X
Mag Stripe X
Bar Code X
NFC X
Table 1: New Access Card
Several items, such as the new access card working with Whatcom Transit Authority
(WTA), Logical Access Control and Compliance with ISO 14443 Apps are classified by
the Stakeholders as being both Needs and Wants.

Issue Need Want


Desire to Continue with Existing Lock Hardware Manufacture? X X
Ability to Remotely Lockdown Exterior Doors? X
Ability to Remotely Lockdown Interior Doors? X
Use of PoE Reader/Lock? Cost
Use of Wireless Reader/Lock? Cost
Use of Wi-Fi Reader/Lock? Cost
Table 2: New Reader/Lock Technology
Stakeholders were split on staying with the current Ingersoll Rand companies (Schlage
and Von Duprin), with some advocating to maintain the relationship, and others
expressing it as a Want.
Issue Need Want
Desire to Continue with Existing “Edge” (Distributed) X
Configuration?

WWU Access Control System Roadmap © 2013 Page 31 of 35


Use of Low-Proprietary Hardware? Cost
Use of High-Proprietary Hardware? Cost
Use of Centralized, Wiegand? Cost
Use of Distributed, Wiegand? Cost
Use of Edge (Ethernet/PoE)? Cost
Table 3: New ACS Hardware Configuration
When the subject of integrated reader/lock technology was broached, they were
assessed to be a “Need” but cost is a principal driving issue.
The consensus of the group was that there is a desire to maintain the “distributed”
configuration that exists with the system today. Again, the primary driving factor voiced
by the group was, “What will the cost be?”
It is apparent from the responses, that a significant amount of the Stakeholders do not
yet have a feel for how cost can be controlled with the use of some of the newer
technology options that are available.

Issue Answer
Desired Operating Software? Linux
Desired Database? Oracle
Desired Hardware (COTS, Appliance, VM)? VMware
Client Stations? 1/Building
Concurrent Licensing
Table 4: New ACS Software Configuration
The group was able to clearly articulate its preference for operating systems and data
base engines.

WWU Access Control System Roadmap © 2013 Page 32 of 35


Issue Need Want
3rd Party Integration w/IDS? X
3rd Party Integration w/VMS? X
3rd Party Integration w/SIS? X X
Incident Command System Integration? X
Active Directory Integration? X
Direct Banner Integration? X
Banner Integration via Active Directory? X
Direct Integration w/CollegeNet? ?
Direct Integration w/Event Management? X
Direct Integration w/Conference Management? X
Mobile Monitoring (handheld and/or laptop)? X
Table 5: New ACS System & Data Integration
There is a “Need” to have an integrated system approach, and that the integration of
data bases (Banner) and other scheduling systems (CollegeNet, Event Management, &
Conference Management) with the ACS are highly desired.

SUMMARY
The repeated theme heard in the Stakeholders’ Meeting and in individual interviews
was that of cost, i.e. budget. Many Stakeholders are unclear on what the true cost of
ownership will be for a new ACS, but general consensus is that an integrated system
and data base approach is necessary and desired.

Installation
$?

Maintenance
New Building
$? Space $?

ACS

SSA $?

Figure 1: Uncertainty of Cost/Budget

WWU Access Control System Roadmap © 2013 Page 33 of 35


WWU Access Control System Roadmap © 2013 Page 34 of 35
BUDGETARY ESTIMATE FIGURE 1: TIMELINE (ENLARGED VIEW)

WWU Access Control System Roadmap © 2013 Page 35 of 35


Appendix D
WWU, BFA, Facilities Management Page 1 of 6

POLICY
Effective Date: September 1, 2015 Authority: RCW 28B.35.120 SAAM Chapter 20
Approved By: President Bruce Shepard WAC 516-24-001

Cancels: POL-U5610.01 Issuing and Using University Keys

See Also: POL-U5346.03 Safeguarding University Assets


POL-U5950.01 Health, Safety and Environmental Protection
POL-U5400.01 Using University Resources
POL-U5300.25 Reporting Loss of University Funds or Property

POL-U5710.01 MANAGING ACCESS TO UNIVERSITY FACILITIES


This policy applies to all faculty, staff, students, volunteers,
guests or visitors who access University owned and leased
facilities and space. Its purpose is to facilitate access to space
and equipment by authorized individuals, to safeguard members
of the Western Washington University community, and to
minimize risk to both the University’s property and the personal
property of the individuals who work, study, and reside at
Western.

Definitions:

Access Control – The means, methods and practices used to minimize risk to persons and property
by regulating entry to buildings and spaces. Control activities may be preventative and/or detective.

Access Device – Any University-authorized device used to lock/unlock mechanical and electronic
door hardware, including traditional metal keys, ID card, application and/or any other electronic
means of access.

Area Access Manager – An Executive Officer, Chair, or Director of an academic or non-academic


department designated to grant access privileges to individuals (i.e. faculty, staff, students, vendors
and volunteers) for space over which they have been granted authority.

Access Control Administrator – A position designated to have operational oversight for access
control to a defined grouping of buildings, facilities or spaces, and is responsible for determining
operating hours.

Authorized Individual – An individual (i.e. University faculty, staff, student, volunteer or contractor)
for whom certain access privileges have been granted by an Area Access Manager.
Departmental Key Controllers – Positions designated by an Area Access Manager to perform access
administrative duties in accordance with University policies and procedures.

Sponsored Guest – A person who is present in a University building or space by way of an


Authorized Individual.

POL-U5710.01 Managing Access To University Facilities


POL-U5710.01 Page 2 of 6
POLICY

1. Vice President for Business and Financial Affairs Ensures an Appropriate and Effective
Access Control Management Process is Established

The Vice President for Business and Financial Affairs (VP for BFA) will ensure physical access
processes:

a) Are implemented and maintained,

b) Are compliant with other University policies, and

c) Minimize risk to the campus community and its property.

The VP for BFA appoints members of the Campus Access Control Committee (CACC) and
approves its charter.

2. Campus Access Control Committee Oversees Access Control

The CACC is a standing committee with the responsibility to:

a) Designate Access Control Administrators (ACA) for campus spaces

b) Develop and maintain guiding documents;

c) Advise vice presidents on access control issues within their divisions

d) Advise ACAs in the development of processes for requesting and granting access
devices within their areas of responsibility; and

e) Interpret this policy to resolve individual disputes and address questions pertaining to
access control.

3. Area Control Authorities Define the Process for Requesting and Granting Access
Devices

ACAs designate Area Access Managers (AAM) for areas and spaces assigned by the CACC.

The specific process for requesting, and the criteria used for granting access and access
devices, is defined by the ACA in accordance with campus guiding documents and divisional
guidance. The following underlying principles apply:

POL-U5710.01 Managing Access To University Facilities


POL-U5710.01 Page 3 of 6
POLICY

a) Employment status does not imply automatic authorization for access,

b) Access is granted at the lowest level of need, and

c) Granting access is to always favor safety and security of persons and property over the
convenience of the requester.

AAMs may only grant access privileges within the parameters established by an ACA, and
only for the areas assigned by the ACA.

4. Guiding Documents

Guiding documents are an extension of this policy. The CAAC, ACAs, AAMs, and Authorized
Individuals are required to follow approved guidelines in order to effectively manage access to
University facilities. Guiding documents will include, but are not limited to:

a) Guidelines for Issuing Access Devices - Describes levels of access and criteria for
granting access privileges and access devices to authorized individuals.

b) Identification of ACAs and AAMs and departmental responsibilities for access control.

c) Access Control Measures - Describes risk and vulnerability considerations when


determining the preventive and detective measures that will be used by the University
for access to areas on campus.

5. Access to All University Owned and Leased Facilities and Space Is Limited to
Authorized Individuals

a) During scheduled hours, academic and administrative buildings and spaces are open
for general use by employees, students, and the public for educational, work related,
and special event purposes.

b) Outside scheduled hours, access is restricted to authorized individuals. Sponsored


guests must be accompanied at all times by an authorized individual.

c) During all hours:

i. Access to certain University areas is limited to authorized individuals only. For


example:

POL-U5710.01 Managing Access To University Facilities


POL-U5710.01 Page 4 of 6
POLICY

1) Operational facilities and spaces (e.g. steam plant and mechanical


rooms).

2) Higher-risk facilities and spaces (e.g. laboratories, hazardous


materials storage areas, and performance venues).

ii. Access to residential facilities is limited to authorized:

1) Students,

2) Guests of students,

3) Employees,

4) Visitors (e.g. pre-authorized conference attendees), and

5) Contractors.

6. Visitors, Students and Employees Must Comply with University Conduct Regulations

In addition to employees and students, guests, contractors and visitors on University property
are expected to comply with all University policies and state and federal regulations related to:

a) Access to and use of University buildings and spaces, and

b) Appropriate conduct as described in WAC 516-24.

7. All Access Devices Are the Property of Western Washington University

a) Access devices and privileges are assigned to authorized individuals on a temporary


basis only,

b) Authorized individuals must sign for the access device, indicating they understand and
will comply with individual rules and responsibilities for access devices,

c) Supervisors of authorized individuals must ensure access devices are promptly


returned or relinquished to the original issuer:

i. When no longer needed for any reason,

POL-U5710.01 Managing Access To University Facilities


POL-U5710.01 Page 5 of 6
POLICY

ii. Before departing the University or transferring to another department, or

iii. Upon request for any reason at any time by an Executive Officer, Access
Control Administrator, Area Access Manager, Supervisor, or Director of
Public Safety.

d) Failure to return access devices by an authorized individual may result in one or more
of the following:

i. Administrative action by the University, up to and including legal action,


and/or,

ii. Assessment of charges for expenses incurred by the University to return


access control to the same level that it was before it was compromised by the
individual’s failure to return the access device.

e) Lost, stolen, or damaged access devices shall be reported immediately to the:

i. Appropriate Access Control Administrator,

ii. Area Access Manager, and

iii. University Police Department.

The Reporting Loss of University Funds or Property (POL-U5300.25) policy is to be followed


when any known or suspected loss resulting in the unauthorized taking of University public or
non-public funds or property or other illegal activity.

8. Authorized Individuals Responsible for Safekeeping Access Devices and Appropriate


Use of Spaces

Authorized individuals who are assigned an access device are prohibited from:

a) Loaning access devices to others,

b) Transferring access devices to others,

c) Duplicating access devices,

d) Altering access devices or access control mechanisms,

POL-U5710.01 Managing Access To University Facilities


POL-U5710.01 Page 6 of 6
POLICY

e) Damaging, tampering, or vandalizing any University access control mechanism,

f) Propping locked doors open, and

g) Admitting unauthorized individual(s) into an access controlled space.

9. Director of Public Safety Ensures Audits of Issued Access Control Devices

The Director of Public Safety may independently conduct periodic audits of issued access control
devices or may request that Access Control Administrators and Area Access Managers conduct
audits of the area(s) for which they have oversight.

POL-U5710.01 Managing Access To University Facilities


Appendix E
TELECOMMUNICATIONS
(APPENDIX F in original document)

F.1 Existing System


F.1.1 Description

Data, telephony, and CATV communications are delivered on campus via fiber optic and
copper cable plants both within and between buildings. Bond Hall is the primary
demarcation point for all internet, telephone, and CATV service to campus from outside
providers. Fiber optic cabling between buildings on campus is both single-mode and
multi-mode (62.5 micron) fiber. The majority of buildings on campus are wired with a mix
of Cat5e and Cat6 copper cabling, though some buildings still contain Cat5 or Cat3
wiring.

Data network service is delivered to all users by Cisco routing, switching, wireless, and
security systems. Analog telephone service is delivered to approximately 4000 users
(including elevators, emergency phones, fax machines, and other services/facilities) via
a Nortel PBX located in Bond Hall, and three fiber remotes in AC, CF, and the
Commissary. IP telephony is delivered to approximately 400 users over the data network
infrastructure using Microsoft Skype4Business; it interfaces with analog gateways in
Bond Hall and AC to connect to both the PBX and the wider PSTN. CATV services are
delivered to campus from a Comcast head-end in Bond Hall via a series of transmitters,
fiber nodes, and amplifiers across campus. The CATV network includes a return path to
Comcast to allow campus to broadcast programming on a community channel in greater
Whatcom County.

The wired and wireless data network is divided into academic and residential sections.
The academic data network is architected in an active-passive redundant core design
with multiple failover points between the two legs. The data network is logically arrayed
in three tiers—the redundant core provides routing between the different nodes in the
distribution layer (routers and switches that service individual buildings or groups of
buildings on campus), and the distribution layer distributes traffic to the access layer
devices (switches that service the endpoints—computers, servers, printers, wireless,
etc.). The residential network also uses a three-tiered logical design, with a single core
router attached to the redundant core routers of the academic network.

Western maintains telecommunications services to several remote sites, such as


Shannon Point Marine Center, Lakewood Watersports Facility, the Technology
Development Center, the Small Business Development Center, and Alumni/Foundation
offices in downtown Seattle and the Bellingham Herald Building. We also maintain colocation
services with Portland State University, site-to-site Virtual Private Network
connections to Microsoft Azure and St. Joseph’s Hospital, and direct fiber connectivity to
the Whatcom County Courthouse.

All services and remote site connections pass through Bond Hall—no endpoint on
campus can access CATV, internet, or the PSTN without going through Bond Hall to do
so. In addition to being the demarcation point for internet, PSTN, and CATV service,
Bond Hall serves as the primary datacenter for the campus. The secondary datacenter is
located on the second floor of AC, with fiber optic cable on above-ground utility poles
connecting AC to the campus network. Internet service is provided via a 10Gbs circuit
from the primary provider, and a 1Gbs circuit from the secondary/backup provider. From
Bond Hall, Comcast and CenturyLink also maintain their own network demarcations to
provide services directly to endpoints on our campus, such as contractors or vendors.

F.2 Existing Conditions Evaluation


• Overall Concerns
o Lack of direct fiber paths from each building to each core – several buildings have to be
patched one or more times through another building to reach a core, which introduces
potential points of failure.
o Multiple instances of chokepoints in our copper cable pathways: daisychained
connections over multiple 110 blocks, CAT5 jumpers on crossconnects between Cat5e
or Cat6 cables, Cat5 or Cat5e hydra cables connected to Cat6 station cables, etc.
o Most of the network equipment is end-of-life or end-of-support, or will be by 2020. No
operating dollars are allocated for upgrading network infrastructure. Most of the
hardware and cabling was funded as part of two capital projects (in 2000 and 2010), or
as part of other construction projects (Buchanan Towers East, Miller Hall, Carver, etc.),
rather than operationalized for regular replacement.
o The primary and secondary internet connections for campus share a demarcation point
in Bond Hall. In the event of a facilities emergency in Bond Hall, there is no second path
to the internet for campus.
o Lack of insight and input into the design of other networks (building automation and
control, fire and life safety, etc.) from our engineers can result in both security and
performance issues for those networks, as well and technical issues for the academic
network in places where the networks are bridged (i.e. Shannon Point Marine Center)
o High risk of failure for existing PBX
o Aging CATV system, lack of training and support for maintenance, lack of funding for
equipment replacement, and lack of clear roadmap for the future of CATV (converged
with data network vs maintained as a separate physical network).
o Current wireless network is deployed “ad-hoc”, rather than designed strategically to
ensure appropriate coverage and density across campus. As a result, the current
wireless network infrastructure is inadequate to meet student needs and operational
demands.
• Datacenter and Distributor Room Concerns
o Lighting in all MDF/IDFs may not meet spec (BICSI TIA-569 Spec.)
o Temp and Humidity in MDF/IDFs may not meet spec (ASHRAE Class 3 Spec.)
o Several MDF/IDFs have become “shared spaces” over time, where our equipment
competes for space with other departments’ equipment (ladders, custodial supplies,
etc.). Lack of strong access controls in these spaces (brass key access only) leaves
critical equipment at risk, and the confined space makes it difficult for people to work.
Storage of some equipment (such as fluorescent lamps) is precarious, which is a safety
concern for people working in the space.
o MDF/IDF are becoming overcrowded with equipment from BAC, Fire and Life Safety
equipment, CCTV hardware, etc. Rack and wall space are become tight, and work
space becomes limited. Additional equipment also pushes up the temperature, requiring
additional cooling systems to meet spec.
o The second network core location (Arntzen Hall basement) is a hightraffic corridor for
FM personnel to access fire control, electrical equipment, and other equipment. For a
network core, this space is inadequately secured and puts south campus network
connectivity at risk. The space allocated for the network core doesn’t have room for
expansion.
o Lack of clarity around electrical codes—can network equipment be operated on the
same circuits as emergency lighting systems? If not, how do we provide a separate
emergency power circuit for these systems to stay up during power failures (especially if
they are supporting VOIP telephones over POE)?
o High risk / low utilization of AC datacenter facility—the AC datacenter is vulnerable to
service breaks due to above-ground utility service. Growth of services in the AC
datacenter is constrained by diminished fiber capacity between the facility and campus,
which is prohibitively expensive to expand. The facility itself is massively overbuilt in
terms of both its physical space and power/cooling systems, relative to the shrinking
physical footprint of modern datacenters (due to virtualization and migration to SaaS
platforms).
o Access to some MDFs/IDFs (for example, Rec Center and Old Main) are frequently
limited because they are only accessible from within another occupied room (training
room, group counseling room, cash-counting room, etc.).
• Capacity Concerns
o Overall fiber capacity between buildings is insufficient in places.
o Fiber capacity to AC from campus is insufficient and cost-prohibitive to expand.
o Single-mode fiber capacity for direct connections between cores (AH and BH) does not
meet future growth needs
o Copper pathway capacity in some buildings is insufficient—cable trays are over-packed
in places, and the changing specifications around Power-over-Ethernet will require fewer
cables to be packed together in order to meet spec.
o Switch port capacity at the access layer of select buildings is insufficient.
o Available bandwidth of secondary ISP circuit is insufficient to accommodate normal
campus bandwidth consumption during business hours—in the event of a primary ISP
failure during a weekday, we will not have sufficient bandwidth on the backup connection
to provide internet service to campus.

F.3 Future Conditions Evaluation


• Increased adoption of SaaS solutions, virtualization of servers, increases in storage
density, and the shift from a large PBX to a small PBX+VOIP services will further
decrease the size of the datacenter footprint required to support services on campus.
• Shifts to hosted solutions and the convergence of services onto the data network will
push demand beyond what our network infrastructure can currently support.
• Resilience and flexibility of Azure computation and storage resources will eliminate the
need for maintaining two datacenters on campus as a business continuity/disaster
recovery solution—one datacenter plus “cloud” backups and a small secondary on-
campus site for business-critical services will suffice.
• Movement toward the adoption of IPTV as a delivery mechanism for CATV service
would allow us to converge data and CATV services on the data network, reducing or
eliminating the need to maintain separate CATV hardware and cable plant.
• Increased use of wireless devices by both students and staff, including the adoption of
mobile network devices in university operations (i.e. Asset Works) and instruction (i.e.
audience response systems) will drive the need for increased coverage and density of
wireless networks, which will in turn drive an increased need for access layer capacity,
more Cat6 cable, more fiber, more Power-over- Ethernet switches, and upgrades to
208v power in more closets. These increased needs will also be driven by the
proliferation of IP-enabled devices on the wired/wireless network (the “Internet of
Things”).
• Not all MDF/IDFs have the physical space to house the additional hardware needed to
support the need for more access-layer port capacity.
• Rapidly evolving cable specification standards and accelerating hardware performance
options may require the copper cable plant to be upgraded more frequently than in
decades past. In lieu of adequate funding to upgrade entire buildings at once, the
problem of ad-hoc upgrades and connections patched with mismatched cables could
proliferate, making the MDF/IDFs more difficult to physically manage and diminishing
overall network performance.

F.4 Recommendations
• Operationalize the costs of network equipment maintenance and replacement, WWU
UTMP F-6 June 2017 and establish a fully-funded strategic plan for the cyclical
replacement and expansion of core-, distribution-, and access-layer network devices,
including a continued expansion of the wireless network and accompanying access-layer
port capacity.
• Expand fiber capacity between buildings, including upgrading fiber to recommended
latest spec.
• Run new fiber optic cables to ensure direct fiber paths exist from each building to each
of the two cores, plus additional capacity directly connecting the cores to each other.
• Evaluate more secure/resilient locations on south campus for the second network core,
such as Campus Services or Commissary, and relocate the core infrastructure there.
• Bring additional fiber to a new campus location (such as a new network core) to serve as
a secondary ISP circuit, physically separating the two ISP connections into separate
facilities.
• Consolidate datacenter services in Bond Hall, with a smaller redundant location on
campus for business continuity of critical services only. Use cost savings from vacating
the AC datacenter to move disaster recovery functions to cloud-hosted platforms.
• Devote time and resources to further investigating Passive Optical Networks (PON) as
an alternative to copper cabling in new/remodeled buildings.
• Incorporate central networking/telecommunications team in the planning, configuration,
security, and maintenance of data networks other than just academic and residential (i.e.
BAC, lighting control, etc.).
• Fully fund the migration of PBX telephone users to IP telephony services, and replace
the existing PBX with a smaller PBX to provide telephony to non-IP telephony
compatible services only (elevators, fax machines, etc.).
• Fund and strategically plan for the upgrade of all MDF/IDFs on campus to 208v power.
Bring humidity/temperature and lighting up to industry specifications. Upgrade and
standardize all 110-block termination fields to new campus standard (current standard is
Commscope Visipatch system), and upgrade all hydra cables to current communication
cable specifications, subject to the study and analysis of PON systems.
• Fund and strategically plan for the upgrade of all horizontal cable systems to latest
specification, subject to the study and analysis of PON systems.
F.5 Conclusions

Campus telecommunications is at a critical point in its lifecycle. The data network is resilient, but nearing
the end of its supported life with no active plan for upgrade. The analog telephone network is at critical
risk, with transition to newer services stymied by lack of funding and lack of clear institutional
prioritization and direction. The CATV network is in a state of transition, where institutional leadership
has sent mixed signals by investing in both an IP-based distribution for the residence halls and in
production/broadcast facilities that rely on non-IP based distribution for academic programs.

The challenges and opportunities facing Western's telecommunications services and infrastructure are
not unique; others have weathered these storms before, and we can do so as well with adequate
funding, coordination, and commitment from the university to a strategic vision for the future.

You might also like