Structuring EPC Contracts - Commentary - Lexology
Structuring EPC Contracts - Commentary - Lexology
KHEM N. THADANI,
Introduction
Industry specifics
Risk allocation
Tax aspects
Comment
Introduction
industry specifics;
risk allocation;
tax aspects;
regulatory regime;
Industry specifics
Risk allocation
An employer often prefers to engage a contractor on a turnkey basis
due mainly to the single point of responsibility. This is quite prevalent in
the energy sector.
The allocation or breakup of the works has its risks in terms of timely
completion or delay, defects and application of the warranty obligations
with its consequent rectification.
The turnkey contractor must ensure that the various suppliers and sub-
contractors deliver timeously to enable integration and sequential
completion of the interdependent components, so that the critical path
is not jeopardised.
Tax aspects
These comprise both direct and indirect taxes together with payments
of similar effect (eg, import duties, levies and stamp duty).
Related taxes (eg, levies and stamp duty payable on a contract) need to
be properly ascertained and structured to accrue savings. In addition,
taxes at federal, state and local government levels need to be
considered and priced in or provided as a reimbursable item.
It is prudent to obtain tax advice if an EPC contract can allow for useful
savings in structuring the contract. Simultaneously a check list of all
taxes applicable under the EPC contract should be finalised. At the
same time the single point of responsibility should not be compromised
or reduced if an EPC contract is split for tax purposes.
The onshore portion will typically cover locally available skills (eg, for
civil works and locally sourced materials, parts and transportation). The
offshore portion comprises imported equipment, goods and services
that are intended for permanent incorporation. In structuring
onshore/offshore contracts it is necessary to have a "wrap or umbrella"
agreement to ensure that the single point responsibility,
notwithstanding the split, is not compromised.
Regulatory regime
The regulatory regime, at all levels, applicable to the energy sector can
be daunting and detailed.
On the other hand, codes (eg, the grid code for electricity and
standards), although couched as benchmarks, are intended to be
followed quite rigorously at times.
The notice to proceed will coincide with the date on which possession
to the site is handed over to the contractor. The completion certificate
will coincide with the taking over of the completed structure or facility
by the employer.
For site possession, it can be handing over of the entire site on a single
date or progressively of various parcels. If it is the latter, which is
common for highways and train systems, then it is common to have
completion and the take-over in stages but on a single date for final
completion.
For power plants with various blocks, the site possession is given all at
the same time but the takeover can be staggered over three, six or more
months. Hence, the effects of the following will each have to be
properly considered, structured and drafted accordingly:
transfer of title;
programme;
Then there is the technical aspect. This would include having the
various tests being successfully conducted and ready for processes
such as acceptance procedures, performance tests, acceptance tests,
and reliability runs. In this regard the certificate issued by the
independent checking engineer is critical as it is usually conclusive
evidence of satisfactory completion or otherwise. If otherwise, the
process for rectification and repetition to demonstrate completion
needs to be explicit.
Comment