Internship Report Full and Final Harsh
Internship Report Full and Final Harsh
Submitted by
Harshad H. Deshmukh
72219296H
CERTIFICATE
This is to certify that Harshad Harishchandra Deshmukh has successfully
completed an Internship in “MAHARASHTRA STATE ELECTRICITY TRANS.
CO. LTD.” Under my guidance, in the partial fulfillment of Bachelor of Engineering-
Electrical Engineering of Savitribai Phule Pune University.
Date:
Place:
SEAL
DECLARATION
TRANS. CO. LTD.” is genuine work and it is not directly or indirectly copied from other
Internship report, resources, published work.
This is original and authentic work and has not been submitted earlier to other university for
entitlement of any degree by me or other and Internship report has not been from any book, journals
or website directly or indirectly.
The reference used in this report work do not violet state, country, international copy right act,
international property rights act and patent act, etc.
Sincerely,
Harshad H. Deshmukh
Date:
Place: Pune
ACKNOWLEDGMENT
It is indeed a great pleasure and moment of immense satisfaction for me to present an Internship in
Harshad H. Deshmukh
ABSTRACT
Institute Certificate ii
Declaration iii
Acknowledgment iv
Abstract v
List of Figures vi
Nomenclature viii
1. Introduction 1
2. Problem Identification 11
3. Methodological details 14
3.2 Logbook 16
4. Conclusion 22
5. Future Plan 23
6. Attendance Record 24
7. List of reference 25
List of Figures
LA Lightning Arrestor
WT Wave Trap
29 (A/B/C/D) Isolator
52 / CB Circuit Breaker
CT Current Transformer
DG Diesel Generator
Mahapareshan Company came into existence in June 2005 after the reorganization of the
erstwhile Maharashtra State Electricity Board. Mahapareshan Company is responsible for
the transmission of electricity from the place of generation to the distribution center. For
this Mahapareshan Company was formally constituted. Mahapareshan Company is
working on various measures to ensure safe transmission of electricity, minimum loss of
electricity and balanced load.
For this, Mahapareshan has set up a comprehensive transmission system in the state. This
involves the use of power lines of various capacities, their towers, poles, etc. It also
includes the construction of transformers, power receiving stations, power substations,
etc. at various places to convert electricity into loads and maintenance of all of them,
establishing offices for management, training centers for employees, etc. Considering all
these aspects, Mahapareshan has become the largest state transmission company
providing transmission services in the whole of India. Today, the total length of power
lines of Mahapareshan Company is a whopping 46217.90 circuit kilometers. 1 lakh 4
thousand 377 m along with the number of 660 ultra high capacity power substations of
the company. that. A. This is the transmission capacity.
1
departments, training centers etc. are functioning. The company manages and maintains
this system. Also, the company is planning expansion plans and implementing them by
predicting the future increasing power generation and the needs of the public.
Operation, monitoring and control of power transmission system is done through load
dispatch center. This center is the heart of the transmission system. Kalwa near Mumbai
and Ambazari at Nagpur are State Despatch Centers of Mahapareshan Co. The work of
despatch center is fully computerized. Also, the latest technology is used there.
2
CHAPTER 2: 400KV RECEIVING END
SUBSTATION JEJURI
Address : 400KV R.S. (O&M) Div. Jejuri. A/P: Jejuri. Tal: Purandhar Dist: Pune,
Pincode-412303
e-mail: [email protected]
Auxiliary load voltage – 33kV , 22kV (Jejuri/Saswad) , Diesel Generator 100 KVA
3
Transformer ratings –
4
Table 2.2: Outgoing 220kV Lines
5
CHAPTER 3:400KV RECEIVING END SUBSTATION JEJURI
SINGLE LINE DIAGRAM
6
CHAPTER 4:TRANSMISSION SUBSTATION
A transmission substation connects two or more transmission lines. The simplest case is where
all transmission lines have the same voltage. In such cases, substation contains high-voltage
switches that allow lines to be connected or isolated for fault clearance or maintenance. A
transmission station may have transformers to convert between two transmission
voltages, voltage control/power factor correction devices such as capacitors, reactors or static
VAR compensators and equipment such as phase shifting transformers to control power flow
between two adjacent power systems.
Transmission substations can range from simple to complex. A small "switching station" may be
little more than a bus plus some circuit breakers. The largest transmission substations can cover a
large area (several acres/hectares) with multiple voltage levels, many circuit breakers, and a
large amount of protection and control equipment
(voltage and current transformers, relays and SCADA systems).
𝟏
Fig 4.1: 400kV 1 Breaker System
𝟐
7
COMPONENTS USED IN SUBSTATION
1. Isolator -It is a no load switch (air arc quench)
2. CVT Capacitive voltage transformer – It measures line voltage. Only frequency
signal will be passed through CVT as it is ahigh pass filter only 5kHz frequency carrier
signal will be passed
3. WT Wave Trap- It is a low pass filter . It will only pass low Frequency power signal
and block high frequency carrier signal .
4. LA Lightning Arrestor – It protects components from lightning strikes. LA are at
the start and end of substation and before and after ICT . It has resistance up to 440kV
if surge voltage above 440kV is present LA will send the extra voltage to ground.
5. ICT Interconnecting Transformer - Transformer used for between EHV transmission
lines are called as interconnecting transformer.
6. NIFPS Nitrogen Injected Fire Protection System – If a fault takes place in main tank
of ICT and oil catches fire this system will drain 10% oil and N 2 nitrogen gas is injected
in transformer to extinguish fire.
7. RTCC Remote Tap Changer Control – 3x167MVA 17 tapping are provided in ICT
RTCC selected middle 9th tap for desired output
8. Earthing Switch – Protection device to ground emf generated in CB while opening
the circuit and protect workers from getting shock while performing maintenance
9. CB Circuit Breaker – It is on load switch as it has quenching medium SF6 gas is present
10. RTU Remote Telemetric Unit
11. IED Intelligent Electronic Device
12. Battery Room – 2V x110 series to store DC power
13. Control panel- control all operations, displays detected errors ,display readings .runs on
DC power as AC power cannot be stored to used in backup.
14. CT Current Transformer - series connected transformer used to measure current
15. PT potential Transformer – transformer used to measure voltage
16. Conductor- 0.4 ACSR ,0.5 ACSR Twin,0.5 MOOSE Twin conductors
17. Insulator- Suspension (tension 120kN),Strain (tension 60kN)
8
CHAPTER 5: 400kV / 220kV BUS SYSTEM
400Kv 1𝟏 Breaker System - 3 circuit breakers per phase are used between 2 main buses
𝟐
Components Quantity
Main Bus (I,II) 2
Isolators per phase 6
Current Transformer per phase 5
Circuit Breaker per phase 3
Isolator with earthing switch per phase 6
Single Phase SYN CVT per phase 1
Total number of Bays 13
Components Quantity
Main Bus (I,II , Auxiliary) 3
Isolators per phase 4
Circuit Breaker per phase 1
Potential Transformer 2
Isolator with earthing switch per phase 1
9
Table 5.1: Lines connected to 220 kV Bus system
220kV Main Bus I 220kV Main Bus II
1. Jejuri I Jejuri II
2. Phursungi I Phursungi II
3. Kondhwa Baramati
4. ICT II ICT I
5. ICT III
10
CHAPTER 6: PROBLEM IDENTIFICATION
The maximum VARs transferred over the line are fixed by the voltage profile. At the time of peak loads, the
VAR demand of load exceeds the maximum VAR limit specified. Due to this the system voltage at some of
the buses becomes lower than nominal voltage. Hence the additional equipment is connected to the system
which can generate lagging VAR to meet the reactive power requirement of load and maintain the voltage at
various buses within specified limits.
During light loads the lagging VAR produced by lines are much more than required by loads. The
additional equipment provided to absorb or generate VARs is called as reactive power
compensating equipment.
The supply voltage must be with range of 380kV to 420kV if supply voltage goes beyond this range
the substation must inform to LDC (Load Dispatch Center) to take required action for line
compensation and prevent load shading.
A daily hourly reading log sheet is maintained to record all readings of the substation. These
readings are also send to LDC at Kalwa Mumbai by fiber optic.
11
Balancing Of Load (Methods For Line Compensation):
Active power is from supply. Reactive power is from capacitor bank.
Generator supplies active power. Generator is used in condenser mode to increase reactive power
I. Reactor Bank
II. Inductive
mode of generator During under
voltage condition-
I. Capacitor Bank
II. Condenser mode of generator
Automatically load is cut at 370kV. Load shading is done when supply voltage goes below
370kV as supply should be ±10% of 400kV to prevent tripping of grid generator and avoid
blackout. Load forecasting and scheduling of load is performed for easier load balancing.
Distribution company gives demand schedule and generation company gives generation
schedule to LDC (Load Dispatch Center). A block of 15 minutes is forecasted using these
schedules.
12
1. Outage for maintenance –
Maintenance is performed on Thursday and when fault has occurred in an equipment or in
transmission line.
I. Tripping of circuit breaker due to fault in transmission line which is detected by relay
system. (breaking of conductor, short circuited due to external object, etc)
II. Temperature sensors not working properly (not able to detect change in temperature).
III. Fire in main tank of transformer.
IV. Cracking of insulator in lightning arrestor
V. Breaking of insulator
Outages is required for maintenance to be performed on equipment like ICT and CB.
Maintenance is also performed on connectors of isolators and earthing switches , main bus ,
isolators of main bus but these maintenance can be performed without taking outage instead
complete supply is transferred to other main bus.
When maintenance is performed a permit must be issued for working on the equipment or
transmission line for both receiving and sending end. This permit is issued by LDC by giving
same password to both ends which is not public. The permit issue time must be reported to LDC
from both ends. The permit ensures that outage has be performed and the line and equipment is
safe for workers to work safely. After the maintenance is completed successfully the circuit
must be reclosed to operate. The reclosing of circuit takes place after matching the passwords on
both ends of transmission. The reclosing time must be reported to LDC.
13
CHAPTER 7: METHODOLOGICAL DETAILS
ARRANGING AN OUTAGE.
The party requiring an outage on equipment (equipment include lines) should send a monthly
proposal to Ex. Engineer of R.S. (O&M) Division well in advance With the following details.
1. Equipment on which outage is required. Nature of work and its exact location.
The outage will be arranged by the E.E. R.S.0&M Dn. in consultation with S.E.
EHV/T'CC/C.E.-Load Des patch center. Kalwa. Ex. Engr. (0&M) of the area that will be effected by
the outage. A message approving the outage shall be sent to all parties concerned two days in advance
with details under 1 to 7 above by the concerned
14
Fig 7.1: Maintenance of ICT
15
LOGBOOK
MAHARASHTRA STATE ELECTRICITY
(CODE NO.) ZONE: 6000 CIRCLE: 6100 DIVISION: 6160 S/S CODE: J454
Art'A’
Signature Name
Jr. Technician
Signature Name
Executive Engineer
16
Date: …………………
17
220 KV JEJURI - II LINE
DOC: 27.01.2005, LINE LENGTH: 8.318 Km, 0.4 ACSR CONDUCTOR, CTR: 800/1
TIME AMP MW MVAR PF KV
01.00
.
24.00
220 KV PHURSUNGI - II LINE
DOC: 16.06.2011, LINE LENGTH: 37.4 Km, 0.4 ACSR CONDUCTOR, CTR: 800/1
TIME AMP MW MVAR PF KV
01.00
.
24.00
220 KV KONDHWA GIS LINE
DOC: 16.06.2011, LINE LENGTH: 36.5 Km, 0.4 ACSR CONDUCTOR, CTR: 800/1
TIME AMP MW MVAR PF KV
01.00
.
24.00
220 KV BUS – COUPLER
DOC : 20.01.2005, CTR : 2400/1
TIME AMP MW MVAR PF
01.00
.
24.00
ICT – I TEMPERATURE
TIME R Phase Y Phase B Phase
Sr. No. : 6005924 Sr. No. : 6005921 Sr. No. : 6005923
OT HV IV LV OT HV IV LV OT HV IV LV
01.00
.
24.00
ICT – II TEMPERATURE
TIME R Phase Y Phase B Phase
Sr. No. : T 09542/1 Sr. No. : T 09542/2 Sr. No. : T 09542/3
OT HV IV LV OT HV IV LV OT HV IV LV
01.00
.
24.00
ICT – III TEMPERATURE
TIME R Phase Y Phase B Phase
Sr. No. : B30726 Sr. No. : B30727 Sr. No. : B30728
OT HV IV LV OT HV IV LV OT HV IV LV
18
01.00
.
24.00
DOC : 31.03.2006, 167 MVA BHEL Make, Sr. No. : R - 6005922
SPARE ICT Ambient Control
TIME TEMPERATURE Temp Room
OT HV IV LV AMP IMP Temp
KMWH
01.00
.
24.00
BUS READING
TIME 400KV Bus Voltage 220KV Bus Voltage Frequency
Bus 1 Bus 2 Bus 1 Bus 2
01.00
.
.
24.00
BATTERY CHARGER READINGS
Particulars 220 V DC CHARGER 48 V DC CHARGER
Source - I Source - II
TIME 9.00 Hrs. 17.00 Hrs. 9.00 Hrs. 17.00 Hrs. 9.00 Hrs. 17.00 Hrs.
V (AC)
V (DC)
AMP
(Main)
DC (Load)
Charging /
Discharging
Charger
Position
Float/Boost
DC EARTH
LEAKAGE
19
CHAPTER 8: CIRCUIT BREAKER
Gas weight – 45 Kg
Fig 8.1: SF6 Circuit Breaker
Gas – SF6 sulfur hexa flouride
Rated frequency – 50 Hz
20
Out of Phase breaking current – 10kA
Maintenance –
21
CHAPTER 9: CONCLUSION
From above industrial training we have learned the working ,equipment and operation of receiving
end substation. We also learned the steps for taking an outage to perform maintenance and give
permits to work on transmission line , maintaining of logbook of readings(like voltage ,
current ,temperature , etc) to record the performance of substation and equipment used in it.
We got deep knowledge of EHV transmission lines and components used in a substation like CB,
ICT, CT, PT, Battery room, AC DC room, CVT, WT, Earthing switch, conductor, insulator, PLCC,
RTCC, etc.
22
CHAPTER 10: FUTURE PLAN
In the next 5 years, Mahapareshan aims to create a robust power transmission structure keeping in
view the growth in power generation and demand. The company has undertaken an ambitious
capacity expansion plan for the year 2015-16. From it evacuation of electricity generated in the power
generation center and through a powerful power transmission network (Grid).
Reaching every nook and cranny of Maharashtra will fulfill these needs. Mahapareshan made a
preliminary estimate and accordingly maintained the system
A policy of improvement has been decided. This has greatly reduced the incidence of power outages.
of Mahapareshan's power grid
Availability has improved to 99.73 percent (HVAC) and 99.30 percent (HVDC). Measures
for value creation and cost containment
Mahapareshan Company has focused on creating value and limiting costs in its operations. The
following measures for this have done
ABT meters have been installed for energy accounting at 530 power sub- stations of
Mahapareshan. In important departments online works are done using computer and information
technology. For that ERP Integrated Computer The system uses –
Existing infrastructure for universal connectivity consists of 2801 km long optical fiber cable
system An effective communication system is being introduced using fiber cable system.
Mahapareshan has tried to start unmanned and remote control power substations on pilot
basis. Efforts are underway to set up Gas Insulated Power Substations (Gas Insulated 5/5 - G/
5) at Bhandup (near Mumbai) and Hinjewadi (near Pune).
Renovation of State Load Despatch Centers at Kalwa and Ambazari for modernization of 140
SCADA- RTUs. That is, supervision Control and data storage and Remote Terminal Unit
RTO are used.An ambitious project to set up a power substation with a huge capacity of 765
KV has been started at Auragabad.
Equity Capital will create a Mahapareshan (P.O. i.e. Initial Public Offering) to raise funds
from the open market to raise capital expenditure.
23
CHAPTER 11: ATTENDANCE RECORD
Date Day
10/2/2023 Friday
11/2/2023 Saturday
16/2/2023 Thursday
18/2/2023 Saturday
24/2/2023 Friday
25/2/2023 Saturday
03/3/2023 Friday
04/3/2023 Saturday
10/2/2023 Friday
24
CHAPTER 12: LIST OF REFERENCE
[1] https://www.mahatransco.in/
25