0% found this document useful (0 votes)
436 views

Internship Report Full and Final Harsh

This document provides details about the author's internship at the 400kV receiving end substation in Jejuri, Maharashtra. It discusses the objectives of the internship, including learning about the working, maintenance, and operation of the substation. The author expresses gratitude to officials at the Maharashtra State Electricity Transmission Company for providing this learning opportunity. Key areas covered during the internship included arranging outages, maintaining logbooks, and understanding circuit breaker operation. The internship helped the author gain practical knowledge of electrical substation equipment and functions.

Uploaded by

Siddhesh Ghadge
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
436 views

Internship Report Full and Final Harsh

This document provides details about the author's internship at the 400kV receiving end substation in Jejuri, Maharashtra. It discusses the objectives of the internship, including learning about the working, maintenance, and operation of the substation. The author expresses gratitude to officials at the Maharashtra State Electricity Transmission Company for providing this learning opportunity. Key areas covered during the internship included arranging outages, maintaining logbooks, and understanding circuit breaker operation. The internship helped the author gain practical knowledge of electrical substation equipment and functions.

Uploaded by

Siddhesh Ghadge
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 35

Internship Report

MAHARASHTRA STATE ELECTRICITY


TRANS. CO. LTD.

A Internship Report submitted to the

SINHGAD TECHNICAL EDUCATION SOCIETY’S


NBN SINHGAD TECHNICAL INSTITUTES CAMPUS
Sr. No.: 10/1, Ambegaon (Bk), Pune – 411 041

In partial fulfillment of the requirement for the degree


of
Graduate Degree Course
in
ELECTRICAL ENGINEERING

Submitted by
Harshad H. Deshmukh
72219296H

Under the Guidance of


Prof. Sujit S. Jalkote
Professor, Department of Electrical Engineering

Department of Electrical Engineering


NBN Sinhgad School of Engineering, Ambegaon (Bk),
Pune-41
Academic Year: 2022-2023
Sinhgad Technical Education Society’s

NBN Sinhgad School of Engineering, Pune-41

CERTIFICATE
This is to certify that Harshad Harishchandra Deshmukh has successfully
completed an Internship in “MAHARASHTRA STATE ELECTRICITY TRANS.
CO. LTD.” Under my guidance, in the partial fulfillment of Bachelor of Engineering-
Electrical Engineering of Savitribai Phule Pune University.

Date:
Place:

Prof. Sujit S. Jalkote Name of Examiner


(Guide) External Examiner

Prof. S. S. Patil Dr. S. P. Patil


Head of Electrical Department Principal
NBNSSOE, Pune NBNSSOE, Pune

SEAL
DECLARATION

It is hereby declared that, an Internship in “MAHARASHTRA STATE ELECTRICITY

TRANS. CO. LTD.” is genuine work and it is not directly or indirectly copied from other
Internship report, resources, published work.
This is original and authentic work and has not been submitted earlier to other university for
entitlement of any degree by me or other and Internship report has not been from any book, journals
or website directly or indirectly.
The reference used in this report work do not violet state, country, international copy right act,
international property rights act and patent act, etc.

Sincerely,
Harshad H. Deshmukh

Date:
Place: Pune
ACKNOWLEDGMENT

It is indeed a great pleasure and moment of immense satisfaction for me to present an Internship in

“MAHARASHTRA STATE ELECTRICITY TRANS. CO. LTD.” amongst a wide


panorama that provided us inspiring guidance and encouragement, give the opportunity to thanks those who gave me
their indebted assistance. I wish to extend my cordial gratitude with profound thanks to our internal guide Prof. Sujit
S. Jalkote for his everlasting guidance. It was his/her inspiration and encouragement which helped me in completing
my internship report. My sincere thanks and deep gratitude to Head of Department, Prof. S. S. Patil and other faculty
members; but also to all those individuals involved both directly and indirectly for their help in all aspect of the
internship report. At last but not least I express my sincere thanks to our Institute’s Principal Dr. S.P. Patil for
providing us infrastructure and technical environment.

Harshad H. Deshmukh
ABSTRACT

A substation is a part of an electrical generation, transmission, and distribution system. Substations


transform voltage from high to low, or the reverse, or perform any of several other important
functions. Between the generating station and consumer, electric power may flow through several
substations at different voltage levels. A substation may include transformers to change voltage
levels between high transmission voltages and lower distribution voltages, or at the
interconnection of two different transmission voltages. Substations may be owned and operated by
an electrical utility, or may be owned by a large industrial or commercial customer. Generally,
substations are unattended, relying on SCADA for remote supervision and control.
In my industrial training in 400kV receiving end substation, Jejuri I gone through the working,
maintenance and operation of substation. First I got information about company history, types of
substation, machines installed and Facilities provided by industry
I would like to express my deep sense of gratitude and thanks to Mr. Rajendra Gaikwad (Chief
Engineer) , Mr. Prashant Chaudhary (HR)[MSETCL main office Rasta peth], Mr. Rupesh
Gaikwad (Executive Engineer)[400kV RS division Jejuri] for giving me this opportunity.
I would like to express my deep sense of gratitude and thanks to Mr. Anil Rakh , Mr. Kale
(Assistant Engineers ) , Mr. Nevase , Mr. Krishna Reddi (Maintenance Engineers) , 400kV RS
Division Jejuri . Without the wise counseled able guidance, it would have been impossible to
complete the report in this manner.
Content
Internship certificate i

Institute Certificate ii

Declaration iii

Acknowledgment iv

Abstract v

List of Figures vi

List of Tables vii

Nomenclature viii

1. Introduction 1

1.1 400kV Receiving End Substation Jejuri 3

1.2 400kV Receiving End Substation Jejuri Single Line Diagram 6

1.3 Transmission Substation 7

1.4 400kV / 220kV Bus System 9

2. Problem Identification 11

3. Methodological details 14

3.1 Arranging An Outage. 14

3.2 Logbook 16

3.3 Circuit Breaker 20

4. Conclusion 22

5. Future Plan 23

6. Attendance Record 24

7. List of reference 25
List of Figures

2.1 400kV receiving end substation jejuri 3

3.1 Single Line Diagram of 400 kV substation 6

4.1 400kV 11 Breaker System 7


2

5.1 Live monitoring of readings 9

5.2 400kV Main Bus I 10

6.1 RTU IED panel 11

6.2 Permit Issue Sign 13

7.1 Maintenance of ICT 15

8.1 SF6 Circuit Breaker 20


List of Tables

2.1 Incoming 400kV Lines 4

2.2 Outgoing 220kV Lines 5

5.1 Lines connected to 220 kV Bus system 10

11.1 Attendance Record 24


Nomenclature

LA Lightning Arrestor

CVT Capacitor Voltage Transformer

WT Wave Trap

LE Isolator with Earthing Switch

29 (A/B/C/D) Isolator

52 / CB Circuit Breaker

CT Current Transformer

ICT Interconnecting Transformer

TBC Transfer Bus Coupler

PLCC Power Line Carrier Communication

RTCC Remote Tap Changer Control

NIFPS Nitrogen Injected Fire Protection System

DG Diesel Generator

RTU Remote Telemetric Unit

IED Intelligent Electronic Device

ACSR Aluminum Conductor Steel Reinforced


CHAPTER 1: INTRODUCTION
Maharashtra State Electricity Transmission Company (abbreviation: Mahapareshan
Mahatransco or M.S.E.T.C.L) is a public sector company wholly owned by the
Government of Maharashtra.

Mahapareshan Company came into existence in June 2005 after the reorganization of the
erstwhile Maharashtra State Electricity Board. Mahapareshan Company is responsible for
the transmission of electricity from the place of generation to the distribution center. For
this Mahapareshan Company was formally constituted. Mahapareshan Company is
working on various measures to ensure safe transmission of electricity, minimum loss of
electricity and balanced load.

For this, Mahapareshan has set up a comprehensive transmission system in the state. This
involves the use of power lines of various capacities, their towers, poles, etc. It also
includes the construction of transformers, power receiving stations, power substations,
etc. at various places to convert electricity into loads and maintenance of all of them,
establishing offices for management, training centers for employees, etc. Considering all
these aspects, Mahapareshan has become the largest state transmission company
providing transmission services in the whole of India. Today, the total length of power
lines of Mahapareshan Company is a whopping 46217.90 circuit kilometers. 1 lakh 4
thousand 377 m along with the number of 660 ultra high capacity power substations of
the company. that. A. This is the transmission capacity.

Through this infrastructure service, Mahapareshan Company is continuously doing the


work of electricity (conduction) transmission throughout Maharashtra. It also provides
services in neighboring states of Maharashtra state. To keep this entire system working,
Mahapareshan has 2 load dispatch centers 559 etc. in its jurisdiction in the state of
Maharashtra. H. V. Sub- centres, reception centres, offices under seven circles, circles,
departments, construction departments, warehouse centers, telecommunication

1
departments, training centers etc. are functioning. The company manages and maintains
this system. Also, the company is planning expansion plans and implementing them by
predicting the future increasing power generation and the needs of the public.

High Voltage Direct Current (HVDC) Scheme-


One of the unique features of Mahapareshan Company is that Mahapareshan Company is
the only State Government owned High Voltage Direct Current System in the country.
The company is successfully operating 46217.90 circuit km long bi polar power
transmission system from Chandrapur in eastern Maharashtra to Padghe near Mumbai.
The capacity of this system is 3582 May. and A 500 kV bipolar is as big as it is.
Successful operation of this system is one of the hallmarks of Mahapareshan Company's
work. Because there are coal mines in the eastern part of Maharashtra, coal which is the
main means of power generation is easily available there. Therefore, there are power
generating stations at Chandrapur, Koradi, Khaparkheda. The highest demand and
consumption of electricity is in Mumbai- Pune- Nashik area. Electricity is increased in
this demand area. Transmission loss of electricity during transmission in ultra high
current system is minimal. So the amount of electricity is sent from Chandrapur. About
the same amount of electricity is coming here.
Dispatch Centers

Operation, monitoring and control of power transmission system is done through load
dispatch center. This center is the heart of the transmission system. Kalwa near Mumbai
and Ambazari at Nagpur are State Despatch Centers of Mahapareshan Co. The work of
despatch center is fully computerized. Also, the latest technology is used there.

2
CHAPTER 2: 400KV RECEIVING END
SUBSTATION JEJURI

Fig 2.1: 400kV receiving end substation jejuri

Address : 400KV R.S. (O&M) Div. Jejuri. A/P: Jejuri. Tal: Purandhar Dist: Pune,

Pincode-412303

e-mail: [email protected]

Receiving end voltage - 400kV

Sending end voltage – 220kV

Auxiliary load voltage – 33kV , 22kV (Jejuri/Saswad) , Diesel Generator 100 KVA

3
Transformer ratings –

1. ICT 501MVA 400/220/33kV ICT I

2. ICT 501MVA 400/220/33kV ICT II

3. ICT 501MVA 400/220/33kV ICT III

Capacity of substation – 1503 MVA

Table 2.1: Incoming 400kV Lines

Incoming Lines Date of Line length Type of Conductor


Commission

1. 400kV Jejuri 31/10/2004 47.5 km 0.5 ACSR twin conductor


– Lonikand I
(substation)

2. 400kV Jejuri 04/11/2022 50 km 0.5 MOOSE twin conductor


– Lonikand II
(substation)

3. 400kV Jejuri 03/11/2022 136.18 km 0.5 MOOSE twin conductor


– Karad
(substation)

4. 400kV Jejuri 31/10/2004 171.5 km 0.5 ACSR twin conductor


– Koyana
(hydro-power
plant)

4
Table 2.2: Outgoing 220kV Lines

Outgoing Lines Date of Line length Type of Conductor


Commission

1. 220kV Jejuri 20/01/2005 38 km 0.4 ACSR


–Phursungi I conductor
(substation)

2. 220kV Jejuri 16/06/2011 37.4 km 0.4 ACSR


- Phursungi conductor
II
(substation)

3. 220kV Jejuri 16/06/2011 36.5 km 0.4 ACSR


– Kondhwa conductor
(GIS gas
insulated
substation
SF6)

4. 220kV Jejuri 27/01/2005 55.15 km 0.4 ACSR


– Baramati I conductor
(substation)

5. 220kV Jejuri 20/01/2005 7.015 km 0.4 ACSR


– Jejuri I conductor
(220kV
substation)

6. 220kV Jejuri 27/01/2005 8.318 km 0.4 ACSR


- Jejuri II conductor
(220kV
substation)

5
CHAPTER 3:400KV RECEIVING END SUBSTATION JEJURI
SINGLE LINE DIAGRAM

Fig 3.1: Single Line Diagram of 400 kV substation

6
CHAPTER 4:TRANSMISSION SUBSTATION
A transmission substation connects two or more transmission lines. The simplest case is where
all transmission lines have the same voltage. In such cases, substation contains high-voltage
switches that allow lines to be connected or isolated for fault clearance or maintenance. A
transmission station may have transformers to convert between two transmission
voltages, voltage control/power factor correction devices such as capacitors, reactors or static
VAR compensators and equipment such as phase shifting transformers to control power flow
between two adjacent power systems.
Transmission substations can range from simple to complex. A small "switching station" may be
little more than a bus plus some circuit breakers. The largest transmission substations can cover a
large area (several acres/hectares) with multiple voltage levels, many circuit breakers, and a
large amount of protection and control equipment
(voltage and current transformers, relays and SCADA systems).

𝟏
Fig 4.1: 400kV 1 Breaker System
𝟐

7
COMPONENTS USED IN SUBSTATION
1. Isolator -It is a no load switch (air arc quench)
2. CVT Capacitive voltage transformer – It measures line voltage. Only frequency
signal will be passed through CVT as it is ahigh pass filter only 5kHz frequency carrier
signal will be passed
3. WT Wave Trap- It is a low pass filter . It will only pass low Frequency power signal
and block high frequency carrier signal .
4. LA Lightning Arrestor – It protects components from lightning strikes. LA are at
the start and end of substation and before and after ICT . It has resistance up to 440kV
if surge voltage above 440kV is present LA will send the extra voltage to ground.
5. ICT Interconnecting Transformer - Transformer used for between EHV transmission
lines are called as interconnecting transformer.
6. NIFPS Nitrogen Injected Fire Protection System – If a fault takes place in main tank
of ICT and oil catches fire this system will drain 10% oil and N 2 nitrogen gas is injected
in transformer to extinguish fire.
7. RTCC Remote Tap Changer Control – 3x167MVA 17 tapping are provided in ICT
RTCC selected middle 9th tap for desired output
8. Earthing Switch – Protection device to ground emf generated in CB while opening
the circuit and protect workers from getting shock while performing maintenance
9. CB Circuit Breaker – It is on load switch as it has quenching medium SF6 gas is present
10. RTU Remote Telemetric Unit
11. IED Intelligent Electronic Device
12. Battery Room – 2V x110 series to store DC power
13. Control panel- control all operations, displays detected errors ,display readings .runs on
DC power as AC power cannot be stored to used in backup.
14. CT Current Transformer - series connected transformer used to measure current
15. PT potential Transformer – transformer used to measure voltage
16. Conductor- 0.4 ACSR ,0.5 ACSR Twin,0.5 MOOSE Twin conductors
17. Insulator- Suspension (tension 120kN),Strain (tension 60kN)

8
CHAPTER 5: 400kV / 220kV BUS SYSTEM

Fig 5.1: Live monitoring of readings

400Kv 1𝟏 Breaker System - 3 circuit breakers per phase are used between 2 main buses
𝟐

Components Quantity
Main Bus (I,II) 2
Isolators per phase 6
Current Transformer per phase 5
Circuit Breaker per phase 3
Isolator with earthing switch per phase 6
Single Phase SYN CVT per phase 1
Total number of Bays 13

220kV 3 bus system ( Main bus I, II, Auxiliary)

Components Quantity
Main Bus (I,II , Auxiliary) 3
Isolators per phase 4
Circuit Breaker per phase 1
Potential Transformer 2
Isolator with earthing switch per phase 1

9
Table 5.1: Lines connected to 220 kV Bus system
220kV Main Bus I 220kV Main Bus II
1. Jejuri I Jejuri II
2. Phursungi I Phursungi II
3. Kondhwa Baramati
4. ICT II ICT I
5. ICT III

Fig 5.2: 400kV Main Bus I

10
CHAPTER 6: PROBLEM IDENTIFICATION

1. Line compensation (Load Management)-


Transmission lines have to transfer power with voltage drop less than 10 %. Most of the loads
connected to the system absorbs positive (lagging) VARs .The flow of reactive power in a
transmission line causes voltage drop. Also it increases I2R losses.

The maximum VARs transferred over the line are fixed by the voltage profile. At the time of peak loads, the
VAR demand of load exceeds the maximum VAR limit specified. Due to this the system voltage at some of
the buses becomes lower than nominal voltage. Hence the additional equipment is connected to the system
which can generate lagging VAR to meet the reactive power requirement of load and maintain the voltage at
various buses within specified limits.
During light loads the lagging VAR produced by lines are much more than required by loads. The
additional equipment provided to absorb or generate VARs is called as reactive power
compensating equipment.

The supply voltage must be with range of 380kV to 420kV if supply voltage goes beyond this range
the substation must inform to LDC (Load Dispatch Center) to take required action for line
compensation and prevent load shading.

A daily hourly reading log sheet is maintained to record all readings of the substation. These
readings are also send to LDC at Kalwa Mumbai by fiber optic.

Fig 6.1: RTU IED panel

11
Balancing Of Load (Methods For Line Compensation):
Active power is from supply. Reactive power is from capacitor bank.

Generator supplies active power. Generator is used in condenser mode to increase reactive power

During over voltage condition-

I. Reactor Bank
II. Inductive
mode of generator During under

voltage condition-

I. Capacitor Bank
II. Condenser mode of generator

LTS – Load Trimming Scheme :

Automatically load is cut at 370kV. Load shading is done when supply voltage goes below
370kV as supply should be ±10% of 400kV to prevent tripping of grid generator and avoid
blackout. Load forecasting and scheduling of load is performed for easier load balancing.
Distribution company gives demand schedule and generation company gives generation
schedule to LDC (Load Dispatch Center). A block of 15 minutes is forecasted using these
schedules.

12
1. Outage for maintenance –
Maintenance is performed on Thursday and when fault has occurred in an equipment or in
transmission line.

Example of faults that may occur –

I. Tripping of circuit breaker due to fault in transmission line which is detected by relay
system. (breaking of conductor, short circuited due to external object, etc)
II. Temperature sensors not working properly (not able to detect change in temperature).
III. Fire in main tank of transformer.
IV. Cracking of insulator in lightning arrestor
V. Breaking of insulator

Outages is required for maintenance to be performed on equipment like ICT and CB.
Maintenance is also performed on connectors of isolators and earthing switches , main bus ,
isolators of main bus but these maintenance can be performed without taking outage instead
complete supply is transferred to other main bus.
When maintenance is performed a permit must be issued for working on the equipment or
transmission line for both receiving and sending end. This permit is issued by LDC by giving
same password to both ends which is not public. The permit issue time must be reported to LDC
from both ends. The permit ensures that outage has be performed and the line and equipment is
safe for workers to work safely. After the maintenance is completed successfully the circuit
must be reclosed to operate. The reclosing of circuit takes place after matching the passwords on
both ends of transmission. The reclosing time must be reported to LDC.

Fig 6.2: Permit Issue Sign

13
CHAPTER 7: METHODOLOGICAL DETAILS

ARRANGING AN OUTAGE.
The party requiring an outage on equipment (equipment include lines) should send a monthly
proposal to Ex. Engineer of R.S. (O&M) Division well in advance With the following details.

1. Equipment on which outage is required. Nature of work and its exact location.

2. Name of the working party/parties.


3. Date. time and duration of the outages.
4. Time to clear the equipment for service in case of emergency.
5. Any special request etc
6. Area affected with alternative arrangement if any for the same.

The outage will be arranged by the E.E. R.S.0&M Dn. in consultation with S.E.
EHV/T'CC/C.E.-Load Des patch center. Kalwa. Ex. Engr. (0&M) of the area that will be effected by
the outage. A message approving the outage shall be sent to all parties concerned two days in advance
with details under 1 to 7 above by the concerned

Steps to perform outage –

1. Open circuit breaker


2. Current is checked to be zero
3. Isolator is opened
4. Earthing switch is closed to ground emf generated during opening of CB.
5. Perform maintenance

For reclosing the circuit perform above steps backwards.

14
Fig 7.1: Maintenance of ICT

15
LOGBOOK
MAHARASHTRA STATE ELECTRICITY

TRANSMISSION COMPANY LTD.

400/220 KV RECEIVING STATION, JEJURI, TAL: Purandar

DIST: PUNE PIN: 412303

S/S Commissioned On Dt.: 31.10.2004

(CODE NO.) ZONE: 6000 CIRCLE: 6100 DIVISION: 6160 S/S CODE: J454

DAILY HOURLY READING LOG SHEET

Date: ……………….. Day: ………………..

Designation Shift A Shift B Shift C General


00:00 to 08.00 Hrs
08:00 to 16.00 Hrs 16.00 to 24.00 Hrs

Add. Ex. Engr.


Signature Name
Assistant
Engineer
Signature Name

Art'A’
Signature Name

Jr. Technician

Signature Name

Executive Engineer

400 KV RS. Jejuri

400 KV RECEIVING STATION JEJURI

16
Date: …………………

DAILY LOG SHEET

220KV ICT-I (IV SIDE) (CTR : 2400/1)


DOC: 03.01.2005, 501 MVA BHEL Make, Sr. No. : R-6005924/Y-21/B-28, IV Cap. : 1314 Amp
TIME AMP MW MVAR PF KV
01.00
.
24.00
220KV ICT-I (IV SIDE) (CTR : 2400/1)
DOC: 20.01.2010, 501 MVA CGL Make, Sr. No. : R-T09542/1,Y-2,B-3, IV Cap. : 1314 Amp
TIME AMP MW MVAR PF KV
01.00
.
24.00
220KV ICT-I (IV SIDE) (CTR : 2400/1)
DOC: 16.05.2018, 501 MVA ALSTOM Make, Sr. No. : R-B30726,Y-27,B-28, IV Cap. : 1314
Amp
TIME AMP MW MVAR PF KV
01.00
.
24.00
220 KV PHURSUNGI - I LINE
DOC: 20.01.2005, LINE LENGTH: 38 Km, 0.4 ACSR CONDUCTOR, CTR: 800/1
TIME AMP MW MVAR PF KV
01.00
.
24.00
220 KV BARAMATI LINE
DOC: 27.01.2005, LINE LENGTH: 55.15 Km, 0.4 ACSR CONDUCTOR, CTR: 800/1
TIME AMP MW MVAR PF KV
01.00
.
24.00
220 KV JEJURI - I LINE
DOC: 20.01.2005, LINE LENGTH: 7.015 Km, 0.4 ACSR CONDUCTOR, CTR: 800/1
TIME AMP MW MVAR PF KV
01.00
.
24.00

17
220 KV JEJURI - II LINE
DOC: 27.01.2005, LINE LENGTH: 8.318 Km, 0.4 ACSR CONDUCTOR, CTR: 800/1
TIME AMP MW MVAR PF KV
01.00
.
24.00
220 KV PHURSUNGI - II LINE
DOC: 16.06.2011, LINE LENGTH: 37.4 Km, 0.4 ACSR CONDUCTOR, CTR: 800/1
TIME AMP MW MVAR PF KV
01.00
.
24.00
220 KV KONDHWA GIS LINE
DOC: 16.06.2011, LINE LENGTH: 36.5 Km, 0.4 ACSR CONDUCTOR, CTR: 800/1
TIME AMP MW MVAR PF KV
01.00
.
24.00
220 KV BUS – COUPLER
DOC : 20.01.2005, CTR : 2400/1
TIME AMP MW MVAR PF
01.00
.
24.00
ICT – I TEMPERATURE
TIME R Phase Y Phase B Phase
Sr. No. : 6005924 Sr. No. : 6005921 Sr. No. : 6005923
OT HV IV LV OT HV IV LV OT HV IV LV
01.00
.
24.00
ICT – II TEMPERATURE
TIME R Phase Y Phase B Phase
Sr. No. : T 09542/1 Sr. No. : T 09542/2 Sr. No. : T 09542/3
OT HV IV LV OT HV IV LV OT HV IV LV
01.00
.
24.00
ICT – III TEMPERATURE
TIME R Phase Y Phase B Phase
Sr. No. : B30726 Sr. No. : B30727 Sr. No. : B30728
OT HV IV LV OT HV IV LV OT HV IV LV

18
01.00
.
24.00
DOC : 31.03.2006, 167 MVA BHEL Make, Sr. No. : R - 6005922
SPARE ICT Ambient Control
TIME TEMPERATURE Temp Room
OT HV IV LV AMP IMP Temp
KMWH
01.00
.
24.00
BUS READING
TIME 400KV Bus Voltage 220KV Bus Voltage Frequency
Bus 1 Bus 2 Bus 1 Bus 2
01.00
.
.
24.00
BATTERY CHARGER READINGS
Particulars 220 V DC CHARGER 48 V DC CHARGER
Source - I Source - II
TIME 9.00 Hrs. 17.00 Hrs. 9.00 Hrs. 17.00 Hrs. 9.00 Hrs. 17.00 Hrs.
V (AC)
V (DC)
AMP
(Main)
DC (Load)
Charging /
Discharging
Charger
Position
Float/Boost
DC EARTH
LEAKAGE

19
CHAPTER 8: CIRCUIT BREAKER

Gas Circuit Breaker

Type – 400 SFM 40A

Rated Lightning impulse withstand voltages


1425 kV

Rated short circuit making current 100 kA

Rated operating pressure – 15.5 kg/cm 2

First pole to clear factor – 1.3

Rated duration of short circuit current – 40kA


3 secs

Switching impulse voltage 1050 kV

Rated line charging current – 600A

Gas pressure lockout at 5.0 Kg/cm2 (at 20oC)

Gas pressure alarm at 5.5 Kg/cm 2(at 20oC )

Gas weight – 45 Kg
Fig 8.1: SF6 Circuit Breaker
Gas – SF6 sulfur hexa flouride

SR. No. : 16622C

Rated voltage – 420 kV

Rated frequency – 50 Hz

Rated normal current – 2000 A

Rated closing voltage – 220 V DC

Rated opening voltage – 220 V DC

Rated gas pressure – 7 Kg/cm2 (at 20oC)

Rated voltage and frequency for AUX. circuit – 415 V AC 50 Hz

Total weight with gas (w/o PIR) – 7950 Kg

20
Out of Phase breaking current – 10kA

Rated operating sequence - 0-0.3s CO-3MIN.CO

Air pressure lockout – At 12.0 Kg/cm2

Air pressure alarm – At 13.2 Kg/cm2


Year 2002

SID IEC 56-1992

14-15 bar air pressure is maintained

LBB/BFR – (200 ms)

Breaker Failure Relay

Local Breaker Backup Protection

Manual tripping time – 150 ms

Automatic tripping time-

0 to 80 km zone 1 instantenous protection (1 cycle = 20ms)

Zone 2 – 400 ms protection

Zone 4 – 500 ms protection

Maintenance –

220 kV , 400kV breakers once in 2 years

21
CHAPTER 9: CONCLUSION

From above industrial training we have learned the working ,equipment and operation of receiving
end substation. We also learned the steps for taking an outage to perform maintenance and give
permits to work on transmission line , maintaining of logbook of readings(like voltage ,
current ,temperature , etc) to record the performance of substation and equipment used in it.

We got deep knowledge of EHV transmission lines and components used in a substation like CB,
ICT, CT, PT, Battery room, AC DC room, CVT, WT, Earthing switch, conductor, insulator, PLCC,
RTCC, etc.

22
CHAPTER 10: FUTURE PLAN
In the next 5 years, Mahapareshan aims to create a robust power transmission structure keeping in
view the growth in power generation and demand. The company has undertaken an ambitious
capacity expansion plan for the year 2015-16. From it evacuation of electricity generated in the power
generation center and through a powerful power transmission network (Grid).
Reaching every nook and cranny of Maharashtra will fulfill these needs. Mahapareshan made a
preliminary estimate and accordingly maintained the system
A policy of improvement has been decided. This has greatly reduced the incidence of power outages.
of Mahapareshan's power grid
Availability has improved to 99.73 percent (HVAC) and 99.30 percent (HVDC). Measures
for value creation and cost containment
Mahapareshan Company has focused on creating value and limiting costs in its operations. The
following measures for this have done
 ABT meters have been installed for energy accounting at 530 power sub- stations of
Mahapareshan. In important departments online works are done using computer and information
technology. For that ERP Integrated Computer The system uses –
 Existing infrastructure for universal connectivity consists of 2801 km long optical fiber cable
system An effective communication system is being introduced using fiber cable system.
Mahapareshan has tried to start unmanned and remote control power substations on pilot
basis. Efforts are underway to set up Gas Insulated Power Substations (Gas Insulated 5/5 - G/
5) at Bhandup (near Mumbai) and Hinjewadi (near Pune).
 Renovation of State Load Despatch Centers at Kalwa and Ambazari for modernization of 140
SCADA- RTUs. That is, supervision Control and data storage and Remote Terminal Unit
RTO are used.An ambitious project to set up a power substation with a huge capacity of 765
KV has been started at Auragabad.
 Equity Capital will create a Mahapareshan (P.O. i.e. Initial Public Offering) to raise funds
from the open market to raise capital expenditure.

23
CHAPTER 11: ATTENDANCE RECORD

Date Day
10/2/2023 Friday
11/2/2023 Saturday
16/2/2023 Thursday
18/2/2023 Saturday
24/2/2023 Friday
25/2/2023 Saturday
03/3/2023 Friday
04/3/2023 Saturday
10/2/2023 Friday

24
CHAPTER 12: LIST OF REFERENCE

[1] https://www.mahatransco.in/

[2] TechKnowledge Power System – II

25

You might also like