BT4 PP Lecture Estimate
BT4 PP Lecture Estimate
SPECIFICATION AND
ESTIMATE
WHY ESTIMATE
➢ Construction Cost Estimate is an approximate of the probable cost of a
project.
➢ Cost estimates will help dictate the scope of work of the project during the
Pre-design phase, Design phase, Bidding phase and Construction phase
enabling the Owner and the Architect to come up with a realizable project.
Estimates related to both the overall budget and to the preliminary allocations of
budget to the various system are periodically prepared. These cost estimates are
successfully revised and refined as working drawings for each system are
developed. Estimating is the basis of financial control, planning and procurement
of resources throughout the project. An accurate estimate can also help the
contractor in a successful tender.
An accurate estimate is helpful in four keys of activity:
• Planning
• Financing
• Tendering
• Constructing
PLANNING – Planning a contract includes studying the project resources such as casn,
labour, materials and equipment. The project duration, project cost are
determined based on the results of the estimate. Planning facilitates:
• Timely ordering of project resources
• Project control
• Preparation of cash flow analysis
FINANCING – There are several outside sources that contractors can use to help with
its cash management aside from their working capital. The principal source is the
bank loan or bankdraft. When preparing loan request, an estimate of the financial
requirements at the different stages of the project shall be submitted to the
Instituion lending the money.
Tendering – Contractors compete to be awarded the contract. The more accurate
the estimate, the better the contractor’s chances of winning the contract and
executing it successfully. A good tender sum is the lowest possible and still allows
the project to be executed with a reasonable profit margin. The tender sum
consist of the following components:
Example: Proposal for the provision and installation of a Dry Ceiling System
In some cases, using a agency which builds the same types of structure many
times has well-developed historical file on cost and use requirements. An
estimate developed on this type of data can be quite accurate.
ESTIMATING BY SQUARE METER METHOD
• Square meter cost are found by multiplying the area of space times a cost
factor. The cost factor is usually available from the historical cost file of past
projects. This is the method commonly used by Architects.
• Enter Area conversion scale at 2.0 intersect curve, read horizontally the
appropriate cost multiplier of 0.97
• Size adjusted cost becomes 0.97 x coverage cost per square meter (table
2)
CUBIC METER METHOD
This approach is very similar to the square meter procedure except that the
cubage provides the basis for cost. The cubic meter method is normally
used in earthwork, civil construction and airconditioning.
There are two times when square meter and cubic meter are useful. The first is
in the schematic design stage when no details are available, when square
meter costs and cubic meter cost makes a useful starting point. The
second is after the bids are in and the costs can be worked back into their
appropriate units for information purposes. As soon as details become
available in the project design, the square meter or cubic meter approach
should be discontinued and the project priced by its particular
components.
STRUCTURAL
15% ELECTRICAL
(5,250)
MECHANICAL
SITEWORKS
OTHERS
PARAMETRIC METHOD
29%
(10,325)
ESTIMATING BY MODULAR COST
In a situation in which the project is made up of repetitious modules such as
housing units, apartments, hospitals rooms or suites accurate cost is
developed for one unit and extrapolated by the total number of units and
their characteristics.
Example:
10 units of socialized housing at 500,000/ house = 5,000,000.00
https://www.lumina.com.ph/property-
listing/model/10
COMBINED METHOD
The combined approach is used when the project is only partially defined. A
detailed bill of materials type take-off is performed for those portions which
are defined, and square meter cost are used for undefined systems. Most
usually, the square meter costs is applied to the electrical, mechanical and
plumbing sections of the building which are the last to be defined.
Example:
Example: An invitation to bid for the provision and installation of the door
system for an office building. Doors shall be hollow metal, 38mm thk,
painted: duco finish. Include locksets:
a. 10 sets of 2.10m x 0.80m.
b. 5 sets of 2.10m x 0.90m.
DETAILED ESTIMATES BY QUANTITY TAKE-OFF METHOD
This is the description of a complete take-off of all materials in the project. Unit
prices are applied to each type of material and the results extended and
summed up to provide a total cost. This method is widely regarded as the
most accurate in estimating.
Note: The more detailed these items are, the more accurate the estimate
become.
All of the above areas can contribute to increased costs for a repair and
remodeling project. Each of the above factors should be considered in the
planning, bidding and construction stage in order to minimize the increased costs
associated with repair and remodeling jobs.
FORMULA - AREA
https://www.cuemath.com/geometric-area-formula/
FORMULA - VOLUME
https://www.cuemath.com/volume-formulas/
CONCRETE
PLAIN AND REINFORCE CONCRETE
Concrete is either Plain or Reinforced. By definition, Plain concrete is an
artificial stone as a result of mixing cement, fine aggregates, coarse aggregates
and water. The conglomeration of these materials producing a solid mass is called
concrete.
Reinforced Concrete on the other hand, is a concrete with reinforcement
properly embedded in such a manner that the two materials act together in
resisting forces.
AGGREGATES
Aggregates for concrete works are classified into two:
1. Coarse Aggregate such as crushed stone, crushed gravel or natural gravel
with particles retained on a 5mm sieve.
2. Fine Aggregate such as crushed stone, crushed gravel, sand or natural sand
with particles passing on a 5mm sieve.
SIZE OF AGGREGATES.- For coarse aggregate (gravel), the maximum nominal
size varies from 40, 20, 14 or 10mm diameter. The choice from the above sizes
depends upon the dimensions of the concrete member more particularly, the
spacing of the steel bars reinforcement or as specified.
Good practice demand that the maximum size of coarse aggregate(gravel)
should not exceed 25% of the minimum thickness of the member structure nor
exceed the clear distance between the reinforcing bars and the form.
The coarse aggregate should be small enough for the concrete mixture
to flow smoothly around the reinforcement. This is referred to as workability
of concrete.
CONCRETE PROPORTION
Proportioning concrete mixture is done in two different: by weight or by volume
method. The most common and convenient way is by the volume method using
the empty plastic bag of cement, or by a measuring box for sand and gravel.
Measuring the aggregates and water by weight is sometimes used in a concrete
batching plant for ready-mix concrete or as specified in the plan
MEASURING BOX
Proportioning concrete by volume method had long been practiced in almost
all types of concrete construction. Time has proven it to be effective and
successful. However, on construction where space for materials stock piling and
mixing does not permit, ready-mixed concrete is the most practical solution.
In actual concreting and masonry work, there are several factors that might
affect the accuracy of the estimate. Some of which are enumerated as follows:
1. Inaccurate volume delivered aggregates which is very common. Delivery truck
should be measured to check if the volume of aggregates being delivered is
exactly as ordered.
2. Dumping of aggregates on uneven ground surface and grass area reduces the
net volume of aggregates.
3. Improper measuring of the aggregates during the mixing operation. This is
common practice when the work is on its momentum where laborers fails to
observe the right measuring of aggregates being delivered to the mixer.
4. The cement and fine aggregate for grouting concrete joints are mostly
overlooked in the estimating processes.
5. Cement waste due to reckless handling and hauling.
6. The pure cement powder used by mason in plastering operations to prevent
the plaster from sliding downward is not considered in estimating.
7. Pilferage of materials. This could be avoided with an effective system of
construction management.
Foundation Components
a. F1
b. F2
c. FTB
d. C1
e. C2
Summary of materials
a. Cement (40kg)
b. Sand (cu.m)
c. Gravel (cu.m.)
MASONRY
Concrete Hollow Blocks is popularly known as CHB. It is classified as load
bearing and non-bearing blocks. Load bearing blocks are those whose thickness
ranges from 15 to 20 centimeters and are used to carry load aside from its own
weight.
Non-bearing blocks on the other hand, are blocks intended for walls, partitions,
fences, dividers and the like carrying its own weight whose thickness ranges from 7
to 10 centimeters.
The standard hollow blocks has three void cells and two half cells at both ends
having a total of four. These hollow cells vary in sizes as there are different
manufacturers using different types of mold. Hence, it is recommended that
concrete hollow blocks with bigger cells be considered in estimating for a more
realistic result.
In this study, what we want to know is the quantity of the materials needed for a
certain masonry work made of concrete hollow block generally comprises of the
following.
1. Concrete hollow blocks.
2. Cement and sand for block laying.
3. Cement, sand and gravel filler for the hollow core or cell.
4. Cement and the fine sand for plastering.
5. Cement, sand and gravel for foundation or footing
6. Reinforcing steel bars and
7. Tie wires
Estimating the materials for masonry work using hollow blocks could be done in
either of the following methods
1. By Fundamental methods
2. By the Area methods
EXAMPLE:
A concrete hollow blocks wall has a general dimension of 3.00m high by 4.00m
long. Determine the number of CHB, cement and sand required to construct the
wall.
SOLUTION 1 (By Fundamental Method)
1. Divide the height of the fence by the height of one block
3.00/.20 = 15 layers
2. Divide the length of the fence by the length of one block
4.00/.40 = 10 pieces
3. Multiply the result of step 1 by step 2
15 x 10 = 150 pieces
2. Refer to the table along 10 x 20 x 40 CHB under class “B: mixture; multiply
2. Solve for the cement and sand. Under 16mm thick plaster class “B” mixture,
multiply
Cement: 24 X .192 = 4.6 say 5 bags
Sand: 24 X .016 = .384 cu.m.
ACTIVITY:
Compute for the number of 6” CHB, bags of cement(40kg) and cu.mts. of sand
needed for mortar joint and plastering.
QUIZ:
Compute for the number of 6” CHB, bags of cement(40kg) and cu.mts. of sand
needed for mortar joint and plastering.
REINFORCEMENT