Annual Report 1998
Annual Report 1998
Electricité du Cambodge
ANNUAL REPORT
1998
November, 1999
Annual_98 1
HISTORY
OF THE ESTABLISHMENT OF EDC
In 1992, EDP was re-named the Electricité du Cambodge and was attached
to the Ministry of Energy. After election in 1993, EDC was restructured
under the Ministry of Industry, Mines and Energy (MIME) and was
responsible for the development, management and operation of the power
system in Phnom Penh.
Power utilities in the provinces are under the control of Provincial
Authorities, who receive budgetary support through MINE.
EDC Today
Annual_98 2
Phnom Penh has a population of around 1 million and 100,000 customers.
The system in Phnom Penh has a peak demand of 61 MW and a power
generation capacity of 87 MW, out of which 35 MW are provided by an IPP.
A second IPP is scheduled to come on line by November 2000, to provide
an additional capacity of 60 MW, while an IPP of 15 MW committed to
provide the electricity in early 1999. The total installed capacity for all
provincial capitals are estimated 37 MW and size range from 300 kW to 5
MW.
Annual_98 3
EDC's STRUCTURE
AND ORGANIZATION CHART
EDC's STRUCTURE
The ownership of EDC vests in the state. The Ministry of Industry Mines
and Energy and the Ministry of Economy and Finance are co-owners of the
EDC.
EDC's Function
EDC is authorized to under take the following function:
1
EDC's Board of Directors was appointed on 5 September 1997.
Annual_98 4
HUMAN RESOURCES
AND DEVELOPMENT
Human Resources
The staff strength of EDC as of December 31, 1998 is 1351, in which 10 %
of the total personnel or 132 are females. The managerial personnel are
totally of 70 or 5.2 % of the total personnel, while the skilled and technician
workers are 516 or 38.19 %, accountants and office staff are 474 or 35.1 %
of the total personnel and the unskilled workers are totally 134 or 9.92 % of
the total personnel. A new salary structure has been being implemented to
motivate the EDC's staff.
Note:
Managers,
Unskilled Engineers,
5.18%
staff, 9.92% 11.62%
Skilled
Workers, Technician,
24.35% 13.84%
Accountant
& Office
Staff,
35.09%
Annual_98 5
Human Resources Development
The EDC management has placed the highest priority of the human
resources development and training to its staff for efficient operation of the
utility. With ADB's assistance, a training centre is being established in
Phnom Penh, which will be ready by October 1999. The key objective of
training center will be to develop a comprehensive programme and
schedule for the training of staff in power sector.
EDC has also identified a need to train their senior staff in the area of
Planning, Operation and Commercial from a management prospective. The
executive directors and senior staff of EDC totally of 24 are participating in a
year training programme sponsored by the World Bank. In 1997, 107 staffs
were trained in 12 divers courses and at the first nine months in 1998, 104
staffs were trained.
Annual_98 6
POWER
SYSTEM OPERATION
Due to the severely damaged by years of war and neglect, the power
system of Cambodia, which concentrated in Phnom Penh, was unable to
supply the demand for electricity from conventional grid connection. A large
amount of demand was supplied from large and small generators owned by
large, medium and small consumers.
Since 1996, EDC, beside of PHN's which adjoining Kandal Province power
system, EDC has also operated isolated grid networks for the provincial
cities of Sihanoukville (SHV's), Siem Reap (SRP's) and Kampong Cham
(KGC's). At the end of 1998, the total installed capacity was 95 MW with the
possible output was 84 %. The possible output increased from 67 % and 75
% in 1996 and 1997, respectively. 1998's generation was 365 Million kWh
including 185 Million kWh purchased from Independent Power Producers
(IPPs) in Phnom Penh and KGC's provincial capital.
Most of EDC's power generation plants are small unit ranges from 2.5 MW
to 6.0 MW. The are traditional diesel engines use light distillated Oil (LDO),
while the plant no C2 (18 MW) and IPP-I (35 MW) are using heavy fuel oil
as the main source of energy.
2
the percentage of the possible output to installed capacity
Annual_98 7
Installed Capacity and the Possible Output
140 Installed Capacity,
120 MW
100 Possible Output,
MW
MW & %
80
Percentage , %
60
40
20
0
1996 1997 1998 Year
At the 1998, power generation for Phnom Penh was from four power
stations excluded the stations C1and C4 that were stopped operating
according to deterioration of those units. The plant C2 (18 MW), IPP-I (35
MW), C3 (14.2 MW), C5 (10 MW) and C6 (18 MW) are serving the power
for Phnom Penh municipality, suburban and the adjoining Takhamu area
(Kandal Province). The thermal oil-fired power plant (IPP-I), that is
generating the electricity sale to EDC, has been commissioned since 1997.
Siem Reap City is supplying the electricity by a power station (3 MW) under
the assistance of former USSR and grant aid of France. In 1998, the energy
generation in SRP's system was 10.02 GWh.
Kampong Cham City has supplied the electricity by a single power plant
equipped with the installed capacity of 2x800 kW, 2x280 kW and a private
temporary generator 1x800 kW. This existing power plant will be functioned
as a substation when the power generation is entirely closed and new
power plant at the other site is commissioned by IPP (Global Technology
Support - GTS).
Annual_98 8
EDC's Energy Seles
400
350
300
Energy, GWh
250
200
150
100
50
0
1996 1997 1998 Year
Energy Generation, Energy Sold
26 %
25
24
23
22
21
1996 1997 1998
Year
Annual_98 9
Daily Generation Curve on the Peak Day
70
60 12/08/96
50 9/3/97
Capacity, MW
2/12/97
40
7/12/97
30
27/02/98
20 04/02/98
10 23/05/98
0
0
8
10
12
14
16
18
20
22
Time, hr
Distribution Networks
There are several voltage levels22kV3, 15 kV, 6.3 kV, 4.4 kV (2-phase) are
using in Phnom Penh network, while in the provinces only 6.3 kV and 4.4
kV. The 4.4 kV system had no longer use in 1997. The EDC's design
standard requires to upgrading the existing medium voltage to 22 kV, to
modernize the system reliability, to minimize the line losses and to adapt
the system standard of the region. For the low tension distribution level is
380/220 V is the country voltage level.
3
Although the Medium Voltage 22 kV have been constructed since 1996, but the only 15 kV energies to
match up with the existing 15 kV equipment which will be upgraded when the entire rehabilitation project
will completed
4
The rate was charged in both Cambodian Currency Riel and US$. It was 3800 Riel to 1 US$ in 1998.
Annual_98 10
EDC's Tariff Rate (Con't)
Sector Tariff Structure, US$/kWh
Old Rate Existing Rate
SHV's (Existing rate was effective March 1999)
I. Residential 0.2300 0.1300
II. Industrial & Handicraft 0.2300 0.1750
III. Commercial & Services 0.2600 0.1950
IV. Embassy, Hotels/Guest Houses, Foreigners 0.2600 0.2000
V. Government Office 0.2600 0.2000
KGC's
Flat Rate (Charge in Riel) 0.2207 0.2207
Annual_98 11
CUSTOMERS'
SERVICE AND OTHER ACTIVITIES
WITH CUSTOMERS:
WITH EMPLOYEES:
WITH SUPPLIERS:
WITH COMMUNITY:
Annual_98 12
CAMBODIA POWER SECTOR
EXPANSION
Power, MW 150 212 273 331 404 477 558 651 746
Energy, GWh 678 956 1036 1215 1454 1700 1968 2292 2634
Annual_98 13
GENERATION MASTER PLAN
1200
800
Annual_98 14
Table 2 Transmission Development Planing
Contingency 0%
Year Connection Terminal Cost Comments
Substation
Capacity 1
M$
2001 Connect IPP2 to GS1 140 2.3 60MW CC established on C4 site
String 2nd circuit for GS1 to GS3 0.6
2002 Connects Kirrirom PStation to GS1 12.6 route through the NPP
Establish Kompong Speu 15 3.6 directly under Kirrirom line
Transmission Thailand-Bantey 30 7.0 115kV, SC
Mean Chey
2003 Transmission Takhmau 46.1 230kV, DC Takhmau-Takeo-
Sihanoukville Kampot- Sihanoukvill
Establish Takhmau 60 10.5 single transformer
Establish Takeo 15 7.0 directly under TL Takhmau-
Sihanoukville
Establish Kampot 30 7.5 230, 115 and 22kV
Establish Sihanoukville 30 7.1 115kV, DC Takhmau to GS2
Connect Takhmau to GS2 3.1
String second circuit for GS2 to 0.6
GS3
Install 2nd transf in GS3 60/240 1.1
Connect IPP3 3.0 90MW SC plant Sihanoukville,
230kV
Connect Prek Thnot Power Station 3.7 to Kompong Speu
Connect Battambang 30 6.9 115kV, SC line to Bantey Mean
Chey
Connect Siem Reap 15 17.4 with Bantey Mean Chey 115kV
2005 Connect IPP4 to SHV 4.5 90MW CC plant Sihanoukville,
230kV
2007 Establish North Phnom Penh, NPP 60/300 6.3 230/115kV, 115kV DC
transmission to GS1
2008 Connect Kamchay PS to Kampot 6.9 47MW hydro PS
2009 Interconnection with Vietnam 9.2 Takeo to Vietnam
Establish East Phnom Penh (EPP) 30/300 6.2 115/22kV terminal sub, 30MVA
Connect Kampong Cham 30 13.5 115/230kV, DC from NPP
(KCHAM)
2011 Establish South Phnom Penh , SPP 60/390 8.9 Connected toTakhmau (TAH)
Connect Battambang 2 11.8 36MW hydro, 115kV, SC to
Battambang
2012 Connect Stung Atay Power Station 71.0 110MW, hydro, 230kV TL via
Pursat and K Cham
Establish Pursat 15 4.6 Direct under TL to Stung Atay
Connect Prey Veng 15 6.1 115kV from EPP
2013 Establish West Phnom Penh WPP 60/450 14.1 115kV, DC from SPP and NPP
2014 Connect IPP5 toSihanoukville 3.0 90MW, SC gas turbine
2015 Establish Central Phnom Penh, GS4 70/520 18.6 U/G cable connection from IPP2
and GS2
2016 Connect Battambang and Pursat 19.7 230kV, DC, establish one system
Connect Middle Stung Russei 12.7 125MW, hydro connected to Stung
Chrum MSRC Atay
Establish Kampong Cham 156.2 directly under TL to Stung Atay
363.6
Source: Government of Cambodia, MIME Nov. 1998, Cambodia Power Strategy 1999-2016
Annual_98 15
Subregional Power Interconnection
Cambodia can be interested in three levels of energy trading with neighboring countries,
which are listed here and explained in detail bellow.
− Low level energy purchase, most likely through distribution line to provide cost
effective sources of power supply to areas close to the border.
− Low capacity transmission links with the initial function to import energy to
provincial load centers, and possible future energy export. Typically this can be a
transmission link with capacity about 100 MW and the reliability (single circuit or
double circuit) justified on a case bas case basis.
− Large capacity transmission lines dedicated to energy export and power wheeling
between countries. This category can contain heavy 230 kV or 500 kV transmission
and generally will be of interest to organizations studying regional
interconnections.
Annual_98 16
ELECTRICITE DU CAMBODGE
PHNOM PENH OPERATIONS
BALANCE SHEETS
As at 31 December 1998 and 1997
1998 1997
Riel '000 Riel '000
(Unaudited)
ASSETS
LONG-TERM ASSETS
Property, plant and equipment-net 365,088,691 197,214,027
CURRENT ASSETS
Cash on hand and in banks 6,623,584 3,474,134
Accounts receivable-net 27,956,633 23,099,221
Inventories-net 8,414,371 5,702,660
42,994,588 32,276,015
CURRENT LIABILITIES
Accounts payable 43,824,062 18,832,111
Guarantee deposits 10,227,667 7,379,858
Taxes payable 9,496,763 825,555
63,548,492 27,037,524
OWNERS' EQUITY
Capital 184,648,449 145,172,054
Revaluation surplus 63,146,244 -
Accumulated losses -58,984,684 -8,369,113
188,810,009 136,802,941
Annual_98 17
ELECTRICITE DU CAMBODGE
PHNOM PENH OPERATIONS
STATEMENTS OF OPERATIONS
For the years end 31December 1998 and 1997
1998 1997
Riel '000 Riel '000
ACCUMULATED LOSS AT
BEGINNING OF YEAR 8,369,113 -
ACCUMULATED LOSS AT
END OF YEAR 58,984,684 8,369,113
Annual_98 18
ELECTRICITE DU CAMBODGE
SIHANOUK VILLE BRANCH OPERATIONS
BALANCE SHEETS
As at 31 December 1998 and 1997
1998 1997
Riel '000 Riel '000
(Unaudited)
ASSETS
LONG-TERM ASSETS
Property, plant and equipment-net 27,501,906 8,340,78
Computer license-net 36,245 46,129
27,538,151 8,386,307
CURRENT ASSETS
Cash on hand and in banks 187,432 71,040
Accounts receivable-net 1,610,006 1,025,762
Inventories-net 580,746 184,757
2,378,184 1,281,559
CURRENT LIABILITIES
Accounts payable 1,390,663 733,684
Guarantee deposits 173,645 88,720
Taxes payable 167,742 36,822
Loan from director - 286,471
1,732,050 1,145,697
OWNERS' EQUITY
Capital 2,709,004 8,390,199
Revaluation surplus 7,059,759 -
Accumulated losses -277,910 -58,275
9,490,853 8,331,924
Annual_98 19
ELECTRICITE DU CAMBODGE
SIHANOUK VILLE BRANCH OPERATIONS
STATEMENTS OF OPERATIONS
For the years end 31December 1998 and
1997
1998 1997
Riel '000 Riel '000
(Unaudited)
ACCUMULATED LOSS AT
BEGINNING OF YEAR 58,275 -
ACCUMULATED LOSS AT
END OF YEAR 277,910 58,275
Annual_98 20
ELECTRICITE DU CAMBODGE
SIEM REAP BRANCH OPERATIONS
BALANCE SHEETS
As at 31 December 1998 and 1997
1998 1997
Riel '000 Riel '000
ASSETS
LONG-TERM ASSETS
Property, plant and equipment-net 7,509,275 7,616,416
Computer license-net 34,901 44,420
7,544,176 7,660,836
CURRENT ASSETS
Cash on hand and in banks 15,630 22,390
Accounts receivable-net 1,008,165 674,584
Guarantee deposits 119,886 126,757
Inventories-net 86,228 54,877
1,229,909 878,608
OWNERS' EQUITY
Capital 1,198,631 6,271,335
Revaluation surplus 5,152,646 -
Accumulated loss -140,415 -62,565
6,210,862 6,208,770
Annual_98 21
ELECTRICITE DU CAMBODGE
SIEM REAP BRANCH OPERATIONS
STATEMENTS OF OPERATIONS
For the years end 31December 1998 and 1997
1998 1997
Riel '000 Riel '000
ACCUMULATED LOSS AT
BEGINNING OF YEAR -62,565 -
ACCUMULATED LOSS AT
END OF YEAR 140,145 62,565
Annual_98 22
ELECTRICITE DU CAMBODGE
KOMPONG CHAM BRANCH OPERATIONS
BALANCE SHEETS
As at 31 December 1998 and 1997
1998 1997
Riel '000 Riel '000
(Unaudited)
ASSETS
CURRENT ASSETS
Cash on hand and in banks 195,731 199,482
Accounts receivable-net 209,079 61,677
Guarantee deposits 19,666 25,796
Inventories-net 198 -
424,674 286,955
CURRENT LIABILITIES
Accounts payable 280,036 177,796
Guarantee deposits 18,812 -
Taxes payable 9,720 705
308,568 178,501
OWNERS' EQUITY
Capital 1,873,764 1,810,274
Accumulated losses 91,977 29,602
1,965,741 1,839,876
Annual_98 23
ELECTRICITE DU CAMBODGE
KOMPONG CHAM BRANCH OPERATIONS
1998 1997
Riel '000 Riel '000
(Unaudited)
ACCUMULATED LOSS AT
BEGINNING OF YEAR 29,602 -
ACCUMULATED LOSS AT
END OF YEAR 91,977 29,602
Annual_98 24