Pryda Roof Truss Installation Guide
Pryda Roof Truss Installation Guide
ROOF TRUSS
2020
CONTENTS
SCOPE &
GENERAL
1.1 GENERAL 1.3 DOCUMENTATION
Timber roof trusses are engineered and manufactured It is the builder’s responsibility to supply all of the
to an exacting standard which require special handling, relevant information required for the truss designs. It is
erection and bracing techniques. To ensure that the recommended that the truss manufacturer confirms all
expected performance is achieved, it is imperative that all details prior to manufacture.
relevant parties are familiar with the requirements set out
in this document. 1.3.1 Layout
The guidelines in this document are a sub-set of the A roof truss layout must be obtained prior to erection, with
full Australian Standard® AS4440-2004 “Installation of the following points considered:
nailplated timber trusses”, and as such should be read in
a. Check dimensions of the supporting structure prior to
conjunction with this Standard.
manufacture.
Pryda Australia acknowledges Standards Australia for b. Check the truss layout to identify the trusses, and also
permission to reproduce some of the drawings and check for the correct orientation of trusses – two span,
technical content from within AS4440-2004. multiple and cantilever trusses.
c. Check that the supporting structure is adequate for the
1.2 APPLICATION loads to be applied, especially where girder trusses are
located, and lintels.
This document intends to apply to nailplate timber roof
d. Check that information on roof bracing, bottom chord
trusses within the following general limitations:
bracing (including the need for BC ties, if applicable)
a. Residential structures (NCC Building classes 1, 2, 3 and any other applied loading (solar tank etc.) on the
and 10) and light commercial structures. roof is provided.
b. Maximum roof pitch 45 degrees. e. Check that information on truss to truss connections,
tie-downs, web-ties, scabs etc. is provided clearly on
c. Maximum truss span 16 m. the layout.
d. Maximum design wind speed of 74 m/s.
TYPICAL TRUSS LAYOUT AND TRUSS TYPES (NOTE: BRACING NOT SHOWN FOR CLARITY)
TRUSS TERMINOLOGY
The erection of trusses may be undertaken from internal Read Pryda Technical Update TU26 for further information
wall top plates or from scaffold planks supported on on upgrading trusses to receive guardrail posts.
internal wall top plates provided:
• No person works closer than 1.5 metres to an external 1.9 TRUSS MODIFICATION OR REPAIR
wall, including gable end walls.
Trusses must not be modified on site without the prior
• No person is exposed to the risk of a fall into a stairwell written approval from the truss manufacturer.
or other void. The installer must report any damage, alterations or
• Planks are adequately supported across their spans. installation errors to the truss manufacturer immediately
and must not attempt to repair a truss without a
The allowable spans for timber planks are given in Table 1 rectification detail from the truss manufacturer.
of section 2.2 Appendix B of “Preventing Falls in Housing
Construction – Code of Practice – July 2012”. Laminated It must be noted that trusses and the type of damage
timber, aluminium and steel planks must be used in could vary immensely, and each repair should be treated
accordance with the manufacturer’s directions. on its merits. The truss installer must refrain from using
his prior knowledge or any ‘standard’ detail that he might
When trusses are erected at up to 600 mm centres, have.
persons working between the trusses to fix or brace them
can use the erected trusses as a form of fall protection
under controlled conditions as described below. If trusses 1.10 CONSTRUCTION LOADS
are erected at greater than 600 mm centres, refer to
Section 8.5 of this Code of Practice for suggested Extreme caution must be demonstrated when placing
methods of working safely at heights. construction loads on roof trusses. Stack only reasonable
amount of materials, by ensuring they are located along
Truss bottom chords are considered a safe working area external supports or directly over internal supports of a
for a competent person if all the conditions below are met. properly braced structure. Construction materials must not
If the person erecting trusses is to walk or work from the be placed at locations that will produce instability such as
bottom chords of the trusses, you should ensure that: ends of cantilevers or girder to girder connections, and
should not be dropped on trusses.
• Trusses are adequately braced to stabilise the structure.
If the bottom chord is used to support the person Failure to heed these recommendations could result in
erecting trusses, then it should be laterally restrained bodily injury and/or property damage.
by ties at a maximum 3000 mm centres (refer Section
3.6.2 for more details).
SUPPORTING
STRUCTURE
2.1 GENERAL 2.2 LOAD-BEARING WALLS
To ensure a satisfactory roof line on completion, the This is where the full load from the roof trusses is
supporting structure must be plumb, and the load supported on walls - generally the exterior perimeter walls,
bearing top plates must be level across the building. This but may occasionally also include some internal walls (eg
will ensure support heights are maintained level, and multiple span trusses).
consequently a level ceiling line is achieved.
2.2.1 Internal Support Walls
Care must be taken to ensure that the supporting
structure (walls, beams etc.) is adequately designed and If internal walls are required as supports, the truss
stable in its own right. itself and the layout shall be marked accordingly, and
this intention must be made very clear.
All trusses are to be fixed to the supporting structure with
appropriate fixings, typically Pryda Multigrips etc. The The installer shall ensure that trusses are orientated
selection of the fixing depends on the magnitude of the correctly when using internal walls as supports. The
support reaction (uplift) and the nature of the support. supporting structure, including footings, should be
Refer to Section 5 for details. checked by the builder to allow for this load. If the trusses
were provided a camber at the internal support locations,
COMMON PRYDA TIE-DOWN CONNECTORS
it is necessary to pack under the truss BC to ensure full
bearing, prior to loading.
2.3.1 Fixing Top Plates to Truss Bottom Chords of c) Non Bracing Wall with FastFix Internal Wall Screw
Non-Load Bearing Walls
Pryda FastFixTM Internal Wall Screw (IWS) laterally
a. Bracing Wall - Pryda Shear Connectors are used to stabilises the tops of internal walls by fixing them to the
transfer racking loads from truss bottom chords to the bottom chord of roof trusses.
bracing walls.
The head-less plain shank of the screw in the top
plate allows for vertical movement in the truss without
transferring load to the wall.
Points to check
POINTS TO CHECK:
TRUSS
INSTALLATION
3.1 GENERAL 3.3 LIFTING
The following recommendations are guidelines only, as Trusses must always be lifted in a manner that minimises
the details are the responsibility of the roof truss installers. lateral bending stresses. It is preferable that they be kept
Refer to AS4440-2004 for more detail. strapped in bundles until they are erected, as this reduces
the chances of damage.
3.2 SET OUT Trusses may be lifted either by crane or manually. The
choice will depend on the truss weight and wall height.
Prior to lifting any truss into place, it is often convenient They should be maintained in a vertical plane as much as
to mark out the truss locations on the top plate using the possible when being handled individually.
supplied truss layout for reference.
Trusses lifted by crane require slings or spreader bars
Girder and truncated girder trusses should be set out as shown in the diagrams. Where trusses are place
first as they have specific fixed locations. Dual purpose in bundles directly onto the top plate, it is imperative
trusses such as truncated girders / girders need special that they are supported by internal walls and that the
attention as they may appear similar to other trusses supporting structure is stable in its own right.
which must not be used accidentally instead.
CRANE CRANE
Standard trusses must then be set out, taking care not
to exceed the design spacing. Generally they would be <60
evenly set out over runs of similar trusses. But it is also <60
acceptable to space them at the design spacing and
have a closing gap smaller than this - adjacent to a more
heavily loaded truss, if possible.
GAUGING ROD
VERTICAL LIFTING OF TRUSSES – SPAN LESS THAN 9M
TRUSS SPACING
NAILS
VERTICAL CHAIN
OR SLING
GAUGING ROD
1/3 to 1/2 SPAN 1/3 to 1/2 SPAN
FIRST
TRUSS
Then the jacks are rotated into position and fixed to the
wall plates with SpeedTruss screws.
This instantly provides a stable hip end with the added 3.6 ERECTION BRACING AND
benefit that the TG is installed plumb with a high degree of TOLERANCES
accuracy.
As the trusses are erected, they must be braced
Once the hip section is installed then the additional longitudinally. This is to provide stability to the trusses
components of the hip end can easily be added and the during the erection process, and the bottom chord ties
standard trusses installed for the rest of the roof should be maintained in place after full installation is
completed.
3.4.2.2 For Hip ends and dutch gables installed
However, the temporary top chord ties may be removed
without SpeedTruss™ once the roof battens are adequately fixed in place.
On hip and Dutch gable roofs, start with the truncated
girder, apex girder or Dutch hip girder truss and brace it Refer to AS 4440-2004 for the full details for temporary
back to the corner of the building as shown. It is important bracing, however the following is a brief summary.
that this truss be correctly plumbed and aligned, as other
trusses must fit exactly up against it. TEMP BRACES ON TC
AT EACH PANEL POINT
(MAX. 3000 MM APART)
Where it is not feasible to install bracing of the first truss
in the manner described, the first two or three trusses
can be erected and cross-braced between them to form a
stable unit.
TEMP BRACES ON BC AT
EVERY MID-PANEL
(MAX. 3000 MM SPACING)
3.6.3 Tolerances
Trusses shall be installed straight and vertical and in their
correct positions.
TRUSS BOW
L (chord length)
BOW
TRUSS
L (chord length)
TRUSS
HEIGHT AT
ANY SECTION
OUT OF PLUMB
(LESSER OF 50MM
AND HEIGHT/50)
ROOF
BRACING
4.1 GENERAL 4.3 TOP CHORDS
The following recommendations allow for bracing of the All trussed roofs require diagonal bracing to the top
roof system only and assume that the walls are stable in chords, which is typically at an angle of 30-45 degrees
their own right. to the ridge line, measured on plan. Braces should be
installed such that each main truss has a brace on it.
Bracing of the trusses is essential to prevent buckling of
members (chords and some webs), and to provide overall Bracing is best located near the ends of buildings, and will
stability to the roof under all relevant loading conditions, be installed on both sides of the ridge line. Some typical
including wind uplift where members may reverse from examples are shown here, but full details are given in
being in tension to being in compression. AS4440-2004.
Care must be taken to ensure that all supporting structure 4.3.1 Speedbrace
bracing is in place prior to the trusses being installed.
The bracing shown here is Pryda Speedbrace which has
been specifically designed for this purpose and should be
4.2 BATTENS fixed with 35 x 3.15 Pryda Timber Connector nails.
The bracing of top chords is achieved via the overlying Bend brace over truss top chord
2 Nails to
and fix with 2 nails to top chord
battens or purlins. Battens are to be nailed to both outer and 3 nails to the face top chord
laminates of any multiple ply trusses eg, double girders.
Steelbrace
Top chord
Masonry wall
END FIXING DETAILS FOR STEEL BEAM FIXING DETAILS FOR BRICKWALL PLATE
REFER TO AS4440 FOR END FIXING DETAILS AND FIXING TO BRICK WALL PLATE.
4.4 BOTTOM CHORDS In addition to web ties, Pryda Web Stiffener, Tee-Stiffeners
or scabs may be also designed to brace webs.
Generally ceiling battens or ceiling fixed directly to the
underside of the bottom chords is sufficient to provide
lateral restraint against buckling.
TIMBER BLOCKS
FIXED IN LINE WITH
THE CHORDS FITTED
TIGHTLY BETWEEN
TRUSSES.
FIXING DETAILS TO BE
SIMILAR TO THE END OF CUT-
OFF OR MONO TRUSSES
Truss manufacturers may choose to form a truss in two segments, Top Hat Construction, often dictated by manufacturing
or transportation restrictions. This form of construction requires special consideration, especially bracing and lateral
restraints for horizontal top chord of the lower truss. Obtain further details from your truss manufacturer.
TRUSS
CONNECTIONS
5.1 SPEEDTRUSS SCREWS
SpeedTruss screws are pre-installed into the truss heel which makes the installation of these connections easy – just
drive the screw down until the head of the screw. makes good contact with the truss chord. Note: Do not over-drive the
screws –they do not need to be countersunk.
SPEEDTRUSS SCREW INSTALLED WITH THE SCREW HEAD IN GOOD CONTACT WITH THE TOP CHORD OF THE TRUSS. IF A SCREW
CANNOT BE INSTALLED FULLY INTO THE TOP PLATE, THEN CONTACT THE FABRICATOR THAT SUPPLIED THE TRUSSES FOR
GUIDANCE.
The hip end connections provided by Pryda Build software are similar to those in AS4440-2004, but they may not be
exactly the same, as every connection is designed specifically for the conditions at each site.
The requirements called up by Pryda Build take precedence over AS4440 or any other guideline. A document (Software
Update No. 7) is available to produce to certifiers if required.
JACK TC
TG HTC
Jack truss to truncated girder truss TG BC
TG BC
TG BC JACK BC DETAIL B1
JACK TC
Extended jack truss top chord to truncated TS HTC
standard trusses
CREEPER TC
CREEPER BC
Top chord – three effective flat-head 65 mm nails
through jack truss top chord into hip truss top chord WEB
HIP TC
HIP BC
PLUS one mitre plate with 3.15 x 35 mm Pryda CREEPER TC
SUPPORTING TRUSS
TOP CHORD
MIN. 35 X 45 TIMBER
LEDGER, OR BLOCK,
FIXED TO TOP CHORD
ALTERNATIVELY, ONE FRAMING
ANCHOR WITHOUT TIMBER LEDGE
STRUTTED OUTRIGGERS
OVERHANG
BLOCK
ZED SPROCKETS