Common Findings and Recommendation - Local Road Sector
Common Findings and Recommendation - Local Road Sector
COMMON DEFECTS,
FINDINGS AND
RECOMMENDATIONS OF
ROAD PROJECTS
Local Project Monitoring Committee
SESSION 7 COMMON FINDINGS AND RECOMMENDATIONS
Local Project Monitoring Committee
SESSION 7 COMMON FINDINGS AND RECOMMENDATIONS
SURFACE DEFECTS
Local Project Monitoring Committee
SESSION 7 COMMON FINDINGS AND RECOMMENDATIONS
Recommendations
CRACKING (PAGBIBITAK)
Longitudinal Cracks
(Pahaba)
Cracks that are predominantly parallel to the
pavement centerline
Possible causes
• Unsuitable materials were not removed
• The subbase/base course materials were not
incorporated
• The required degree of compaction of
subbase was not attained
• Poorly constructed subgrade and subbase
Local Project Monitoring Committee
SESSION 7 COMMON FINDINGS AND RECOMMENDATIONS
CRACKING (PAGBIBITAK)
Examples
Longitudinal Cracks
(Pahaba)
Recommendation
Remove and replace the affected
PCCP blocks
Local Project Monitoring Committee
SESSION 7 COMMON FINDINGS AND RECOMMENDATIONS
CRACKING (PAGBIBITAK)
Possible cause
• Late cutting of contraction joints or Weakened
Plane Joints (WPJ)
• Overload
• Failure of unstable foundations
No inspection, test results and
T i p s / M e as u res :
approval – “NO POURING”
Local Project Monitoring Committee
SESSION 7 COMMON FINDINGS AND RECOMMENDATIONS
Recommendation
CRACKING (PAGBIBITAK)
Possible cause
T i p s / M e as u res :
No inspection, test results and
approval – “NO POURING”
Local Project Monitoring Committee
SESSION 7 COMMON FINDINGS AND RECOMMENDATIONS
Recommendation
CRACKING (PAGBIBITAK)
Possible cause
• Late cutting of contraction joints or Weakened
Plane Joints (WPJ)
• Overload
• Failure of unstable foundations
Slide 16
Recommendation
SURFACE DEFECTS
Hairline / Temperature Cracks
A series of cracks in pavement blocks running either in
longitudinal or transverse direction. Cracks are shallow
and short.
Possible causes
Recommendation
Minor Scaling
Possible causes
Examples
SURFACE DEFECTS
Major Scaling
Deterioration of the upper slab surface of
more than *10 mm
Recommendations
*DPWH DO 41 s2016
Local Project Monitoring Committee
SESSION 7 COMMON FINDINGS AND RECOMMENDATIONS
Minor Scaling
Deterioration of the upper slab surface of
*10 mm or less
Recommendation
Possible cause
Recommendation
Pock Marks
are tiny holes in the pavement surface caused by
loss of aggregates or foreign materials such as
wood splits and dirty or soft aggregates from the
pavement surface.
Possible causes
Recommendation
Seal with concrete epoxy mortar
Local Project Monitoring Committee
SESSION 7 COMMON FINDINGS AND RECOMMENDATIONS
Recommendation
• Provide adequate warning signs, bollards, barricades,
construction caution tape, and watchmen all around
the concrete pavement
• Request households to restrain their pets during
concrete pouring
Corrections:
If the width and depth of marks are more than 1 cm,
seal all marks with concrete epoxy mortar / grout
Local Project Monitoring Committee
SESSION 7 COMMON FINDINGS AND RECOMMENDATIONS
SURFACE DEFECTS E x a m p le
Rain Damage Surface
Smooth, polished or glassy appearance associated
with damaged finished brooming of the completed
pavement surface.
Possible cause
Recommendation
Possible causes
Recommendations
• Ensure that the contractor provides equipment (concrete
saw cutter) on-site
• Ensure that the contractor has a designated project
engineer on-site to supervise the activity
Corrections:
Redo the cutting of PCCP joints with concrete saw to the required depth
of 50 mm (2”) to conform with specifications
Local Project Monitoring Committee
SESSION 7 COMMON FINDINGS AND RECOMMENDATIONS
Possible causes
Recommendations
OTHERS Examples
Possible causes
• Absence of concrete vibrator and screeder
• Poor or improper use of concrete vibrators
• Contractor has no project engineer on-site
to supervise the concrete pouring activity
• Over-size aggregates
Local Project Monitoring Committee
SESSION 7 COMMON FINDINGS AND RECOMMENDATIONS
OTHERS C o n c r e t e SVcibreraetdoerrs
Possible causes
• Absence of concrete vibrator and screeder
• Poor or improper use of concrete vibrators
• Contractor has no project engineer on-site
to supervise the concrete pouring activity
• Over-size aggregates
Local Project Monitoring Committee
SESSION 7 COMMON FINDINGS AND RECOMMENDATIONS
OTHERS
- Honeycombs (Ampaw)
Recommendations
Possible causes
Recommendations
Oversized aggregates
Oversized aggregates were noted on the stockpile
of aggregate base course materials
Possible causes
• Materials on the stockpiles were not
screened before delivery at the job site
Recommendations
• Ensure that the materials being delivered are in accordance with approved
plans and specifications with test results
• Handpick oversized aggregates on the stockpiled aggregate base course
• Screening
Local Project Monitoring Committee
SESSION 7 COMMON FINDINGS AND RECOMMENDATIONS
Recommendations
Recommendations
OTHERS E x a m p le
• Lush of vegetation
• Reshaping of road shoulders
• Road and Drainage clearing
Possible causes
Recommendations
• Vegetation control
• During DLP period contractor are still responsible on the
maintenance of completed roads prior to acceptance
Local Project Monitoring Committee
SESSION 7 COMMON FINDINGS AND RECOMMENDATIONS
NON-COMPLIANCE TO
CONSTRUCTION STANDARDS,
PLANS AND SPECIFICATIONS
Local Project Monitoring Committee
SESSION 7 COMMON FINDINGS AND RECOMMENDATIONS
No weakened plane
joints
Non-provision of road
shoulders
Major scaling
Local Project Monitoring Committee
SESSION 7 COMMON FINDINGS AND RECOMMENDATIONS
Non-provision of road
shoulders
Presence of
Longitudinal Cracks
Local Project Monitoring Committee
SESSION 7 COMMON FINDINGS AND RECOMMENDATIONS
Improper rectification
Local Project Monitoring Committee
SESSION 7 COMMON FINDINGS AND RECOMMENDATIONS
Tarpaulin: White,8 ft x 8 ft
Resolution: 70 dpi
Font: Helvetica
Font S ize: M ain Information – 3”
S ub – information – 1”
Font Color: Black
Slide 52
END OF SESSION 7
COMMON FINDINGS AND
RECOMMENDATIONS