MTRC NEC4 Training Level 2 - Module 4 Rev 3
MTRC NEC4 Training Level 2 - Module 4 Rev 3
October 2021
Training modules
Roles &
responsibilities Compensation Time and the
Precontract Commercial
and risk events programme
management
Training modules
Roles &
responsibilities Compensation Time and the
Precontract Commercial
and risk events programme
management
Contract dates
■ Contract Date – the date the contract came into existence (cl
11.2(4))
■ starting date – the date the Contractor starts work under the contract
■ access date(s) – the date by which the Client will provide access to
and use of the parts of the Site needed by the Contractor (in the PSC
access is provided to people, places and things – see later slide)
■ Key Date(s) – the date by which the Contractor must achieve a
Condition stated for the works
■ Completion Date – the date by which the Contractor must achieve
completion by
■ Completion Date is the completion date identified in the Contract
Data either by the Client or the Contractor, unless later changed in
accordance with the contract
■ planned Completion is the date the Contractor is planning to
complete the works by as shown on the Accepted Programme
■ date of Completion is the date that Completion is achieved
Turner & Townsend MTRC NEC4 Level 2 – Module 4 7
Turner & Townsend Confidential
Contract dates
Contract Date
planned Completion
starting date (by the Contractor) The Completion Date – is the –
completion date – unless
access date(s) otherwise changed in accordance
with this contract
* * * * * *
■ Contractor does not start work on Site until first access date and
does work so that Completion is on or before Completion Date (cl
30.1)
■ Project Manager decides date of Completion and certifies it within
one week (cl 30.2)
■ Completion Date can only be changed by Project Manager as a
result of compensation events, acceleration or accepting a Defect
■ The Client allows access to and use of each part of the Site to the
Contractor which is necessary for the work included in the contact
(cl 33.1)
■ Access and use is allowed on or before later of its access date and
date for access shown on the Accepted Programme (cl 34.1)
■ Consultant does not start work until the starting date and does
work so that Completion is on or before Completion Date (cl 30.1)
■ The Client provides access to a person, place or thing to the
Consultant as stated in the Contract Data on before the later of
its access date and date for access shown on the Accepted
Programme (cl 33.1)
Completion
Sectional Completion
Key Dates
■ Key Dates are a way of dealing with interfaces between the work
of the Contractor and the work of Others, including other
contractors engaged by the Client
■ key dates are set out in the Contract Data long with a condition
which the works must achieve by the relevant key date
■ key dates and conditions can be changed in accordance with the
contract with the defined terms Key Date and Condition referring
to the date / condition in the Contract Data or as changed under
the contract
■ Key Dates and Conditions can be changed by the Project Manager
■ giving an instruction under clause 14.3, which will be a
compensation event (cl 60.1(4)) or
■ due to a compensation event, acceleration or accepting a
Defect
Key Dates
■ If the Project Manager decides that the work does not meet the
Condition stated for a Key Date by the date stated and, as a
result, the Client incurs additional cost either
■ in carrying out work or
■ by paying an additional amount to Others in carrying out work
on the same project, the additional cost which the Client has paid
or will incur is paid by the Contractor
■ The Project Manager assesses the additional cost within four
weeks of the date when the Condition for the Key Date is met (cl
25.3)
Management of time
■ Allowance for the time risk the Contractor carries under the
contract must be shown on the programme
■ Demonstrate that the Contractor’s programme is realistic
Revised programmes
Revised programmes
Delay assessment
■ Who owns any free float (not terminal float) in the programme?
Float
Completion Date
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Operation 1
Operation 2
Free Float
Operation 3 4 weeks
Operation 4
Operation 5
Non-critical
Critical
Planned Completion
Float
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Operation 1
Operation 2
Free Float
Operation 3 4 weeks
Operation 4
Operation 5
Non-critical
Critical
Compensation event
Planned Completion
Float
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Operation 1
Operation 2
Free Float
Operation 3 2 weeks
Operation 4
Operation 5
Non-critical
Critical
Compensation event
Planned Completion
Assessment of delay
Float
Completion Date
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Operation 1
Operation 2
Free Float
Operation 3 4 weeks
Operation 4
Operation 5
Non-critical
Critical
Planned Completion
Float
Completion Date
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Operation 1
Operation 2 Contractor’s delay
Operation 3
Operation 4
Operation 5
Non-critical
Critical
Planned Completion
Float
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Operation 1
Operation 2 Contractor’s delay
Operation 3
Operation 4
Operation 5
Non-critical
Critical
Planned Completion
Float
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Operation 1
Operation 2 Contractor’s delay
2 weeks
CE 1
Operation 3
Operation 4
Operation 5
Non-critical
Critical
Compensation event
Planned Completion
Float
Completion Date
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Operation 1
Operation 2
Operation 3 Terminal Float
4 weeks
Operation 4
Operation 5
Non-critical
Critical
Planned Completion
Float
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Operation 1
Operation 2
Operation 3 Terminal Float
4 weeks
Operation 4
Operation 5
Non-critical
Critical
Compensation event
Planned Completion
Float
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Operation 1
Operation 2
Terminal
Operation 3 Float
2 weeks
CE 1
Operation 4
Operation 5
Non-critical
Critical 2 weeks
Compensation event
Planned Completion
Float
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Operation 1
Operation 2
Terminal 2 weeks
Operation 3 Float
2 weeks
CE 1
Operation 4
Operation 5
Non-critical
Critical 2 weeks
Compensation event
Planned Completion
Float
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Operation 1
Operation 2
Operation 3 Terminal Float
4 weeks
CE 1
Operation 4
Operation 5
Non-critical
Critical 2 weeks
Compensation event
Planned Completion
Assessment of delay
Float
Completion Date
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Operation 1
Operation 2 Terminal Delay
Operation 3 4 weeks
Operation 4
Operation 5
Non-critical
Critical
Planned Completion
Float
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Operation 1
Operation 2 Terminal Delay
Operation 3 4 weeks
Operation 4
Operation 5
Non-critical
Critical
Planned Completion
Float
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Operation 1
Operation 2
Operation 3 Terminal Delay
4 weeks
CE 1
Operation 4
Operation 5
2 weeks
Non-critical
Critical
Compensation event
Planned Completion
Float
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Operation 1
Operation 2
Operation 3
CE 1 2 weeks
Operation 4
Operation 5
2 weeks
Non-critical
Critical
Compensation event
Planned Completion
Float
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Operation 1
Operation 2
Operation 3
CE 1
Operation 4
Operation 5 Terminal Delay
4 weeks
Non-critical
Critical
Compensation event
Planned Completion
Float
Completion Date
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Operation 1
Operation 2
Operation 3 Terminal Float
4 weeks
Operation 4
Operation 5
Non-critical
Critical
Planned Completion
Float
Completion Date
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Operation 1
Operation 2
Operation 3 Terminal Float
4 weeks
Operation 4
Operation 5
Non-critical
Critical
Planned Completion
Float
Completion Date
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Operation 1
Operation 2
Operation 3 Terminal Float
4 weeks
Operation 4
Operation 5
Non-critical
Critical
Planned Completion
Float
Completion Date
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Operation 1
Operation 2
Operation 3 Terminal Float
6 weeks
Operation 4
Operation 5
Non-critical
Critical
Planned Completion
Assessment of delay
Assessment of delay
Delay assessment
Delay assessment
Quotation
Acceleration
Acceleration
Completion
Take Over
■ The Client takes over no later than two weeks after Completion
(cl 35.1)
■ The Client need not take over the works before the Completion
Date if stated in the Contract Data (cl 35.1)
■ The Client may use any part of the works before Completion and
if it does it takes over on the date that it uses it. This will be a
compensation event, unless
■ the use is for a reason stated in the Scope,
■ to suit the Contractor’s method of working or
■ the Completion Date has passed (cl 35.2)
■ The Project Manager certifies the date the Client takes over and
its extent within one week of the date (cl 35.3)
■ Note there is no take over in the PSC as there is no physical
works
© Turner & Townsend Limited. This content is for general information purposes only and does not purport to constitute professional advice. We do not make any
representation or give any warranty, express or implied, and shall not be liable for any losses or damages whatsoever, arising from reliance on information contained in this
document.
It must not be made available or copied or otherwise quoted or referred to in whole or in part in any way, including orally, to any other party without our express written
permission and we accept no liability of whatsoever nature for any use by any other party.