Division 2: Earthworks Specifications
Division 2: Earthworks Specifications
College of Architecture
Submitted to:
Submitted by:
ARC 214
January 5, 2024
Exercise 3: Earthworks Specifications and Estimates
Site Clearing
Part 1: General
The work done under this consists of rubbish, debris, designated trees, brush, and
and items to remain after site clearing. All work should be performed to meet
uniform surface, making sure not to damage the materials or the uniform surface.
Excavate no further than the dimensions and elevations established, and do not
remove any material until the staking and cross sectioning of the site is complete.
All excavated materials should be used to build, subgrades, shoulders, and other
Part 2: Products
Materials
1. Tree protection
P a g e 2 | 11
Exercise 3: Earthworks Specifications and Estimates
Insulation)
3. Backhoe loader
Part 3: Execution
Preparation
construction activities.
construction.
the damaged vegetation. Remove any dense grass growth before stripping.
avoid soil erosion and the discharge of soil-bearing water runoff or airborne
requirements.
A. Remove any obstructions trees, shrubs, and other vegetation to make way
P a g e 3 | 11
Exercise 3: Earthworks Specifications and Estimates
be relocated.
Topsoil Stripping
B. Strip topsoil so that it does not mix with underlying subsoil or other waste
items.
materials, and waste materials, including waste and debris, from the
site.
Earth Moving
Part 1: General
Provide all personnel, materials, and equipment required to execute all work as
detailed on the Drawings. The works included in this section are excavating and
filling for rough grading the site, preparing subgrades for walks, pavements, turf
P a g e 4 | 11
Exercise 3: Earthworks Specifications and Estimates
and grasses and plants, subbase course for concrete walks and pavements,
subbase course and base course for paving, subsurface drainage backfill for walls
and trenches, and excavating and backfilling trenches for utilities and pits for
buried utility structures. Suitable fill from off-site if on-site amounts are insufficient
The work under this section comprises of executing all activities required to shape
the existing ground preparatory to the placement of the fill or surface material.
Grade trench bottoms accurately to give uniform bearing and support for each
section of pipe on undisturbed soil along its entire length. Make sure the pipe
subgrade has a smooth, uniform surface where the bedding material will be laid.
Excavation
dimensions are provided. Excavate the building pad to the stipulated dimensions
and depths in the approved site plan. Provide trenching and backfill for mechanical
and electrical work and utilities. Borrow materials are to be provided when off-site
suitable fill if on-site quantities are insufficient or undesirable, and legal off-site
disposal of excess fill. It must be ensured that the excavation does not extend
P a g e 5 | 11
Exercise 3: Earthworks Specifications and Estimates
enough to allow for the appropriate installation and removal of concrete forms or
Excavated trenches must be wide enough to allow for adequate pipe, conduit, or
cable laying, and banks must be sloped to meet current safety standards.
Fill
Ensure that the excavations and areas to be filled are clear of loose dirt, trash,
and standing water. Cobbles, boulders, and rock fragments whose biggest
dimension exceeds the allowed limitations for each type of fill (usually less than
75 mm for structural fill and 125 mm for general fill) are not permitted to be
incorporated into the fill. The Earthworks Contractor should consider removing big
fragments and sending them through a crusher unit to reduce their size to a
suitable grading.
Backfill
Excavated soil that is devoid of frozen material, stumps, roots, brush, other organic
matter, debris, and other objects. Place backfilled material above embedment
the thickness required to provide the prescribed backfill density or to meet other
regulatory criteria.
P a g e 6 | 11
Exercise 3: Earthworks Specifications and Estimates
Excess Excavation
Backfill any excavations taken that is wider than required specified for backfilling
and deeper than required with compacted material specified for backfilling.
Part 2: Products
- Excavator
- Trencher
- Loader
Geotextiles:
Materials:
stone.
P a g e 7 | 11
Exercise 3: Earthworks Specifications and Estimates
a dense state
Part 3: Execution
Preparation
Dewatering
prepared subgrades, and flooding the project site and surrounding region.
3. Surface water runoff should be diverted away from excavated areas. Allow
4. Excavate soil with a 0.6m diameter and 2.4m depth for shallow wells.
P a g e 8 | 11
Exercise 3: Earthworks Specifications and Estimates
Excavation
2. Excavate 300mm for the preparation of slab with 200mm topsoil thickness.
allow for sufficient drainage, and avoid stockpiling items within the drip line
of trees.
following:
P a g e 9 | 11
Exercise 3: Earthworks Specifications and Estimates
supported walls
bedding course to give continuous support for pipe bells, joints, and barrels,
6. Backfill voids with suitable soil while removing shoring and bracing. To
backfills under pipe haunches and with a 100mm allowance from pipes
uniformly up on both sides and along the whole length of piping or conduit.
Coordinate backfilling with utility testing. After that, place and compact final
ASTM D698:
for heavy equipment and no more than 100mm loose depth for hand
indicated
drainage.
P a g e 10 | 11
Exercise 3: Earthworks Specifications and Estimates
conduit
changes. Comply with compaction standards and grade to the given cross
*End of Section*
P a g e 11 | 11
Exercise 3: Earthworks Specifications Estimates
VOLUME TOTAL
EXCAVATION WIDTH LENGTH HEIGHT QTY.
(m3) VOLUME (m3)
SLAB
Slab 1 6.1 11.17 0.3 1 20.4411 20.4411
Total 20.4411
FOOTINGS
Footing (C1) 0.2 0.4 1.3 12 0.104 1.248
Total 16 1.768
GROUND BEAMS
Ground beam 1 0.2 10.7 0.9 1 1.926 1.926
Estimates Page 1 of 5
Exercise 3: Earthworks Specifications Estimates
Total 13 11.088
WALL FOOTINGS
Wall footing 1 0.4 10.7 0.1 1 0.428 0.428
Total 13 2.464
SEPTIC TANK
Septic Tank 3.9 1.88 2 1 14.664 14.664
Total 1 14.664
DEWATERING WELL
VOLUME TOTAL
RADIUS LENGTH QTY.
(m3) VOLUME (m3)
Dewatering well 1 0.3 2.4 1 2.71434 2.71434
Total 1 2.71434
TRENCHES
Estimates Page 3 of 5
Exercise 3: Earthworks Specifications Estimates
Trench 2 (Sewage
0.42 5 0.9 1 1.89 1.89
pipe)
Total 14 38.9718
Estimates Page 4 of 5
Exercise 3: Earthworks Specifications Estimates
Estimates Page 5 of 5