ACEM Manual
ACEM Manual
SECTION 2: COMMISSIONING
2.1 Energizing.
SECTION 3: OPERATION
3.1 General precautions.
3.2 Transformer life.
3.3 Parallel operation.
3.4 Frequency.
SECTION 4: MONITORING
4.1 General requirements
SECTION 5: MAINTENANCE
5.1 General.
TABLE OF CONTENTS
1.2 Transport.
The transformer is supplied filled with oil and normally all accessories fitted, except for the larger
units where the radiators and expansion vessels (Conservators) may be dismantled during transport.
When transporting the following should be considered:
- Larger transformers should preferably be positioned with the longitudinal axis in the
direction of movement.
- Vehicle capacity must be adequate for the transport weight of the transformer.
- The transformer must be secured against movement by means of e.g. wooden blocks and
lashes.
- Ensure prevention of damage to bushings, corrugated panels or radiators and accessories.
- Adapt vehicle speed to the road conditions.
SECTION 1: INSTALLATION
- Delivery note against goods received, details of transformers can be seen on the rating and
diagram plate.
- If there are any visual oil leaks.
- Any external damage.
Note!
No repairs should be started until responsibilities are clarified and actions are agreed upon all
involved parties
1.5 Storage prior to energizing
When storage of the transformer is required, the following should be adhered to:
- Store in dry and clean area with a solid foundation to prevent any possibilities of mechanical
damage.
- The transformer should be placed on supports to allow for ventilation under the bottom of
the base.
- The oil conservator and dehydrating breather must be checked to ensure that dry air is
breathed. (Conservator and free breathing types only).
- Avoid condensation in auxiliary terminal and cable boxes.
- Although all gasket joints are torqued in the factory it is very important that all nuts be
checked on site. Torque bolts to the settings listed in the table under 1.7 below.
Thread size Grade 8.8 not plated in Nm Grade 8.8 plated in Nm. e.g.,
hot
dipped galvanized, zinc etc.
M6 12 8
M8 28 20
M10 56 40
M12 98 70
M16 244 174
1.8 Earthing
Earth the transformer at the earthing terminals provided. Earthing resistance must be in
accordance with electricity utilities or national standards.
After the transformer has been energized, air may cause a gas relay alarm. It could be a false alarm
caused by an air bubble, which has been trapped inside the core and winding or under the cover. If
the air is not odorless an oil / gas sample should be taken for analysis
SECTION 3: OPERATION
3.1 General precautions.
- Do not energize or perform maintenance on the transformer without proper earth
connection.
- Never work on transformers or any installed electrical equipment alone.
- Do not change the position of the off-circuit tap-changer while the transformer is energized.
3.4 Frequency.
Transformers are designed for 50 Hz operation unless otherwise requested at tender stage.
SECTION 3: OPERATION
SECTION 4: MONITORING
4.1 General requirements.
Requirements are,
- Periodical recording of protection indicators and visual inspection.
- Oil condition monitoring
Periodically recording is normally done when the transformer is energized. The indicators recorded
are, oil level, top oil temperature, winding temperature and load current. The equipment to be
monitored will depend on the type of transformer and the protection equipment fitted. Depending
on the importance of the transformer the recording of these indicators could be done weekly or
monthly. A visual inspection for oil leaks and breather silica gel can be performed at the same time.
Periodical analysis and conditioning of the oil in a transformer is by far the most widely used method
for monitoring the general condition of a transformer. The condition of the oil and, of the
transformers insulation system, can be determined by taking oil samples from the transformer for
dissolved gas analysis (DGA) and other tests. The tests are comprehensively described for example,
in the IEC Standard 60296 and the Guides 60422 and 60567. The presence of an incipient fault in a
transformer will normally be detected by monitoring trends and total gas counts.
Normally oil samples are taken when the transformer is energised please ensure that necessary
safety precautions are taken. The most common frequency for oil condition monitoring is annually,
however when there is suspicion of an incipient fault in progress, the oil samples should be taken
more frequently, e.g. every three months.
SECTION 4: MONITORING
SECTION 5: MAINTENANCE
5.1 General requirements.
The primary purpose of transformer maintenance is to ensure the internal and external parts of the
transformer and accessories are kept in good condition.
Transformer maintenance can be done periodically or as condition-based maintenance. The latter is
usually the most economical way of doing maintenance. Recommended maintenance are then done
based on one or more of the following; inspections, analysis of oil samples, electrical measurements,
test of equipment, measurement of temperatures by using a heat sensitive camera, monitoring (off-
line and/or on-line).
SECTION 5: MAINTENANCE
Items to be considered are:
- Bushing gaskets; if leaks occur, tightening usually will help, if the gasket has lost its elasticity,
it must be replaced. The reason for loss of elasticity could be excessive heating or over
tightening.
- Welded joints. Leaking joints can be repaired only by welding. A skilled welder and a welding
instruction are required. Contact ACEM for further instructions.
- Cleaning contaminated bushings (cleaning agent e.g. methylated spirits, do not use
thinners).
- Cleaning glasses on gas relay, thermometer and liquid level indicator.
- Functional inspection and testing of applicable accessories.
- Move Tap-changer through all positions a few times.
- Oil sampling from bottom drain valve when required.
- Check drying material in the dehydrating breather.
- - Clean and touch-up paint work.
ARMCOIL AFRIKA (PTY) LTD